Professional Documents
Culture Documents
S5 - Schedule M - Tender Queries Responses No.2 (ISSUED20210511)
S5 - Schedule M - Tender Queries Responses No.2 (ISSUED20210511)
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
S1a - Instruction and Condition of Tendering
RFP Response Requirements
Tenders will close on the Tender Closing Date.
Does it mean the starting date of project will be delayed?
Tenders will be required to remain valid for one
Could you give late starting date? That is because that we No intention to delay on the starting date of project. This is client's
05.05.2021 15 hundred and twenty (120) days from the Tender General Closed TT CM 11-May-21
must consider the influence of material market price requirement for having tender validity of 120 days.
Closing Date (“Tender Validity Period”) stipulated
movement and weather condition.
in the Invitation to Tender and no tenderer may
withdraw his tender within the Tender Validity
Period.
For Phase 1 position please refer to red box (Grid AP to AG), for block a
building position please refer to blue box (Grid AP to AA)
Could you provide the completed key plan which can clearly
05.05.2021 22 S5 - Schedule H - Piling Scope Demarcation show the block A building and Phase I building position General Closed TT CM 7-May-21
relation?
S5 - Schedule M - Tender Queries Template
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
Is Phase I part of block A building?
If it is correct, the volume of Phase I is around more than
60% of block A building. However, 150KV substation and Yes, phase 1 is part of Block A Building. Yes Confirm on the schedule, full
S6 - Schedule H - Piling Scope Demarcation
05.05.2021 23 phase I building should be finished 3.5 months after General Block A should finish 7 months after the commencement date or 3.5 months Closed TT PM/ TT CM 7-May-21
commencement date. And full block A building should be after the completion of phase 1 building and 150 kv Substation
finished 7 months after commencement date. Please confirm
this schedule.
S5 - Schedule I - GIIC Estate Regulations
05.05.2021 24 IV. Construction requirement - item 5 Is temporary fencing and gate tenderer's work scope? General Temporary fencing and gate are not part of the piling contractor's scope Closed TT PM/ TT CM 7-May-21
Please make clear description. Add the necessary and Please rephrase your queries. Deviations List is need when there are items
05.05.2021 27 S5 - Schedule K - Bidders Deviations List additional works item and its cost which excluded in the General in the BOQ are different from the specifications or drawings and all this Cost Closed TT CM 7-May-21
BOQ? need to be part of your BOQ
Please rephrase your queries. Exclusion List is when you excluded some of
05.05.2021 28 S5 - Schedule L - Bidders Exclusion List Please make clear description. General Closed TT CM 7-May-21
the works highlighted in the "Drawings" and "Specifications"
S10.1 - Project Bored Piling Specification According to bore piling specification and drawing, all piles
Based on preliminary SI data, no rock is anticipated, thus the query is not
05.05.2021 30 S11.2 - Drawings are entering-rock pile. Please confirm the depth for entering Civil Closed RED/ MAVERICK 7-May-21
relevant.
Rock Coring rock.
S10.1 Project Bored Piling Specification Based on preliminary SI data, no rock is anticipated, thus the query is not
05.05.2021 31 Is the load test for rock material requested at all piles? Civil Closed RED/ MAVERICK 7-May-21
Rock Coring relevant.
S10.1 - Project Bored Piling Specification
Section 2.5
05.05.2021 32 Backfilling of Empty Bore - on completion of Please confirm the material for blind boring. Civil Contractor to propose. Please also refer to tender queries no.7 above Closed RED/ MAVERICK 11-May-21
concreting, the remaining empty bore shall be
backfilled with sand or lean concrete unless
S10.1 - Project Bored Piling Specification
Please confirm the work scope of cutting off pile head.
Section 2.6 - Stripping pile head and bonding Cutting off pile head is part of piling contractor's scope. Soil excavation TT PM/ TT CM/ RED/
05.05.2021 33 How about the foundation soil excavation before cutting off Civil / General Closed 11-May-21
S8 - Bill of quantities before the cutting off pile head will be part of General Contractor Scope. MAVERICK
pile head? Also this soil disposal works?
Cutting off pile head
S10.1 - Project Bored Piling Specification Please confirm the test method. The maximum test pile
05.05.2021 35 Civil Yes for piles more than 50m. Closed RED/ MAVERICK 7-May-21
Section 3.0 - Integrity testing of pile length is 50m. If more than 50, CSL test is applied.
S10.1 Project Bored Piling Specification Which part will be test for integrity test? Top part with rebar
05.05.2021 36 Civil Full pile. Closed RED/ MAVERICK 7-May-21
Section 3.0 Integrity testing of pile cage or full pile?
S10.1 - Project Bored Piling Specification Any requirement on coring test? What is the test number?
05.05.2021 37 Civil Contractor to allow for 5% of piles. Closed RED/ MAVERICK 7-May-21
Section 3.0 - Integrity testing of pile Please confirm it.
S5 - Schedule M - Tender Queries Template
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
As the load test capacity for PTP is 3 times of work load, so
the work pile can no be used as PTP. Any detail design on
S10.2 - Project Bored Piling Test Specification Kentledge method recommended. Location to be decided.
05.05.2021 38 preliminary test pile and anchor pile? Where is the location? Civil Closed RED/ MAVERICK 7-May-21
S11.2 - Drawing SI required nearby PTP as specified on drawing.
Do tenderer do new soil investigation nearby the preliminary
test pile?
05.05.2021 40 S11.2 - Drawing What is the PDA test number for each capacity? Civil 15 per type. There are 4 types and thus 60 altogether as specified on drawin Closed RED/ MAVERICK 7-May-21
CONTRACTOR TO CARRY OUT 2 NOS. PTP FOR BORED PILES CAPACITY OF
05.05.2021 41 S8 - Bill of Quantities How about the test for PTP? Civil Closed RED/ MAVERICK 7-May-21
6000kN & 9000kN as specified on drawing.
How about the reaction system for pile test? Included in the
05.05.2021 42 S8 - Bill of Quantities Civil Kentledge method recommended. Closed RED/ MAVERICK 7-May-21
pile test or add another new item?
Is the length of rebar cage length half of pile whatever the
05.05.2021 43 S11.2 - Drawing Civil Yes. Closed RED/ MAVERICK 7-May-21
pile length
Please give detail description on specification of rebar (both
05.05.2021 44 S11.2 - Drawing Civil ALL REBAR to GRADE BJTS 420 B to SNI2052-2017. Closed RED/ MAVERICK 7-May-21
main rebar and helical link).
Please explain. How to calculate the steel content? By
05.05.2021 45 S11.3 Drawing - Notes 6a Civil Yes by weight (kg) Closed TT CM/ RED/ MAVERICK 7-May-21
weight?
About over filling height for bore pile diameter 1200, it is
05.05.2021 46 S11.2 - Drawing - Notes 8 Civil Yes agreed Closed RED/ MAVERICK 7-May-21
better no less than 1m. Please suggest.
S11.2 - Drawing - Notes on Pile Load Test (PTP) Piles above the cut off level to not contribute pile capacity. Hence the pile
05.05.2021 47 Please give clearly explain on this. Civil Closed RED/ MAVERICK 7-May-21
No. 5 needs to be debonded using casing or some other material
15 per type. There are 4 types and thus 60 altogether as specified on
S11.2 - Drawing - Notes on Pile Load Test Civil / Quote
05.05.2021 48 Drawing show PDA test 60 piles, but 35 piles in BOQ. drawing. 30 nos on the block A building and 30 nos on the substation. The Closed TT CM/ RED/ MAVERICK 7-May-21
(Working Pile) B Template
revised quantity will be reflected in the revised BOQ in Addendum no.1
S11.2 - Drawing - Notes on Pile Load Test As all pile need do PIT test, the pile need pour until platform Civil / Quote Yes unless at certain areas excavation to a lower platform level is done.
05.05.2021 49 Closed TT PM/ RED/ MAVERICK 7-May-21
(Working Pile) C elevation consider the project duration. Please suggest. Template Contractor to plan accordingly.
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
Phase 1 building (Grid AP to AG) is part of Block A building. Block A
building is the day 1 piling package. Please refer to red box below for phase
1 building area and blue box for Block A building
10.5.2021 66 For your reminding, please provide soil investigation data. Civil SI will be provided later after the submission Closed TT PM/ TT CM 11-May-21
S10.1 - Project Bored Piling Specification If the air-lifting work is used for clean hole, is it necessary to
10.5.2021 67 Civil Yes Closed RED/ MAVERICK 11-May-21
2.7 - Drilling Fluid and Soil Tests test the slurry from the bottom of pile before concreting?
S10.1 - Project Bored Piling Specification As mentioned above "contractor to allow for depth of 3.3m
Section 2.6 - Stripping pile head and bonding from existing ground level", it is much better that the cutting Civil / Quote Yes. The cutting off pile head is after the general contractor excavate the
10.5.2021 69 Closed TT CM/ RED/ MAVERICK 11-May-21
S8 - Bill of quantities pile works is started after general contractor excavate the Template foundation
Cutting off pile head foundation. Please confirm it.
S5 - Schedule M - Tender Queries Template
PILING CONTRACTOR SERVICES FOR THE YONDR JKT1X0 DATA CENTRE DEVELOPMENT AT GREENLAND INTERNATIONAL INDUSTRIAL CITY, BEKASI, WEST JAVA
Open/
Date Item No. Drawing/ Clause/Spec Ref Tender Query (English) Discipline Tender Query Response Responsible Issue Date
Closed
Architecture/ Civil/
Structural/
25.09.2018 1 Drawing # or Doc or Clause # Question? Queries Response Open - Leave blank- - Leave blank-
Electrical/
Mechanical/
The pile in main building block A shown in drawing is 686
nos, but 678 nos in BOQ. Please confirm. What is the
meaning of revcloud in the drawing shown as above? Any
revised there? Please also reconfirm if the helical link will
use diameter 16 rebar.
The qty measured is 678nos for main building and 56 nos for 150kv
Substation. Please recheck.
S8 - Bill of Quantities Civil / Quote Cloud in the drawings is only to indicate the changes from R0 drawings to
10.5.2021 70 Closed TT CM 11-May-21
S11.2 - Drawing Template R1 drawings. In the RFP document, the tenderers have received the R1
drawings.