Project: DRAWING 1

Item Times Dims Sqrg Total Qty Units


1.1

1.1.01

15.30
8.30 126.99

(5.00)
2.00 10.00
116.99 m2

1.1.02
116.99 m2

1.1.03

15.30
8.30
0.50 63.50

(5.00)
2.00
0.50 (5.00)
58.50 m3
1.1.04
45.08
0.53
0.80 19.11

13.41
0.53
0.80 5.69
24.80 m3

1.1.05
24.80
1.00
1.00 24.80

(58.16)
0.23
0.58 (7.76)

-7.13
1.00
1.00 (7.13)
9.91

1.1.06 14.89

1.00
1.00
1.1.07
1.00 1.00 item

1.00
1.1.08 1.00
1.00 1.00 item
1.1.09

1.1.10
45.08
0.53 23.89

2 45.08
0.58 52.29

8.23
0.53 4.36

6.23
0.53 3.30

2 6.23
0.58 7.23

2 8.23
0.58 9.55
100.62 m2

1.1.11
45.08
0.53
0.23 5.50

13.42
0.53
0.23 1.64

7.13 m3
1.1.12

45.08
0.88 39.67

13.08
0.88 11.51
51.18 m2

1.1.13

5.54
4.77 26.43

2 7.54
4.66 70.27
96.70 m2

1.1.14 96.70 m2

1.1.15 96.70 m2

1.1.16 96.70 m2
1.1.17 96.70 m2

1.1.18 96.70 m2

1.1.19

60.00
60.00 m
Descriptions
SUBSTRUCTURE

Clearing site of bushes, scrub, undergrowth and the like


and grubbing up their roots, and burn all arisings or cart
away from site as directed (including cutting down trees
not exceeding 600mm girth)

Length 5000+5000+5000=15000mm
Add 2/147.5=295mm
15295mm.
width 6000+2000=8000mm
Add 2/147.5=295mm
8295mm
Ddt void
Length= 5000mm
width = 2000mm

SMM D4(C)
&
Excavating top(vegetable) soil to be preserved, avarage
200mm deep, including storing in temporary spoil heaps
on site away from excavations and later spread and level
where directed on site

SMM D3

Excavating surfaces over 300mm deep to reduce levels,


starting from the stripped level but not exceeding 1.5m
deep, and cart away arisings from site - PROVISIONAL

Length =15295mm. a.b


width = 8295mma.b
Average depth to reduce level: 500mm

Ddt Void
Length=5000mm a.b
width =2000mm a.b
Average depth to reduce level: 500mm

SMM (D6)
Excavating trenches to receive strip foundations, starting
from the reduced level but not exceeding 1.5m deep

Mean girth Length 2/14770 + 2/7770 = 45080mm


Width 147.5+230+147.5 =525 mm
Max. depth taken = 800mm

Internal Trenches,
length 6000+8000=14000mm
less 2 /2/147.5=590mm =13410mm
Width = 525mm
Depth=800mm

SMM D9
&
Backfilling with selected excavated material around
foundations, compacted to 98% MDD (modified
AASHTO) to Engineer's approval - PROVISIONAL
Total excavation =24800 a.b

less plinth wall total length=58160mm


depth 800-225=575mm

less concrete in strip =7.13m3

SMM D15(C)
&
Dispose off surplus off site in heaps

Planking and strutting to uphold the sides of excavation by


whatever means necessary (other than special shoring and
steel sheet piling
SMM D19

Keeping excavations free from water(i.e all water excapt


spring or running water.
SMM D18(a)
Extra over all excavations for excavation in rock-provisional
SMM D5 ( e)

Treating the surfaces of the ground or the surface using


anti termite treatment to subsoil of filling .
mean girth=45080mm a.b
width=525 mm

mean girth=45080mm a.b


Depth 800-225=575mm

internal trenches (longer)


Length 8000+2/115=8230mm
width=525mm a.b

length 6000+2/115=6230mm
width = 525mm a.b

length=6230mm a.b
Depth=575mm

length =8230mm a.b

Plain in-situ concrete, Class 15/20 mm aggregates (or


minimum mix ratio 1:3:6) in strip foundations to receive
plinth wall, manually vibrated (measured separately)

Mean girth Length = 45080mm


Width = 525mm
Depth =225mm

Internal Trenches=13410mm a.b


Width = 525mm
Depth =225mm

SMM F2
230mm thick solid bricks plinth wall bonded in class II
(1:3) Cement sand mortar strecher bond with 25mm hopp
iron reinforcement every after two courses
Mean girth Length=45080mm
Max height = 800-225(Fdn concrete)+200+100=875mm

Internal plinth wall. 7540+5540=13080mm


Max height = 800-225(Fdn concrete)+200+100=875mm
SMM G4(a)

150mm thick bed of hardcore, well ramped and compacted


to receive blinding layer

Room 1
Length 6000-2/230=5540mm
Width 5000-230=4770

Room 2.
Length 8000-2/230=7540mm
Width 5000-230-115=4655mm
SMM D20(a)

&
Apply 50mm thick quality sand blinding on top of the
hardcore .
SMM D16(a)
&
Anti- termite treatement to hardcore surfaces
SMM D2

&

Lay 1000 gauge clear polythene sheet damp proof


membrance on 50mm thick sand blinding to prevent
moisture (m.s) to receive concrete bed (m.s)
SMM G96
&
100mm thick ground floor slab in reinforced cast in-situ
concrete class 25/20mm aggregates ( or minimum mix ratio
1:3:6) vibrated using a pocker and well cured before
superstructure.
SMM F7
&
50mm sand screed in ratio 0f 1:3 well finished with a
wooden float.
SMM T2

Lay an asphalt bituminous felt Dpc material underneath


the external and internal walls
external wall line 2/3/5000+2/8000=46000mm
internal walls 8000+6000=14000mm
total=60000mm
NAME STUDENTS NUMBER
TURINOMUJINI DAVIS 19/U/20241/PSA

MUHANGUZI JOHNSON 19/U/0906

NDUHURA RICHARD 19/U/20085/PS

ALINAITWE SHALIFU 19/U/22191/PSA

BUHWA EMMANUEL 19/U/19557/PSA

KAYIWA PHILIP 19/U/19668/PS


TAK
REGISTRATION NUMBER
1900720241

1900700906

1900720085

1900722191

1900719557

1900719668
Element: SUBSTRUCTURE
Item Descriptions QTY
1.1 SUBSTRUCTURE
1.1.01 Clearing site of bushes, scrub, undergrowth and the like and grubbing up their roots, 116.99
and burn all arisings or cart away from site as directed (including cutting down trees
not exceeding 600mm girth)
1.1.02 Excavating top(vegetable) soil to be preserved, avarage 200mm deep, including 116.99
storing in temporary spoil heaps on site away from excavations and later spread and
level where directed on site
1.1.03 Excavating surfaces over 300mm deep to reduce levels, starting from the stripped 58.50
level but not exceeding 1.5m deep, and cart away arisings from site -
PROVISIONAL
1.1.04 Excavating trenches to receive strip foundations, starting from the stripped level but 24.80
not exceeding 1.5m deep
1.1.05 Backfilling with selected excavated material around foundations, compacted to 98% 9.91
MDD (modified AASHTO) to Engineer's approval - PROVISIONAL
1.1.06 Remove surplus excavated material from site - PROVISIONAL 14.89
1.1.07 Planking and strutting to uphold the sides of excavation by whatever means are 1.00
necessary (other than special shoring or steel sheet piling)
1.1.08 1.00
Keeping excavations free from water(i.e all water excapt spring or running water.
1.1.09
Extra over all excavations for excavation in rock-provisional

1.1.10 100.62
Treating the surfaces of the ground or the surface using anti termite treatment to
subsoil of filling .

1.1.11 Plain in-situ concrete, Class 15/20 mm aggregates (or minimum mix ratio 1:3:6) in 7.13
strip foundations to receive plinth wall, manually vibrated (measured separately)
1.1.12 230mm thick solid bricks plinth wall bonded in class II (1:3) Cement sand mortar 51.18
strecher bond with 25mm hopp iron reinforcement every after two courses
1.1.13 96.70
150mm thick bed of hardcore, well ramped and compacted to receive blinding layer
1.1.14 Apply 50mm thick quality sand blinding on top of the hardcore . 96.70
1.1.15 Anti- termite treatement to hardcore surfaces 96.70
1.1.16 Lay 1000 gauge clear polythene sheet damp proof membrance on 50mm thick sand 96.70
blinding to prevent moisture (m.s) to receive concrete bed (m.s)
1.1.17 96.70
100mm thick ground floor slab in reinforced cast in-situ concrete class 25/20mm
aggregates ( or minimum mix ratio 1:3:6) vibrated using a pocker and well cured
before superstructure.
1.1.18 50mm sand screed in ratio 0f 1:3 well finished with a wooden float. 96.70
1.1.19 Lay an asphalt bituminous felt Dpc material underneath the external and internal 60.00
walls
UNIT RATE AMOUNT

m2

m2

m3

m3

m3
m3
item

item

m2

m2

m3

m2

m2

m2
m2
m

m2

m2
m

You might also like