Professional Documents
Culture Documents
Group 10 - Workforce Scheduling - FINAL
Group 10 - Workforce Scheduling - FINAL
Group 10 - Workforce Scheduling - FINAL
Prod
Recently Davis started hiringtemporary workers supplied by WorkForce Unlimited
WorkForce Unlimited offered to provide temporary employeesunder three contra
The three options are summarized:
Managerial Report
Therefore,
Months
Number of months hired (M) 1
Number of months hired (M) 2
Number of months hired (M) 3
Objective Function:
Minimize: 2875(E11+E12+
5675(E21+E22+E23+E24
8375(E31+E32+E33+E34
One Constraint is required for each of the six months
Constraint 1
Need 10 additional employees in Janua
E11= number of temporary employees
E21= number of temporary employees
E31= number of temporary employees
E11+E21+E31=10
Constraint 2
Need 23 additional employees in Febru
E12, E22 and E32 are the number of te
hired under Option 2 or Option 3 in Jan
E12 + E22 + E32 + E21 + E31 = 23
Constraint 3
Need 19 additional employees in Marc
E13 + E23 + E33 + E31 + E22 + E32
Constraint 4
Need 26 additional employees in Apri
E14 + E24 + E34 + E32 + E23 + E33
Constraint 5
Need 20 additional employees in May
E15 + E25 + E35 + E33 +E24 + E34
Constraint 6
Need 14 additional employees in June
E16 + E26 + E36 + E34 + E25 + E35
Non-Negativity Constraint
(Eom) >= 0
Question 1.) A Schedule that shows the number of temporary employees that Davis should hire each
January February
Option 1 0 4
Option 2 0 0
Option 3 10 9
Training
Option 1 875
Option 2 875
Option 3 875
January February
Option 1 2000 2000
Option 2 4800 4800
Option 3 7500 7500
January February
Option 1 0 4
Option 2 0 0
Option 3 10 9
10 23
Sign = =
Requirement 10 23
Question 2.) A summary table that shows the number of temporary employees that Davis should hir
Provide summary totals showing the total number of temporary employees hired, tota
Training Contract
Option 1 875 2000
Option 2 875 4800
Option 3 875 7500
Total
Question 3.) If the cost to train each temporary employee could be reduced to $700 per month, wha
Discuss the implications that this effect on the hiring plan has for identifying methods f
How much of a reduction in training costs would be required to change the hiring plan
January February
Option 1 2000 2000
Option 2 4800 4800
Option 3 7500 7500
January February
Option 1 10 23
Option 2 0 0
Option 3 0 0
10 23
Sign = =
Requirement 10 23
January February
Option 1 0 4
Option 2 0 0
Option 3 10 9
We can see that the total cost of the plan reduced to $302400 in comparison to $31352
A training cost of $700 per temporary employee would recommend Davis Instruments
If the training cost kept getting lower, option 1 would still be the vital option to choose
Question 4.) Suppose that Davis hired 10 full-time employees at the beginning of January in order to
If Davis can hire full-time employees for $16.50 per hour, including fringe benefits, wha
Assume that full-time and temporary employees both work approximately 160 hours p
January February
Option 1 2000 2000
Option 2 4800 4800
Option 3 7500 7500
January February
Option 1 0 4
Option 2 0 0
Option 3 0 9
0 13
= =
Requirement 0 13
Hired
10
23
19
26
20
14
Davis Instruments should not continue to contract with WorkForce for temporary empl
Hiring 10 full-time employees ($313,175) compared to hiring temporary employees ($3
Davis Instruments will save more money by hiring 10 full-time employees by $350 and
Workforce Scheduling
s located in Atlanta, Georgia. Product demand varies considerably from month to month, causing Davis extreme difficulty in
s supplied by WorkForce Unlimited, a company that specializes in providing temporaryemployees for firms in the greater At
rary employeesunder three contract options that differ in terms of the length of employment and the cost.
anagerial Report
Total Costs = Contract Cost + Training Cost
Objective Function:
Minimize: 2875(E11+E12+E13+E14+E15+E16)+
5675(E21+E22+E23+E24+E25+E26)+
8375(E31+E32+E33+E34+E35+E36)
d for each of the six months
(Eom) >= 0
mployees that Davis should hire each month for each contract option
Decision Variables
March April May June
0 0 3 0
0 3 0 0
0 14 0 0
Cost Matrix
March April May June
2000 2000 2000 2000
4800 4800 4800 100000
7500 7500 100000 100000
Cost Matrix
March April May June
0 0 3 0
0 3 0 0
0 14 0 0
19 26 20 14
= = = =
19 26 20 14
rary employees that Davis should hire under each contract option, the associated contract cost for each option, and the associated t
of temporary employees hired, total contract costs, and total training costs.
Summary Table
Number of employees Training cost Hiring cost Total Cost
7 6125 14000 20125
3 2625 14400 17025
33 28875 247500 276375
43 37625 275900 313525
be reduced to $700 per month, what effect would this change have on the hiring plan? Explain.
ng plan has for identifying methods for reducing training costs.
e required to change the hiring plan based on a training cost of $875 per temporary employee?
Resolving the LPP with the reduced costs (700) indicates that Davis should hire all temporar employees on a 1 month basis
specifically to meet each months employee needs
If training costs were any lower, this would still be the optimal hiring strategy.
Cost Matrix
March April May June
2000 2000 2000 2000
4800 4800 4800 100000
7500 7500 100000 100000
Cost Matrix
March April May June
19 26 20 14
0 0 0 0
0 0 0 0
19 26 20 14
= = = =
19 26 20 14
t the beginning of January in order to satisfy part of the labor requirements over the next six months.
r hour, including fringe benefits, what effect would it have on total labor and training costs over the six-month period as compared t
oth work approximately 160 hours per month. Provide a recommenda_x0002_tion regarding the decision to hire additional full-time
Cost Matrix
March April May June
2000 2000 2000 2000
4800 4800 4800 100000
7500 7500 100000 100000
Cost Matrix
March April May June
0 0 3 0
0 3 0 0
0 4 0 0
9 16 10 4
= = = =
9 16 10 4
Inequality Requirement
= 10
= 23
= 19
= 26
= 20
= 14
with WorkForce for temporary employees and instead hire 10 full-time employees.
d to hiring temporary employees ($313,525) results in $313,525 - $313,175 = $350 cheaper.
10 full-time employees by $350 and will only have to pay for a one time training cost per employee after hiring.
vis extreme difficulty in workforce scheduling.
firms in the greater Atlanta area.
Cost
$2000
$4800
$7500
Total
7
3
33
n a 1 month basis
n a 1 month basis
Total
112
0
0
Total
7
3
33
11125
Variable Cells
Final Reduced Objective Allowable Allowable
Cell Name Value Cost Coefficient Increase Decrease
$C$21 Option 1 January 10 0 2700 100 1E+030
$D$21 Option 1 February 23 0 2700 100 1E+030
$E$21 Option 1 March 19 0 2700 100 1E+030
$F$21 Option 1 April 26 0 2700 100 1E+030
$G$21 Option 1 May 20 0 2700 100 1E+030
$H$21 Option 1 June 14 0 2700 100 1E+030
$C$22 Option 2 January 0 100 5500 1E+030 100
$D$22 Option 2 February 0 100 5500 1E+030 100
$E$22 Option 2 March 0 100 5500 1E+030 100
$F$22 Option 2 April 0 100 5500 1E+030 100
$G$22 Option 2 May 0 100 5500 1E+030 100
$H$22 Option 2 June 0 98000 100700 1E+030 98000
$C$23 Option 3 January 0 100 8200 1E+030 100
$D$23 Option 3 February 0 100 8200 1E+030 100
$E$23 Option 3 March 0 100 8200 1E+030 100
$F$23 Option 3 April 0 100 8200 1E+030 100
$G$23 Option 3 May 0 95300 100700 1E+030 95300
$H$23 Option 3 June 0 98000 100700 1E+030 98000
Constraints
Final Shadow Constraint Allowable Allowable
Cell Name Value Price R.H. Side Increase Decrease
$C$24 January 10 2700 10 1E+030 10
$D$24 February 23 2700 23 1E+030 23
$E$24 March 19 2700 19 1E+030 19
$F$24 April 26 2700 26 1E+030 26
$G$24 May 20 2700 20 1E+030 20
$H$24 June 14 2700 14 1E+030 14