María Paula Suarez - 2903439

Nicolas Sebastian Betancourt – 2904005

PARCIAL

Rta: b

Rta:d

Rta:d

Rta:a
PARTE B

a)

Period 1 2 3 4 5 6 7 8 9 10

Gross requirement 14 12 12 13 5 90 20 20 20 20

Scheduled receipts

Projected-on-hand 50 36 24 12 5 20 20

Net requeriments 1 90 20 20

Planned order receipt 6 110 40 20

Planned order release 6 110 40 20


b)

Period 1 2 3 4 5 6 7 8 9 10

Gross requirement 12 0 220 0 80 0 40 0 0 0

Scheduled receipts 0 0 0 0 0 0 0 0 0 0

Projected-on-hand 100 163 0 0 0 0 0 0 0 0

Net requeriments 0 163 0 80 0 40 0 0 0

Planned order receipt 0 163 0 80 0 40 0 0 0

Planned order release 0 80 0 40 0 0 0 0 0

c)

Gear Assembly

Period 1 2 3 4 5 6 7 8 9 10

Gross requirement 12 12 12 13 5 90 20 20 20 20

Scheduled receipts

Projected-on-hand 100 38 26 14 1 90 20 20

Net requeriments 4 20 20

Planned order receipt 94 40 40

Planned order release 94 40 40


Gear Assembly

Period 1 2 3 4 5 6 7 8 9 10

Gross requirement 188 80 80

Scheduled receipts

Projected-on-hand 100 100

Net requeriments 88 80 80

Planned order receipt 88 80 80

Planned order release 80 80