Pre Commissioning Procedure
Pre Commissioning Procedure
Rev. No.: 10
Project Construction and Pre-
commissioning Procedure Issuance Date: 17 09 2020
proper planning of Contractor activities in the facility, shut-downs and Operator responsibilities in
the process.
6.2.1 The Contractor is responsible for the initiation of the Pre-commissioning activities according to
the schedule prepared earlier.
6.2.2 At the end of each Pre-commissioning walkdown, the Contractor issues Punch Lists (PL A, B and C)
for the relevant system and discipline to be reviewed and approved by PJ and Commissioning
Team. For definitions of Punch List categories and included items, refer to MVEP-1-CE-405: Project
Commissioning Procedure.
6.2.3 After Clearing the Punch List A & preparing a detailed plan to describe how the Punch List B items
will be closed-out during Pre-commissioning activities, the contractor initiate the Pre-
commissioning witness request to PJ & Commissioning Team.
6.2.4 The Commissioning Leader (with the Commissioning team) witnesses the Pre-commissioning
activities for each system/sub-system and discipline. The list of checks and tests that will be
performed is prepared by the CT. The Contractor develops the relevant check sheets per
system/sub-system and discipline.
6.2.5 The Contractor delivers the required deliverables (Vendor and Training manuals, RSPL, PEL, MEL,
IFC and Red-marked drawings). These deliverables are reviewed initially by the BU and comments
are provided to the PM. The PM consults with QA/QC to run the final review and approve the
Contractor submittals (QA/QC should run a quality check of the Red-marked drawings). The RSPL
submitted by the Contractor has to follow the available template (MPRF-3-PJ-081: Recommended
Spare Part List) and contain the required details related to the project, main equipment, and