Professional Documents
Culture Documents
Program of Work Budget b1
Program of Work Budget b1
Lao Construction
Km. 12 Diversion Road, Panacan, Davao City
MONTHLY BUDGET
Month of November, 2015
14LO-0029
Widening of Davao River Bridge (B01458MN) and Approaches along Davao City Diversion Road
Davao City
CONTRACT ID : 14LO-0029
Project Name : Wid Widening of Davao River Bridge (BO1458MN) and
Approaches along Davao City Diversion Road, Davao City
Location : Davao City
SUMMARY
I - REVENUE
1.0 Contract Amount (Monthly Projection, B1) 26,476,525.66
2.0 Taxes 7% 1,654,782.85
3.0 Net Amount Receivable 24,821,742.81
II - EXPENSES
1.0 Total Direct Construction Cost (Month of Nov.) 16,916,783.14
2.0 Indirect Cost (Month of Nov.) 556,149.25
Total Expenses 17,472,932.39
III - INCOME
1.0 Net Income 7,348,810.41
2.0 Percentage 29.61%
Page 3 of 78
PROJECTED ITEM OF WORK
Original Contract Previous Qty. Qty Projected this Total Cost this
Item No.
400(22)b High Strain Dynamic TestDescription
(P.D.A) Unit
each Unit Cost
322,000.00 6.00 1,932,000.00 %Wt.
1.219 - Total Qty to Date - % Wt. -
Accomp. - Month Billing
401 Railing ln.m. 4,528.79 277.36 1,256,104.65 0.792 - - - -
404(a) Reinforcing Steel, Grade 40 kg. 91.19 87,148.00 7,947,026.12 5.013 - - - -
404(b) Reinforcing Steel, Grade 60 kg. 98.74 50,640.00 5,000,193.60 3.154 - - - -
405(1) Structural Concrete, Class A cu.m. 11,841.66 707.54 8,378,448.12 5.286 - - - -
405(2) Structural Concrete Class B cu.m. 6,583.23 1.13 7,439.05 0.005 - - - -
Prestressed Structural Concrete Members (Girder Type IV-
406(1)a each 1,030,400.00 12.00 12,364,800.00 7.800 - - - -
B - 24.40 m)
Prestressed Structural Concrete Members (Girder Type IV-B
406(1)b each 1,223,600.00 18.00 22,024,800.00 -
- 29.40 m) 13.894 - - -
412 Elastomeric Bearing Pad (Duro 60) each 21,252.00 12.00 255,024.00 0.161 - - - -
Provide/Maintain and Remove Craneway Steel Component
SPL 5 (Materials to be turned over to the government after l.s. 11,886,457.72 1.00 11,886,457.72 7.499 0.13 0.370 0.50 4,397,989.36 2.774
completion of project)
Page 4 of 78
Project Name: Widening of Davao River Bridge (B01458MN) and Approaches along Davao City Diversion Road
DETAILED BUDGET SUMMARY (for the month of Novemeber 2015)
RF PAYROLL IN-HOUSE RENTAL ACCOUNTS PAYABLE EX-STOCKS
Item No. Description TOTAL
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
Part A - Facilities for the Engineer
A.1.1 Camphouse w/ 2CR for Male and Female -
Prepared by:
JOSELITO L. HENIEL
Site Engineer
PROJECT I.D. 14LO-0029
PROJECT Name Consruction of Widening of Davao River Bridge (BO1458MN) and
Approaches along Davao City Diversion Road, Davao City
LOCATION Davao City
SUPERVISION AND OVERHEAD COST
484,149.25
Prepared by:
JOSELITO L. HENIEL
Site Engineer
DETAILED COST ESTIMATE :
PROJECT ID : 13LO-0058
PROJECT Name : Widening(Concreting)/Rehab./Improvement of Davao-Cotabato Road
(Davao City-Jct. Digos) including ROW-Toril-Inawayan Section, Davao City
ITEM & DESCRIPTION : SPL-4 - Traffic Management
QUANTITY : - l.s.
A. MATERIALS
DESCCRIPTION UNIT QTY. UNIT PRICES TOTAL COST
-
Warning Sign each 1,500.00 -
10 - Roadwork Ahead sign
10 - Roadwork Machinery Ahead sign
10 - Workmen Ahead sign
10 - Temporary Hazard Marker
Informatory Signs each 1,500.00 -
Guide Signs each 1,000.00 -
Bollards (Bamboo) each 50.00 -
Blinking Lights each 2,500.00 -
Caution Tape roll 230.00 -
Tiebox roll 45.00 -
-
B. EQUIPMENT SUB-TOTAL P -
NO. DESCRIPTION UNIT CAL.DAYS UNIT COST TOTAL COST
Hauling of Equipments :
-
-
1.00 Mini Dumptruck 1.00 1,120.00 -
JOSELITO L. HENIEL
Site Engineer
Unit Cost 169,044.71
157,211.58
DETAILED COST ESTIMATE:
PROJECT ID : 13LO-0058
PROJECT Name : Widening(Concreting)/Rehab./Improvement of Davao-Cotabato Road
(Davao City-Jct. Digos) including ROW-Toril-Inawayan Section, Davao City
ITEM & DESCRIPTION : B.4(1) - Construction Survey and Staking
QUANTITY : 2.50 km
A. MATERIALS
DESCCRIPTION UNIT QTY. UNIT PRICES TOTAL COST
Nails kg 60.00 -
Tie Box pc. 45.00 -
Paints gal 450.00 -
-
-
-
B. EQUIPMENT SUB-TOTAL -
NO. DESCRIPTION UNIT CAL.DAYS UNIT COST TOTAL COST
Prepared by:
JOSELITO L. HENIEL
DETAILED COST ESTIMATE:
PROJECT ID : 14LO-0029
PROJECT Name : Consruction of Widening of Davao River Bridge (BO1458MN) and
Approaches along Davao City Diversion Road, Davao City
ITEM & DESCRIPTION : 400(17)a - Concrete Piles Cast in Drilled Holes 2.00m dia
QUANTITY : 142.00 l.m.
A. MATERIALS
DESCCRIPTION UNIT QTY. UNIT PRICES TOTAL COST
Steel Casing 2.0m dia kg 56,566 40.00 2,262,629.08
RSB G40 kg 17,769 40.00 710,760.00
RSB G60 kg 116,486 40.00 4,659,440.00
Tie wire #16 kg 2,014 50.00 100,691.25
Welding Rod kg 1,343 60.00 80,553.00
Readymix Concrete cu.m. 468 900.00 421,571.30
Portland Cement bags 5,621 230.00 1,292,818.67
Polymer bags 45 7,500.00 334,580.40
10x10x6m I-Beam (square hole) kg 1,060 50.00 52,987.50
2" dia G.I. Pipe s20 (sonic) pcs 163 500.00 81,500.00
Misc. 299,925.94
-
F&H 393,353.04
B. EQUIPMENT SUB-TOTAL P 10,690,810.18
NO. DESCRIPTION UNIT CAL.DAYS UNIT COST TOTAL COST
Rebar Caging
1.00 Labor Pakyaw l.s. 3.00 402,765.00
Bored Piling
2.00 Crane Operator day 28 450.00 25,200.00
1.00 Bhoe Operator day 28 450.00 12,600.00
1.00 Foreman day 87 500.00 43,500.00
4.00 Rigger day 28 400.00 44,800.00
5.00 Laborer day 28 200.00 28,000.00
1.00 Electrician day 28 300.00 8,400.00
1.00 Mechanic day 28 350.00 9,800.00
4.00 Welder day 28 350.00 39,200.00
Prepared by:
JOSELITO L. HENIEL
Site Engineer
Steel Casing: Length Diameter thickness Radius Circum x-section Volume unit wt
Pier 1 2 0.012 1.006 6.320899 0.075851 0 7850
Pier 2 30 2 0.012 1.006 6.320899 0.075851 2.275524 7850
Pier 3 35 2 0.012 1.006 6.320899 0.075851 2.654778 7850
Pier 4 30 2 0.012 1.006 6.320899 0.075851 2.275524 7850
Total
Concrete Mix
Length Diameter Radius x-section Volume Dirty Conc.
Pier 1 2 1 3.1416 0 0.000
Pier 2 42 2 1 3.1416 131.9472 6.597
Pier 3 50 2 1 3.1416 157.08 7.854
Pier 4 50 2 1 3.1416 157.08 7.854
142
284 Total
Polymer
Length Diameter Radius x-section Volume rate (ltrs/bag)
Pier 1 2 1 3.1416 0 10000
Pier 2 42 2 1 3.1416 131947.2 10000
Pier 3 50 2 1 3.1416 157080 10000
Pier 4 50 2 1 3.1416 157080 10000
142
284 Total
Total
kg
0
17863
20840
17863
56566
113131
kg
0
139
165
165
468
937
kg
0 12500
13
16
16
45
89
kg
0
353
353
353
1060
DETAILED COST ESTIMATE:
PROJECT ID : 14LO-0029
PROJECT Name : Consruction of Widening of Davao River Bridge (BO1458MN) and
Approaches along Davao City Diversion Road, Davao City
ITEM & DESCRIPTION : SPL5 - Provide/Maintain/Remove Craneway Steel Component
QUANTITY : 0.37 l.s.
A. MATERIALS
DESCCRIPTION UNIT QTY. UNIT PRICES TOTAL COST
Steel Component kg 32,383 40.00 1,295,321.60
-
-
-
Welding Rod kg 324 60.00 19,429.82
Acetylene-Oxygen set 6 2,500.00 16,191.52
-
-
-
-
Misc. 6,654.71
-
-
1.00 Service crane 45t unit 30 15,156.00 454,680.00
1.00 Crawler Bhoe unit 30 10,010.03 300,300.78
1.00 Vibro Hammer unit 30 8,400.00 252,000.00
1.00 Genset unit 30 1,800.00 54,000.00
-
-
-
2.00 Cutting Outfit unit 30 500.00 30,000.00
2.00 Welding Machine 500amp unit 30 500.00 30,000.00
-
-
Bored Piling
1.00 Crane Operator day 30 450.00 13,500.00
1.00 Bhoe Operator day 30 450.00 13,500.00
1.00 Foreman day 30 500.00 15,000.00
2.00 Rigger day 30 400.00 24,000.00
4.00 Laborer day 30 200.00 24,000.00
1.00 Electrician day 30 300.00 9,000.00
1.00 Mechanic day 30 350.00 10,500.00
4.00 Welder day 30 350.00 42,000.00
Prepared by:
JOSELITO L. HENIEL
Site Engineer