Professional Documents
Culture Documents
Edl Agnew Hybrid Project
Edl Agnew Hybrid Project
Edl Agnew Hybrid Project
Microgrid Owner/operator
EDL
EDL owns and operates the Agnew Hybrid Renewable
Microgrid, a ground-breaking energy solution for Gold Customer
Fields’ Agnew Gold Mine in Western Australia. Gold Fields
The power station provides the mine with more than Location
50% renewable energy over the long term, without Leinster, Western Australia,
compromising power quality or reliability. Australia
Installed generation
18MW capacity
56MW
wind generation
56MW
installed capacity Primary fuel
4MW Hybrid
solar generation
Approximately
40,000 13MW
tonnes of battery system
carbon dioxide
equivalents
avoided p.a.
12,700 8,700
cars off the road p.a. homes p.a.
The new microgrid comprises four key The Agnew Hybrid Renewable Microgrid comprises
wind, solar, gas and diesel generation and
components managed by an advanced control battery storage.
system:
• five 110m wind turbines, each with a rotor
diameter of 140m, delivering 18MW Project suppliers
• a 10,710-panel solar farm generating 4MW
• a 13MW/4MWh battery system
• off-grid 21MW gas/diesel engine power plant.