ON THE JOB TRAINING

Weekly Log Report

Name of the Company: LGU Kauswagan, Lanao del Norte Name of Student Trainee: Allas, Jaicca Faith Tandih
Name of OJT Supervisor: Engr. Saidale S. Maruhom, CE Program: Bachelor of Science in Civil Engineering
Date: Mar. 7-10, 2022 Required No. of hours: 240 hours

WEEK TASK/ACTIVITIES DOCUMENTATION

 Site visit:

- Central Stage, where they start


fixing the truss frame, welded it
well, they almost done piling the
hollow blocks for the wall.

W - Central water flow, the water


flow canal is almost done, they
E just need to finish the pavement
E so that they can level it with the
canal.
K
- Central Pavement, the other
9 side was done and I even
witness slope pavement.
(32hours)