Professional Documents
Culture Documents
Ch6 - Project Network - Summer2021
Ch6 - Project Network - Summer2021
Ch6 - Project Network - Summer2021
IMSE-372
Project Management and Control
11/21/2021
Dr. Ayedh Almutairi 1
Dr. Ayedh Almutairi 2
Developing the Project Network
The project network is a tool used for planning,
scheduling, and monitoring project progress
It is developed from information collected for the WBS
and is a graphic flow chart of the project job plan
Work packages from the WBS are used to build the
activities in the project network
A network consists of activities
FIGURE 6.1
Terminology
• Path: a sequence of connected, dependent activities.
• Critical path: the longest path through the activity network that allows for the
completion of all project-related activities;
the shortest expected time in which the entire project can be completed.
Delays on the critical path will delay completion of the entire project.
A B D
Dr. Ayedh Almutairi (Assumes that minimum of A + B > minimum of C in length of times to complete activities.) 9
Constructing a Project Network (cont’d)
Terminology
• Event: a point in time when an activity is started or completed. It does
not consume time.
• Burst activity: an activity that has more than one activity immediately
following it (more than one dependency arrow flowing from it).
Two Approaches B
• Activity-on-Node (AON)
• Uses a node to depict an activity
A C
• Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity
D
Dr. Ayedh Almutairi 10
Basic Rules to Follow in Developing Project Networks
FIGURE 6.2
TABLE 6.1
FIGURE 6.3
FIGURE 6.4
TABLE 6.2
FIGURE 6.5
FIGURE 6.6
FIGURE 6.7
Let
• D(j): Duration of activity j
• ES(j):Early starting time of activity j
• EF(j):Early finishing time of activity j
• LS(j):Late starting time of activity j
• LF(j):Late finishing time of activity j
FIGURE 6.8
FIGURE 6.12
FIGURE 6.14
FIGURE 6.14
Use of Lags to
Reduce Detail
FIGURE 6.15
36
Use of Lags (cont’d): Finish-to-Finish
• Finish of on activity depends on the finish
Finish-to-Finish
of other activity
Relationship
Example, testing a prototype: where testing cannot be completed
FIGURE 6.17 any
earlier than four days after the prototype is done
Note this is not a finish-to-start
FIGURE 6.18
FIGURE 6.18
FIGURE 6.18
FIGURE 6.20