Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 17

Version 4.

Budget - Actuals

Field
Project Name
Start Date
Contract Amount
Price ($/hrs)
Cost ($/hrs)
Report Dur. (d)

Tip

Planned Hrs After filling project schedule (tasks + resources). Generate the 'WorkLoad' report. Select the 'Task Usage' option. The report will genera

EV Analysis
Project Earned Value Analysis measures the health of a project by looking at cost information and schedule information concurrently. It tells you whether the
project is on budget for the amount of work done so far.

Metric Abbrev.
Budget at Completion BAC
Actual Cost AC
Earned Value EV
Planned Value PV

Cost Variance CV

Cost Performance Index CPI

Schedule Variance SV
Schedule Performance Index SPI
Estimate to Completion ETC
Estimate at Completion EAC
Variance at Completion VAC
Status

Tip
This is the % of how confident the PL of the Actual Completion % value entered in the 'Budget - Actuals' sheet. If % is below 100%, the E
Confidence Level % Actual Completion % = 25%, and Confidence Level = 90%, then EV metrics calcualtion will consider Actual Completion % = 22.5%
The values are entered manually at time of budgeting the project. It should equal the 'Total Cost' of the project in the 'Budget - Actuals
BAC have the flexibility to update BAC in case there should be a new baseline (Change Requests).
Description
Name of the project being tracked
Starting date of the project
The contract amount agreed on with the client … This value should match the total value of 'Revenue' column
The price rate communicated from the EM or client
The cost rate communicated and announced by the professional services
The reporting duration of the project. The value will be used to generate the dates of reporting the EV starting from the value entered in 'Start Date'

After filling project schedule (tasks + resources). Generate the 'WorkLoad' report. Select the 'Task Usage' option. The report will generate the weekly hours of the whole schedule.

easures the health of a project by looking at cost information and schedule information concurrently. It tells you whether the project is on schedule and on budget, as well as
nt of work done so far.

Description
Baseline cost for 100% of project.
Total costs actually incurred so far.
Amount of budget earned so far based on physical work accomplished, without reference to actual costs.
The budget for the physical work scheduled to be completed by the end of the time period.

Measure of cost overrun. The difference between the budget for the work actually done so far and the actual costs so far.

Cost efficiency ratio. A CPI of 1.00 means that the costs so far are exactly the same as the budget for work actually done so far.
Measure of schedule slippage. The difference between the budget for the work actually done so far and the budgeted cost of work
scheduled.
The schedule efficiency ratio. An SPI of 1.0 means that the project is exactly on schedule.
The expected additional cost to complete.
Expected total cost based on the current cost efficiency ratio.
Estimated cost overrun at the end of project.
Average of CPI & SPI.
GREEN = On track
YELLOW = Slightly behind schedule or budget
RED = Needs immediate attention
BLACK = Killed or Restore

This is the % of how confident the PL of the Actual Completion % value entered in the 'Budget - Actuals' sheet. If % is below 100%, the EV metrics are calculated according to the worst case s
Actual Completion % = 25%, and Confidence Level = 90%, then EV metrics calcualtion will consider Actual Completion % = 22.5%
The values are entered manually at time of budgeting the project. It should equal the 'Total Cost' of the project in the 'Budget - Actuals' sheet. The reason behind not having a direct link to th
have the flexibility to update BAC in case there should be a new baseline (Change Requests).
value entered in 'Start Date'

kly hours of the whole schedule.

on schedule and on budget, as well as whether the

Formula/Value
Total Planned Hrs X Cost ($/hrs)
N/A
BAC * Actual % Completion
N/A

EV – AC

EV / AC

EV – PV
EV / PV
EAC – AC
BAC / CPI
BAC – EAC
(CPI + SPI) / 2
>1.0
>0.85
>0.65
<0.65

are calculated according to the worst case scenario. Ex. If

e reason behind not having a direct link to this field is to


Project Name Start Date Contract Amount Price ($/hrs)
<Project Name> 3/1/2008 $ 30,000 $ 30

Budget
Planned
Week Revenue Planned Hrs Labor Cost Expenses Total Cost
Completion %
Total 6,000 200 $ 3,800 $ - $ 3,800
8-Mar-08 $ 6,000 200 $ 3,800 $ 3,800 100.0%
15-Mar-08 $ - $ - $ - 100.0%
22-Mar-08 $ - $ - $ - 100.0%
29-Mar-08 $ - $ - $ - 100.0%
5-Apr-08 $ - $ - $ - 100.0%
12-Apr-08 $ - $ - $ - 100.0%
19-Apr-08 $ - $ - $ - 100.0%
26-Apr-08 $ - $ - $ - 100.0%
3-May-08 $ - $ - $ - 100.0%
10-May-08 $ - $ - $ - 100.0%
17-May-08 $ - $ - $ - 100.0%
24-May-08 $ - $ - $ - 100.0%
31-May-08 $ - $ - $ - 100.0%
7-Jun-08 $ - $ - $ - 100.0%
14-Jun-08 $ - $ - $ - 100.0%
21-Jun-08 $ - $ - $ - 100.0%
28-Jun-08 $ - $ - $ - 100.0%
5-Jul-08 $ - $ - $ - 100.0%
12-Jul-08 $ - $ - $ - 100.0%
19-Jul-08 $ - $ - $ - 100.0%
26-Jul-08 $ - $ - $ - 100.0%
2-Aug-08 $ - $ - $ - 100.0%
9-Aug-08 $ - $ - $ - 100.0%
16-Aug-08 $ - $ - $ - 100.0%
23-Aug-08 $ - $ - $ - 100.0%
30-Aug-08 $ - $ - $ - 100.0%
6-Sep-08 $ - $ - $ - 100.0%
13-Sep-08 $ - $ - $ - 100.0%
20-Sep-08 $ - $ - $ - 100.0%
27-Sep-08 $ - $ - $ - 100.0%
4-Oct-08 $ - $ - $ - 100.0%
11-Oct-08 $ - $ - $ - 100.0%
18-Oct-08 $ - $ - $ - 100.0%
25-Oct-08 $ - $ - $ - 100.0%
1-Nov-08 $ - $ - $ - 100.0%
8-Nov-08 $ - $ - $ - 100.0%
15-Nov-08 $ - $ - $ - 100.0%
22-Nov-08 $ - $ - $ - 100.0%
29-Nov-08 $ - $ - $ - 100.0%
6-Dec-08 $ - $ - $ - 100.0%
13-Dec-08 $ - $ - $ - 100.0%
20-Dec-08 $ - $ - $ - 100.0%
27-Dec-08 $ - $ - $ - 100.0%
3-Jan-09 $ - $ - $ - 100.0%
10-Jan-09 $ - $ - $ - 100.0%
17-Jan-09 $ - $ - $ - 100.0%
24-Jan-09 $ - $ - $ - 100.0%
31-Jan-09 $ - $ - $ - 100.0%
7-Feb-09 $ - $ - $ - 100.0%
14-Feb-09 $ - $ - $ - 100.0%
21-Feb-09 $ - $ - $ - 100.0%
28-Feb-09 $ - $ - $ - 100.0%
7-Mar-09 $ - $ - $ - 100.0%
14-Mar-09 $ - $ - $ - 100.0%
21-Mar-09 $ - $ - $ - 100.0%
28-Mar-09 $ - $ - $ - 100.0%
4-Apr-09 $ - $ - $ - 100.0%
11-Apr-09 $ - $ - $ - 100.0%
18-Apr-09 $ - $ - $ - 100.0%
25-Apr-09 $ - $ - $ - 100.0%
2-May-09 $ - $ - $ - 100.0%
9-May-09 $ - $ - $ - 100.0%
16-May-09 $ - $ - $ - 100.0%
23-May-09 $ - $ - $ - 100.0%
30-May-09 $ - $ - $ - 100.0%
6-Jun-09 $ - $ - $ - 100.0%
13-Jun-09 $ - $ - $ - 100.0%
20-Jun-09 $ - $ - $ - 100.0%
27-Jun-09 $ - $ - $ - 100.0%
4-Jul-09 $ - $ - $ - 100.0%
11-Jul-09 $ - $ - $ - 100.0%
18-Jul-09 $ - $ - $ - 100.0%
25-Jul-09 $ - $ - $ - 100.0%
1-Aug-09 $ - $ - $ - 100.0%
8-Aug-09 $ - $ - $ - 100.0%
15-Aug-09 $ - $ - $ - 100.0%
22-Aug-09 $ - $ - $ - 100.0%
29-Aug-09 $ - $ - $ - 100.0%
5-Sep-09 $ - $ - $ - 100.0%
12-Sep-09 $ - $ - $ - 100.0%
19-Sep-09 $ - $ - $ - 100.0%
26-Sep-09 $ - $ - $ - 100.0%
3-Oct-09 $ - $ - $ - 100.0%
10-Oct-09 $ - $ - $ - 100.0%
17-Oct-09 $ - $ - $ - 100.0%
24-Oct-09 $ - $ - $ - 100.0%
31-Oct-09 $ - $ - $ - 100.0%
7-Nov-09 $ - $ - $ - 100.0%
14-Nov-09 $ - $ - $ - 100.0%
21-Nov-09 $ - $ - $ - 100.0%
28-Nov-09 $ - $ - $ - 100.0%
5-Dec-09 $ - $ - $ - 100.0%
12-Dec-09 $ - $ - $ - 100.0%
19-Dec-09 $ - $ - $ - 100.0%
26-Dec-09 $ - $ - $ - 100.0%
2-Jan-10 $ - $ - $ - 100.0%
9-Jan-10 $ - $ - $ - 100.0%
16-Jan-10 $ - $ - $ - 100.0%
23-Jan-10 $ - $ - $ - 100.0%
30-Jan-10 $ - $ - $ - 100.0%
6-Feb-10 $ - $ - $ - 100.0%
13-Feb-10 $ - $ - $ - 100.0%
20-Feb-10 $ - $ - $ - 100.0%
27-Feb-10 $ - $ - $ - 100.0%
6-Mar-10 $ - $ - $ - 100.0%
13-Mar-10 $ - $ - $ - 100.0%
20-Mar-10 $ - $ - $ - 100.0%
27-Mar-10 $ - $ - $ - 100.0%
3-Apr-10 $ - $ - $ - 100.0%
10-Apr-10 $ - $ - $ - 100.0%
17-Apr-10 $ - $ - $ - 100.0%
24-Apr-10 $ - $ - $ - 100.0%
1-May-10 $ - $ - $ - 100.0%
8-May-10 $ - $ - $ - 100.0%
15-May-10 $ - $ - $ - 100.0%
22-May-10 $ - $ - $ - 100.0%
Total $ 6,000 200 $ 3,800 $ - $ 3,800
Cost ($/hrs) Report Dur. (d)
$ 19 7

Actual / Forecast
Actual
Actual Hours Labor Cost Expenses Total Cost
Completion%
240 $ 4,560 - $ 4,560
240 $ 4,560 $ 4,560 21.0%
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
$ - $ -
240 $ 4,560 - $ 4,560
Earned Value Analysis
Confidence
Week BAC EV AC PV CV SV CPI
Level %
8-Mar-08 100.0% $ 18,240 $ 3,830 $ 4,560 $ 3,800 $ (730) $ 30 0.84
15-Mar-08 #N/A #N/A #N/A #N/A #N/A #N/A
22-Mar-08 #N/A #N/A #N/A #N/A #N/A #N/A
29-Mar-08 #N/A #N/A #N/A #N/A #N/A #N/A
5-Apr-08 #N/A #N/A #N/A #N/A #N/A #N/A
12-Apr-08 #N/A #N/A #N/A #N/A #N/A #N/A
19-Apr-08 #N/A #N/A #N/A #N/A #N/A #N/A
26-Apr-08 #N/A #N/A #N/A #N/A #N/A #N/A
3-May-08 #N/A #N/A #N/A #N/A #N/A
10-May-08 #N/A #N/A #N/A #N/A #N/A #N/A
17-May-08 #N/A #N/A #N/A #N/A #N/A #N/A
24-May-08 #N/A #N/A #N/A #N/A #N/A #N/A
31-May-08 #N/A #N/A #N/A #N/A #N/A #N/A
7-Jun-08 #N/A #N/A #N/A #N/A #N/A #N/A
14-Jun-08 #N/A #N/A #N/A #N/A #N/A #N/A
21-Jun-08 #N/A #N/A #N/A #N/A #N/A #N/A
28-Jun-08 #N/A #N/A #N/A #N/A #N/A #N/A
5-Jul-08 #N/A #N/A #N/A #N/A #N/A #N/A
12-Jul-08 #N/A #N/A #N/A #N/A #N/A #N/A
19-Jul-08 #N/A #N/A #N/A #N/A #N/A #N/A
26-Jul-08 #N/A #N/A #N/A #N/A #N/A #N/A
2-Aug-08 #N/A #N/A #N/A #N/A #N/A #N/A
9-Aug-08 #N/A #N/A #N/A #N/A #N/A #N/A
16-Aug-08 #N/A #N/A #N/A #N/A #N/A #N/A
23-Aug-08 #N/A #N/A #N/A #N/A #N/A #N/A
30-Aug-08 #N/A #N/A #N/A #N/A #N/A #N/A
6-Sep-08 #N/A #N/A #N/A #N/A #N/A #N/A
13-Sep-08 #N/A #N/A #N/A #N/A #N/A #N/A
20-Sep-08 #N/A #N/A #N/A #N/A #N/A #N/A
27-Sep-08 #N/A #N/A #N/A #N/A #N/A #N/A
4-Oct-08 #N/A #N/A #N/A #N/A #N/A #N/A
11-Oct-08 #N/A #N/A #N/A #N/A #N/A #N/A
18-Oct-08 #N/A #N/A #N/A #N/A #N/A #N/A
25-Oct-08 #N/A #N/A #N/A #N/A #N/A #N/A
1-Nov-08 #N/A #N/A #N/A #N/A #N/A #N/A
8-Nov-08 #N/A #N/A #N/A #N/A #N/A #N/A
15-Nov-08 #N/A #N/A #N/A #N/A #N/A #N/A
22-Nov-08 #N/A #N/A #N/A #N/A #N/A #N/A
29-Nov-08 #N/A #N/A #N/A #N/A #N/A #N/A
6-Dec-08 #N/A #N/A #N/A #N/A #N/A #N/A
13-Dec-08 #N/A #N/A #N/A #N/A #N/A #N/A
20-Dec-08 #N/A #N/A #N/A #N/A #N/A #N/A
27-Dec-08 #N/A #N/A #N/A #N/A #N/A #N/A
3-Jan-09 #N/A #N/A #N/A #N/A #N/A #N/A
10-Jan-09 #N/A #N/A #N/A #N/A #N/A #N/A
17-Jan-09 #N/A #N/A #N/A #N/A #N/A #N/A
24-Jan-09 #N/A #N/A #N/A #N/A #N/A #N/A
31-Jan-09 #N/A #N/A #N/A #N/A #N/A #N/A
7-Feb-09 #N/A #N/A #N/A #N/A #N/A #N/A
14-Feb-09 #N/A #N/A #N/A #N/A #N/A #N/A
21-Feb-09 #N/A #N/A #N/A #N/A #N/A #N/A
28-Feb-09 #N/A #N/A #N/A #N/A #N/A #N/A
7-Mar-09 #N/A #N/A #N/A #N/A #N/A #N/A
14-Mar-09 #N/A #N/A #N/A #N/A #N/A #N/A
21-Mar-09 #N/A #N/A #N/A #N/A #N/A #N/A
28-Mar-09 #N/A #N/A #N/A #N/A #N/A #N/A
4-Apr-09 #N/A #N/A #N/A #N/A #N/A #N/A
11-Apr-09 #N/A #N/A #N/A #N/A #N/A #N/A
18-Apr-09 #N/A #N/A #N/A #N/A #N/A #N/A
25-Apr-09 #N/A #N/A #N/A #N/A #N/A #N/A
2-May-09 #N/A #N/A #N/A #N/A #N/A #N/A
9-May-09 #N/A #N/A #N/A #N/A #N/A #N/A
16-May-09 #N/A #N/A #N/A #N/A #N/A #N/A
23-May-09 #N/A #N/A #N/A #N/A #N/A #N/A
30-May-09 #N/A #N/A #N/A #N/A #N/A #N/A
6-Jun-09 #N/A #N/A #N/A #N/A #N/A #N/A
13-Jun-09 #N/A #N/A #N/A #N/A #N/A #N/A
20-Jun-09 #N/A #N/A #N/A #N/A #N/A #N/A
27-Jun-09 #N/A #N/A #N/A #N/A #N/A #N/A
4-Jul-09 #N/A #N/A #N/A #N/A #N/A #N/A
11-Jul-09 #N/A #N/A #N/A #N/A #N/A #N/A
18-Jul-09 #N/A #N/A #N/A #N/A #N/A #N/A
25-Jul-09 #N/A #N/A #N/A #N/A #N/A #N/A
1-Aug-09 #N/A #N/A #N/A #N/A #N/A #N/A
8-Aug-09 #N/A #N/A #N/A #N/A #N/A #N/A
15-Aug-09 #N/A #N/A #N/A #N/A #N/A #N/A
22-Aug-09 #N/A #N/A #N/A #N/A #N/A #N/A
29-Aug-09 #N/A #N/A #N/A #N/A #N/A #N/A
5-Sep-09 #N/A #N/A #N/A #N/A #N/A #N/A
12-Sep-09 #N/A #N/A #N/A #N/A #N/A #N/A
19-Sep-09 #N/A #N/A #N/A #N/A #N/A #N/A
26-Sep-09 #N/A #N/A #N/A #N/A #N/A #N/A
3-Oct-09 #N/A #N/A #N/A #N/A #N/A #N/A
10-Oct-09 #N/A #N/A #N/A #N/A #N/A #N/A
17-Oct-09 #N/A #N/A #N/A #N/A #N/A #N/A
24-Oct-09 #N/A #N/A #N/A #N/A #N/A #N/A
31-Oct-09 #N/A #N/A #N/A #N/A #N/A #N/A
7-Nov-09 #N/A #N/A #N/A #N/A #N/A #N/A
14-Nov-09 #N/A #N/A #N/A #N/A #N/A #N/A
21-Nov-09 #N/A #N/A #N/A #N/A #N/A #N/A
28-Nov-09 #N/A #N/A #N/A #N/A #N/A #N/A
5-Dec-09 #N/A #N/A #N/A #N/A #N/A #N/A
12-Dec-09 #N/A #N/A #N/A #N/A #N/A #N/A
19-Dec-09 #N/A #N/A #N/A #N/A #N/A #N/A
26-Dec-09 #N/A #N/A #N/A #N/A #N/A #N/A
2-Jan-10 #N/A #N/A #N/A #N/A #N/A #N/A
9-Jan-10 #N/A #N/A #N/A #N/A #N/A #N/A
16-Jan-10 #N/A #N/A #N/A #N/A #N/A #N/A
23-Jan-10 #N/A #N/A #N/A #N/A #N/A #N/A
30-Jan-10 #N/A #N/A #N/A #N/A #N/A #N/A
6-Feb-10 #N/A #N/A #N/A #N/A #N/A #N/A
13-Feb-10 #N/A #N/A #N/A #N/A #N/A #N/A
20-Feb-10 #N/A #N/A #N/A #N/A #N/A #N/A
27-Feb-10 #N/A #N/A #N/A #N/A #N/A #N/A
6-Mar-10 #N/A #N/A #N/A #N/A #N/A #N/A
13-Mar-10 #N/A #N/A #N/A #N/A #N/A #N/A
20-Mar-10 #N/A #N/A #N/A #N/A #N/A #N/A
27-Mar-10 #N/A #N/A #N/A #N/A #N/A #N/A
3-Apr-10 #N/A #N/A #N/A #N/A #N/A #N/A
10-Apr-10 #N/A #N/A #N/A #N/A #N/A #N/A
17-Apr-10 #N/A #N/A #N/A #N/A #N/A #N/A
24-Apr-10 #N/A #N/A #N/A #N/A #N/A #N/A
1-May-10 #N/A #N/A #N/A #N/A #N/A #N/A
8-May-10 #N/A #N/A #N/A #N/A #N/A #N/A
15-May-10 #N/A #N/A #N/A #N/A #N/A #N/A
22-May-10 #N/A #N/A #N/A #N/A #N/A #N/A
G 1
Y 0.85
R 0.65
lysis

SPI ETC EAC VAC Status

1.01 $ 17,154 $ 21,714 $ (3,474) 0.92


#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
$(000) Efficiency

0.00
0.20
0.40
0.60
0.80
1.00
1.20

$500
$-
$(500)

$(4,000)
$(3,500)
$(3,000)
$(2,500)
$(2,000)
$(1,500)
$(1,000)

$17,000
$18,000
$19,000
$20,000
$21,000
$22,000
8-Mar-08

$10,000
$12,000
$14,000
$16,000
$18,000
$20,000

$2,000
$4,000
$6,000
$8,000

$-
8-Mar-08
15-Mar-08 8-Mar-08
15-Mar-08
15-Mar-08
22-Mar-08
22-Mar-08
22-Mar-08
29-Mar-08
29-Mar-08
29-Mar-08
5-Apr-08
5-Apr-08
5-Apr-08
12-Apr-08
12-Apr-08
12-Apr-08
19-Apr-08
19-Apr-08
19-Apr-08
26-Apr-08
26-Apr-08
26-Apr-08
3-May-08
3-May-08
3-May-08
10-May-08
10-May-08
10-May-08
17-May-08
17-May-08
BAC

17-May-08
24-May-08

CV
24-May-08
24-May-08
31-May-08
31-May-08

CPI
31-May-08
AC

7-Jun-08

SV
7-Jun-08
7-Jun-08
14-Jun-08
14-Jun-08
14-Jun-08

SPI
EV

Page 16 of 17
21-Jun-08
21-Jun-08
EV Analysis (Charts)

21-Jun-08

VAC
28-Jun-08

Variance Analysis
28-Jun-08 28-Jun-08
Performance Index
PV

5-Jul-08
Earned Value Analysis

5-Jul-08 5-Jul-08

Estimate at Completion
12-Jul-08
12-Jul-08 12-Jul-08

19-Jul-08 19-Jul-08
19-Jul-08

26-Jul-08 26-Jul-08
26-Jul-08

2-Aug-08 2-Aug-08
2-Aug-08

9-Aug-08 9-Aug-08
9-Aug-08

16-Aug-08 16-Aug-08 16-Aug-08

23-Aug-08 23-Aug-08 23-Aug-08

30-Aug-08 30-Aug-08 30-Aug-08

6-Sep-08 6-Sep-08 6-Sep-08

13-Sep-08 13-Sep-08 13-Sep-08

20-Sep-08 20-Sep-08 20-Sep-08

27-Sep-08 27-Sep-08 27-Sep-08


$16,000
$17,000
8-Mar-08

15-Mar-08

22-Mar-08

29-Mar-08

5-Apr-08

12-Apr-08

19-Apr-08

26-Apr-08

3-May-08

10-May-08

17-May-08

24-May-08

31-May-08

BAC
7-Jun-08

14-Jun-08

EAC

Page 17 of 17
21-Jun-08
EV Analysis (Charts)

28-Jun-08

5-Jul-08

12-Jul-08

19-Jul-08

26-Jul-08

2-Aug-08

9-Aug-08

16-Aug-08

23-Aug-08

30-Aug-08

6-Sep-08

13-Sep-08

20-Sep-08

27-Sep-08

You might also like