Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SME Annual Meeting

Feb. 28-Mar. 03, 2010, Phoenix, AZ

Preprint 10-037

CASE STUDY - BENEFITS OF BUILDING AN EFFICIENT MINE PLANNING PROCESS

W. A. Wilkinson, Jr., Mincom Inc., Denver CO


J. Buenemann, Kiewit Mining, Omaha, NE

ABSTRACT mining and another area covering the remaining planned mine area.
The model covering the next two years of mining was built on a 100
Mine planners are under pressure to evaluate the impact of feet (30.48 meters) grid cell size, while the longer term area was built
changing economic times and newly acquired data on the mine plan. on a 400 feet (121.92 meters) grid cell size. The amount of time to
Incorporating change, such as commodity prices, customer sales, update these two models took approximately 18 hours. The time
changing cost assumptions, and newly acquired geologic data into the required to complete the workflow limited the availability of new data to
mine plans requires quick turn-around for model building and planning the mine planning, so engineers were not working with the latest
to keep the mine plan on pace with changes as they are occurring. information.
Because of the length of time required to perform some of the geologic
modeling and mine planning tasks, planning frequency may not be
keeping pace with the frequency of change. This paper discusses
how one company has increased the frequency rate and accuracy of
mine plans to keep current with incoming data, ensuring mine plans
reflect the latest information, thereby minimizing or eliminating
production cost variance.
BACKGROUND
The case study is based on a a truck, shovel surface coal mine in
the western United States that produces approximately 25+million
short tons (22.67+ million metric tons) of coal per year. The mine
employs two geologist and seven mining engineers to gather new
data-build geologic models and produce short, medium and long range
mine plans. The mine was acquired by another company, who
implemented Mincom MineScape software to replace its existing mine
planning systems. The majority of the existing engineering staff were
retained and trained in the use of MineScape software.
MINE PLANNING PROCESS
Producing mining plans follows a fairly linear workflow. Drill hole
and/or mine survey information is gathered to measure the structure
and sample the chemical analysis of the deposit. The collected data is
then used to create a geologic model of the structure and chemistry
and define the resource based on mining constraints. Mine planning Figure 1. Mine Planning Workflow.
uses the geologic model information to design three-dimensional
Mine plans were completed with multiple software systems. Mine
mining blocks, which reflect the ground control plan and are of a size to
layout and design was performed in one system, while mine
provide sufficient resolution for the mine scheduling. The resource
scheduling was performed using Microsoft Excel. Long range mine
quantity and quality contained in the mining blocks are estimated and
plans on average took 5 weeks to complete. The majority of time was
the data used to produce a planned production schedule based on
spent generating economic pit-shells, which were then estimated for
mining constraints.
volume and quality. Resource estimates from the pit shells were then
Optimizing the plan typically requires completing multiple plan exported to Excel for Scheduling. Plan progress maps were
scenarios. Having an efficient, integrated and streamlined process will constructed manually in CAD by color coding the scheduled blocks in
reduce the amount of time required to complete a mine planning Excel by planned periods.
scenario. Additionally, the process should be repeated as new
IMPLEMENTED IMPROVEMENTS
geological information becomes available to ensure mining plan
assumptions will reasonably reflect actual field conditions. Inaccurate Drawing from experiences at their other mines, the company
geologic models will introduce error into the downstream mining plans, began improving processes to get geologic modeling and mine
which can result in surprise cost increases and revenue reductions to planning turn-around times lower, thus providing an opportunity to
the operation. develop more accurate and optimized mine plans. A significant part of
the plan to improve the process was the replacement of the multiple
ORIGINAL WORKFLOW
existing mine planning systems with a single integrated mine planning
The mine planning process was reviewed when the mine was system, namely the Mincom MineScape geologic modeling and mine
purchased. Planners obtained new geologic data during a planned planning system.
drilling season. Drill hole information was accumulated but planners
Geologic Modeling
would only update the geologic model at the end of exploration drilling.
A major improvement in geologic modeling process flow was
Therefore, continuous updates were not performed due to the time
made by combining both short and long range model areas into one
required to generate the geologic model. The geologic model
model with a 100 feet (30.48 meters) grid cell size, eliminating the
consisted of two areas, an area planned for the next two (2) years of
need to build more than one geologic model. Eliminating the
1 Copyright © 2010 by SME
SME Annual Meeting
Feb. 28-Mar. 03, 2010, Phoenix, AZ

necessity of building a second model and the increased automation Increased Minable Reserves
provided by the MineScape geologic modeling system process Exploration drilling revealed a geologic complex area within the
reduced model building time by 75 percent. mine site. Typically two (2) coal intervals were being modeled and
mined in the planned and active operations. The geologically complex
Mine Planning area showed eight (8) coal units, which were splits from the main two
Using a single integrated mine planning and geologic modeling coal intervals. Adding to this complexity in the coal formation was the
software improved the process flow. Rather than exporting block presence of a sand channel unit, which presented a significant ground
resource estimates to Excel, scheduling was completed in a single control risk to the mining operation. Prior to implementing the
mine planning system. Plan progress map generation was MineScape geologic modeling system, this complex area was mined
automated as the scheduling system was integrated with the CAD around, because the existing modeling system could not effectively
system. By implementing this change, the time to complete long range and confidently model and therefore plan mining in this area. As a
mine plans was reduced by approximately 60 Percent. result of the improvements made in the geologic modeling and mine
BENEFITS REALIZED planning system, the area was modeled and multiple mining scenarios
developed to address the challenges of the area. Coal reserves that
Improvements in the process flow resulted in both direct and were previously avoided due to geologic anomalies are now part of the
indirect benefits to the operation. Faster geologic modeling and mine mining plan, increasing the available reserves and extending the mine
planning provided significant benefits and cost savings to the life.
operation, not through the reduction of engineering staff, but by
liberating technical staff from tasks to facilitate the process and Confidence in Purchasing Decisions
enabling them to spend more time investigating better design Coal sales drive the production for this operation and accurate
solutions, which increased minable reserves and reduced operation geologic modeling using the latest data increased the confidence in the
costs. mine plans to meet coal quality specifications on upcoming shipments.
Furthermore, optimizing the mining plan enabled engineers to
Improved Geologic Model and Mine Design Accuracy accurately predict when a significant multi-million dollar capital
The significant time reduction in developing geologic models investment in new equipment would be required due to upcoming
allowed multiple models to be created on the fly as new drill hole and increased overburden volumes and sales volume.
quality data was received. Geologists were able to analyze the effect
of the additional drilling on the model and continually keep the geologic SUMMARY
model updated for mine planning. Accuracy was increased though a Mine planning process improvements described above have
higher resolution model, which reflected measured data more closely. resulted in direct and indirect cost savings for this mine. The quality of
The model publishing capabilities of the Mincom software enabled new the geological model and mining plans was constrained by the time to
model updates to be distributed to the mining engineers quickly and complete the tasks and the requirement to plan ahead of the constantly
easily so the mining engineers are always designing with the latest shifting operations. Since planning must precede operations, the
information. quality of geological modeling and mine planning will be reduced as
Incorporating the latest information into the geologic model the time it takes to complete those tasks increases. Streamlining the
improved the accuracy of the mining plans. The reduction in time to work flow will reduce the effort required and increase the quality of the
develop mine plans resulted in better decision making through the mining plan. Some may think that reducing the effort to complete a
ability to compare multiple mine plan scenarios. mining plan leads to cost savings by reducing staff; however, as
experienced by this company, much more cost benefit can be realized
Improved Operations by investing the additional available time and expertise of skilled
Operations were encountering water bearing sand zones, which mining professionals back into the operation. In the case of this mine,
were impacting shovel production and ground control. Prior to the investment of additional staff time resulted in a higher cost benefit
modeling the sand units, the shovel would explore for the zones during than saving some staff salaries through optimizing drilling programs,
operations. Exploring for problem zones with the shovel posed a increased confidence in mining plans, increasing mine reserves by
significant risk of getting the shovel stuck in the sand or worse, a finding ways to mine in difficult geologic conditions and leveraging
highwall slope failure resulting in an unproductive shovel, which geologic and engineering knowledge into improved work flow in
impacted coal production. Improving geology model turn-around and operations where ongoing optimization still occurs.
accuracy provided geologists time to model the non-coal, water
bearing sand zones. Once identified, shovel bench plans were
developed to efficiently work in these difficult areas and communicated Quality, Time and Money
to operations. Planning for the sand zoned improved shovel New Workflow
productivity and high-wall failure risk.
Streamlining the work flow gave the engineers more time to get Q Required
out of the office and get experience in field management roles where
Quality

their analytical skills improved the operational work flow and daily
Quality

decisions made in field operations.


Reduced Exploration Costs
Because geologists had more accurate models in less time, they Q Achieved
were able to spend more time optimizing the exploration drilling plan. Takes too long
Through this exercise they were able to reduce the number of planned Never get to Q Required
exploration holes for the next drilling season compared to the previous
method of planning holes. The increased geologic model accuracy
and resolution also eliminated the cost of drilling pilot holes in areas Time = $
Time
where infill drilling was performed to get supplemental coal quality
data. The model predict function was performed at the proposed drill
Quality = $$$$ Time (effort)
hole locations and the information was provided to the drilling crew.
The predicted holes were found to correlate very well with the actual
coal elevations and geology. Figure 2. Effect of Quality vs. Time and Potential Cost Savings.

2 Copyright © 2010 by SME

You might also like