FAJ Construction and Development Corporation

Subject : Change Order No. 4 - Summary

Item No Project Name Total Amount Remarks

A Bacolod Project - Change Order


I General Requirements / Preliminaries 326,178.97 - Project Overhead Cost

II For Additional Works

1 Revision of Perimeter Wall Paint


- Arch . Jenina instructed FAJ to rectify wall painting due to appearance of dark
2a Konstrukt to Konstrukt plus Aquaseal 763,021.61
marks when the wall was soaked with rain.
- Arch . Jenina instructed FAJ to rectify wall painting due to appearance of white and
2b Konstrukt plus Aquaseal to Konstrukt plus Acrytex Top Coat 205,180.39
dark marks when Aquaseal washed out and soaked with rain.
- Arch . Jenina instructed FAJ to paint the wall with coral paint to prevent
2c Konstrukt plus Acrytex Top Coat to Coral Paint 432,374.39
appearance of white and dark marks.
- Not included in original plan / No details.
2 Dental Room - Additional Works 370,682.08
- Sunfu supplier of dental chair provided plan for water, air, vacuum and drain.
- Not included in original plan / No details.
3 Additional Ramp for Elevated Septic Tank 58,773.60
- Due to elevated septic tank.
4 Additional Countertop Support for Virces Requirements 54,237.60 - Virces requirements for granite countertop.
- Not included in original plan / No details.
5 Additional Sliding Door for Admin Cubicle. 33,760.80 - Arch. Jenina instructed FAJ to install sliding door for 2 cubicle room at admin
room.
- Not included in original plan / No details.
6 Additional Abang For All Hanging Cabinet and Signages 66,268.80 - Arch. Jenina instructed FAJ to provide abang for hanging cabinets strip lights of
Virces.
- Due to unupdated plan, some abang for sanitary and waterline are in conflict with
7 Adjustment of sanitary and waterline pipe in conflict with cabinet 33,998.40
the cabinets.
- Not included in original plan / No details.
8 Additional Lights for Various Toilets 51,694.40 - Arch. Jenina instructed FAJ to provide additional lights for various toilets (OPD, lab
GF, Xray and ultrasound toilet).
- Due to continous buzzing of T5 cove light. Arch. Jenina agreed to change installed
9 Removal of existing cove light and installation of strip light 38,592.00
light to strip light for all lights not less than 2m.
- As per plan, 1 sump pump only.
10 Additional Sump Pump 65,942.40 - FAJ consulted Arch. Jenina if it is 1 sump pump only will be provided for sump pit.
- Arch. Jenina, agreed to have another sump pump for back up.

Subtotal 2,500,705.44

B Horshoe Project - Change Order


A. Garden and Garage
FAJ Construction and Development Corporation
Subject : Change Order No. 4 - Summary

Item No Project Name Total Amount Remarks

Replacement & Installation of New Stair Handrail at Grotto, Cacao


59,482.50 - Additional scope of works. Not included in the Original Proposal
and Pool Area
Additional Pebbles installation at Vertical Planters & Black Stairs
89,369.40 - Additional scope of works. Not included in the Original Proposal
Landing
Repair & Replacement of Bollard, Post lamp, wall mounted lights &
632,276.40 - Additional scope of works. Not included in the Original Proposal
busted lights including at Senyora Oca

Construction of 3 units of catch basin & fabrication of manhole cover 22,794.00 - Additional scope of works. Not included in the Original Proposal

Repair of Two-Old Pumps at Sump Pit 37,777.80 - Additional scope of works. Not included in the Original Proposal

Repainting of main & service gate 37,905.00 - Additional scope of works. Not included in the Original Proposal

Repainting of wall-mounted lights 27,090.00 - Additional scope of works. Not included in the Original Proposal

Fabrication and installation of removable cover at vertical planters 24,360.00 - Additional scope of works. Not included in the Original Proposal

Hauling & Transfer of Piedra, Vases and Other Garden Materials to


75,000.00 - Additional scope of works. Not included in the Original Proposal
Batangas

B. Pool House

Repair of Canopy 53,937.00 - Additional scope of works. Not included in the Original Proposal

Re-wiring & Replacement of Outlets 8,772.75 - Additional scope of works. Not included in the Original Proposal

Replacement of Busted Lights 28,245.00 - Additional scope of works. Not included in the Original Proposal

C. Main House

Repair of canopy at game room & main door 38,197.50 - Additional scope of works. Not included in the Original Proposal

Replacement of Busted Lights at Main Kitchen & Garage 20,664.00 - Additional scope of works. Not included in the Original Proposal

Repair of telephone & Internet Wiring 5,974.50 - Additional scope of works. Not included in the Original Proposal

D. Four Storey Building

Repair of cladding due to removal of Beehive 2,925.00 - Additional scope of works. Not included in the Original Proposal

Replacement of level type door knob 10,290.00 - Additional scope of works. Not included in the Original Proposal
FAJ Construction and Development Corporation
Subject : Change Order No. 4 - Summary

Item No Project Name Total Amount Remarks

Repair of cabinets & leak at 4th floor 28,558.50 - Additional scope of works. Not included in the Original Proposal

Retiling at 3rd floor T&B 7,482.00 - Additional scope of works. Not included in the Original Proposal

Subtotal 1,211,101.35

C. Sta. Elena Project - Change Order


Project Overhead 150,000.00 - Project Overhead Cost

Additional Lights at Main Kitchen 20,173.36 - Additional scope of works. Not included in the Original Proposal

Canopy Lights 148,091.90 - Additional scope of works. Not included in the Original Proposal

- Due to reduction of ledge overhange resulting in water coming to Basement Service


Additional Ledge Cover 6,750.00
Kitchen
- Additional edging to eliminate leak seepage due to design mechanics of the Biowood
Biowood Edging at Master's Bedroom (Exterior) 14,336.60
cladding

Supply and Installation of Elevator Door Wallpaper Film 162,158.67 - Additional scope of works. Not included in the Original Proposal

Additional Garden Lights and Spot Light 99,287.35 - Additional scope of works. Not included in the Original Proposal

Additional Towel Ring at Bedroom 1, 2 & Den Guest 9,982.50 - Additional scope of works. Not included in the Original Proposal

Additional Vertical post at Bridgeway 2,565.00 - Additional scope of works. Not included in the Original Proposal

Additional Main Entrance Railings 30,337.50 - Additional scope of works. Not included in the Original Proposal

Additional Outlet at Storage Room (2 sets) 16,841.67 - Additional scope of works. Not included in the Original Proposal

Additional Brackets for Paintings 9,450.00 - Additional scope of works. Not included in the Original Proposal

Additional Canopy Glass at Main Door area (Bradphil) 71,500.00 - Additional scope of works. Not included in the Original Proposal

Subtotal 741,474.54

GRAND TOTAL 4,453,281.33