Professional Documents
Culture Documents
Preprint 10-042: SME Annual Meeting Feb. 28-Mar. 03, 2010, Phoenix, AZ
Preprint 10-042: SME Annual Meeting Feb. 28-Mar. 03, 2010, Phoenix, AZ
Preprint 10-042
ABSTRACT the material to the surface. This system should transport an average
of approximately 160,000 tonnes per day (tpd).
The feasibility study for the Grasberg Block Cave mine, finalized
in May 2008, indicated a production capacity of 160,000 tonnes per
day. A rail haulage system was an integral part of the mine design.
This paper describes the simulation process used in optimizing the
design and discusses the key factors and variables that impact the
capacity of the system. The final recommendations for the haulage
level layout and associated equipment are also included.
INTRODUCTION
Freeport-McMoRan Copper and Gold Inc (FCX) is an international
mining company with large long-lived, geographically diverse assets
and significant reserves of copper, gold and molybdenum.
PT Freeport Indonesia (PTFI) is a subsidiary of FCX. Its principal
asset is the world-class Grasberg open pit mine which was discovered
in 1988. The mine is located in the Sudirman Mountain range of
Papua, Indonesia. These mountains contain the Grasberg/Ertsberg
mineral district which forms one of the world’s largest copper and gold
reserves. Current PTFI Reserve estimates show about 2.7 billion
tonnes of ore with approximately 75% of them in undeveloped
underground reserves.
There are six main areas within the Reserves: Grasberg Open Pit,
Grasberg Block Cave (GBC), Kucing Liar, Big Gossan, Deep Ore Zone
(DOZ) and the Deep Mill Level Zone (DMLZ). These are depicted in
Figure 2. GBC Rail Haulage Layout.
Figure 1.
OBJECTIVES
N Grasberg
The aim of the work described in this paper is to optimize the ore
handling system design for the GBC mine and thus determine the
open pit
Grasberg appropriate ore haulage elevation.
accommodated. A Microsoft Excel interface enabled entry of input that allowed the variables for a number of scenarios to be input and
parameters and reporting of results from alternative simulation run as a batch. Scenarios did not have to be run individually.
scenarios. Model results are presented and updated by Arena in Excel
worksheets. The model and the associated logic were developed by The logic in the simulation allows the program to simulate many
an external consultant. “what if” scenarios that occur in a block cave mining operation. For
example, the program takes into account delays such as random
equipment breakdowns or hung-up drawpoints. On completion of the
simulation run, a results sheet is created for the specific scenario. The
results sheet contains productivity data for equipment and all
production data along with other user-defined results.
Variables
The variables used for this series of scenarios included:
• Number of trains
• Number of cars per train
• Orepass length
• Rail dump pocket capacity
• Crushed ore bin capacity
If each of the variables above only had 5 reasonable values, that
would require 3,125 simulations to test all the possible combinations
5
(5 ). To reduce the number, many of the non-plausible variable
combinations could be eliminated based on inspection of scenario
Figure 3. Feasibility Study Layout of Rail Dump, Crusher and Ore results that did not come close to meeting the 160,000 tpd
Handling System. requirement.
For example, if a scenario was simulated using 4 trains with 24
cars and the result was significantly short of 160,000 tpd, simple
reasoning will eliminate all 4 train scenarios with less than 24 cars.
However, even after initially eliminating the unlikely scenarios,
hundreds of possible combinations remained.
Some input variables such as the LHD loading and tramming
time, drawpoint hang-ups, and time required to break oversized
material on the grizzlies were kept constant. Early scenario results
showed that sufficient associated resources were available to ensure
that they were not limiting factors in the system.
The base cases from the feasibility study determined that the ore
handling system would be capable of producing 160,000 tpd and these
were used as general starting points. A broad range of scenarios were
run and any scenarios that yielded results 5% lower than the 160,000
tpd requirement were discarded.
Figure 4. Proposed Removal of Secondary Crusher.
Smaller variations to each scenario were conducted with a focus
The model simulates and evaluates the ore handling system of on holding multiple variables constant and only changing one variable
the 160,000 tpd GBC mining operation. The model is utilized to at a time. Exceptions to this were where two variables were linked by
evaluate changes in ore handling productivity. Such changes may a common constraint (one can only increase if the other decreases).
result from fluctuations in ore handling and process equipment This approach allowed better understanding of the effect each variable
capacities, variations in the number of available drawpoints, deviations had on the production rate.
in ore fragmentation, and modifications to designed surge capacities.
Trains and Cars
Operations simulated on the extraction level include the following: The number of trains operating on the haulage level was varied
along with the number of ore cars per train. The feasibility base case
• Loading from production drawpoints by LHDs and tramming used 6 trains of 24 cars with a spare train. Scenarios ranging from 4
to orepasses. trains to 12 trains were run with a range of cars and rail dump surge
• Drilling and blasting of drawpoint oversize and hang-ups capacities in order to determine the most robust combination.
(frequency estimated using a Geotechnical model).
• Breaking of oversize rocks on orepass grizzlies as predicted The combination of 6 trains with 20 cars appeared to be the
by modeling completed by Stantec. combination which was the most suitable. This was then used in the
further scenarios where ore pass and surge capacities were varied.
Simulated operations on the haulage level and ore handling
system include the following: Orepass Length and Dump Capacity
The orepass capacities (volumes) were varied by changing the
• Loading of trains orepass lengths from the extraction level to the ore haulage level. The
• Hauling from orepasses to crushers and dumping into length of the ore passes and crusher dumps were varied in correlation
pockets with each other in 5-m increments. For example if the ore passes were
• Crushing and conveying of ore to the surface stockpiles at lengthened by 20 m the crusher dump would only be lengthened by 5
the mill. m.
With a set of input variables established and entered in the Excel The calculated capacity for the crusher dump was 1,000 tonnes
file, a user can run a simulation that covers a chosen amount of time. per 5-m increment. It was assumed that all the orepasses have the
All the scenarios were set up to simulate a 12 month period in order to same constant diameter and the capacity was calculated based on
gain statistical reliability of the outcomes. An input macro was utilized overall length. The extraction level (top of the orepass) was kept
constant and the haulage level elevation was varied.
2 Copyright © 2010 by SME
SME Annual Meeting
Feb. 28-Mar. 03, 2010, Phoenix, AZ
Determining the optimal relationship between ore pass volume, The number of runs used in this process was 815. This number
rail dump pocket and crushed ore bin capacities, will enable the of scenarios might appear to be excessive. However, when the life of
optimal orepass length to be determined and consequently dictate the the mine and the ore to be handled is considered (almost 20 years and
elevation of the haulage level. 1 billion tonnes), this is a relatively small investment in time for such a
significant undertaking.
SIMULATION RESULTS
The optimization process has allowed management to make the
Trains and Cars decision on the appropriate elevation for the rail haulage.
Initial results from the scenarios varying the number of trains
indicated that 6 trains with 20 cars each (plus a spare train) appeared REFERENCES
to be the optimal combination because it met the 160,000 tpd most
reliably when other capacities were changed. This combination was Hewitt, S., Sudjatmoko, Casten, T. and Brannon C. 2008. Grasberg
then used in the next series of scenarios to determine the optimal Block Cave Access and Logistic Support Systems. In
combination of pass capacities and available surge capacity. Proceedings MassMin 2008, Lulea, Sweden, June 9-11. Lulea,
Sweden: Lulea University of Technology Press.
Model Revision
During the process of running all the scenarios some problems Botha, J., Watson, S., Arkadius, T. and Samosir, E. 2008.
were encountered. Where repeated instances of apparently illogical Simulation Applications at PT Freeport Indonesia’s DOZ/ESZ
results or trends were observed, the root causes were sought. After Block Cave Mine. In Proceedings MassMin 2008, Lulea, Sweden,
investigation, amendments were made to the train dispatch logic that June 9-11. Lulea, Sweden: Lulea University of Technology Press.
solved the ambiguous results. Once the new version of the Arena ACKNOWLEDGEMENTS
model was created, this effectively made all the previous scenario runs
obsolete. The previous runs needed to be re-run with the new Arena The authors wish to thank to Freeport-McMoRan Copper and
model to ensure that the results could be properly compared. Gold for permission to publish this paper. Thanks also go to Stantec
Mining and Jaco Botha for their assistance during the simulation
Pass Capacities process.
Using 6 trains with 20 cars, the results indicated in Figure 5 show
the improvement in productivity of the system as Rail Dump capacity
was increased. It can be seen in Figure 5 that the outcomes are non-
linear. The general trend is that higher production tonnage is achieved
with more rail dump pocket capacity but there are diminishing
increases above 2,200 tonnes.