Professional Documents
Culture Documents
Assessing Maximum DG Penetration Levels in A Real Distribution Feeder by Using OpenDSS
Assessing Maximum DG Penetration Levels in A Real Distribution Feeder by Using OpenDSS
Assessing Maximum DG Penetration Levels in A Real Distribution Feeder by Using OpenDSS
978-1-5090-3792-6/16/$31.00
2016
c IEEE 71
eff.
V1
Inductive Capacitive
100%
% Available vars
P V2 V3
Percent Voltage
Pmpp @ 1 kW/m² .
Temperature I 100%
V4
Base Irradiation 100%
dc .
V
Daily P ac P x eff.
Temperature(t)
Yearly Fig. 3. Volt-Var Curve
Irradiation(t)
Duty
One-Line System - High Side
Pmpp (T)
kV kvar PF Connection
T
Substation Transformer
Fig. 2. PV System Model LTC
72
TABLE I TABLE III
F EEDER ’ S DATA T RANSFORMER ANDLTC E QUIVALENT DATA
TABLE II feeder A were neglected and the active power for its consumers
T RANSMISSION E QUIVALENT DATA
were considered according to the Equation 2 and reactive
power of each customer is related to its own power factor,
Parameter Value
Positive Sequence Resistance 0.40 Ω
obtained from the feeder data in CYME. This equation is
Positive Sequence Reactance 3.79 Ω reasonable, once that the consumers of each feeder have the
Zero Sequence Resistance 1.45 Ω same nature.
Zero Sequence Reactance 6.21 Ω
PB (t) + PC (t)
PAN ew (t) = M aximum
(2)
PB + PCM aximum
• Substation transformer including its Load Tap Changer Where
(LTC) • PA
N ew
(t): Defined active power for loads in Feeder A, in
• Three capacitor banks pu, at a specific time, t.
• Technical information on the existing wind turbine • PB (t): Actual active power measured at the feeder’s B
• Active and reactive power measurements on each feeder head, at a specific time, t.
during one year • PC (t): Actual active power measured at the feeder’s C
73
Fig. 5. Load shape for the Loads in Feeder A Fig. 6. Load shape for Feeder A customers, Feeder B, and Feeder C in the
Selected Days
A. Load Shapes
As the goal was to evaluate voltage issues in feeder A, the
criteria was applied in the load shape defined by Equation 2,
shown in Fig. 5 for the whole year. To simplify the analysis,
only the load shape for two days were chosen according to
the criteria of maximum and minimum demand, which are Fig. 7. Irradiation and Output Power Curves for the Wind Systems
expected to be related to undervoltage and overvoltage issues,
respectively. The maximum demand criteria was basically
V. S IMULATIONS AND R ESULTS
to pick the day in which the highest absolute demand was
verified. The selected day was 08/26/2014, in which there A. Snapshot Simulation
was a demand of 1 pu at 4:15pm. This day was named as In the snapshot mode the power flow is calculated for a
workday. The minimum criteria was to select the day in which specific condition in time. For the simulations three variables
the lowest absolute demand was verified between 10am and were defined:
2pm. This interval was assumed, because it is likely that the • Feeder loading value, 2 options: workday (1 pu) or
peak PV system’s generation happens during this window and weekend (0.39 pu)
it is known that under these circumstances, the overvoltage • Wind System Power, 4 options: 0 , 0.9 MVA, 1.5 MVA,
problem is amplified. The selected day was 04/19/2015 in 2.25 MVA
which there was a demand of 0.39 pu at 10:30am. This day • PV System Power, 4 options: 0 , 1 MVA, 2 MVA, 3 MVA
was named as weekend. The load shape for the selected days Hence, two groups of 16 connections each were defined.
are shown in Fig. 6. The first group of connections corresponds to a heavy load
(workday) and the second group corresponds to a light load
B. Irradiation Curve and Output Power Curve of the Wind
(weekend). Besides that, a base case was defined considering
System
no extra DG connection. To analyze the influence of a high
Two typical irradiation curves and output power curve of DG penetration in the feeder, the simulations were performed
the wind system with a 1-s step size were defined. As for the fixing the capacitor banks control and the LTC control accord-
irradiation, one curve represents a sunny day and the other one ing to its state obtained from the base case, as shown in Table
a cloudy day. As for the wind system, one curve represents a IV. The idea was to evaluate the worst case, in which there is
day with high-speed winds and the other one a day with low a transition between a state with no prior DG connection to a
speed winds. The total four curves are shown in Fig. 7. state where the system has a maximum per unit DG penetration
74
TABLE IV TABLE VI
BASE C ASE E QUIPMENT S TATES S CENARIOS
75
TABLE VIII
M AXIMUM P ENETRATION L EVELS IN DAILY S IMULATION M ODE
WITHOUT VOLT-VAR
TABLE IX
M AXIMUM P ENETRATION L EVELS IN DAILY S IMULATION M ODE WITH
VOLT-VAR
Fig. 8. Maximum ∆V
TABLE X
M AXIMUM P ENETRATION IN S NAPSHOT S IMULATION M ODE
76