Professional Documents
Culture Documents
Attachment R (Draft Offshore Decommissioning Safety Requirement Guideline)
Attachment R (Draft Offshore Decommissioning Safety Requirement Guideline)
1. INTRODUCTION
Safety issue is one of major concerns in the decommissioning activities because of the
potential higher risks than normal operation. Although various laws and regulations regarding
safety and occupational health are existed, however there is no reference or guideline which
is specifically developed for the offshore E&P facilities decommissioning. This guideline is
developed to outline minimum requirements on the Occupational Health and Safety to ensure
that adequate risk assessment is conducted and mitigation measures are established and
implemented at all stages of decommissioning activities.
2. OBJECTIVE
The objective of the guideline is to provide minimum requirement for safety implications in the
offshore decommissioning activities.
3. SCOPE OF GUIDANCE
The scopes of the guideline covers offshore decommissioning activities including well
plugging and abandonment, pipeline and subsea structures decommissioning, structural
removal, onshore dismantling and disposal.
5. GENERAL REQUIREMENTS
5.1 Selecting decommissioning option
Concessionaires shall include human safety as one of major components in selecting
decommissioning options as required but not limited to activities stated in BEPO guideline.
3. DECOMMISSIONING PERCEPTION
3.1 Risk comparison between installation and decommissioning processes
Installation Decommissioning
• Require lifting crane barge, labor • Require lifting crane barge, labor
skills skills
• Clean and New Facility • Likely Contaminated Facility
• Well Engineered, well planned • Potential to unexpected events at all
procedure time
• Pile Hammering through seabed • Pile cut with Explosive, water-jet,
diamond wire
• Weight Controlled, fixed center of • Weight, CG change due to
Gravity (CG) modification, marine growth
• New Structure High Integrity • Aged structure unexpected weak
point due to fatigue or corrosion
• Hazardous Operation • More hazardous operation
• Jacket installation aided by gravity • Jacket removal against gravity
• Accurate known weight • Uncertainty in weight due to friction,
marine growth, over-burden on mud-
mats.
• Piles are always separate driven • Piles may have to be lifted with
jackets.
Ministry of Interior
Ministry of Industry
Hazardous Substances Act B.E 2535 Re: The control of 29 March B.E. 2535
hazardous substances
2 June B.E. 2542
Notification of Ministry of Industry No.2 (B.E. 2542) Re:
Reporting information regarding type, quantity, source,
usage method and storage of radioactive substances
18 November B.E. 2542
Notification of Ministry of Industry No.3 (B.E. 2542) Re:
Safety measures for the operation
17 November B.E. 2543
Regulation of Department of Industrial Works Re:
Danger indication of risk assessment and preparation of
risk management plan
Hazardous Substances Act (No.2) B.E. 2544 9 November B.E. 2544
23 August B.E. 2545
Notification of Ministry of Industry No.1 (B.E. 2545) Re:
Safety measures in the operation issued under the
Factory Act B.E. 2535
6 November B.E. 2546
Notification of Ministry of Industry Re: Safety measures
in the factory business’s operation with regard to working
environment B.E. 2546
Ministry of Labor