Professional Documents
Culture Documents
Pedoman TA
Pedoman TA
MANAJEMEN TURNAROUND
NO. A- 01/E10200/2010-S0
BAB I UMUM 1
A. TUJUAN 3
B. RUANG LINGKUP 3
C. PENGERTIAN 3
D. REFERENSI 7
C. SCOPE OF DEVELOPMENT 21
1. Job Collection 22
a. Post TA report (Closed Out TA Report) 22
b. Hystorical. 23
c. Program Preventive dan Predictive Maintenance 24
d. Modification (MOC approved). 25
e. Plant Test. 25
f. MOC dan pekerjaan project. 25
2. Critical Job list 27
3. Scope challenge & freeze process 27
4. Final job list 31
5. Preparing BOM LLD material 31
6. Identify Risk Process and Mitigation 32
E. DETAIL SCHEDULING 49
1. Develop network planning and detail scheduling 50
a. Membuat network planning untuk job list. 50
b. Menentukan jam kerja (working hours). 50
c. Menghubungkan seluruh network planning dari job 50
list TA.
2. Critical path 55
3. Critical path management 56
a. Optimisation tools, equipment & heavy equipment 56
b. Mengelola implementasi critical path 58
4. Develope detail schedule shutdown and start-up 59
5. Develop Start-Up Process 59
a. Pre Start Up Safety Review (PSSR) execution 59
b. Commisioning 63
c. Start up and feed in 63
6. Develop Quality Management 66
a. Sebelum eksekusi TA 66
b. Pada saat eksekusi TA 69
c. Setelah selesai eksekusi TA 69
7. Develop HSE Management 69
a. Risk Assessment 70
b. Job Safety Analysis (JSA) 70
c. Contractor Safety Management System 71
d. Personal Protective Equipment (PPE) identification 71
e. HSE Up skilling and Training 71
f. HSE Inspector outsourcing 71
g. Release Equipment 71
h. Turnaround HSE Activities 72
i. PSSR 72
j. PIR TA 72
F. CONTRACTOR MANAGEMENT 72
1. Contractor scoping analysis. 73
a. Strategi pembuatan kontrak TA 73
b. Scope kontrak untuk eksekusi pekerjaan TA 75
2. Contractor Performance Criteria & Indicator. 82
3. Contract Type. 84
4. Proses tender. 84
5. Contractor Safety Management System (CSMS). 84
a. Penilaian resiko (risk assessment) 85
b. Prakualifikasi (pre-qualification) 89
c. Seleksi (selection) 93
d. Aktifitas Awal Pekerjaan (pre-job activity) 94
e. Pekerjaan Berlangsung (work in progress) 98
f. Evaluasi Akhir (final evaluation) 100
g. Supervision (pengawasan) dan Monitoring dalam 102
aspek Kualitas
h. Supervision (pengawasan) dan Monitoring dalam 103
aspek Administrasi Kontrak
B. TA EXECUTION 127
1. Shutdown execution. 127
a. Shut down unit 128
b. Pemasangan / pelepasan blind 128
c. Pengosongan peralatan unit process 129
2. Decontamination process. 129
3. Release to TA Execution Team 130
4. TA Scope Execution 130
a. Supervision mechanism (mekanisme 131
kepengawasan).
b. Schedule adherence & progress control 132
c. Meeting Map & Report 135
d. Quality Control Execution 135
e. HSE & Security execution 136
f. Change Order (Emergent Order) approval procedure 136
g. Equipment handover to production 137
h. PSSR Execution 138
BAB I
UMUM
Tahap yang diatas adalah standar normal tahapan untuk suatu kegiatan TA. Hal-hal
yang khusus adalah adanya kegiatan kajian engineering yang diperlukan dan
memerlukan waktu relatif lebih lama. Contoh untuk TA Unit RCC, bila akan ada
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 2 dari 153
TURNAROUND
Sub- Set Interval Define and Job WSA Develop Contractor Prework Shutdown PSSR Preliminary
elements Timing Establish Collection (Work network & scoping activity execution execution Report.
optmisa-tion Organiza- –Post TA Scope detail analysis Critical Deconta- Commi- PIR
External tion (TA Report Analysis) schedule Selection Equipment mination sioning (codifying
manage- Team & –Gov. Reg Prepare Critical criteria execution process & Start Up learning)
ment Steering –PM/PdM Job Plan path Contract scenario release Eq and Feed Close out
Planning tool Committee) –Vendor/ ( BOM Non manage- type Facility Supervisi- in report
selection Roles & Liscensor LLD, tools, ment. Tender layout on mecha- (Inspection
(Preparation responsi- –Risk Heavy Eq, Develop process Permitting nism report
& Exec) bilities Asses- supporting detail Develop process Schedule &Post TA
Budgeting Staffing ment Tools) schedule contractor Deconta- adherence report,next
(proposal) schedule –Eqptment TA “work SD & SU. Perfor- mination & Progress TA
TA Master and link to optimisa- grouping” Develop mance prepara- control Planning)
Schedule rest of tion prepara- Start-up criteria & tion Change Schedule
organiza- –Process tion & out process indicator Readiness order next TA
tion Integrity sourcing Develop CSMS(Co Execution, Mgmt MOC as
TA KPIs –MOC schedule Quality ntractor HSE, Execution built
(premise) –Risk Cost Manage- Safety Quality HSSE
Critical Process & Estimation ment . Mgmt etc. Execution.
success Mitigation Budget Develop System) Shut-down Quality
indicators –etc alocation HSE prepara- Control
Final Joblist Procure- Manage- tion. Execution
Preparing ment ment Kick off Handover
BOM LLD Strategy Meeting to line
category Materials with process
Scope arrival Contractor
challenge & scheduling
freeze proc.
A. TUJUAN
Tujuan pemberlakuan pedoman ini dimaksudkan untuk menyamakan pola
fikir dan pengertian, serta merupakan pedoman bertindak dalam hal
pengelolaan TA, agar pengelolaan TA dapat dilakukan dengan efektif,
disamping memudahkan koordinasi mulai dari saat perencanaan,
pelaksanaan dan pembuatan laporan TA (post TA report) sehingga sasaran
TA dapat dicapai secara optimal.
B. RUANG LINGKUP
Pedoman ini merupakan acuan untuk pengelolaan Turnaround di lingkungan
Refining Directorate.
C. PENGERTIAN
1. Turnaround (TA) adalah kegiatan pemeliharaan yang berskala besar
(extraordinary maintenance activities), yang dilakukan secara berkala
(repeated large scale maintenance), dimana pekerjaan dimaksud hanya
dapat dilaksanakan pada saat unit dalam keadaan stop operasi.
2. Pit stop (stop perbaikan kecil) adalah aktifitas pemeliharaan planned
Corrective Maintenance, dimana aktivitas pemeliharaan tersebut
dilakukan pada saat equipment dan unit/plant shutdown secara parsial,
dimana kegiatan tersebut dilaksanakan sebagai kegiatan antara
sebelum dilaksanakan kegiatan TA.
3. Inspeksi peralatan kilang adalah kegiatan pemantauan/pemeriksaan
dan pengujian terhadap kondisi peralatan/instalasi yang dapat dilakukan
pada saat peralatan/instalasi beroperasi dan yang hanya dapat
dilakukan pada saat peralatan/instalasi dalam keadaan stop.
4. Post TA report adalah laporan eksekusi TA yang berisi kondisi
equipment, performance unit operasi setelah dilaksanakan TA, dan
rekomendasi perencanaan dan eksekusi TA serta rekomendasi untuk
eksekusi next TA.
5. Plant test report adalah laporan hasil pengetesan performance plant/unit
proses yang dilakukan sebelum dan setelah eksekusi TA
6. Joblist adalah daftar pekerjaan yang mencakup pemeriksaan &
pengujian, pembersihan (cleaning), pekerjaan modifikasi (plant change),
dan penggantian catalyst, yang mana keseluruhan pekerjaan bertujuan
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 4 dari 153
TURNAROUND
15. Best practice adalah ketentuan yang telah teruji (proven) yang dijadikan
sebagai dasar acuan pertimbangan untuk melakukan kegiatan
pemeliharaan.
16. Statutory adalah kegiatan inspeksi peralatan yang perijinannya
berkaitan/dikeluarkan oleh Depnaker seperti boiler, alat angkat dan lain
lain.
17. Vendor adalah pembuat suatu peralatan yang digunakan untuk
keperluan proses pengolahan (unit proses) di Kilang.
18. Kalibrasi adalah suatu kegiatan untuk memastikan atau menyesuaikan
bahwa penunjukan atau indikasi suatu peralatan telah sesuai dengan
penunjukan peralatan yang sudah distandarisasi.
19. Safety induction adalah kegiatan pemberian penjelasan tentang Health
Safety Environment (HSE) kepada pekerja/mitra yang sedang dan akan
melaksanakan pekerjaan di dalam Kilang.
20. Letter of Credit (L/C) adalah cara pembayaran jual beli barang dan jasa
yang menggunakan jasa perbankan (Opening Bank dan
Corespondence Bank) dengan persyaratan pembayaran yang
disepakati didalam kontrak jual beli.
21. Bill of Material (BOM) adalah daftar kebutuhan material untuk
pelaksanaan suatu pekerjaan pemeliharaan.
22. Preliminery Inspection Report adalah laporan awal pelaksanaan
assessment yang telah dilaksanakan pada saat TA terhadap critical
equipment berdasarkan data hasil pemeriksaan dan rekomendasi yang
telah dilaksanakan serta temuan-temuan dan rekomendasi yang perlu
mendapatkan perhatian dan prioritas dalam pengoperasian unit kilang
setelah eksekusi TA.
23. Post Implemetation Report (PIR) adalah laporan review terhadap
eksekusi TA yang merupakan pembelajaran (lessons learned) TA
mencakup hal-hal yang dianggap prestasi pada kegiatan end to end TA,
dan hal-hal yang perlu diperbaiki untuk TA berikutnya.
24. Total Inciedent Recordable (TIR) adalah jumlah kecelakaan kerja yang
tercatat dalam periode satu tahun
25. Steering Committee adalah Organisasi Komite Pengarah yang
bertanggung jawab memberikan pengarahan dan menetapkan
keputusan strategis dalam setiap kegiatan proses / tahapan TA.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 6 dari 153
TURNAROUND
D. REFERENSI
• STK yang relevan
• Pedoman pelaksanaan pengadaan barang dan jasa SK. No.
075/C0000/2008-S0 tanggal 16 Desember 2008.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 8 dari 153
TURNAROUND
BAB II
PREPARATION PHASE
- Pernyataan dari vendor equipment atas batas waktu akhir toleransi dimana
equipment harus dilakukan pemeriksaan/inspection.
- Konfirmasi kedatangan Long Lead Delivery (LLD) material.
Semua informasi hal tersebut diatas disampaikan pada rapat TA Steering
Commettee dalam bentuk tabel, yang selanjutnya ditetapkannya timing TA.
Untuk pengendalian timing TA maka diperlukan cockpit untuk informasi TA
readiness. TA readiness tersebut terdiri atas :
a. Plant & Equipment readiness.
Yang dimaksud dari Plant dan Equipment Readiness adalah kesiapan
Plant dan Equipment (Mechanical Integrity Aspect) untuk mendukung
tidak ada kendala operasi sampai timing TA yang sudah ditetapkan.
b. Process system readiness.
Yang dimaksud dari Process system readiness adalah kesiapan Plant dari
aspek proses ( end off run catalyst, moulsive, corossion rate, fouling rate ,
operating condition dan lain-lain) untuk mendukung tidak ada kendala
operasi sampai timing TA yang sudah ditetapkan.
c. Preparation readiness.
Yang dimaksud dengan preparation readiness adalah kesiapan TA
ditinjau dari :
- Material.
- Service.
- Equipment , Tools dan Heavy Equipment.
- Procedure termasuk Quality Plan dan Job Safety Analysis.
d. Feed readiness.
Yang dimaksud dari feed readiness adalah pengaturan feed sehingga
ketersediaan feed sampai dengan shutdown.
Status dari feed readiness TA ini disampaikan pada setiap rapat TA
Steering Committee.
# !
%
#
!
"
"
Untuk hal tersebut maka pada phase “scope development “ pekerjaan utama
yang dominan membutuhkan anggaran sudah harus masuk.
Untuk pekerjaan yang repetitif maka diperlukan pengelolaan data base harga.
Pengalaman dari beberapa perusahaan maka penganggaran tahap awal
memiliki nilai akurasi sekitar 70%, dengan demikian diperlukan 30% untuk
contigency plan.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 13 dari 153
TURNAROUND
5. TA master schedule.
Yang dimaksud dengan TA master schedule adalah schedule dari masing-
masing 10 (sepuluh) tahap, mulai dari awal sampai akhir satu siklus proses
TA. Selanjutnya setiap tahap juga memiliki schedule dari setiap sub element.
Kemudian schedule tersebut digunakan sebagai acuan dari TA Steering
Committee dan tim TA untuk melakukan kegiatannya. Master schedule rev-0
sudah dapat didistribusikan kepada TA Steering Committee pada saat T+4
atau paling lambat pada T-21.
Tahap satu proses TA secara umum sudah harus dimulai dari T-21 s/d T-15,
namun bila diperlukan tahapan kajian engineering untuk suatu pekerjaan
tertentu, maka tahap satu sudah harus dimulai T+4.
6. External management.
Yang dimaksud dengan external management adalah kompetensi/keahlian
yang berada diluar perusahaan (Pertamina), umumnya menyangkut Project
Management, yaitu pengelolaan TA (management TA), constructability, baik
secara parsial maupun secara keseluruhan TA tersebut.
Kebutuhan external management ini, bilamana TA yang dikelola relatif besar
dan komplek baik pada tahap preparasi maupun tahap eksekusi, ditetapkan
di RU dalam rapat TA Steering Committee pada tahap awal.
1. Struktur Organisasi.
a. Organisasi TA Steering Committee.
Organisasi TA Steering Committee adalah organisasi yang bertanggung
jawab memberikan pengarahan dan menetapkan keputusan strategis
dalam setiap kegiatan proses/tahapan TA.
Secara umum, organisasi ini sudah harus ditetapkan pada T-21 (21 bulan
sebelum TA), namun bila diperlukan tahapan kajian engineering untuk
suatu pekerjaan tertentu, maka organisasi TA Steering Committee
sudah harus dimulai pada T+4 (empat bulan setelah TA sebelumnya
selesai).
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 14 dari 153
TURNAROUND
Full time
> 50% Full time during
General Manager
preparation phase
&
Senior Manager Operation & Advising relationship
Manufacturing
TA scope challangers
Planning
Section
Head
Owner of Prepare Recom- Prepare Recom- Provide Set Provide Provide Manage
TA and mend Budget mend execution procure- guidance inputs to security
preparation execute scope Prepare scope team ment on HSE product- and PR
and release, f rom quality from members strategy policy ion
execution deconta- process plan mechani- and tools for Provide schedul-
Manage mination, aspect cal f or TA goods specific ing
Roles
T-21 T-12 T-12 T-12 T-12 T-12 T-12 T-12 T-6 T-12
Full time
General Manager > 50% Full time during
& preparation phase
Senior Manager Operation & External
Manufacturing
Advising relationship
Engineer Main
Product- Procure-
Central TA
ion
-ing & MPS Rel ME
ment
HSE RPO G&A ))
contrac-
team Manager Dev. Manager Manager Manager Manager Manager Manager tor
Manager Manager
Manager Manager
scope challangers
TA
Planning
Section
Head
Owner of Prepare Recom- Prepare Recom- Provide Set Provide Provide Manage Provide
TA and mend Budget mend execution procure- guid- inputs security inputs
prepara- execute scope Prepare scope team ment ance on to and PR regard-
tion and release, f rom quality from members strategy HSE product ing
execution deconta- process plan mecha- and tools for policy -ion capabili-
Manage mination, aspect nical for TA goods Provide schedul ties and
Roles
T-21 T-12 T-12 T-12 T-12 T-12 T-12 T-12 T-6 T-12 T-3
b. Organisasi TA Team.
Organisasi TA Team adalah organisasi dibawah kendali organisasi TA
Steering Committee, yang bertanggung jawab melaksanakan keputusan
TA steering committee. Organisasi TA Team ini melakukan kegiatan mulai
dari tahap preparasi, pelaksanaan sampai dengan post TA.
Secara umum, organisasi ini sudah harus ditetapkan pada T-21 (21 bulan
sebelum TA), hal yang sama dengan TA Steering Committee, bila
diperlukan tahapan kajian engineering untuk suatu pekerjaan tertentu,
maka organisasi TA Team juga sudah harus dimulai pada T+4 (empat
bulan setelah TA sebelumnya selesai).
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 16 dari 153
TURNAROUND
Full time
(T-21) > 50% Full time during
Central Steering preparation phase
TA Manager
brick team Committee
Advising relationship
TA
Area Kabag
Kabag
Section Scheduling G&A/
Planing Engineer Maintenance Budget HSE
coordina- forTA
Head TA
for Procure-
Section Area for Section Security
MPS tor complex
TA ment monitoring supervisor
Head Section complex Head &PR
Head complex
Mechanical, Lead
Process Civil Mon &
Planner electrical, &
Engineer- Operations construc- contl mat’l
instrument-
ing tion & service
ation
support
Scope Inspection Provide Provide Perm itting Supervise Provide Manage Manage Budget Conduct Manage
collection work inputs and process Determine scaffol- detailed Schedule procure- planning safety security
Meeting Coordina- supervise inputs spading ding and know- for ment Cost induction/ Coordinate
process tion with mechanical during require- other civil ledge of prepara- activities m onitoring training PR with
owner external , electrical, prepara- ments work com plex tion & Manage Conduct external
Scheduling inspectors and tion Deconta- execution. facility continuous bodies
Roles
T-21 T-6 T-6 T-6 T-6 T-3 T-12 T-10 T-2 T-6 T-2 T-2
Full time
(T-21) > 50% Full time during
Central Steering preparation phase
TA Manager
brick team Committee External
Advising relationship
TA Kabag
Area
Area Kabag
Section Scheduling G&A/
Planing Engineer Maintenance Procure- Budget HSE
Section
coordina-
coordina-
Area
forTA
Head
for TA
for Section Security
MPS tor complex ment monitoring supervisor
Head Sect tor
Head TA
complex Head &PR
complex
(T-12)
Lead
Mechanical,
Process Civil Mon &
Planner electrical, & Contractor
engineer- Operations construc- Contl mat’l
instrument- supervisors
ing tion & service
ation
support
Scope Inspection Provide Provide Permitting Supervise Manage Manage Manage Budget Conduct Manage
collection work inputs and process Determine scaffold- contractor Schedule procure- planning safety security
Meeting Coordina- supervise inputs spading ing and teams for ment Cost induction/ Coordinate
process tion with mechanical during require- other civil preparation activities monitoring training PR with
owner external , electrical, prepara- ments work & Manage Conduct external
inspectors execution.
Roles
T-21 T-6 T-6 T-6 T-6 T-3 T-6 T-10 T-2 T-6 T-2 T-2
4. KPI TA (Premise).
Yang dimaksud dengan pernyataan ”Premise” sehubungan dengan KPI TA
adalah suatu tantangan dari Pimpinan dan Central Committe nya terhadap
hasil TA project (T+4 sampai dengan performance test setelah TA), yang
kemudian menjadi target KPI TA yang dituangkan setiap tahun sesuai dengan
tahapannya.
Untuk melaksanakan hal tersebut diatas maka masing-masing GM RU’s
selaku Pimpinan Steering Committee di Unit memberikan usulan target KPI
TA berkaitan dengan tahapan TA yang akan dilaksanakan RU tersebut pada
tahun anggaran berjalan untuk persetujuan Pimpinan Central Committee.
KPI TA meliputi antara lain :
a. TA Quality :
• Kesesuaian proses preparasi dan eksekusi TA, terhadap proses/
tahapan dalam TA Brick (brick compliance rating).
• Jumlah kejadian kerusakan peralatan kilang akibat ketidaksesuaian
pelaksanaan quality plan dengan eksekusi TA, yang diukur dari
setelah unit beroperasi sampai dengan next TA (TA Impact).
b. Financial :
• Prosentase actual cost vs planned cost/budget (TA cost).
• Prosentase material tidak terpakai vs material yang direncanakan
(exces material).
e. HSE :
• Loss time incident (jumlah jam kerja hilang selama eksekusi TA).
• Total Recorded Incident Rate (TRIR), adalah jumlah insiden yang
terjadi selama eksekusi TA.
f. Operation performance :
• Performance plant test (prosentase perbandingan capacity plant
setelah TA vs sebelum TA).
KPI yang diaplikasikan tersebut diatas adalah KPI lagging yang terdiri dari 3
(tiga) tahap yaitu kinerja untuk preparasi, eksekusi dan start up.
Contoh Premise TA seperti berikut :
TA PREMISE
Contoh kriteria pembuatan KPI TA untuk KLBB tahun 2010 seperti dibawah ini :
TA Manager
TA
Man Reliability
Excess materials % of unused products vs TA Planner +- 5% Post TA report
procured Man Reliability
Scope change % volume change vs plan SMOM +- 5% TA manager receives monthly
before execution TA Manager report
(Preparation)
Operational
Man Reliability
Man Eng & Dev
TA milestones % of milestones TA Manager and Planner 90 % TA planner submits in monthly
achieved completed on time (all) report
TA Execution members
Release and Days vs plan Man Eng & Dev 100% Shutdown report
decontamination Man Production
TA duration Mechanical days vs plan Man Maint Execution 100% Daily execution reports
( execution)
Operational
TA team
Startup Days vs plan until “on Man Eng & Dev 100% Start up reports
spec” Man Production
TA Manager
Scope change % volume change vs plan Man Reliability +-10% Post TA report
during execution Man Production
Man Eng & Dev
Lost time incidents Hours lost during TA execution TA Manager 0 HSE monitors throughout TA
Man Production GM target execution
HSE
C. SCOPE DEVELOPMENT
Tahapan scope development meliputi sub elemen kegiatan Job collection sampai
dengan Identify risk process & mitigation.
Scope development meliputi sub elemen kegiatan sebagai berikut :
• Job Collection
• Scope challenge & freeze process
• Final Joblist
• Preparing BOM LLD material.
• Identify Risk Process & Mitigation.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 22 dari 153
TURNAROUND
1. Job Collection
Job Collection adalah kegiatan untuk mengumpulkan dan membuat lingkup
kerja pekerjaan TA yang meliputi dari hasil identifikasi resiko-resiko aspek
Mechanical Integrity, Process Integrity dan Equipment Optimization.
Masukkan untuk ketiga kelompok tersebut diatas adalah merupakan dari hasil
assessment dan test, juga berdasarkan analisa symptom pada saat unit
beroperasi yang selanjutnya digabungkan terhadap Joblist yang berasal dari
inspection schedule.
Dalam melakukan collection agar dibuat suatu strategi (criteria untuk input
termasuk system dan tools untuk mengelola input), sehingga terhindar dari
kehilangan maupun overlook dari input Joblist TA. Tahap ini dilakukan sebelum
pentahapan seleksi Joblist dengan mengaplikasikan criteria maupun tahap
freezing.
b. Hystorical
1) Mechanical Integrity
Semua catatan (hystorical) kerusakan peralatan yang terjadi sejak TA
terakhir, dimana perbaikannya belum tuntas, baik kerusakan satu kali
maupun berkali-kali.
2) Process Integrity
Semua catatan (hystorical) kegagalan proses operasional yang terjadi
sejak TA terakhir, yang mengakibatkan produk yang dihasilkan tidak
maksimal baik dari segi jumlah dan kualitasnya. Hal ini dapat
disebabkan oleh internal peralatan dan atau katalis, carbon active,
moulsieve dan sejenisnya yang sudah tidak memadai.
Untuk menjadi perhatian :
Pastikan bahwa semua catatan kondisi alat ukur yang terpasang di
peralatan, panel field dan di control room selalu ter-up date dan menjadi
masukan dalam membuat Joblist TA.
3) Lain-lain
a) Equipment optimization
Yang dimaksud dengan equipment optimization adalah optimasi
kinerja peralatan sehubungan dengan energy.
Joblist yang berkaitan dengan equipment optimization antara lain :
kondisi air register, damper, soot blower, burner, steam trace,
insulation yang berkaitan dengan kinerja dapur (furnace) dan
boiler.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 24 dari 153
TURNAROUND
b) Equipment release
Joblist yang berkaitan dengan keperluan equipment release dalam
hal aspek proses safety, antara lain : steaming out, chemical
decontamination.
c) Equipment Maintainability.
Joblist ini berkaitan dengan adanya informasi dari principal perihal
spare part sudah tidak lagi diproduksi (obsolete).
d) Masukan dari fungsi.
Bila ada Joblist yang merupakan masukkan dari fungsi maka
masukkan tersebut dikelola sebagai berikut :
Masukan dari produksi diteruskan ke fungsi engineering untuk
dilakukan kajian, bila diperlukan diteruskan sampai ke fungsi
Refining Technology untuk mendapatkan persetujuan menjadi
Joblist. Hal yang sama berkaitan dengan pemeliharaan maka perlu
diteruskan ke fungsi MPS untuk di justifikasi dan diteruskan ke
fungsi Reliability.
1. Assessment
Assessment adalah kegiatan pemeriksaan peralatan pada saat
equipment dalam keadaan stop. Kegiatan assessment ini dilakukan
berdasarkan :
a) Government regulation
Peraturan dan ketentuan pemerintah yang berkaitan langsung
antara lain adalah:
1) Peraturan Menteri Pertambangan No.06P/0746/M.PE/91
tanggal 1 Nopember 1991 perihal pemeriksaan keselamatan
kerja atas instalasi, peralatan dan teknik yang dipergunakan
dalam Pertambangan Minyak dan Gas Bumi
2) Undang-Undang dan Peraturan Uap tahun 1930.
3) Peraturan Pemerintah No.11 tahun 1979.
Peralatan/installasi tertentu yang dipasang di kilang harus
dilengkapi dengan SKPP dan SKPI yang mana masa berlakunya
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 25 dari 153
TURNAROUND
Penjelasan :
a) Kelompok Mechanical Integrity :
Joblist yang masuk didalam kelompok Mechanical Integrity adalah seluruh
Joblist yang domain tujuan pekerjaan adalah untuk mengetahui dan atau
memperbaiki kondisi peralatan sehingga mechanical integrity equipment
menjadi standard untuk mendukung operational kilang pasca pelaksanaan
TA.
b) Kelompok Process Integrity :
Joblist yang masuk didalam kelompok Process Integrity adalah Joblist
yang domain tujuan pekerjaan untuk mengetahui dan atau memperbaiki
kondisi process operasi kilang yang berkaitan dengan peralatan maupun
catalyst/chemical sehingga kendala process operasi kilang sudah
dieliminasi, sehingga kinerja kilang pasca pelaksanaan TA kembali
optimal.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 27 dari 153
TURNAROUND
2. Critical Joblist
Seluruh Joblist dikumpulkan menjadi satu Joblist TA, tahap selanjutnya
dilakukan pemilahan terhadap Joblist yang tergolong didalam kelompok critical.
4. Final Joblist
a. Tahapan pengesahan Joblist adalah sebagai berikut :
- Semua Joblist, terutama critical Joblist sudah di challenge (tidak
terbatas pada item tetapi juga content dan metodologi cara
penanganan) oleh Facility Engineering dan Process Technology-
Refining Technology yang di kawal oleh Manager Maintenance Control.
- Freezing oleh Steering Committee di RU’s.
- Persetujuan final oleh Central Committee.
Joblist dinyatakan final (revisi 0) bila seluruh Joblist telah melalui rangkaian
proses sampai disetujui oleh Central Committee.
b. Penulisan Joblist
Penulisan Joblist dituliskan secara ringkas agar semua fungsi yang terlibat
dan bertanggung jawab dapat menindak lanjuti. Bila dibutuhkan penjelasan
tambahan dan dokumen-dokumen lain harus dituliskan di dalam lampiran.
Standard format pada lampiran no. 3
Scope development
Scope Detail planning
challenge Contractor management
Work Contract
package package
development development
Process
F G
Job List Cost Budget
estimation allocation
A B C D E
BOM
Work scope Job plan Procurement Material
preparation
analysis development strategy scheduling
& grouping
Catatan :
Untuk scope of repair sudah termasuk di dalamnya seluruh strategi untuk
pelaksanaan repair (termasuk construcability-nya apabila diperlukan).
Scope analysis juga menentukan kebutuhan pelaksana setiap activity sesuai
table dibawah ini :
Kontractor
Konsultan
Perihal
Spesialis
Tertentu
Licensor
Lain-lain
Semua
Manuf.
(OEM)
Kontr.
PTM
Tdk
Ya
Kontractor
Kontractor
Konsultan
Perihal
Spesialis
Tertentu
Licensor
Lain-lain
Semua
Manuf.
(OEM)
Kontr.
PTM
Tdk
Ya
Menentukan Kualifikasi
kontraktor
Kombinasi dari task list dan network planning akan memberikan output :
a. Bill Of Material (BOM).
b. Kebutuhan resources lainnya (manpower, peralatan, tools dan supporting).
c. Schedule.
Untuk melaksanakan detail Joblist/task list maka diperlukan quality plan dan
Job Safety Analysis (JSA).
Penjelasan masing-masing kegiatan sebagai berikut:
a. Detail Joblist/task list
Untuk setiap tag number sudah harus mempunyai detail task list yang
dapat digunakan secara berulang-ulang atau repetitif.
Task list dibuat oleh planner yang mana dalam hal tertentu dibantu oleh
Engineer MPS (rotating engineer, stationary engineer, electrical &
instrument engineer) atau vendor.
Ketika detail task list sudah tersimpan dalam data based, dalam aplikasinya
planner harus mempunyai kompetensi dalam penggunaannya.
Catatan :
Untuk pekerjaan critical yang berkaitan terhadap kehandalan baik dari
aspek mekanikal maupun proses diperlukan :
• Standard task list (termasuk standard inspection)
• Material yang harus ada tanpa menunggu hasil inspection
Contoh :
1. Untuk overhaul recycle compressor dan steam turbine sebagai
penggerak :
- Selain material consumable, rotor dan coupling assy harus
tersedia.
- Untuk steam turbine penggerak recycle compressor selain
consumable, rotor, governor yang sudah dikalibrasi harus
tersedia.
2. Untuk Emergency Shutdown System (ESD) :
Selain pekerjaan kalibrasi dan pengetesan, kualitas insulation
transmiter adalah mandatory untuk dilakukan pemeriksaan, bila
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 39 dari 153
TURNAROUND
Catatan :
Khusus penggantian part yang hampir menyeluruh, maka diperlukan kajian
ke-engineering-an untuk penggantian keseluruhan (total) hal ini untuk
mencegah permasalahan yang tidak terprediksi.
Untuk menentukan strategi pengadaan material kebutuhan TA maka, Bill of
Material dapat dikelompokkan dalam 2 katagori berdasarkan Delivery Time
(DT) pengadaan yaitu:
• Material kategori Long Lead Delivery (LLD).
• Material kategori Non Long Lead Delivery (NLLD).
Perlu dibuatkan strategi pengadaan material tambahan akibat adanya
additional/emergent work.
Material LLD adalah pengadaan material yang memerlukan waktu
pengadaan lebih dari 12 (dua belas) bulan setelah terbit surat pesanan
atau Purchase Order (PO)
Material Non LLD adalah pengadaan material yang memerlukan waktu
pengadaan (delivery time) kurang dari 12 bulan setelah terbit surat
pesanan atau purchase order.
Hal-hal yang perlu di antisipasi agar tidak terkendala pengadaannya yang
menyebabkan waktu pengadaan berkepanjangan antara lain:
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 40 dari 153
TURNAROUND
Job Request
Ya
PTMN bisa
mengerjakan
Sendiri ?
Tidak
Ya
Apakah memerlukan
material spesif ic ?
Tidak
Ya
Ya
Catatan :
Catatan:
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 49 dari 153
TURNAROUND
E. DETAIL SCHEDULING
Detail schedule execution terdiri dari schedule pre execution dan execution yang
dibuat secara terperinci dengan tujuan dapat dijadikan acuan semua fungsi yang
terlibat untuk pengendalian milestone pada jadwal yang terkendali sehingga
execution (shutdown, mechanical work and start-up) dapat dilaksanakan sesuai
jadwal.
Penyusunan detail scheduling preparasi antara lain dibuat berdasarkan :
• Master schedule.
• Timing TA.
• Ruang lingkup pekerjaan.
• Lama proses pengadaan jasa, material dan heavy equipment termasuk proses
administrasi.
• Jadwal kebutuhan jasa (termasuk kajian engineering), material dan heavy
equipment pada saat preparasi atau pra TA.
• Durasi fabrikasi dan pemasangan di lapangan.
Penyusunan detail scheduling execution dibuat berdasarkan:
• Aktivitas TA execution yang terdiri atas aktivitas :
• Shutdown sampai dengan release setiap peralatan/instalasi (termasuk proses
decontamination)
• Aktivitas mechanical
• Aktivitas start-up (termasuk aktivitas PSSR)
• Task list masing-masing aktivitas tersebut diatas
• Durasi masing-masing task
• Sequence dan interdependensi dari setiap task
• Constraint atau obstacle yang ada pada jadwal atau schedule yang tersedia.
Catatan:
Pada prinsipnya detail scheduling mencakup schedule seluruh aktivitas
preparation dan execution yang dibuat secara terperinci sehingga dapat dijadikan
sebagai tools untuk acuan pengendalian terhadap jadwal.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 50 dari 153
TURNAROUND
Detail schedule ini sudah harus tersedia setelah adanya master schedule dan
menjadi lebih lengkap setelah scope development selesai.
Detail Schedule preparasi dibuat dengan tujuan untuk melihat readiness TA dari
waktu ke waktu ditinjau dari sisi kesiapan organisasi, pengadaan material dan
jasa.
c) Planned Progress
Sejalan dengan kebutuhan seperti yang dijelaskan pada point
planned schedule, maka hal yang sama juga dapat dilakukan
terhadap planned progress yaitu :
• Planned progress untuk masing-masing aktivitas untuk tiap
job.no.
• Planned progress untuk semua job.no (overall progress)
• Planned progress untuk suatu peralatan atau pakerjaan
khusus (mis. pekerjaan rigging, inspection dll).
• Planned progress khusus untuk pekerjaan pada jalur kritis
(critical path planned progress).
• Planned progress dari 3 (tiga) bagian besar daerah aktivitas
(group activities) eksekusi TA yaitu:
• Planned progress untuk pembongkaran (dismantling).
• Planned progress untuk kegiatan pembersihan,
pemeriksaan/pengujian
dan perbaikan (cleaning, inspection/ test & repair).
• Planned progress untuk kegiatan pemasangan
(reassembling/ box up).
• Planned progress berdasarkan ruang lingkup tanggung jawab
yaitu:
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 55 dari 153
TURNAROUND
2. Critical path
Critical path execution adalah durasi terpanjang dari rangkaian aktivitas
pekerjaan mechanical yang hanya bisa dikerjakan secara seri sehingga
menjadi penentu mechanical days TA. Bilamana salah satu atau beberapa
aktivitas dari critical path mengalami keterlambatan maka akan berpotensi
penyelesaian TA menjadi mundur. Selanjutnya critical path execution ini
disebut critical path utama namun masih terdapat critical path kedua dan
ketiga.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 56 dari 153
TURNAROUND
Critical path kedua dan ketiga adalah durasi dari rangkaian aktivitas pekerjaan
yang memiliki floating days terkecil terhadap start-up unit secara ber urutan :
Ilustrasi critical path tersebut seperti pada gambar dibawah ini :
Critical path list is made up of a leading critical path and potential critical paths (within 24 and 48
hours of leading critical path). Significant delays in the activities on these potential critical path
might lead to a delay in the TA schedule
<24 hours
<48 hours
3) Review & field inspection terhadap seluruh hasil QC/QA (loop check,
safe guarding test, function check, dan lain lain) instrumentasi sistim
peralatan.
4) Review & field inspection terhadap seluruh hasil QC/QA peralatan
stationary dengan mengecek bolting completeness , bolting tensioness,
gasket, dan lain lain.
5) Review & field inspection terhadap seluruh report de-blind list dan
memastikan bahwa tidak terdapat satupun blind plate yang tertinggal
dan masih terpasang di interconnection system, pipeline flanges, dan
lain lain.
6) Review & field inspection terhadap seluruh fasilitas dan pastikan bahwa
seluruh peralatan, system dan section sudah terintegrasi secara
menyeluruh dan menjadi satu kesatuan unit proses atau unit production.
7) Review & field inspection terhadap “readiness” seluruh individual
equipment, integrated equipment and system dan seluruh interlock &
safe guarding system.
8) Collect & review seluruh dokumen Quality Control & Quality Acceptance
yang telah dilakukan oleh Inspektor, HSE, Process Engineer &
Production.
9) Review start up procedures untuk rotating equipment (Compressor,
Blower, dan lain lain).
10) Review start up procedures untuk fire heater, steam superheater, waste
heat boiler.
11) Review start up procedures untuk pressure vessel (column, stripper,
splitter, dan lain lain).
12) Review drying out & heating up procedures.
13) Review start up procedures unit proses secara individu maupun secara
terintegrasi.
14) Review organisasi start up.
15) Review Personnel In Charge (PIC) dalam start up.
• Motor driver
• Fin fan
Stationary equipment:
• Columns
• Drums
• Vessels
• Regenerators
• Reactors
Piping system
Instrumentation system
• Safe guarding system
• Interlock system
• Local indicator
Dan lain-lain.
2) TKA & TKO/TKI
3) Start Up procedures
4) P & ID for construction
5) Isometric drawing for construction
6) Hammer for hammer test
7) Permanent marker
8) Safety hardness
9) Review & field inspection terhadap seluruh kegiatan MOC “Management
of Change” terhadap setiap peralatan, fasilitas dan system unit operasi
10) Review & field inspection terhadap seluruh kegiatan new installation,
modification.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 63 dari 153
TURNAROUND
b. Commisioning
Commissioning adalah merupakan kegiatan lanjutan dari tahapan
mechanical completion dan PSSR, yang bertujuan untuk meyakinkan
bahwa seluruh equipment, instalasi baik secara individu maupun secara
sistim dapat difungsikan secara baik sesuai dengan peruntukannya (under
suitable service fluid).
Kegiatan pada tahap commissioning mencakup beberapa aktifitas antara
lain:
• Purging line system
• Flushing line system
• Purging equipment system
• Freeing debrace material
• Soda boiling
• Online
Key Success Factors yang harus diperhatikan dalam fase prior to cut in
feed (feed in) dan selama periode feed in (cut in feed) hingga mencapai
kapasitas turn down ratio (TDR) agar dapat berlangsung dengan baik
dan lancar antara lain:
a) Seluruh check list start up dan prior to cut in feed telah di
acknowledge & short sign oleh operator panel DCS.
b) Yakinkan sekali lagi seluruh indikasi parameter operasi atau process
variable telah sesuai dan memenuhi batasan – batasan yang
dipersyaratkan untuk melakukan cut in feed.
c) Setelah di re-check dan di acknowledge oleh panel DCS dan chief
start up & cut in feed baru dilakukan cut in feed.
d) Kordinasi antar PIC (personnel in charge) harus align.
e) Fungsi, lingkup kerja dan tanggung jawab setiap PIC area, section
baik di field maupun Pusat Ruang Pengendali (Central Control
Room) sudah jelas dimengerti dan dipahami oleh setiap PIC.
f) Seluruh parameter kunci (key parameters) sudah diyakinkan dan
diyakini telah sesuai dan memenuhi criteria set point atau batasan-
batasan yang ditentukan dalam SOP, check list, dan operating
manual.
g) Chief start up dan cut in feed harus menguasai seluruh process
variable (limitation, caused and effect), logic process flow diagram.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 66 dari 153
TURNAROUND
h) Chief start up dan cut in feed harus bisa dan dapat memberikan
instruksi operasi secara jelas, mudah dimengerti dan dipahami oleh
sub ordinate (operators atau PIC) sehingga tidak terjadi time delay
berkepanjangan dalam melakukan perubahan kondisi operasi atau
set point.
2) Quality Assesment.
Quality Assesment ditentukan oleh kombinasi dari kualitas standard
assessment (SEIG) yang akan digunakan dan standard kualifikasi
personel yang dipersyaratkan untuk melakukan assessment.
3) Material Quality.
Material quality ditentukan oleh kesesuaian spesifikasi material pada
saat design, yang selanjutnya ditentukan oleh konsistensi aplikasi atau
penggunaan spesifikasi tersebut dimulai dari awal permintan (BOM),
pemesanan sampai dengan penerimaan, kecuali pada rekomendasi
dinyatakan adanya perubahan.
Tahapan pengendalian kualitas material adalah sebagai berikut:
• TA Planner membuat BOM di MySAP per Tag No. (Line No. untuk
piping system, cable no. untuk cable electrical dan instrument).
• Selanjutnya BOM yang sudah di key in, di print out (sesuai dengan
field yang di request) dan dikirim ke Engineer MPS untuk
pemeriksaan item, spesifikasi, dan quantity untuk persetujuan
proses lanjut.
• Update final BOM ke MySAP oleh Planner (jika update item dan
jumlah dilakukan di RU’s, update spesifikasi di MDM-CSS).
• Selanjutnya final BOM dikirim ke Procurement (Inventory Control)
untuk dilakukan pemeriksaan stock dan pembuatan PR untuk
proses pengadaan.
• Engineer MPS bertanggung jawab atas kebenaran spesifikasi
BOM yang akan dilelang.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 68 dari 153
TURNAROUND
7) Quality readiness
Adalah kesiapan penanganan quality dari end to end process. Untuk
setiap tahapan telah memiliki format standard quality plan,
persyaratan kualifikasi dari personil dan personil (knowledge &
experience) yang akan melaksanakan pengendalian kualitas.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 69 dari 153
TURNAROUND
a) Risk Assessment
Adalah kegiatan yang melakukan analisa sistematik dan terstruktur
tentang hazard suatu pekerjaan dengan tujuan memitigasi bahaya
tersebut dengan cara dan metodologi yang tepat. Kegiatan risk
assessment tersebut dilaksanakan harus oleh personil yang memiliki
knowledge dan experience dalam hal tersebut. Tahapan risk
assessment tersebut adalah sebagai berikut:
• Pengidentifikasian hazard berdasarkan Joblist
• Penilaian hazard
• Pengendalian sumber hazard/mitigasi
g) Release Equipment
Pada tahap ini kegiatan yang dilakukan adalah penyerahan
peralatan/instalasi dari pihak Produksi ke pihak Maintenance Execution
untuk dimulainya kegiatan terhadap equipment tersebut.
Sehubungan dengan hal tersebut maka untuk pengendalian safety
diperlukan dokumen release equipment sesuai format yang sudah ada.
Dokumen ini akan dipakai sebagai alat untuk memastikan bahwa
peralatan yang akan diserahkan oleh Fungsi Production ke Fungsi
Maintenance Execution dalam kondisi aman dan siap untuk dikerjakan.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 72 dari 153
TURNAROUND
i) PSSR
Penjelasan detil PSSR seperti pada Bab II.E.5.a.
j) PIR TA
Penjelasan detil Post Implemetation Review (PIR) TA seperti pada Bab
IV.A.2.
F. CONTRACTOR MANAGEMENT
Yang dimaksud dengan contractor management adalah manajemen dalam
melaksanakan pemilihan kontraktor, berdasarkan atas ruang lingkup pekerjaan
yang akan dikontrakkan, dimana didalam ruang lingkup pekerjaan ditetapkan
semua kompetensi yang dipersyaratkan.
Secara umum kompetensi yang dibutuhkan adalah:
• Memiliki pengalaman mengelola pekerjaan yang relatif besar, kompleks dengan
waktu pelaksanaan yang singkat (project management).
• Memiliki sumberdaya tenaga trampil (skill labor) baik organik maupun
outsourcing, termasuk supervisor.
• Memiliki basic tools dan peralatan safety dengan jumlah yang cukup untuk
melaksanakan pekerjaan.
• Memiliki safety procedure dan safety officer.
• Memiliki kemampuan financial yang memadai.
Contoh:
Untuk pekerjaan overhaul turbo machinery, service DCS, PLC, UPS, inspection
CFE-Packinox di Platformer dan Refractory.
• Memiliki tools spesifik (bolt tensioner, flange refacing, wash water jet) dan
heavy equipment (crane, lowbed, forklift) dan rigging tools.
Disamping itu masih ada jenis pekerjaan lain yaitu pekerjaan spesifik.
1. Contractor scoping analysis.
a. Strategi pembuatan kontrak TA
Strategi kontrak dibuat berdasarkan proses bisnis sebagai berikut :
Identifikasi
Develop
Task, Tools Work Scope Procurement Contractor Contractor
Job List Contractor
& Material Analysis Strategy Selection Performance
Scope
Required
Contoh :
a) Construtcability :
Kajian ke-engineeringan, untuk membuat “window patch” FCCU
pada saat penggantian air grid dan penggantian skirt dome
regenerator RCC Balongan).
b) Inspection proprietary equipment :
Membuat inspection task dan methode assessment untuk
peralatan DCS, UPS, tube reformer ,tube hanger , high temp
expansion bellow joint (EBJ) ,CCI Drug, CFE Packinox/BLC.
c) Consultant Software Planning :
Membuat aplikasi software planning & scheduling untuk
monitoring kegiatan TA.
d) Define rigging plan :
Menentukan methode rigging (termasuk equipmentnya) untuk
pekerjaan yang kompleksitasnya tinggi (berat dan tidak simetris,
space terbatas), contohnya seperti catalyst cooler RCC
Balongan, vertical combined feed di platformer dan lain-lain.
e) Define kebutuhan heavy equipment dan special tools.
Pekerjaan yang membutuhkan special tools misalnya bolt
tensioner, refacing, wash water jet, dan lain-lain.
% Jumlah
No Jenis Pekerjaan Keterangan
Pekerjaan
HE, Column, Vessel dan
1 Cleaning & Inspection 60
Drum
PSV, instrumentasi &
2 Sertification & Recalibration. 30
elektrikal
3 Repair/replacement. 10 Termasuk overhaul
• Besar dan tingkat kompleksitas dari Joblist (TA untuk satu unit
produksi berbeda dengan TA untuk beberapa unit produksi).
• Ketersediaan kontraktor di Indonesia.
• Area geografis (TA di RU VII penanganannya berbeda dengan
TA di RU VI).
• Peraturan Daerah (otonomi daerah).
Dari pertimbangan tersebut diatas maka scope kontrak dikelompokan
menjadi :
• Kontrak dengan Main contractor (untuk semua area).
• Kontrak vendor specialist untuk quality control pekerjaan
perbaikan.
• Kontrak berdasarkan skill group (mekanikal, instumen, listrik).
• Kontrak berdasarkan specific skill.
TA Overall
MAIN (1 contractor)
CONTRACTOR
BRUSH
SCAFFOLDING
PJIT
REACTOR & VESSEL &
HE & FIN FAN FURNACE PIPING RIGGING
REGENERATOR COLUMN
Can the RU
manage the No
task with
better quality
and schedule
management? Combination of these
3 contractor strategies
Yes Outsource can be deployed in a
specific skill single turnaround
type
2) Contractor selection.
a) Berdasarkan ketersediaan sumbernya :
i. Multi sources, untuk pekerjaan yang umum
ii. Limited sources, untuk pekerjaan dengan kompetensi
khusus
iii. Single source, untuk pekerjaan yang dilakukan oleh vendor
a) Kelompok fabrikator.
Pekerjaan dikerjakan di
Safety NA
luar Pertamina.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 81 dari 153
TURNAROUND
Kemampuan teknis
(a) Kemampuan
Mempunayi Engineer yang
organizing untuk
kompeten di bidangnya
mencapai :
Load pekerjaan di workshop
- Quality
Mampu membuat jadwal yang
sesuai.
- Durasi
Untuk calon pemenang
Mempunyai man power organik
(b) Resources harus di-validasi.
untuk kompetensi tertentu.
Kemampuan financial NA
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 82 dari 153
TURNAROUND
Kriteria untuk hal tersebut di atas terdiri dari kriteria umum (progres harian,
safety record, man power record) dan kritria khusus yang spesifik sesuai
dengan jenis pekerjaannya. Umumnya tujuan criteria spesifik sudah menjadi
bagian dari article “ criteria acceptance “ di dalam dokumen kontrak Surat
Perjanjian Borongan (SPB).
Berdasarkan list pekerjaan TA yang umum dilaksanakan, maka kriteria khusus
yang dapat dipakai adalah sebagai berikut :
Indicator Performance
No Pekerjaan TA
Quality Durasi
Pekerjaan Pengelasan Maks. 5 % reject Jumlah joint yg
01 khusus/spesifik diselesaikan sesuai
dg schedule
Pekerjaan Water Jet Rework maks. 10 % Sesuai target per
02 Cleaning equipment dan tidak
menyebabkan delay.
Indicator Performance
No Pekerjaan TA
Quality Durasi
Pekerjaan Refacing Kerataan dan kekasaran Sesuai dengan
09 sesuai dengan standard. target.
3) Contract Type.
Yang dimaksud dengan contract type adalah jenis kontrak yang digunakan
untuk melaksanakan pengadaan jasa untuk pekerjaan TA.
Ada berbagai jenis kontrak yang ada di dunia konstruksi tetapi berdasarkan
SK Direksi SK-075/C00000/2008, Pedoman pengadaan barang dan jasa No.
A-001/I10100/2008-S0 yaitu : Fixed lump sum contract, kontrak harga satuan
(fixed unit price contract), kontrak terima jadi (turn key contract), kontrak
pengadaan bersama (sharing contract), kontrak presentase (success fee).
Berdasarkan jenis pekerjaan yang ada di TA maka jenis kontrak yang dapat
diaplikasikan adalah kontrak harga satuan, fixed lump sum contract dan time
sheet.
4. Proses tender.
Yang dimaksud dengan proses tender adalah bagaimana menentukan
metode pemilihan penyedia barang dan jasa. Proses pemilihan penyedia
barang dan jasa tersebut sesuai dengan SK Direksi SK-075/C00000/2008
adalah: pelelangan, pemilihan langsung, penunjukan langsung dan cash &
carry
Menentukan
persyaratan
Mengidentif ikasi
Risiko & mengisi
f ormulir
Pengesahan
Formulir oleh
Tim CSMS
Menentukan
persyaratan
Tidak
Tidak
Ya
Persetujuan
Disetujui ?
Tim CSMS
Tidak
Disetujui TA
Manager ?
Ya
Kirim ke Contract
Of f ice
2) Tugas dan tanggung jawab dalam penilaian resiko HSE (roles and
responsibilities).
Kontraktor KKS/JOB
migas Internasional
migas di Indonesia
Internasional
Indonesia
Tidak ada
dampak Tidak ada Tidak ada Tidak ada
0 kerusakan
kesehatan/k dampak pengaruh
ecelakaan
Kelola perbaikan secara
Dampak
kesehatan Dampak Kerusakan Pengaruh
terus menerus
1 (R)
kecelakaan tidak penting sangat kecil kecil
sangat kecil
Dampak
Dampak
kesehatan/ Kerusakan Pengaruh
2 kurang
kecelakaan kecil terbatas
penting
kecil
Dampak
Dampak Pengaruh
3
kesehatan/
cukup
Kerusakany
Yang cukup Gabungan tindakan
kecelakaan ang terbatas pengurangan risiko
penting luas
utama
(S)
Fatalitas Dampak Kerusakan Pengaruh
4
tunggal penting utama nasional
Tidak dapat
ditolerir
Dampak Pengaruh
(T)
Fatalitas Kerusakan
5 penting dan Interna-
ganda yang luas
besar sional
b. Prakualifikasi (pre-qualification).
1) Kegiatan pra kualifikasi yang dimaksud adalah melakukan kajian
terhadap dokumen administrasi yang menyangkut pengelolaan
HSE oleh kontraktor, termasuk kemampuan teknis dan finansial.
a) Bila main kontraktor memiliki sub kontraktor, maka kajian
harus difokuskan pada sub kontraktornya.
b) Untuk mendapatkan input dari para kontraktor digunakan
kuisioner yang menyangkut hal-hal sebagai berikut :
• Leadership and commitment
• Policy and strategic objectives
• Organization, responsibility, resources, standards and
documentation
• Hazards and effect management
• Planning and procedures
• Implementation and performance monitoring
• Audit and review
• Emergency response procedure
• HSE Management – additional features
2) Evaluasi sistim pengelolaan HSE kontraktor terdiri dari :
• 9 sections
• 9 sections tersebut terdiri dari 26 categories
• 9 sections dan 26 categories tersebut dinilai dalam 4
levels of performance
(Aplikasi sistim evaluasi tersebut sesuai lampiran 5).
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 90 dari 153
TURNAROUND
Tidak
Tinggi ?
Ya
Ya Ya
Penerimaan
bersyarat
Memasukan Calon
dalam daftar
penawar
5) Tugas & tanggung jawab pada saat pra-kualifikasi HSE (roles &
responsibilities)
PRE- Respective
Tim CSMS Contract
QUALIFI- HSE Sr. Manager Contractor
Pertamina Office
CATION Contractor
Prepares Helps to Determines Responds to Prepares pre-
contract HSE provide HSE the necessity question- qualification
requirements requirements of continuing naires and package for
for inclusion for the with the provides work classifi-
into the bid contract, prequalificatio HSEMS ed as high
documentation provides help n process information. risk:
. to contractors when no
Provides Instructions
to understand candidates
Ensure that the clarifications, to Bidders
the pre- meet the
HSE document if requested. Questionn
qualification minimum
for Pre- aire
questionnaires, HSE scores.
Qualification is Evaluation
and successful
evaluated by criteria
criteria to meet
HSE team Checks
Company HSE
dept. contractor
requirements
d.base during
the evaluation
process.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 92 dari 153
TURNAROUND
PRE- Respective
Tim CSMS Contract
QUALIFI- HSE Sr. Manager Contractor
Pertamina Office
CATION Contractor
Participation Conducts Monitors site Obliged to Develops
and team-up in inspection verification undergo HSE bidder list
the HSE activities and activities. site based on the
evaluation inputs the verification. pre-
team is highly results into the qualification
recommended C-HSE MS d- Ensure the results.
to embrace an base. prequalificatio
ownership and n evaluation is
If necessary,
quality of conducted In a Ensures all
conducts site
evaluation. properly pre-
verification
manner, with a qualification
activities,
high quality evaluation
provides HSE
Ensure the and integrity to results are
assurance,
prequalification company, well
produces the
evaluation is fairness and documented
necessary
conducted In a meet w/ and easy to
recommendatio
properly ethical locate.
ns and
manner, with a conduct.
monitors Provides
high quality
follow-ups of feedback to
and integrity to
the contractors
company,
recommendatio that fail the
fairness and
ns. pre-
meet w/ ethical
qualification.
conduct.
Prepares
contract HSE
requirements
for inclusion
into the bid
documentation
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 93 dari 153
TURNAROUND
c. Seleksi (selection)
Yang dimaksud dengan seleksi (selection) adalah prosedur untuk
memilih kontraktor terbaik di antara mereka yang mengikuti
tender/lelang, dimana proses yang dilakukan adalah sebagai berikut :
A
Menyusun Dokumen
Penawaran
Mengadakan Pengumuman public
(Jika diperlukan)
B
Pertemuan Pra-Lelang
Departemen Pemrakarsa Pelayanan Kontrak Stakeholder Kunci Lainnya
Evakuasi Peninjauan
Kemampuan saat ini dan B
pelaksanaan K3LL masa
Menbagikan Undangan
lalu dalam Proposal lelang. Bagi Penawar
Menyusun penjelasan
Penawar dan menjawab Mengkoordinasi Rapat Penawar Menyusun Penawaran
Pemberian Kontrak Pertanyaan penawar Klarifikasi Penawaran (Proporsi menawarkan harga)
yang diperlukan
Mengadakan Rapat Klarifikasi
Penawaran
HSE KONTRAKTOR Mengadakan evaluasi Non
Melaksanakan evaluasi Teknis
dan keselamatan teknis (komersial)
1) Pra-mobilisasi
Selama pra-mobilisasi, semua aspek yang mempunyai relevansi
dengan penilaian risiko kontrak dan aspek HSE lainnya
dikomunikasikan agar dipahami oleh semua pihak sebelum
pelaksanaan kontrak dimulai. Yang termasuk dalam kegiatan-
kegiatan ini adalah rapat awal, pemeriksaan, audit, orientasi
lapangan dan rapat persiapan HSE. Topik-topik yang dibahas
selama kegiatan ini adalah:
• Diskusi rencana kerja
• Peninjauan semua bahaya yang potensial dan masalah HSE,
• Memeriksa kesiapan dari semua perlengkapan, peralatan dan
APD yang dibutuhkan
• menyiapkan prosedur tanggap darurat dan lain sebagainya.
Plan TA dengan HSE melakukan pemeriksaan/audit, dengan
menggunakan prosedur audit pra pekerjaan yang telah tersedia.
2) Rapat awal
Rapat Awal dipimpin oleh Pemrakarsa pekerjaan segera setelah
persetujuan kontrak dan sebelum pelaksanaan pekerjaan. Rapat
awal dilakukan untuk memberikan kesempatan bagi kontraktor
agar terbiasa dengan lokasi kerja perusahaan, fasilitas, personil
yang berhubungan dengan pekerjaan, dan informasi kerja lainnya.
Rapat ini harus diikuti oleh semua pihak yang terlibat didalam
pekerjaan, termasuk personil kontraktor yang berkompeten dan
para subkontraktornya.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 95 dari 153
TURNAROUND
Jika mobilisasi dilakukan secara lokal pada area kerja yang sama,
rapat awal dapat diadakan secara lokal, baik pada kantor
perusahaan atau pada kantor kontraktor setempat. Tetapi jika
mobilisasi harus di lakukan dari area yang berbeda, maka rapat
awal harus dilakukan pada kantor pusat Perusahaan atau
Kontraktor. Planer TA akan menentukan tempat dan waktu untuk
rapat awal ini.
Topik-topik dalam rapat awal mencakup:
• Pembahasan terhadap potensi-potensi bahaya berisiko tinggi
yang terkait,
• Kepastian Rencana HSE yang akan diimplementasikan
termasuk konfirmasi bahwa peran tugas dan tanggung jawab
telah diuraikan dan dipahami dengan jelas,
• Konfirmasi kompetensi pekerja perusahaan dan Kontraktor
yang terpapar bahaya di tempat kerja, seperti yang di
jelaskan pada fase uraian pekerjaan dan penilaian risiko,
• Konfirmasi tujuan dan sasaran pelaksanaan HSE,
• Distribusi dan penjelasan pernyataan kebijakan HSE, aturan
dasar HSE dan prosedur kerja,
• Konfirmasi dari ruang lingkup dan jadwal kegiatan HSE,
misalnya rapat HSE, audit, inspeksi dan peninjauan. Jumlah /
frekuensi inspeksi HSE akan disetujui sebelumnya dan
dicatat dalam sistem data base.
• Konfirmasi tersedianya prosedur tanggap darurat kontraktor
dan interaksi antara rencana tanggap darurat kedua belah
pihak.
• Penjelasan ketentuan-ketentuan HSE pada sub-kontraktor
termasuk : Safety Talk, Tool Box Meeting, Safety Inspection
dan lain – lain.
• Prosedur pelaporan dan penyelidikan kecelakaan.
Rapat juga dapat dimanfaatkan untuk menjelaskan atau
membicarakan masalah HSE yang baru muncul dan belum
tercantum dalam dokumen kontrak.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 96 dari 153
TURNAROUND
4) Pelatihan HSE
Kontraktor bertanggung jawab atas pelatihan dan persiapan
pegawainya pada semua potensi bahaya dan masalah yang
berkaitan dengan pekerjaan. Perusahaan bertanggung-jawab
untuk memeriksa apakah pelatihan telah dilakukan dan
didokumentasikan dengan baik. Metode untuk memastikan
pemahaman terhadap bahan-bahan pelatihan, dapat dilakukan
melalui pengujian tertulis atau lisan, demonstrasi, evaluasi
pekerjaan. Pelatihan dan persiapan lanjutan dapat dilakukan jika
pengetahuan yang ditampilkan masih di bawah harapan.
5) Mobilisasi
Selama fase mobilisasi, Rencana HSE harus dikomunikasikan ke
semua personil perusahan dan kontraktor yang terkait. Beberapa
kegiatan dasar dalam fase ini antara lain:
- Rapat awal lokal,
- Mobilisasi staf dan perlengkapan kontraktor,
- Finalisasi Rencana HSE kontraktor,
- Mengadakan audit mobilisasi.
Selama mobilisasi, perusahaan dan kontraktor menjamin bahwa
masing-masing pihak menetapkan metode operasi yang sesuai
dengan rencana HSE yang telah disetujui. Pada fase inilah
implementasi dari Rencana HSE kontraktor secara formal dimulai.
Staf pengawas tambahan dari kontraktor mungkin dibutuhkan
untuk mempercepat penetapan dan penerapan Rencana HSE.
Selama fase awal mobilisasi, semua personil kunci yang
ditugaskan untuk pekerjaan tersebut harus menghadiri program
orientasi HSE yang digunakan untuk mengkomunikasikan
Rencana HSE dan aspek-aspek HSE lainnya yang penting dalam
kontrak.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 97 dari 153
TURNAROUND
Pemberian Kontrak
Tidak
Selesai ?
Ya
Mobilisasi
Mengkomunikasikan
rencana HSE, Audit,
Menyelesaikan masalah
HSE
Pelaksanaan Kontrak
Kunjungan
Planer TA & HSE
Perubahan Ya
Lingkup Kerja,
Bahaya lain
Tidak
Evaluasi sementara :
Daf tar pemeriksaan Audit,
Daf tar Program
Tindakan
Perbaikan yang
dilakukan
Ya
Tidak
Tidak
Pekerjaan
Selesai ?
Ya Tindakan
Evaluasi Akhir
Kedisiplinan
Memperoleh persetujuan
Manager TA
6) Intervention Activities
Sesuai Kontrak bila terjadi ketidak sesuaian pelaksanaan
pekerjaan yang berpotensi terjadinya keterlambatan pelaksanaan
dan tidak terpenuhinya kualitas pekerjaan maka Pengawas
Pekerjaan Pertamina berhak melakukan segala upaya
(penggantian/ penambahan manpower, tools/equipments) hingga
pengalihan scope pekerjaan sebagian maupun keseluruhan pada
perusahaan pelaksana pekerjaan lain.
h. Supervision (pengawasan) dan Monitoring dalam aspek
Administrasi Kontrak (Quality) yang dilakukan adalah memastikan
bahwa :
Semua dokumen yang harus disupply oleh Kontraktor harus sesuai
dengan yang tertuang dalam Kontrak, dimana dokumen dimaksud
adalah:
1) Sebelum Pelaksanaan Pekerjaan.
Dokumen yang harus diterima sebelum pelaksanaan
pekerjaan adalah :
• Quality Plan yang sudah disetujui dan ditandatangani
(diapproved) oleh Pertamina.
• Schedule Eksekusi harus sudah disetujui dan ditandatangani
(diapproved) oleh Pertamina.
• Dokumen Manpower yang akan masuk Kilang (ID Card). Sudah
• Harus sesuai dan diterima Pertamina sebelum pelaksanaan
pekerjaan.
• Dokumen Kendaraan untuk Mobilisasi.
BAB III
EXECUTION PHASE
A. PRE EXECUTION
Yang dimaksud dengan tahapan pre execution adalah tahapan preparasi termasuk
kegiatan yang dapat dilakukan sebelum eksekusi TA, agar kegiatan eksekusi
dapat dimulai dan diselesaikan sesuai dengan schedule yang sudah ditetapkan
menjadi acuan
Kegiatan pre execution yang meliputi kegiatan sbb :
• Prework activity
• Critical equipment execution scenario
• Facility layout
• Permitting process
• Decontamination preparation
• Readiness Execution, HSE, Quality (Mechanism implement JSA & quality
plan)
• Shut-down preparation.
• Kick off meeting with contractor
Kegiatan tersebut diatas dari sisi TA readiness dapat ditinjau dari 5 (lima) sisi
yaitu:
• Process
• People
• Material
• Equipment
• Facilities
b. Execution phase
Procedure yang sudah harus tersedia meliputi :
1) Job Safety Analysis (JSA)
Tujuan JSA dibuat adalah agar pada peralatan yang akan diperbaiki
ter indentifikasi hazard yang ada serta penanganannya sehingga
peralatan dalam kondisi aman untuk dikerjakan.
JSA dibuat oleh Maintenance Execution Area sebagai lead, dan di
support oleh Produksi, HSE dan MPS.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 107 dari 153
TURNAROUND
1 Preparation
Install Scaffolding. Falling from height Use full body harness
Setting Equipments (vacuum, pump, hose). Raining Set canvas in work area
Lifting, using crane Falling items from lifting attempt Ensure that the knot is correct and safe
2 Reactor Cooling
Install Nitrogen Connector Hose to Reactor Nozzle Nitrogen leak Ensure worker is in the right position
Filling Nitrogen into Reactor. Nitrogen leak Ensure worker is in the right position
3 Release Manhole, Nozzle, Spool Piece, and Blind Flange.
Release Bolt using Hydratight / Wrench Flash due to Hydrocarbon leftover released to air Use chemical mask and prepare APAR.
Release Manhole, Nozzle, Spool Piece, and Blind Flange. Hydratight & Blower air-hose leak . Ensure that there's no leakage in Hydratight and Blower.
Lifting using crane Hit by loose Hydratight compressor hose Ensure worker is in the right position
Falling items from lifting attempt Ensure that the knot is correct and safe
4 Unloading Catalyst and Reactor Entry.
Open Chimney and Tray. Hydrocarbon gas residue. Run Gas Test for Hydrocarbon and Oksigen
Unloading Catalyst. Lack of Oxygen. Conduct purging, using Chemical Mask.
Install lighting inside Reactor Catalyst dust. Use Breathing Apparatus or Air Line Compressor unit.
Install Scaffolding. Irritated eyes and respiratory problem Use Goggles and Breathing Apparatus.
Neutralizing with Ash Soda. Electrical shock use lighting < 50 Volt DC
Cleaning Reactor Walls Noise inside reactor due to activities conducted by Snapper Machine Use Ear Plug / Ear Muff.
Check Walls and Accessories of Reactor Standby officer near manhole
Install Blower. Use communication equipment
Isolate cable connectors well
5 Repair with welding.
Grinding Fire due to welding Run gas test for Hydrocarbon and Oksigen
Welding Lack of Oxygen Conduct purging and prepare APAR.
Checking welding result Leakage in Pneumatic Tool. Use Breathing Apparatus.
Testing Prepare APAR.
Repairing/Replacing Thermowell. Standby officer near manhole
6 Loading Catalyst..
Install Chimney and Tray. Catalyst dust. Run gas test for Hydrocarbon and Oksigen
Loading Catalyst , and leveling Lack of Oxygen Use Chemical Mask and Breathing Apparatus.
Install Nozzles. Standby officer near manhole
7 Box Up
Installing Top Manhole. Stuck, hit, during bolt installation Install bolt correctly and safely
Tying bolt Falling equipment Ensure that the knot is correct and safe
Place equipments on the right place
2) Permit To Work
Dalam hal work permit mengikuti TKO yang berlaku di masing-
masing RU, dimana harus jelas tanggung jawab masing-masing dari :
• Pejabat yang berwenang untuk menyetujui permit
• Fungsi yang melaksanakan pekerjaan
• Fungsi yang melakukan observer
Sehubungan dengan release equipment maka harus diyakini tidak
adanya sisa material hazard. Untuk hal tersebut maka perlu dibuat
matrik yang memperlihatkan hubungan antara equipment release
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 108 dari 153
TURNAROUND
To prepare the equipment and properly tick the To clearly understand the conditions of the Whether the exact location of area/unit and
checklist items equipment and residual hazards equipment has been mentioned clearly
To identify and indicate any residual hazard to To discuss the above with issuing authority and Detail description of work is properly written
release equipment decide upon the protective measures Fire station has been informed and properly
To advise on protective measures and mention To describe the job and associated hazards to ticked
To carry out gas test wherever required and the workmen Permit issued to which Dept., Div.,Section and
enter the result with sign, date and time To ensure that safe procedure of execution are Craft - all mentioned
To discuss and explain with/to executing being followed Equipment preparation - Equipment has been
authority To check all the hand tools/devices/ equipment properly prepared, all checklist items area
Carry out electrical isolation whenever required and ensure that they are healthy properly checked & ticked
Close the permit when the job is complete or end To make the permit available at work site all the Residual Hazards - Identified and
of permit duration, which one is earlier time ticked/indicated
To preserve the permit for next one month To close the permit when the job is over or at the Protective Measures- Requirements identified
end of permit duration, which one is earlier and properly marked
To preserve the closed permit for next Other details - like provision of continuous
one month ventilation, additional precautions
Gas test
Test for all probable gases carried out
and reading recorded with sign., date and time
etc
Frequency of rechecking identified and carried
out
Electrical isolation was reqd., carried out and
documented
Both issuing and executing authority
signed mentioning name and signature, date and
time
Permit has been closed by both issuing
and executing authority with date and time
Closed permits has been kept properly filed and
being preserved for next one month
Gambar 21. Contoh work permitting prochedure & plan (roles & responsibilities)
Gambar 22. Contoh work permitting prochedure & plan (protective measures to be
ensured for residual hazardous before equipment handover)
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 109 dari 153
TURNAROUND
SECTION 1 : EQUIPMENT
Work Location
Work Description
Work Executer
SECTION 2 : Safety requirements SECTION 3 : Pelampiran surat izin & dokumen lain
Safety Check List ( Filled by GSI ) Yes No Permit Letter Attachment Yes No
A. Hereby state the equipments already Hereby state the equipments already
1 Freed from pressure 1 Permit to enter confined/closed space
2 Drained 2 Permit to enter restricted area
3 Isolated by : Blank 3 Permit to block/closed the road
Released 4 Permit to operate heavy equipment
Locked valve 5 Permit to use fire hydrant
Labeled 6 Permit for electrical / Instrument
7 Permit for radiation work
Gambar 23. Contoh work permitting prochedure & plan (equipment release
prochedure, section1: equipment)
10 ……………………….
SPECIAL INSTRUCTION :
APD required
Safety helmet Dust / Chemical Mask Safety glasses Safety suit / Appron
Gloves Face protection Respiration support Full Body Harness
Safety shoes Ear protection Chemical Suit …………………………….
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 110 dari 153
TURNAROUND
Gambar 24. Contoh work permitting prochedure & plan (equipment release
prochedure, section2: safety requirements; section 3: pelampiran surat
ijin/dokumen
SECTION 4 : AUTHORIZATION
I personally already checked the location and condition. Permission to guarantee the start of hot work
Authorized Operational Personnel ( GSI Authority )
Name: Signature: Date: Time:
All equipment and machines already checked, safe to use in work location.
Authorized Technical Personnel ( Authorized Engineer )
Name: Signature: Date: Time:
The work already completed, all material and equipment ready to operate with safe and clean condition
Not completed and the condition as follow…………………………………………………
SECTION 6 : GSI
I already check the equipment, material and work place and agree with the condition.
DISTRIBUSI : White original - Project Supervisor Yellow - Operational personnel / GSI Green - Technical expert Red - K3LL
Gambar 25. Contoh work permitting prochedure & plan (equipment release
prochedure, section4: authorization)
3) Execution Readiness
Pada tahap ini dilakukan kajian atas kesiapan untuk semua joblist
untuk eksekusi ditinjau dari :
b) Material
c) Kontrak
d) People
• Pekerja Pertamina (Produksi, ME, MPS, Eng & Dev, HSE,
Rel)
Perihal Kondisi readiness yang dimaksud
Joblist Memahami semua aktifitas dalam
joblist
Basic Safety Memahami untuk melaksanakan
prosedur safety
Risk & Hazard Memahami bahaya dan resiko yang
ada pada joblist dan mampu
mengikuti langkah mitigasi yang
sudah ditetapkan
Role & Responsibility Memahami tugas dan tanggung jawab
dan dapat melaksanakannya
Quality Plan Memahami quality plan dan dapat
melaksanakannya
PSSR Memahami PSSR dan dapat
melaksanakan
e) Equipment
f) Facilities
4) HSE Readiness
5) Quality readiness
c. Start-up phase
Procedure yang sudah harus tersedia meliputi:
1) Box-up
Dalam hal melaksanakan box-up maka dokumen acceptance sudah
di terima oleh fungsi yang berwenang (Engineer MPS), dan
selanjutnya pada format box-up di tanda tangani untuk release
equipment untuk box-up.
Note :
For application in RU’s , name
of the approver and executer
needs to be mentioned
4) Start-up
b. Pekerja kontraktor
1) Alokasi pekerjaan kontraktor dan rencana kerja.
Bahwa pada tahap ini setiap kontraktor sudah harus jelas area kerja
yang menjadi tanggung jawabnya dan rencana kerjanya pun sudah
dibahas bersama pihak Pertamina yang kemudian menjadi acuan
pada saat eksekusi. Hal-hal yang penting dijelaskan dalam kick of
meeting. Success factor dari setiap pekerjaan kontrak harus
teridentifikasi dari sejak awal dan menjadi bagian yang dimonitor
secara terus menerus sampai dengan pekerjaan dinyatakan selesai.
2) Manajemen kinerja kontraktor
Bahwa pada tahap ini Pertamina harus mendapatkan indicator kinerja
dari kontraktor yang menjadi item pantau selama TA berjalan.
Indicator (lagging) yang secara umum sudah harus ada adalah :
• Plan progress
• Safety aspect khusus untuk kontraktor utama (main contractor)
mencakup hal-hal sebagai berikut :
Total Recordable Injury Rate (TRIR)
Number Of Injury (NOI)
Lost Time Injury (LTI) = 1.000.000 / mhrs x No. LTI
Medical Treatment Case (MTC) = 1.000.000 / mhrs x No. MTC
Total Recordable Case (TRC=LTI+MTC) = 1.000.000 /mhrs x
TRC
First Aid Case (FAC) = 1.000.000 /mhrs x FAC
High Potential Incident (HPI)
Pada saat pelaksanaan hal ini dilengkapi dengan leading indicator
agar kinerja kontraktor senantiasa terkendali.
3) Kejelasan peran Safety Inspectors.
Peran safety inspector dalam pengawasan pada saat eksekusi TA
antara lain adalah :
• Mengetahui lingkup kerja, potensi bahaya dan pengendaliannya.
• Tahapan dan kelengkapan permit.
• Kelengkapan APD.
• Kelengkapan alat kerja.
• Pengelolaan limbah kerja.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 122 dari 153
TURNAROUND
Keterangan :
I : Inisiator
A : Action (pelaksanaan pengawasan safety pekerjaan)
M : Monitoring (memantau progress pelaksanaan pekerjaan)
W : Witness (memeriksa hasil pekerjaan/acceptance)
R : Review (evaluasi rencana dan pelaksanaan pekerjaan)
• Permit to work
• Working in confined space
• Working at height
• Hazardous classification
• Safe work practice
• Kesehatan lingkungan kerja
• Pengelolaan lingkungan
• Emergency response plan
c) Melakukan sertifikasi terhadap safety man kontraktor
d) Melakukan upskilling terhadap pekerja front line melalui safety
man pada saat safety talk
e) Melakukan security talk.
b. Fabrication management
Yang dimaksud dengan fabrication management adalah pengelolaan
terhadap pekerjaan fabrikasi yang sudah harus selesai sebelum TA
eksekusi dimulai.
Untuk hal tersebut maka diperlukan control atau pengendalian progress
baik yang dikerjakan di RU atau di workshop luar.
Selanjutnya untuk material-material eks fabrikasi perlu dikelola baik lokasi
maupun preservasinya. Material-material fabrikasi antara lain : tube
dapur, piping, vessel, shell & tube bundle, rotor, shaft, dan lain lain.
1) Readiness material (LLD dan NLLD) baik dari sisi item, jumlah dan
kualitas serta lokasi penyimpanan.
2) Readiness heavy equipment, special tools, equipment, scaffolding, small
tools, lighting (jenis, jumlah dan kualitas).
3) Readiness SEIG dan Quality Plan (format, personil dan strategi
pelaksanaan assessment & QC).
4) Readiness HSE (JSA, format, personil dan strategi pelaksanaan)
5) Readiness TA Project Management & Progress Control (strategi
pelaksanaan TA on time).
6) Readiness TA Executor (strategi, jumlah dan kompetensi personil).
7) Readiness Shutdown Phase ( strategi, jumlah dan kompetensi personil).
8) Readiness PSSR & Start Up ( strategi, jumlah dan kompetensi personil).
Bila General Manager RU’s telah meyakini kesiapan tersebut maka General
Manager RU’s mengundang Central Committee (Kantor Pusat) untuk
mengadakan TA Kick Of Meeting di RU, yang selanjutnya menjadi acuan
General Manager RU’s untuk melaksanakan TA.
B. TA EXECUTION.
TA execution adalah kegiatan yang dimulai dari Shutdown unit, pekerjaan
mekanikal sampai dengan penyerahan unit ke fungsi produksi dengan tahapan
sebagai berikut :
Release
Handover
Shutdown Deconta- to TA TA scope
PSSR to
execution mination execution execution
operation
team
1. Shutdown execution :
Gambar 28. Diagram alir proses shutdown plant, sampai dengan release peralatan
untuk pelaksanaan pekerjaan mekanikal.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 128 dari 153
TURNAROUND
Yang dimaksud dengan shutdown execution adalah tahapan yang dimulai dari
shutdown unit hingga unit proses siap untuk dilakukan decontamination
process dengan kegiatan meliputi :
a. Shutdown unit :
Shutdown unit adalah pelaksanaan penurunan kondisi operasi yang
meliputi temperatur, flow, tekanan dari system unit proses yang sedang
beroperasi hingga unit proses aman (expose atmosphere) untuk
dilakukan pengosongan peralatan. Agar pelaksanaan shutdown unit dapat
dilaksanakan dengan aman maka harus dilakukan langkah-langkah
sebagai berikut :
a. Tersedia detail sequence operation shut down plan yang telah ter-
challenges (termasuk durasi dari tiap sequence, dan lain lain) dan
visual management-kan seluruh tahapan dan tata waktu shutdown
unit proses pada tempat yang mudah diakses oleh pelaksana yang
terlibat sebagai langkah sosialisasi proses shutdown.
b. Laksanakan shutdown sesuai dengan SOP/TKO dan mentaati
seluruh tahapan serta tata waktu yang telah direncanakan.
c. Yakinkan bahwa seluruh tahapan dan tata waktu shutdown unit
sudah dipahami dan dilakukan oleh seluruh pekerja yang terlibat
dalam proses shutdown dengan mengisikan check list/format yang
telah disediakan.
b. Pemasangan/pelepasan blind/insulation unit proses dan peralatan proses.
Tujuan pemasangan blind adalah untuk mengisolasi sytem unit proses
operasi. Agar tidak terjadi kekeliruan pemasangan blind maka yakinkan
bahwa blind yang akan dipasang telah sesuai dengan jumlah, spesifikasi
(diameter, class) dan lokasi pemasangan berdasarkan daftar blind list
(tertera pada tahapan pre excution), juga langkah-langkah sebagai
berikut :
1) Pengendalian blind
Pengendalian blind adalah pengendalian terbatas kepada
pengendalian lokasi pemasangan saja .
Lokasi pemasangan ditentukan oleh produksi, daftar lokasi
pemasangan blind tersebut diserahkan kepada masing-masing
pengawas pemeliharaan area tersebut. Pada saat pemasangan
pengawas produksi menunjukan lokasi seperti yang tertulis pada
daftar kepada pengawas pemeliharaan area dengan saksi dari HSE.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 129 dari 153
TURNAROUND
2. Decontamination process
Adalah proses tahapan yang dilakukan oleh Produksi untuk membebaskan
peralatan proses dari sisa-sisa service yang bersifat flamable dan toxic
sampai dengan peralatan dapat di release.
Agar kegiatan decontamination process berjalan dengan aman maka :
a. Process decontamination mengacu kepada TKO/TKI pembebasan
peralatan proses dari sisa-sisa service yang bersifat flamable dan toxic.
b. Sosialisasi TKO/TKI terhadap Pengawas dan Operator Produksi sampai
dengan pemahaman tercapai.
c. Senior Supervisor Produksi berkewajiban membuat tahapan
decontamination process sampai dengan peralatan di release dilengkapi
dengan durasi masing-masing tahapan (dalam bentuk bar chart), satu
copy diserahkan kepada Planner/Schedulling TA untuk di masukkan
kedalam network planing. Senior Supervisor Produksi memastikan
schedule yang dibuat sudah di challenges dan mungkin untuk
dilaksanakan.
d. Process Engineering mengkoordinir fungsi Produksi dalam pelaksanaan
kegiatan decontamination.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 130 dari 153
TURNAROUND
4. TA Scope Execution
Pada tahap ini yang dilakukan oleh fungsi Maintenance Execution dibawah
koordinasi TA Manager adalah kegiatan yang meliputi :
• Schedule adherence & progress control
• Adherence to pre execution plan
• HSE & Security management
• Emergent work & contingency plan
KETERANGAN
Equipment Supervisor
2) Progress control
Pada tahapan ini dilakukan pembuatan matrik responsibility yang
berisikan sbb :
• Update pencapaian progres setiap aktifitas dan overall setiap hari
oleh TA Planner dengan masukan dari pengawas Maintenace
Execution untuk di key in ke dalam Primavera oleh TA Planner.
• Laporan progres dibawakan ke rapat steerco oleh TA Manager
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 135 dari 153
TURNAROUND
• TA Team meeting, dilakukan setiap sore hari yang dihadiri oleh TA Team
dan contractor supervisor, dengan agenda :
- Contractor issues
- Job tasks yang berhubungan dengan issues
- Review aksi lanjut dari issues hari sebelumnya.
• Tool-box meeting untuk tiap area, dilakukan setiap hari yang dihadiri oleh
HSE/TA Execution dan contractor, dengan agenda :
- Safety incident/accident pada hari sebelumnya
- Pencapaian progres dan rencana kerja hari ini
- Potensi bahaya dan mitigasinya
- Quality plan
Engineering completion
Instrument and Electrical (I&E) TA engineer/ ---
safeguarding/IPF checks on the system Process engineer
complete
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 138 dari 153
TURNAROUND
h. PSSR Execution
Group
PasangBlind/Sorokan Stationary,
Audit Doc Box Up …
Proses,
dan Safety
Buka Man
Hole
Audit Doc Hydro Group
…
Test Stationary
Cleaning/Repair/Replace
Group
Equipment
Cabut Blind Proses & …
Readiness status
produksi
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 139 dari 153
TURNAROUND
Studi Keenjiniringan
Audit studi ABP
Studi ABP
Audit doc punch list
Group
Proses &
PIC refer produksi
check list Konstruksi
aktivitas Audit Doc Prosedur/STK
MOC Group
Stationary,
Punch list rotating,
dan Safety
C. START UP PROCESS
Preparation
of auxiliary Tightness Bringing
Preliminary Elimination Backing in Elimination
of air the unit
preparation equipment of air fuel gas of water
on-stream
and services
1. Preliminary preparations
Checklist
Status PIC
1 Seluruh material asing sudah dipindah dari seluruh vessels,
columns, dan peralatan lainnya
2 Trays, floats, float arms, dan jalur-jalur pipa sudah bersih, ada
di tempatnya masing-masing dan berfungsi dengan baik
3 Manways, pipe flanges dalam kondisi tertutup & dibaut/bolded
4 Sudah periksa kekencangan semua sambungan/flange yang
dibuka selama TA
5 Material scaffolding, alat-alat, dan materi surplus sudah
dipindahkan dari area operasi
6 Noda, debu, kotoran sudah disingkirkan dari firebox
dapur/furnace
7 Blind/sorokan untuk shutdown sudah disingkirkan dan
blind/sorokan yang hendak dipakai sudah terpasang
8 Kartu terima peralatan diberikan dadri eksekusi ke produksi
9 Tim PSSR memeriksa dan konfirmasi
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 141 dari 153
TURNAROUND
3. Elimination of air
Steam atau purge gas yang hendak dipakai untuk mengeliminasi udara
sebelum hydrocarbon dimasukkan ke unit
4. Tightness of air
a. Pengetesan kebocoran untuk memastikan bahwa hydrocarbons tidak lolos
dan udara tidak masuk
b. Berbagai metode pengetesan yang dipakai:
• Pressure tightness test memakai purge gas
• Vacuum tightness test
5. Backing in fuel gas
Pengganti materi purging dengan refinery fuel, gas, gas alam atau hydrocarbon
untuk diproses, tergantung materi purging -nya
6. Elimination of water
a. Hilangkan seluruh air sebelum hot oil masuk
b. Setelah seluruh air dikeringkan, oil yang bersirkulasi dipanaskan untuk
meningkatkan temperaturnya secara bertahap
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 142 dari 153
TURNAROUND
c. Overpressurizing
Hindari over-pressurizing (kelebihan tekanan) dengan memastikan tidak
ada sumbatan di jalur outlet
LAMPIRAN - LAMPIRAN
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 143 dari 153
TURNAROUND
BAB IV
POST TA
A. POST TA REPORT
Tahapan post turnaraound adalah tahapan penyusunan post TA report yang
sudah harus di-issue 3 (tiga) bulan sejak unit on stream. Isi dari post TA report
adalah kondisi equipment (dalam closed out report/ laporan hasil assessment),
performance unit operasi setelah dilaksanakan TA (dalam closed out
TAreport/KPI), dan rekomendasi perencanaan dan eksekusi TA serta
rekomendasi untuk eksekusi next TA(dalam closed out TA report).
Post TA report tersebut juga merupakan salah satu bahan yang akan
digunakan untuk menyusun scope of development TA yang akan datang,
termasuk data pasca TA yang diperoleh dari hasil on stream inspection dan
performance operasi unit, dan pemenuhan regulasi untuk pemeriksaan
peralatan kilang.
Post TA Report terdiri dari :
• Prelimenary inspection report (Part A)
• Post implementation review TA (PIR TA) (Part B)
• Closed out TA report (Part C)
a. Inspection TA report.
Inspection TA report merupakan summary hasil assessment kondisi
unit dan peralatannya secara menyeluruh, hasil
pemeriksaan/pengetesan detil peralatan, perbaikan yang
dilaksanakan pada saat TA, kajian untuk perbaikan/penggantian pada
next TA serta kajian dan saran pengoperasian peralatan pasca TA.
Detail inspection TA report dibuat sebagai lampiran.
PEDOMAN
FUNGSI : RELIABILITY REFINING NOMOR : A - 01/E10200/2010-S0
OPERATION REFINING
REVISI KE :0
DIRECTORATE
BERLAKU TMT : 26 April 2010
JUDUL : MANAJEMEN HALAMAN : 147 dari 153
TURNAROUND
1
c. Pada saat pelaksanaan, bertanggung jawab terhadap pembuatan
jadwal kerja mingguan dan harian.
d. Mengawasi critical path dan progres secara keseluruhan pada
saat persiapan, pelaksanaan dan start up.
e. Mengatur process rapat TA mingguan dan harian.
f. Melakukan koordinasi dengan Engineering & Development
(sebagai owner MOC) untuk memastikan bahwa setiap dilakukan
perubahan terhadap equipment dan material harus mengikuti
prosedur MOC.
3. Disipline Engineer/Area Inspection
a. Melaksanakan pekerjaan inspeksi
b. Mwlakukan koordinasi dengan inspektor eksternal
4. Maintenance Area Section Head /executor
a. Memberikan masukan dan mengawasi pekerjaan mechanical,
electrical, dan instrumentation
b. Melaksanakan pekerjaan pembersihan peralatan
5. Process Engineering
a. Memnerikan masukan berkaitan dengan proses pada saat
persiapan TA
b. Memberikan dukungan pada saat proses shutdown dan start up
6. Operation
a. Melaksanakan kegiatan pengurusan perijinan
b. Menentukan kebutuhan pemasangan blank
c. Melakukan Dekontaminasi
d. Melakukan Gas test
7. Civil and construction
a. Mengawasi pekerjaan scaffolding dan pekerjaan sipil lainnya
8. Scheduling Section Head
a. Mengelola schedule TA (perencanaan & pengendalian)
9. Lead monitoring & Control Material & Service Support
a. Mengelola kegiatan pengadaan material dan jasa untuk
menunjang pelaksanaan TA
10. Procurement/Logistic
2
a. Mengelola pengadaan material & jasa
b. Mengatur facility layout
c. Mengatur hal-hal yang berkaitan dengan perjalanan/makanan
11. Budget monitoring
a. Menyiapkan anggaran TA
b. Melakukan pengawasan terhadap biaya TA
12. HSSE supervisor
a. Melakukan pelatihan mengenai safety
b. Melakukan pengawasan mengenai safety secara berkelanjutan
c. Mengatur tim paramedis
13. General Affair/Security & PR
a. Mengatur tim security
b. Mengkoordinasikan public relation dengan lembaga eksternal
3
6. Maintenance Planning & Support Manager
a. Melakukan assessment peralatan
b. Melakukan quality control terhadap pekerjaan TA
c. Menyiapkan quality plan
7. Reliability Manager
a. Memberikan rekomendasi terhadap lingkup pekerjaan TA dari
aspek mechanical integrity
8. Procurement Manager
a. Membuat strategi pengadaan barang dan jasa
9. HSE Manager
a. Menyediakan panduan kebijakan HSE
b. Memberikan solusi masalah safety yang spesifik
10. Refining Planning & Optimization Manager
a. Memberikan masukan perihal jadwal produksi
11. General Affair Manager
a. Mengatur kegiatan yang berhubungan dengan security dan public
relation
12. Execution Manager
a. Menyediakan anggota tim dan tools untuk pelaksanaan TA.
4
Lampiran 2 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
TA Performance Assessment
Element Sub-element Score (X)
1 1 2 3 4 5
1 Set Interval
2 Timing optimization
3 External management
TA goal and
strategy 4 Planning tool selection (Preparation & Exec)
5 Budgeting (proposal)
6 TA Master Schedule
2
1 Optimal org structure
3
1 Identify Risk Process
3 RBI
4 Equipment optimization
Scope
Development 5 MOC (Plant Change &Process)
6 Other tasks
4 Cost Estimation
Detail
Planning
5 TA “work grouping” preparation & out sourcing schedule
6 Procurement strategy
7 Budget allocation
5
1 Develop network & detail schedule
5 Develop PSSR
6
1 Contractor scoping analysis
2 Selection criteria
3 Contract type
Contractor
Management 4 Tender process
3 Facility layout
4 Permitting process
Pre Execution
5 Decontamination preparation
7 Shut-down preparation.
8
1 Shutdown execution
3 Supervision mechanism
6 HSSE Management
7 Quality Control
2 Commissioning
Startup
3 Start Up and Feed in
Process
5 MOC as built
Lampiran 3 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
NO :
UNIT :
(FORMAT PEKERJAAN MEKANIK)
EQUIPMENT KRITERIA SCOPE OF WORK REKOMENDASI RELIABILITY TUJUAN & ALASAN
NO URAIAN PEKERJAAN UTAMA
TAG. NO MI PI OPT CLN INP RPR GTB UT NDT MSR DWG NOMOR URAIAN PEKERJAAN
Note : CLN = Cleaning Internal, INP = Inspection ( Internal & External ), RPR=Repair, GTB= Ganti Baru, UT = Ultrasonic Test ( Ukur Tebal ), NDT = Non Destructive Test.
MSR=Measure, DWG=Drawing, OH=Overhaul, S=Simulasi, RS=Resetting, KLB=Kalibrasi, MGT=Merger Test, RT= Resistance test, UL=Unload Test, LT= Load Test
FT= Function Test, LC=Loop Check, ZC=Zero Check
Kriteria : MI=Mechanical Integrity; PI=Process Integration; OPT=Optimization
Lampiran 3 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
NO :
UNIT :
(FORMAT PEKERJAAN RE)
EQUIPMENT KRITERIA SCOPE OF WORK REKOMENDASI RELIABILITY TUJUAN & ALASAN
NO URAIAN PEKERJAAN UTAMA
TAG. NO MI PI OPT CLN INP RPR GTB OH MSR DWG NOMOR URAIAN PEKERJAAN
Note : CLN = Cleaning Internal, INP = Inspection ( Internal & External ), RPR=Repair, GTB= Ganti Baru, UT = Ultrasonic Test ( Ukur Tebal ), NDT = Non Destructive Test.
MSR=Measure, DWG=Drawing, OH=Overhaul, S=Simulasi, RS=Resetting, KLB=Kalibrasi, MGT=Merger Test, RT= Resistance test, UL=Unload Test, LT= Load Test
FT= Function Test, LC=Loop Check, ZC=Zero Check
Kriteria : MI=Mechanical Integrity; PI=Process Integration; OPT=Optimization
Lampiran 3 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
NO :
UNIT :
(FORMAT PEKERJAAN LISTRIK)
EQUIPMENT KRITERIA SCOPE OF WORK REKOMENDASI RELIABILITY TUJUAN & ALASAN
NO URAIAN PEKERJAAN UTAMA
TAG. NO MI PI OPT CLN INP RPR GTB S RS KLB MGT RT UL LT NOMOR URAIAN PEKERJAAN
Note : CLN = Cleaning Internal, INP = Inspection ( Internal & External ), RPR=Repair, GTB= Ganti Baru, UT = Ultrasonic Test ( Ukur Tebal ), NDT = Non Destructive Test.
MSR=Measure, DWG=Drawing, OH=Overhaul, S=Simulasi, RS=Resetting, KLB=Kalibrasi, MGT=Merger Test, RT= Resistance test, UL=Unload Test, LT= Load Test
FT= Function Test, LC=Loop Check, ZC=Zero Check
Kriteria : MI=Mechanical Integrity; PI=Process Integration; OPT=Optimization
Lampiran 3 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
JOB LIST TURN AROUND KILANG RU …….
TENTATIVE ……..
NO :
UNIT :
(FORMAT PEKERJAAN INSTRUMENT)
EQUIPMENT KRITERIA SCOPE OF WORK REKOMENDASI RELIABILITY TUJUAN & ALASAN
NO URAIAN PEKERJAAN UTAMA
TAG. NO MI PI OPT CLN INP RPR GTB S RS KLB FT LC ZC NOMOR URAIAN PEKERJAAN
Note : CLN = Cleaning Internal, INP = Inspection ( Internal & External ), RPR=Repair, GTB= Ganti Baru, UT = Ultrasonic Test ( Ukur Tebal ), NDT = Non Destructive Test.
MSR=Measure, DWG=Drawing, OH=Overhaul, S=Simulasi, RS=Resetting, KLB=Kalibrasi, MGT=Merger Test, RT= Resistance test, UL=Unload Test, LT= Load Test
FT= Function Test, LC=Loop Check, ZC=Zero Check
Kriteria : MI=Mechanical Integrity; PI=Process Integration; OPT=Optimization
Lampiran 4 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
RAM Criteria for Internal Tasks
in the scope
consequence benefit analysis
out of scope
Lampiran 5 Pedoman Manajemen Turnaround No : A- 01/E10200/2010-S0
Lampiran Evaluasi Sistim Pengelolaan HSE Kontraktor
A B C D
Section 1 : Leadership and Commitment
Commitment to SHE through leadership : Item 1(1)
No Commitment SHE disciplines Evidence of active Evidence of a
from senior delegated to line senior management positive SHE culture
management. managers – no direct Involvement in SHE in senior
involvement by aspect. management and at
senior management. all levels.
Section 2 : Polycy and Strategic Objectives
SHE policy documents and avaibility : items 2(1) and 2(2)
Policy statements A policy statement SHE policy Policy with clearly
exist but exists with clear esthabilishes estabilished
responsibility for responsibility for SHE responsibility for responsibility and
SHE is unclear. but not in a widely SHE in languages accountability, is
distributed document. easly understood, distributed to all
but not widely employees, and is
distributed. visible on notice
board.
Section 3 : Organization, Responsibilities, Resources, Standarts and
Documentation
SHE communication and meeting programmes : Item 3(1)
No management Management Regular Regular
involvement or Involvement and management management
commitment commitment toward Involvement and Involvement and
fowar SHE SHE in special commitment toward commitment toward
activity. occasion only, SHE. SHE.
likewise for periodic SHE meetings Regular SHE
SHE meeting. performed on a meetings performed
regular basis at and employees are
management and assigned topics to
supervisor level. discuss on a
rotational basis.
Staff SHE training Item 3(2)
No SHE training SHE training SHE training SHE training
estabilished estabilished but not estabilished and estabilished and fuly
Implemented. Implemented but Implemented to all
only to a limited staff staff related to the
only. work.
Section 3 : Organization, Resposibilities, Resource, Standarts and Documetation
(cont’d)
Employee competency and SHE training : Item #(3) (a) – (d)
No formal Formal program Formal program Formal program
programe estabilished to estabilished and estabilished and
update employee Implemented for Implemented for and
knoeledge on SHE. and new employee new employee on
Verbal Instructions on SHE. SHE.
on company Employee handbook Employee handbook
procedures only for provide and provide and
new employee. supervisor outline, supervisor outline,
Orientation booklet explans and explans and
1
A B C D
provided for new demonstrates new demonstrates new
employees but no employee’s job. employee’s job. With
on-the-job orientation follow-up observation
by supervisor. or the new
employee’s work is
also included.
Supervisor has
explaned to him safe
practices and
emergency duties.
Specialized training : Item 3(4) (a) and 3(5)
No specialized Specialized SHE Specialized SHE Specialized SHE
SHE training training estabilished training estabilished training estabilished
estabilished but not implemented. but not but not implemented
implemented. on a regular basis.
Retraining periods
are estabilished.
Qualified SHE
professional are
employed.
Subcontractorrs : Item 3(6) (a) - (d)
No assessment Assessment program Assessment Assessment program
program for and standarts for program and and standart for
subcontractor subcontractor are standart for subcontractor are
estabilished. estabilished, subcontractor are estabilished and
covering limited area estabilished and Implemented. Quality
only but not Implemented. assurance for
implemented yet. complance in place.
SHE Performance Standarts : Items 3(7) (a) – (e)
No SHE SHE performance SHE performace SHE performace
performance standarts standarts standarts
standarts estabilished for estabilished an In estabilished an In
available limited purposes only complance with complance with local
or partial and in local industry and global industry
complance with local regulatory standarts. regulatory standarts.
industry regulatory
standarts only.
SHE Performance records Latest year injury rate comparison to contractor’s three
preceding years average) : Item 6(4) (a) – (d)
Contractor Rate is not Shows only minor Rate steadly
supplied Improving, but it is rate improvement, improving by more
insufficient to reviewed annually and it is reviewed than 20 percent per
estabilish rate or quanterly. years, and reviewed
rate increases, monthly.
no review
conducted
Incident Investigation and reporting : Item 6(5) (a) – (d)
Procedure are Procedure are Procedure are As In C but with the
available but available but available but addition of details of
Findings not Findings not Findings not Implication for
generally generally generally improving SHE
communicated. communicated to key communicated to all performace,
personel only via employees via Including near miss
limited company specific company learning.
Internal memo or notice.
similar media.
Section 7 : Auditing and Review
Auditing : Item 7 (a) – (d)
Audit process is Company SHE Company SHE As in C but
cursory only – documents include documents include additionally specifies
SHE documents reference to auditing details of how managemen’s role in
are not explicit but there are no auditing is to be audit an follow-up on
about auditing specific details about implemented with action items.
scheduling and schedules/
coverage. coverage for the key
areas.
5
A B C D
Section 8 : Emergency Response Procedure
Emergency Respose Procedure
No. written Basic procedure Emergency Emergency
Emergency only. procedures written procedures written
Respose. for major scenerios, for major scenerios,
e.q. fires explosions, e.q. fires explosions,
H, S, evacuation, H, S, evacuation,
reales of toxic or reales of toxic or
flammable materials flammable materials
and medical and medical
emergencies no emergencies.
requirements Procedures
estabilished for dril documented in an
frequencies. emergency
procedures manual,
which is widely
distributed. Frequecy
of conducting drills
estabilish.
Section 9 : SHE Management – Additional Features
Membership of Associations : Items 9 a-b
No memberships Company has Company is a Company is in active
membership of at member of at least participant in at least
least one association one SHE one SHE association
but with no association. or having
prominence given to achievement in SHE
SHE.
6
Contractor SHE Management System Evaluation
Contrctor :
Address :
Date :
Contrctor Safety Contract :
Phone :
Circle number, which best represents this evaluation based on the criteria for rating purpose attached
The numerical values below are the weighted ratings calculated above. The
total represent the overall score for the Contractor.
TOTAL RATING *)
EVALUATED BY
NAME NAME
TITLE TITLE
DATE DATE
8
Lampiran 6 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
A. RINGKASAN EKSEKUTIF
Unit Proses yang melaksanakan TA.
B. BATASAN KAJIAN
1. Kajian Objektif TA
2. Lingkup Kajian Post TA (aspek pembelajaran TA)
C. PARTISIPAN TA (Pekerja/outsource yang terlibat TA)
D. LINGKUP/ AREA KAJIAN
1. TA Preparation
2. Scope management
3. Quality management
4. Cost management
5. Contract management & Contractor performance
6. Procurement & Material management
7. HSSE (Health, Safety, Security & Environment)
8. Execution Management
9. Operations (shutdown, Decontamination and Start Up)
10. Project integration
11. Heavy equipment & tools
12. Resource
13. Material
14. Durasi/schedule
E. GENERAL RECOMMENDATIONS (rekomendasi secara menyeluruh)
F. ISSUES TO BE ADDRESSED FOR NEXT TURNAROUND (issues dan
rekomendasi untuk TA berikutnya)
G. ACTION PLAN (rencana tindak lanjut beserta PIC dan target waktu)
H. ATTACHMENT :
1. TA Organization
2. Schedule TA
3. Critical path
4. Incident record
5. Highlight picture
6. Etc.
Lampiran 7 Pedoman Manajemen Turnaround A- 01/E10200/2010-S0
2
N. OPERATIONAL
O. PROCESS
P. DOCUMENTATION (dokumentasi kegiatan elektronik maupun hardcopy)
1. Electronic
2. Hardcopy (drawing)
Q. ATTACHMENTS (lampiran dokumen pendukung Close Out Report)
1. Lessons Learned Report (PIR TA)
2. Condition of Equipment Upon Opening
3. HSE
1) Incident Report and Action Items
2) Number of Shutdown Audits Performed
4. As-Built Schedules
1) Pre-Shutdown Milestone Schedule
2) Primavera Shutdown Schedule per Process Unit
3) Primavera Shutdown Summary Schedule: Actual vs Target
4) Primavera Shutdown Summary Schedule: Actual vs Target
5. Contract Register
6. Cost Reports
1) Summary Cost Report
2) Detail Worklist Cost Report
7. Manpower Reports
1) Manhours per Person per Company
2) Cumulative Manhours per Date: Direct Hours vs Indirect Hours
3) Number of Personnel per Date: Direct Hours vs Indirect Hours
4) Manhours per Discipline
5) Manhours per Contract
8. Organigrams
1) Pre-Shutdown Organigram
2) Shutdown Organigram
9. Document Filing Structure
10. Plot Plans
11. Etc.
3
% <=+ * > ," " =1 43 ? 4?
! * +$ , - . ! /
#
- .
+ .
( .
! #
- .
+ .
( .
!$$ % " #
! "" # $ % &' / / / ) 0 1+1 (" * 1 , 2 - .
! ( ) * * + " , + * ) 1 " 3 + " 4 * "// 5 ( .
& ' % ( ) % #
+
6 // 5 / # /" :
37" 80 "" " 95 0
%/ " / / 3 " /
6 - - ;; - 3 "
- 5 - 3 "
* - ;; + 5
" 4 " : / 0 # 1+1 5
* - ;; + 5 5 3 " @ 5
%/ " : 3 "
/ / 3 " /
3 5
, 5 : " 5 " ) , / :
# 5 % / 2 5 " " " * 5
6 " 5 # 1 " 1 % " 5
6 // 5 6 : # ) 1 " 5
- " ; 1 5 3 " &' ! (
- " 0 " : * # 3 + " 4 3 * "//5
1 / : //
6 5 # " 7"
6 :
5
) " " / :
% / 2 " " 1+1 5
" % + " , 5 # 1 " 5
, + 1+1 5
4 , 5 : //
% 55
6 , 5 " 5 " / :
% 0 % / 2 # * 1 " 5
6 - ;; 5 : //
2#
6 , * 5 " " : 6 : /
, : 7" 3 " /
+ 7"
% <=+ * > ," " =1 43 ? 4?
# % %
+ % & % #0 # & 0 % %
+ : : : "
2 " "
: /
: 0 / 2
?
% <=+ * > ," " =1 43 ? 4?
1 # % %
% % & ' % & %
+ % & ' %
37" % / 2 + 0
6 8/ > :9 ? 4 2 %/ " 0
6 / : :" : ) 0
0
( " ; 4 /
( + 3
+ 0 4: "
/"
! / A / 7" :
" " / 4 " "
7" 0 0 / : :" :
! 4 7" 0 / "
: :
" 0 8 / 1 1
9 A
1 " : " : /
/
, " 0
"
3 " 7" 0
"
( /
% <=+ * > ," " =1 43 ? 4?
1 % %
%
5(" 6 -+ 7 ! 3!+
3-"* 4 5(" 6 -
)
2 "
&
9 ::: ::: + # $877
- ::: - ::: " %%
- & 02 ; # #
4 =* > + % 44 =
< =* ? 3 4< =4= //
8 ) =": =/ = =4= " @ 9 48 :::::::::
= 3 =37" =8=) =1 4( = 0 =5559 A 4= :::::::::
B - 4C & 4B :::::::::
- & 02 ; # #
4 = = ? 3 =" 48 +
< = :> @ % = " = 4= 0
8 %/ = 0 = A = 7" 4B :::::::::
= 4 / = 4C 2 = 4> :::::::::
B , 2 = =4= 7" =4= 44 = " = = = 4? :::::::::
> : = =4= 7" =4= 4< ( " =/ = ==C C C 55 4@ :::::::::
B
% <=+ * > ," " =1 43 ? 4?
1 % %
%
5(" 6 -+ 7 ! 3!+
3-"* < 3-"* 8 ' E %
3& 7 .9 % 2 "/ D 7 ! & D
= = " =4= " < + =/ = 2 0
B " = = F + = = =+ =4=!
> * =4= " =: + = = 0 =0 = 7"
F 4 1 = = = =0 0 = = '= = =/ = = = = = = 5 $ := / =1 =8=$ 1=9
< 0 = =/ : = 5 ? =4=( =4=+ 6( =4= = =+ ( =
8 =: =/ = 7" = "
= =: =/ =/ B 6 = = = 7"
B 1 = = 7" = = = " = = = " 5 ' ( = =8=* ( =9
> = = = = = = 7" 4 D =4= =
? = = = 7" E , = = = :
@ 1 = = = = = = /= < = =4=( =4=
F CCCCCCCCC5
CCCCCCCCC5
3 1 = = 7" = = =.
4 6 = = :
< 6 =/ = = "
4 * = = =
B = =
3 = =: =. - . " . + .
+3 61%=6- , # ,6 - =.
1+( = 7"
/ = ( " =4= =* / = = / = " =4=1
) 0 = =" " = =
/ = 3 = =" CCCCCCCCCCC5
'
% <=+ * > ," " =1 43 ? 4?
1 % %
%
5(" 6 -+ 7 ! 3!+
3-"* = !( -, * +"G!-"*
" % & % & % % # & & )
1" ; = =+ =8=) 6=1" =9
# -
1" ; = =+ =8= =+ =1" =9
# -
! % & % & %0 )
1" ; =, =+ =8=1" ; =3 =9=
# -
3-"* B ,! * ; + 9+* 6 - 3, "3!7 2" +" 2
, = = = = = = = 7" = = = = = /= = =
- = = = = = =/ CCCCCCCCCCCCCCCCCCC
# -
3-"* > 2 "
6= = = = 7" = = = = = = = = = 5
# -
D
Gambar 1. Pertamina Best Practice dan TA Process
Sub- Set Interval Define and Job WSA Develop Contractor Prework Shutdown PSSR Preliminary
elements Timing Establish Collection (Work network & scoping activity execution execution Report.
optmisa-tion Organiza- – Post TA Scope detail analysis Critical Deconta- Commi- PIR
External tion (TA Report Analysis) schedule Selection Equipment mination sioning (codifying
manage- Team & – Gov. Reg Prepare Critical criteria execution process & Start Up learning)
ment Steering – PM/PdM Job Plan path Contract scenario release Eq and Feed Close out
Planning tool Committee) – Vendor/ ( BOM Non manage- type Facility Supervisi- in report
selection Roles & Liscensor LLD, tools, ment. Tender layout on mecha- (Inspection
(Preparation responsi- – Risk Heavy Eq, Develop process Permitting nism report
& Exec) bilities Asses- supporting detail Develop process Schedule &Post TA
Budgeting Staffing ment Tools) schedule contractor Deconta- adherence report,next
(proposal) schedule – Eqptment TA “work SD & SU. Perfor- mination & Progress TA
TA Master and link to optimisa- grouping” Develop mance prepara- control Planning)
Schedule rest of tion prepara- Start-up criteria & tion Change Schedule
organiza- – Process tion & out process indicator Readiness order next TA
tion Integrity sourcing Develop CSMS(Co Execution, Mgmt MOC as
TA KPIs – MOC schedule Quality ntractor HSE, Execution built
(premise) – Risk Cost Manage- Safety Quality HSSE
Critical Process & Estimation ment . Mgmt etc. Execution.
success Mitigation Budget Develop System) Shut-down Quality
indicators – etc alocation HSE prepara- Control
Final Joblist Procure- Manage- tion. Execution
Preparing ment ment Kick off Handover
BOM LLD Strategy Meeting to line
category Materials with process
Scope arrival Contractor
challenge & scheduling
freeze proc.
Gambar 2. Contoh tentatif jadwal sourcing harga dan pengusulan anggaran TA
!
"
!
"
# #
##
##
##
$
%
%
1
Gambar 3. Organisasi TA Steering Committee tanpa menggunakan main contractor
Full time
> 50% Full time during
General Manager
preparation phase
&
Senior Manager Operation & Advising relationship
Manufacturing
TA scope challangers
Planning
Section
Head
Owner of Prepare Recom- Prepare Recom- Provide Set Provide Provide Manage
TA and mend Budget mend execution procure- guidance inputs to security
preparation execute scope Prepare scope team ment on HSE product- and PR
and release, from quality from members strategy policy ion
execution deconta- process plan mechani- and tools for Provide schedul-
Manage mination, aspect cal for TA goods specific ing
Roles
T-21 T-12 T-12 T-12 T-12 T-12 T-12 T-12 T-6 T-12
Gambar 4. Organisasi TA Steering Committee dengan menggunakan main contractor
Full time
General Manager > 50% Full time during
& preparation phase
Senior Manager Operation & External
Manufacturing
Advising relationship
Engineer Main
Product- Procure-
Central TA
ion
-ing & MPS Rel ME
ment
HSE RPO G&A ))
contrac-
team Manager Dev. Manager Manager Manager Manager Manager Manager tor
Manager Manager
Manager Manager
scope challangers
TA
Planning
Section
Head
Owner of Prepare Recom- Prepare Recom- Provide Set Provide Provide Manage Provide
TA and mend Budget mend execution procure- guid- inputs security inputs
prepara- execute scope Prepare scope team ment ance on to and PR regard-
tion and release, from quality from members strategy HSE product ing
execution deconta- process plan mecha- and tools for policy -ion capabili-
Manage mination, aspect nical for TA goods Provide schedul ties and
Roles
T-21 T-12 T-12 T-12 T-12 T-12 T-12 T-12 T-6 T-12 T-3
Gambar 5. Organisasi TA Team tanpa menggunakan main contractor)
Full time
(T-21) > 50% Full time during
Central Steering preparation phase
TA Manager
brick team Committee
Advising relationship
TA
Area Kabag
Kabag
Section Scheduling G&A/
Planing Engineer Maintenance Budget HSE
coordina- forTA
Head TA
for Procure-
Section Area for Section Security
MPS tor complex ment monitoring supervisor
Head Section TA
complex Head &PR
Head complex
Lead
Mechanical,
Process Civil Mon &
Planner electrical, &
Engineer- Operations construc- contl mat’l
instrument-
ing tion & service
ation
support
Scope Inspection Provide Provide Permitting Supervise Provide Manage Manage Budget Conduct Manage
collection work inputs and process Determine scaffol- detailed Schedule procure- planning safety security
Meeting Coordina- supervise inputs spading ding and know- for ment Cost induction/ Coordinate
process tion with mechanical during require- other civil ledge of prepara- activities monitoring training PR with
owner external , electrical, prepara- ments work complex tion & Manage Conduct external
Scheduling inspectors and tion Deconta- execution. facility continuous bodies
Roles
T-21 T-6 T-6 T-6 T-6 T-3 T-12 T-10 T-2 T-6 T-2 T-2
Gambar 6. Organisasi TA Team dengan menggunakan main contractor
Full time
(T-21) > 50% Full time during
Central Steering preparation phase
TA Manager
brick team Committee External
Advising relationship
TA
Area
Area Kabag
Kabag
Section Scheduling G&A/
Planing Engineer Maintenance Procure- Budget HSE
Section
coordina-
coordina-
Area
forTA
Head
for TA
for Section Security
MPS tor ment monitoring supervisor
Head Sect tor
Head complex
TA
complex Head &PR
complex
(T-12)
Lead
Mechanical,
Process Civil Mon &
Planner electrical, & Contractor
engineer- Operations construc- Contl mat’l
instrument- supervisors
ing tion & service
ation
support
Scope Inspection Provide Provide Permitting Supervise Manage Manage Manage Budget Conduct Manage
collection work inputs and process Determine scaffold- contractor Schedule procure- planning safety security
Meeting Coordina- supervise inputs spading ing and teams for ment Cost induction/ Coordinate
process tion with mechanical during require- other civil preparation activities monitoring training PR with
owner external , electrical, prepara- ments work & Manage Conduct external
inspectors execution.
Roles
T-21 T-6 T-6 T-6 T-6 T-3 T-6 T-10 T-2 T-6 T-2 T-2
Gambar 7. Contoh kriteria pembuatan KPI TA untuk KLBB tahun 2010
TA Manager
TA
Man Reliability
Excess materials % of unused products vs TA Planner +- 5% Post TA report
procured Man Reliability
Scope change % volume change vs plan SMOM +- 5% TA manager receives monthly
TA Manager report
(Preparation)
before execution
Operational
Man Reliability
Man Eng & Dev
TA milestones % of milestones TA Manager and Planner 90 % TA planner submits in monthly
achieved completed on time (all) report
TA Execution members
Release and Days vs plan Man Eng & Dev 100% Shutdown report
decontamination Man Production
TA duration Mechanical days vs plan Man Maint Execution 100% Daily execution reports
( execution)
Operational
TA team
Startup Days vs plan until “on Man Eng & Dev 100% Start up reports
spec” Man Production
TA Manager
Scope change % volume change vs plan Man Reliability +-10% Post TA report
during execution Man Production
Man Eng & Dev
Lost time incidents Hours lost during TA execution TA Manager 0 HSE monitors throughout TA
HSE
Joblist katagori
non Inspection
RAM analysis
Yellow Blue
RAM
Results
Red
Cost Estimate
Out of TA
Job
7
Gambar 9 Overall process Detail Planning
Scope development
Scope Detail planning
challenge Contractor management
Work Contract
package package
development development
Process
F G
Job List Cost Budget
estimation allocation
A B C D E
BOM
Work scope Job plan Procurement Material
preparation
analysis development strategy scheduling
& grouping
Critical path list is made up of a leading critical path and potential critical paths (within 24 and 48
hours of leading critical path). Significant delays in the activities on these potential critical path
might lead to a delay in the TA schedule
<24 hours
<48 hours
Identifikasi
Work Develop
Task, Tools, Procurement Contractor Contractor
Job list Scope Contractor
& Material Strategy Selection Performance
Analysys Strategy
Required
Gambar 12. Flow proses effective contract development
Job Request
Ya
PTMN bisa
mengerjakan
Sendiri ?
Tidak
Ya
Apakah memerlukan
material spesific ?
Tidak
Ya
Ya
TA Overall
(1 Contractor)
MAIN
CONTRACTOR
BRUSH
SCAFFOLDING
PJIT
REACTOR & VESSEL &
HE & FIN FAN FURNACE PIPING RIGGING
REGENERATOR COLUMN
14
Gambar 15. Penentuan scope kontrak ke kelompok kontraktor
1 Outsource the
Each task Does the RU
starting have the
No entire TA or
resource in- complex level Chose between these
with the house for
management options based on ranking
most task
of :
critical management?
2 Outsource the Quality
skill group Schedule
consisting of Cost
Yes
several skill type
Can the RU
manage the No
task with
better quality
and schedule
management? Combination of these
3 contractor strategies
Yes Outsource can be deployed in a
specific skill single turnaround
type
Gambar 18. Proses penilaian resiko HSE (risk assessment process)
no gambar 16
Menentukan persyaratan
Pengesahan Formulir
oleh
Tim CSMS
Menentukan persyaratan
Tidak
Tidak
Ya
Persetujuan
Disetujui ?
Tim CSMS
Tidak
Disetujui TA
Manager ?
Ya
17
Gambar 20. Proses pra-kualifikasi aspek HSE (pre-qualification process)
Rev no
gambar
18
Penilaian
Risiko
Tidak
Tinggi ?
Ya
Ya Ya
Penerimaan
bersyarat
Memasukan Calon
dalam daftar
penawar
18
Rev no
Gambar 21. Proses seleksi kontraktor dari sisi HSE gambar
19
Departemen Pemrakarsa Pelayanan Kontrak Stakeholder Kunci Lainnya
A
Menyusun Dokumen
Penawaran
Mengadakan Pengumuman public
(Jika diperlukan)
B
Pertemuan Pra-Lelang
Departemen Pemrakarsa Pelayanan Kontrak Stakeholder Kunci Lainnya
Evakuasi Peninjauan
Kemampuan saat ini dan B
pelaksanaan K3LL masa
Menbagikan Undangan
lalu dalam Proposal lelang. Bagi Penawar
Menyusun penjelasan
Penawar dan menjawab Mengkoordinasi Rapat Penawar Menyusun Penawaran
Pemberian Kontrak Pertanyaan penawar Klarifikasi Penawaran (Proporsi menawarkan harga)
yang diperlukan
Mengadakan Rapat Klarifikasi
Penawaran
HSE KONTRAKTOR
Melaksanakan evaluasi Teknis Mengadakan evaluasi Non
dan keselamatan teknis (komersial)
Preparation
1
Install Scaffolding. Falling from height Use full body harness
Setting Equipments (vacuum, pump, hose). Raining Set canvas in work area
Lifting, using crane Falling items from lifting attempt Ensure that the knot is correct and safe
Reactor
2 Cooling
Install Nitrogen Connector Hose to Reactor Nozzle Nitrogen leak Ensure worker is in the right position
Filling Nitrogen into Reactor. Nitrogen leak Ensure worker is in the right position
Release
3 Manhole, Nozzle, Spool Piece, and Blind Flange.
Release Bolt using Hydratight / Wrench Flash due to Hydrocarbon leftover released to air Use chemical mask and prepare APAR.
Release Manhole, Nozzle, Spool Piece, and Blind Flange. Hydratight & Blower air-hose leak . Ensure that there's no leakage in Hydratight and Blower.
Lifting using crane Hit by loose Hydratight compressor hose Ensure worker is in the right position
Falling items from lifting attempt Ensure that the knot is correct and safe
Unloading
4 Catalyst and Reactor Entry.
Open Chimney and Tray. Hydrocarbon gas residue. Run Gas Test for Hydrocarbon and Oksigen
Unloading Catalyst. Lack of Oxygen. Conduct purging, using Chemical Mask.
Install lighting inside Reactor Catalyst dust. Use Breathing Apparatus or Air Line Compressor unit.
Install Scaffolding. Irritated eyes and respiratory problem Use Goggles and Breathing Apparatus.
Neutralizing with Ash Soda. Electrical shock use lighting < 50 Volt DC
Cleaning Reactor Walls Noise inside reactor due to activities conducted by Snapper Machine Use Ear Plug / Ear Muff.
Check Walls and Accessories of Reactor Standby officer near manhole
Install Blower. Use communication equipment
Isolate cable connectors well
Repair
5 with welding.
Grinding Fire due to welding Run gas test for Hydrocarbon and Oksigen
Welding Lack of Oxygen Conduct purging and prepare APAR.
Checking welding result Leakage in Pneumatic Tool. Use Breathing Apparatus.
Testing Prepare APAR.
Repairing/Replacing Thermowell. Standby officer near manhole
Loading
6 Catalyst..
Install Chimney and Tray. Catalyst dust. Run gas test for Hydrocarbon and Oksigen
Loading Catalyst , and leveling Lack of Oxygen Use Chemical Mask and Breathing Apparatus.
Install Nozzles. Standby officer near manhole
Box
7 Up
Installing Top Manhole. Stuck, hit, during bolt installation Install bolt correctly and safely
Tying bolt Falling equipment Ensure that the knot is correct and safe
Place equipments on the right place
SOURCE: OPI 21
Rev no
Gambar 23. Contoh work permitting prochedure & plan (roles & responsibilities) gambar
21
To prepare the equipment and properly tick the To clearly understand the conditions of the Whether the exact location of area/unit and
checklist items equipment and residual hazards equipment has been mentioned clearly
To identify and indicate any residual hazard to To discuss the above with issuing authority and Detail description of work is properly written
release equipment decide upon the protective measures Fire station has been informed and properly
To advise on protective measures and mention To describe the job and associated hazards to ticked
To carry out gas test wherever required and the workmen Permit issued to which Dept., Div.,Section and
enter the result with sign, date and time To ensure that safe procedure of execution are Craft - all mentioned
To discuss and explain with/to executing being followed Equipment preparation - Equipment has been
authority To check all the hand tools/devices/ equipment properly prepared, all checklist items area
Carry out electrical isolation whenever required and ensure that they are healthy properly checked & ticked
Close the permit when the job is complete or end To make the permit available at work site all the Residual Hazards - Identified and
of permit duration, which one is earlier time ticked/indicated
To preserve the permit for next one month To close the permit when the job is over or at the Protective Measures- Requirements identified
end of permit duration, which one is earlier and properly marked
To preserve the closed permit for next Other details - like provision of continuous
one month ventilation, additional precautions
Gas test
Test for all probable gases carried out
and reading recorded with sign., date and time
etc
Frequency of rechecking identified and carried
out
Electrical isolation was reqd., carried out and
documented
Both issuing and executing authority
signed mentioning name and signature, date and
time
Permit has been closed by both issuing
and executing authority with date and time
Closed permits has been kept properly filed and
being preserved for next one month
SOURCE: OPI 22
Rev no
gambar
Gambar 24. Contoh work permitting prochedure & plan (protective measures to be ensured for
residual hazardous before equipment handover) 22
SOURCE: OPI 23
Rev no
Gambar 25. Contoh work permitting prochedure & plan (equipment release prochedure,
gambar
section1: equipment)
23
Process: Execution – Work permit procedure and plan
Equipment release procedure
EQUIPMENT RELEASE CARD
SECTION 1 : EQUIPMENT
New Extension
Section no. / GSI
Duration for this permit : Date :
From : Date ……….. until Date ……….. Registration No. / K3LL
Time ……….. until Time ……….. Issued date
Work Location
Work Description
Work Executer
SECTION 2 : Safety requirements SECTION 3 : Pelampiran surat izin & dokumen lain
Safety Check List ( Filled by GSI ) Yes No Permit Letter Attachment Yes No
A. Hereby state the equipments already Hereby state the equipments already
1 Freed from pressure 1 Permit to enter confined/closed space
2 Drained 2 Permit to enter restricted area
3 Isolated by : Blank 3 Permit to block/closed the road
Released 4 Permit to operate heavy equipment
Locked valve 5 Permit to use fire hydrant
Labeled 6 Permit for electrical / Instrument
7 Permit for radiation work
SOURCE: OPI 24
Rev no
Gambar 26. Contoh work permitting prochedure & plan (equipment release prochedure,
gambar
section2: safety requirements; section 3: pelampiran surat ijin/dokumen
24
Process: Execution – Work permit procedure and plan
Equipment release procedure
EQUIPMENT RELEASE CARD
SECTION 2 : Safety requirements SECTION 3 : Pelampiran surat izin & dokumen lain
Safety Check List ( Filled by GSI ) Yes No Permit Letter Attachment Yes No
4 Steaming out / purging 8 Permit for excavation
5 Flushed with water 9 Permit to take Photo / Video
6 Mechanical / natural blowing 10 Permit to deactivate vital equipment
B. 1 All sewer, drain and valve within 15 m distance from the working area that already closed. 1 Job Safety Analysis ( JSA )
2 Remove all flammable material. 2 Sketch / Drawings / P&IDs / Work location PFDs
3 Stand by fire equipment 3 Work procedure
4 Stand by fire fighter 4 Inspection on special equipment
5 All welding equipment already in secured place, with grounding. 5 Data sheet ( MSDS )
6 Constant water spraying to the work equipment/area 6 Checklist / Blind list
7 Other work permit required 7 Tagging already in database
8 All machine, diesel, compressor already in safe location 8 Waste management / Disposal / Storage
9 ……………………….
10 ……………………….
SPECIAL INSTRUCTION :
APD required
Safety helmet Dust / Chemical Mask Safety glasses Safety suit / Appron
Gloves Face protection Respiration support Full Body Harness
Safety shoes Ear protection Chemical Suit …………………………….
SOURCE: OPI 25
Rev no
Gambar 27. Contoh work permitting prochedure & plan (equipment release prochedure,
gambar
section4: authorization)
25
Process: Execution – Work permit procedure and plan
Equipment release procedure
EQUIPMENT RELEASE CARD
SECTION 4 : AUTHORIZATION
I personally already checked the location and condition. Permission to guarantee the start of hot work
Authorized Operational Personnel ( GSI Authority )
Name: Signature: Date: Time:
All equipment and machines already checked, safe to use in work location.
Authorized Technical Personnel ( Authorized Engineer )
Name: Signature: Date: Time:
The work already completed, all material and equipment ready to operate with safe and clean condition
Not completed and the condition as follow…………………………………………………
SECTION 6 : GSI
I already check the equipment, material and work place and agree with the condition.
DISTRIBUSI : White original - Project Supervisor Yellow - Operational personnel / GSI Green - Technical expert Red - K3LL
SOURCE: OPI 26
TA Brick Content: Pre-execution
Isu-isu kunci
1 Bagaimana menjamin terlaksananya pekerjaan
yang berkualitas tinggi oleh vendor OEM
2 Untuk critical equipment, bagaimana menjamin
kualitas pekerjaan sesuai permintaan
3 Bagaimana menjamin komitmen para inspector
Check point
1 … … … … …
Pemilik otoritas
TA Brick Content: Pre-execution
Name of organization:
JSA No. Task: QAP No.
Client: Inspection authority: AI (LR Insurance Inc.) Date: 15 /11/2008
Project: Drg. Nos.: 2 - GP-1121 -1768, Rev.1 Item No: 99-D-20
P.O. No.: Item: Feed Coalescer Job No. GP-1121
Item: Feed Coalescer Code of Construction: ASME SEC. VIII, DIV.1, EDITION 2007
Quantity: 01 No.
Reference documents / procedures
Abbreviations ASME Section VIII Division 1, Edition 2007
GP - Grand Prix ASME Section V, Edition 2007
AI - Authorized Inspector ASME Section IX, Edition 2007
QC - Grand Prix Quality Control Engineer ASME Section II Part A, Edition 2007
MTC - Material Test Report or Certificate of complaince ASME Section II Part C, Edition 2007
Legend
H (Hold): Stage of Inspection beyond which work shall not progress unless GP-QCP-01-R8: Procedure for Radiographic Examination
accepted by QC/AI GP-QCP-02-R8: Procedure for Liquid Penetrant Examination
W (Witness): Stage of Inspection for which AI shall be notified in advance, GP-QCP-05-R3: Procedure for Hydrostatic test
However work may proceed with AI' s consent if AI is unable to undertake the GP-QCP-06-R2: Procedure for Heat Treatment
inspection GP-WP-01-R3: Written Practice for Training, Qualification and Certification
R (Review): QC to perform the activity, document all results of NDT Personnel
SUMBER: OPI
TA Brick Content: Pre-execution
Name of organization:
JSA No. Task: QAP No.
Client: Inspection authority: AI (LR Insurance Inc.) Date: 15 /11/2008
Project: Drg. Nos.: 2 - GP-1121 -1768, Rev.1 Item No: 99-D-20
P.O. No.: Item: Feed Coalescer Job No. GP-1121
Acceptance Responsibility
S. No. Operations Characteristics Extent Reference documents Format of record
Standard GP AI …
Drawing & Design Review of Drawing & Design ASME Section ASME Section VIII Drawing and
01 100% H R …
Calculations calculation VIII Division 1 Division 1 Design Calculations
Drawings and
ASME Section VIII
02 QA Plan Hold/ Witness/Review stages 100% ASME Section QAP H H …
Division 1
VIII Division 1
SUMBER: OPI
Start up phase 1) box up; tugas dan tanggungjawab
Note :
For application in RU’s , name
of the approver and executer
needs to be mentioned
TA Brick Content: Pre-execution
Dokumen/
Verifikasi & Berita Acara
Daftar Pelaksanaan
tanda Cross Check Penyerahan
Check List pekerjaan
Tangan oleh Work Permit Install Blind oleh Equipment dari
Blind yang Mecahnical
ME, PE & PE & Produksi Produksi ke ME,
dibutuhkan oleh ME
Produksi diketahui
oleh PE
34
Gambar 29. Organisasi pelaksana TA di frontline Rev no
gambar
27
ORGANISASI PELAKSANA TA DI FRONT LINE
KETERANGAN
Equipment Supervisor
Tukang Maintenace Area Section Head
35
Rev no
Gambar 30. Aktivitas awal pekerjaan (pre job activity) gambar
28
Pemberian Kontrak
Tidak
Selesai ?
Ya
Mobilisasi
Mengkomunikasikan
rencana HSE, Audit,
Menyelesaikan masalah
HSE
Pelaksanaan Kontrak
36
Rev no
gambar
Gambar 31. Inspeksi dan penilaian pelaksanaan pekerjaan berlangsung (work in progress)
29
Permulaan
Kunjungan
Planer TA & HSE
Perubahan Ya
Lingkup Kerja,
Bahaya lain
Tidak
Evaluasi sementara :
Daftar pemeriksaan Audit,
Daftar Program
Tindakan
Perbaikan yang
dilakukan
Ya
Tidak
Tidak
Pekerjaan
Selesai ?
Ya Tindakan
Evaluasi Akhir
Kedisiplinan
37
Rev no
Gambar 32. Proses evaluasi dan laporan akhir gambar
30
Menyimpulkan Laporan Evaluasi
Akhir
Memperoleh persetujuan
Manager TA
38
Proses shutdown
39
B. TA EXECUTION
40
Gambar 33. Tahapan kegiatan dalam rangka untuk Rev no
handover sampai dengan tahap PSSR dan start up gambar
31
Dokumen/
Box up Daftar Pre-
Berita Acara
Pelaksanaan equipment oleh Un-Install Cross Check Start up
Penyerahan
pekerjaan ME yang telah Blind/ Install Blind safety review Start up oleh
Equipment dari
mechanical diverifikasi Sorokan oleh PE & oleh HSE, Produksi
Produksi ke ME,
oleh ME oleh PE dan oleh ME Produksi ME, PE dan
diketahui
Produksi Produksi
oleh PE
41
Lampiran 4
in the scope
consequence benefit analysis
out of scope 0
Matrik Penentuan Joblist TA
Integrity Aspect
Fungsi Kegiatan
Mechnical Process Equipment
Symptom
Reliability
Asessment
Symptom
Maintenance Planning & Support
Asessment
Symptom
Maintenance Execution
Asessment
Symptom
Production
Asessment
Symptom
Engineering & Development
Asessment
Symptom
HSE
Asessment
Symptom
Refinery Planning & Optimization
Asessment
Quality management process
44
HSE management process
45
TA execution readiness
Job
Job Work Equipment Job quality
Job plan safety Box up PSSR
schedule permit release plan
analysis
Tahapan eksekusi
Release
Shutdown Deconta- to TA TA scope Handover to
execution PSSR
execution mination execution operation
team
TA brick content: Execution
5A PSSR: Process flow and roles & responsibilities
Group
PasangBlind/Sorokan Stationary,
Audit Doc Box Up …
Proses, dan
Safety
Buka Man
Hole
Audit Doc Hydro Group
…
Test Stationary
Cleaning/Repair/Replace
Group
Equipment
Cabut Blind Proses & …
Readiness status
produksi
Studi Keenjiniringan
Audit studi ABP
Studi ABP
Audit doc punch list
Group
Proses &
PIC refer produksi
check list Konstruksi
aktivitas Audit Doc Prosedur/STK
MOC Group
Stationary,
rotating,
Punch list
dan Safety
6 Handover to operations
Engineering completion
Instrument and Electrical (I&E) TA engineer/ ---
safeguarding/IPF checks on the system Process engineer
complete
SOURCE: OPI 50
Start up process flow
Preparation
of auxiliary Bringing
Preliminary Elimination Tightness Backing in Elimination
the unit
preparation equipment of air of air fuel gas of water
and services on-stream
TA brick content: Shut down and Start Up Procedure
2A Startup procedure – Preliminary preparations
Checklist
Statu PIC
1 Seluruh material asing sudah dipindah dari seluruh vessels, s
columns, dan peralatan lainnya
2 Trays, floats, float arms, dan jalur-jalur pipa sudah bersih, ada di
tempatnya masing-masing dan berfungsi dengan baik
3 Manways, pipe flanges dalam kondisi tertutup & dibaut/bolded
4 Sudah periksa kekencangan semua sambungan/flange yang
dibuka selama TA
5 Material scaffolding, alat-alat, dan materi surplus sudah
dipindahkan dari area operasi
6 Noda, debu, kotoran sudah disingkirkan dari firebox
dapur/furnace
7 Blind/sorokan untuk shutdown sudah disingkirkan dan
blind/sorokan yang hendak dipakai sudah terpasang
8 Kartu terima peralatan diberikan dadri eksekusi ke produksi
9 Tim PSSR memeriksa dan konfirmasi