Contract No. : ICB-CTTLP-2017-01 220 kV Chilime-Trishuli Transmission System Project PINGGAO GROUP CO. LTD.

Date Effective From: 1st April 2022 Design, Supply and Installation of Package-I for 220 kV Chilme Hub - Trishuli 3B Hub Transmission Line Project NO. 22, NANHUANDONG ROAD
(Chilime-Trishuli 220 kV Transmission Line Project) PINGDINGSHAN CITY, HENAN PROVINCE
ID Task Name Duration Start Finish Half 2, 2022
M A M J J
1 Chilime-Trishuli 220 KV Transmission Line 122 days Fri 4/1/22 Sun 7/31/22
2 Foundation Works 90 days Fri 4/1/22 Wed 6/29/22
3 Erection of Towers 95 days Fri 4/1/22 Mon 7/4/22
4 Stringing Work in the Double Circuit Portion 55 days Sun 6/5/22 Fri 7/29/22
5 Protection Work in All Required Tower 60 days Tue 5/31/22 Fri 7/29/22
6 Supply of remaining Tower Part 30 days Thu 5/26/22 Fri 6/24/22
7 Supply of remaining Equipment 25 days Thu 6/30/22 Sun 7/24/22
8 Testing of the Line 11 days Wed 7/20/22 Sat 7/30/22
9 Hand over of the project 1 day Sun 7/31/22 Sun 7/31/22

Task External Tasks Inactive Summary Start-only Deadline


Split External Milestone Manual Task Finish-only
Milestone Inactive Task Duration-only External Tasks
Summary Inactive Milestone Manual Summary Rollup External Milestone
Project Summary Inactive Milestone Manual Summary Progress

Page 1

You might also like