"MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E.

PACHACUTEC DEL DISTRITO DE SAN MARCOS - PROVINCIA


OBRA : DE HUARI - DEPARTAMENTO DE ANCASH"
UBICACIÓN : SAN MARCOS - HUARI - ANCASH CONTRATO: LP Nº 09-2021-MDSM/CS-1
CONTRATISTA : CONSORCIO LUKI S/. 5,538,257.62
MONTO DEL CONTRATO:
SUPERVISOR : CONSORCIO ROKA INICIO DE OBRA: 26/08/2021
MES DE : Enero-2022 02/04/2022
TERMINO CONTRACTUAL:

RESUMEN DE VALORIZACON DE AVANCE FISICO DE OBRA - Enero 2022


PRESUPUESTO AVANCES FISICO DE OBRA SALDO POR
FP DESCRIPCION CONTRACTUAL ACTUAL ACUMUL. ANTERIOR ACUMUL. ACTUAL VALORIZAR
PARCIAL (S.) VAL. (S/.) % VAL. (S/.) % VAL. (S/.) % VAL. (S/.) %

1 ESTRUCTURAS 1,909,863.19 513,161.47 26.87 895,288.55 46.88 1,408,450.02 73.75 501,413.17 26.25%
2 ARQUITECTURA 1,713,325.89 27,678.80 1.62 579,889.40 33.85 607,568.20 35.46 1,105,757.69 64.54%
3 INSTALACIONES SANITARIAS 238,987.06 7,920.25 3.31 0.00 0.00 7,920.25 3.31 231,066.81 96.69%
4 INSTALACIONES ELECTRICAS 71,116.86 0.00 0.00 0.00 0.00 0.00 0.00 71,116.86 100.00%
Z

COSTO DIRECTO 3,933,293.00 548,760.52 1,475,177.95 2,023,938.47 1,909,354.53

GASTOS GENERALES 8.28% 325,815.91 45,456.80 122,196.96 167,653.76 158,162.15


UTILIDADES 8.00% 314,663.44 43,900.84 118,014.24 161,915.08 152,748.36

SUB TOTAL EJECUCION DE OBRA 4,573,772.35 638,118.16 13.95% 1,715,389.15 37.50% 2,353,507.31 51.45% 2,220,265.04 48.55%

SUB TOTAL PLAN COVID -19 119,666.32 15,348.90 12.83% 81,664.22 68.24% 97,013.11 81.07% 22,653.21 18.93%

FACTOR DE RELACION 1.00000 4,693,438.67 653,467.06 1,797,053.37 2,450,520.42 2,242,918.25


I.G.V 18.00% 844,818.96 117,624.07 323,469.61 441,093.69 403,725.27

TOTAL PRESUPUESTO 5,538,257.63 771,091.13 2,120,522.98 2,891,614.11 2,646,643.52