Rupees Two Crore Ten Thousand Only
Rupees Two Crore Ten Thousand Only
The estimate is prepared based on prevailing local market and PWD rates.
Contract labour rates are adopted for finished items of works. A brief specification
report certificate is also here with enclosed.
The estimate includes provision for the Electrification of the entire building
with Concealed Wiring, Water Supply and Sanitary arrangements, installation of
0.50HP Electric Motor, Architectural finishing of the building etc., the estimate also
includes reasonable provision for the contingencies and petty supervision charges.
(2)
SPECIFICATION REPORT
FOUNDATIONS: The foundation for all columns will be taken to a depth of 1.50m
and to size of 1.20m x 1.20m. The foundation concrete shall be of 1:5:10 mix, using
40mm and down graded hard broken granite metal other than granite to size of 1.20m
x 1.20m and to a thickness of 0.15m. Above that RCC 1: 1 ½ :3 for column footing of
size 1.20m x 1.20m with a thickness of 0.15m at free end and 0.38 at column end will
be laid. There will be flooring itself. The sides of trenches are to be filled with
excavated earth. The size of the column to be adopted is 0.23m x 0.30m using RCC 1:
1 ½: 3mix
BASEMENT: The walls in basement are to be constructed with Brick Masonry in
cement mortar 1:8 to a width of 0.23m and a height of 0.60m. The basement is to be
filled with carted earth collected from outside and is to be well compacted and
consolidated. There will be a continuous Plinth beam of size 0.23m x 0.30m using
RCC 1: 1 ½: 3mix
SUPERSTRUCTURE: The walls in Ground Floor and shall be raised to a height of
3.00m above the basement and above the slab and to a thickness of 0.23m using Brick
Masonry in cement mortar 1:8 using 2nd class table moulded country bricks. There
will be a continuous lintel beam alround to a thickness of 0.10m and to a width of
0.23m RCC 1: 1 ½:3mix. There will be a continuous ‘T’ beams of size 0.23m x 0.30m
using RCC1:1 ½ :3mix.
SUNSHADE: Reinforced cement concrete1: 1 ½ :3 mix, using 20mm and down
graded hard broken granite metal is to be adopted. The thickness at the support is
0.75m from the face of wall.
ROOFING: The Roofing will be with RCC 1:1 ½: 3mix using 20mm and
downgraded hard broken granite metal. The thickness of slab is 0.11cm and the
reinforcing steel shall not be less than 0.12% of grass sectional area and should be in
accordance with the Engineer’s design details.
FLOORING: Vitrified tile flooring over 100mm thick cement concrete 1:5:10 bed in
Ground floor.
PLASTERING: Both external and internal walls are to be plastered with cement
mortar 1:5 - 12mm thick. The Ceiling will be plastered with cement mortar 1:3-12mm
thick
WOOD WORK: All the wood work is to be carried out using well seasoned
Country wood and the sizes are as per the detailed drawings and specifications.
PAINTING WALLS: Two coats with best white cement over plastered surface of
walls and ceiling.
PAINTING WOOD WORK: Two coats with best synthetic enamel paint over a
primary coat of white lead.
ELECTRIFICATION: The Electrification will be Concealed type and number of
points will be as per actual requirements.
WATER SUPPLY: Bore well, 0.50 HP Electric Motor.
SANITARY ARRANGEMENTS: Septic tank along with soak pit. The entire work
is to be executed in accordance with Andhra Pradesh detailed standards specification
and other standard specifications
(3)
1 2 3 4 5 6 7
1. Earth work excavation in foundation with an initial lead 10m and an initial lift of
2m, for foundation.
3. Reinforced cement concrete 1:1 ½ :3 using 20mm H.B.G metal and also using 60kg
of steel per cum of concrete including cost and conveyance of all material labour
charges.
4. RCC 1: 1 ½ : 3 for plinth beam alround including cost of necessary steel and labour
charges.
@ Rs.16,000.00/cu.M Rs.436200.00
(4)
5. Basement filling with Local sand for the basement including cost and conveyance
of all material and labour charges, pudling and consolidation charges.
6. Brick Masonry in Cement Mortar 1:8 in superstructure in Stilt +G. F, +FF, S.F
using 1nd class table moulded country bricks.
Deduct (-)
7. Supply and fixing of best Country wood doors and with Paneled shutters and
Including cost of all materials like holdfasts, tower bolts and hinges and including
cost of labour charges.
(5)
8. Supply and fixing of teak wood glazed windows including cost conveyance of all
Material and labour charges.
9. RCC 1: 1 ½ :3 using 20mm and down graded hard broken crushed metal for
Sunshades alround cost of necessary steel and centering charges
Sunshades in 40 67.54 0.75 - 2026.20m2
10. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for Lintel beams alround including cost of necessary steel and
centering and labour charges.
11. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for Roof slab alround including cost of necessary steel and
centering and labour charges..
(6)
12. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for ‘T’ beams alround including cost of necessary steel and
centering and labour charges.
13 Flooring the rooms with vitrified tiles flooring of 20mm thick with vitrified tiles
over C.C .1:6:10 of 100mm including cost of necessary steel and labour charges.
14. Ceiling – Plastering with Cement mortar 1:3-12.50mm thick vide ref item No.
(12)
734..48m2
Add for Sunshades 56.31m2
Deduct (-)
Walls area 22.02m2
-----------
768.77m2
----------
@ Rs.2000.00/10 sq.M Rs.461262.00
15. Plastering the walls in C.M 1:5 of 20mm thick including cost and conveyance of
all material and labour charges.
External Walls in 8 77.47 - 3.00 1859.28m2
Internal walls in 8 240 - 3.00 5760.00m2
Parapet walls in 2 77.47 - 0.90 154.94m2
-------------
7774.22m2
(7)
16. Painting walls two coats with best white cem including cost of all materials like
brushes, waste cloth putty etc., and including cost of labour charges.
Plastering area 5869.40m²
Ceiling area 735.12m²
------------
6604.00m²
------------
@ Rs 600.00/10 Sq.M Rs.1188720.00
17. Painting wood work two coats with best synthetic enamel paint over a painting
coat of white lead including cost of all materials like brushes, waste cloth, putty etc.,
and labour charges.
Total Rs.2,4557,495.00
-- ------------------
Rs,3,12,57,495.00
--------------------
(RUPEES THREE CRORE TWELVE LAKSH FIFTY-SEVEN
THOUSAND FOUR HUNDRED AND NINETY-FIVE ONLY)
The Estimated Cost of Construction work out to Rs. 3,12,57,495.00)