1. PROJECT DESCRIPTION
Energy Equity EPIC (Sengkang) Pty. Ltd plans to upgrade Kampung Baru Gas
Plant Facility with built Train #2 gas processing plant called CPP Train #2. This
facility will be located at Kampung Baru, Wajo, Sulawesi Selatan, Indonesia. The
CPP train #2 facility will be designed for Capacity of 35 MMSCFD. This facility
shall cover fluid/gas from new KB-9, KB-10, KB-11 Well and existing wells. The
upgrading also built new PMS Receiving facilities.
2. APPLICATION
This procedure shall apply to Hydrostatic Test for EPCI Kampung Baru Gas Plant
Upgrading Project.
3. SCOPE
• This procedure covers the detail of hydro testing of process piping to meet
the code and client’s specification and ASME B31.3
• The scope of pressure test of systems shall be in accordance with isometric or
hydrostatic test flow diagram.
• All valves dia. 2 inch and above shall also be hydro-tested for body leakage
and seat leakage
4. REFERENCE
ASME B31.3 – Process Piping
5. RESPONSIBILITY
• Contractor shall assure that the procedure is executed and record are kept
and documented
• QC Inspector shall monitor that each stage of procedure is performed and the
report is properly maintained
• Piping Supervisor shall perform the hydrostatic test in accordance with
approved procedure.
• Vents and drains are to be provided for the system before the
commencement of hydro test.
• All welded, screwed and flanged joints shall be exposed for examination
during hydro testing. Welded joints should be free of slag’s and rust on the
surface.
• Careful examination shall be done to assess the requirement of additional
support before hydro testing.
• Approved water (clean and non – saline) with a minimum temperature of 45°
F shall be use as a Test medium.
• The thickness of any temporary blind flanges and blanking spades used shall
be in accordance with ASME B31.3 as applicable.
• All QC documentation shall be ready prior to performing the hydro-testing
8. TESTING PROCEDURE
• Piping system shall be dimensionally and geometrically confirmed to agree
with the latest approved revisions of piping drawing.
• Applicable isometric drawing/hydro test flow diagrams shall be submitted to
owner specifying the details of lines to be tested.
• Pressure shall be applied by means of a suitable test pump gradually to
working pressure. There after the pressure is to be applied in stages
preferably in increment of 10 % test pressure. Once the required test
pressure is reached, pump/compressor should be isolated from the test line
by means of cut – off valves.
• The test pressure shall be maintained for fifteen minute minimum. QC
inspector referencing the company shall carry out a detailed inspection of the
weld joints, flange and threaded dislocation/movement of support. The test
pressure and time is recorded on a calibrated recorder as per requirement.
ENERGY EQUITY EPIC (SENGKANG) PTY LTD
HYDROSTATIC TEST EPCI KAMPUNG BARU GAS PLANT UPGRADING PROJECT
PROCEDURE CONTRACT NO.: OPS/10/011
SHEET: Page 4 of 6
10. RECORDS
Hydrostatic test report package are to be prepared and signed by authorized
person. The reports shall include :
• Application for Inspection
• Identification of piping system ( System Test Number ).
• Line number, sizes and line check.
• Termination points of the system.
• Weld Traceability Sheet
• Test medium.
• Test pressure and duration.
• Operating and design temperature.
• P&ID/Test Block Diagram
• Isometric Drawing List
• Summary of NDT Record
• NDT Record
• Certificate Calibration of Pressure Gauge
• Mill Certificate
• Tag number for items to be removed during testing.
• Signature and names of company representative.
• Sketch of drawing showing line number, limits test and gauge points, etc.
• Post pipe installation check list
• Certificate Calibration of Recorder (Equipment)
• Sketch of Equipment
11. SAFETY
• Safety shall be strictly observed at all times during hydro testing. The area
shall be cordoned of and sign boards and barriers are to be provided.
• Protection shall be applied a necessary to electric motors, junction boxes
and instruments in the vicinity of flushing.
• Vent are to be kept open to prevent air locking during commencement of
pressurizing.
• Safety Valves shall be provided and set pressure shall be 10% above the
test pressure to prevent over pressurizing the system.
ENERGY EQUITY EPIC (SENGKANG) PTY LTD
HYDROSTATIC TEST EPCI KAMPUNG BARU GAS PLANT UPGRADING PROJECT
PROCEDURE CONTRACT NO.: OPS/10/011
SHEET: Page 5 of 6
RECORDER PRESSURE
GAUGE
MANIFOLD Package to
Test
PUMP
TEST ITEM:
INSTALLATION AREA:
SYSTEM NO. /DESCRIPTION:
WITNESSED BY VERIFIED BY
PREPARED BY
ENERGY EQUITY EPIC ENERGY EQUITY EPIC
PT. BINA SARANA PUTRA
(SENGKANG) PTY LTD (SENGKANG) PTY LTD
PROJECT TITLE:
EPCI KAMPUNG BARU GAS PLANT UPGRADING PROJECT
TEST PRESSURE:
TEST MEDIUM:
ITEM DESCRIPTION BSP REPRESENTATIVE ENERGY EQUITY REPRESENTATIVE THIRD PARTY REPRESENTATIVE
SIGNATURE NAME DATE SIGNATURE NAME DATE SIGNATURE NAME DATE
1 WELDING COMPLETED
NDT COMPLETED AND
2
ACCEPTED
LINE CHECK BEFORE
3
TESTING
4 RELEASE FOR TESTING
HYDROSTATIC TEST
5
COMPLETED AND ACCEPTED
FLUSHING/BLOWING
6
COMPLETED AND ACCEPTED
REINSTATEMENT
7
COMPLETED
REMARKS:
INSPECTION CHECKLIST (PRE-HYDROTEST)
PT. BINA SARANA PUTRA EPCI KAMPUNG BARU GAS PLANT UPGRADING PROJECT
JOB NO.
DISCIPLINE : PIPING
1 Line Routing
2 NDE Result
3 Weld Joints & Finish
4 Bolt Tightened
5 Gasket
6 Ball Valves Position
7 Plug Valves Position
8 Safety Valves Isolation
9 Check Valves Isolation
10 Control Valves Isolation
11 Globe Valves Isolation
12 Instrument and Electrical Protection
13 Vents and Drains
14 Chart Recorders Certificate
15 Pressure Gauge Certificate
16 Potable Water
17 Test Pump
18 Test Manifold
19 Other
TEST DATA
TEST ITEM :
DESIGN WORKING PRESSURE :
TEST PRESSURE :
DURATION OF TEST : HOUR/S
TEST MEDIUM :
OBSERVATION :
TEST CONDUCTED BY
WITNESSED BY WITNESSED/VERIFIED BY