Professional Documents
Culture Documents
Preprint 10-041: The Longest Pipe Conveyor of The World With Double Load Transport at Cementos Lima in Peru J. Wiedenroth
Preprint 10-041: The Longest Pipe Conveyor of The World With Double Load Transport at Cementos Lima in Peru J. Wiedenroth
Preprint 10-041
THE LONGEST PIPE CONVEYOR OF THE WORLD WITH DOUBLE LOAD TRANSPORT AT CEMENTOS LIMA IN PERU
conventional disposal
loading-bottom run
Panel
Belt
Patented idler
brackets
Bulk material 1
Idlers
Bulk material 2
the clinker is extracted by a vibrating feeder from the clinker silo. The Table 3. Design data of the Pipe Conveyor.
upper strand then closes to form the pipe belt. Units Value
Speed m/s 4.0
Diameter of the Pipe mm 300
Panel spacing at straight line m 1.75
Panel spacing in curves m 1.40
No. of panels -- 5005
No. of idlers -- 60080
Sum of bending angles of all curves degree 286
The result of the calculations is shown in Fig. 12. At each end the
Pipe Conveyor has a drive pulley with rubber-ceramic friction lagging,
each with two drive units with installed ratings of 800 kW. The drives
are provided with frequency converters and external aeration to ensure
the necessary acceleration ramp time of 240 s. Under normal
circumstances the belt conveyor system is stopped over a ramp-down
time of 45 s. A ST 2500 6T+6T steel cord belt is used that is also
suitable for elevated temperatures of the material being transported.
Figure 10. Transfer area in the Atocongo Cement Plant. Feeding point Cement
and Clinker Belt ST 2500 6T+6T
Transfer area Conchan 2 drives à 800 kW incl.
frequency converter
The Pipe Conveyor leaves the tunnel again at Conchan, i.e. on
the Atlantic coast, where the loading terminal is situated (Fig. 11). The
upper strand separates from the lower strand and rises over a distance
of 248 m to the discharge point at the top of the silos. The lower strand Take-up carriage incl.
weights and Kapstan break
rises only slightly to the feeding point for the coal or limestone. The
routing was chosen as it had the least conflict with the existing
facilities. 2 drives à 800 kW incl.
frequency converter Belt turnover 1
Belt turnover 2
Figure 12. Results of the calculations of the double strand Pipe
Conveyor at Cementos Lima in Peru.
The diagram in Fig. 13 shows the development of the calculated
belt tension during normal operation when the upper strand is loaded
with cement (600 t/h) and the lower strand with limestone (500 t/h).
Obertrum beladen
Untertrum beladen
Obertrum leer
Untertrum leer
OT steigend beladen
OT fallend beladen
Gurtzugkraft in kN
Figure 11. Discharge pulley with drive units; transfer chute cement
and clinker; take up system; belt turning station and material loading
point for coal or limestone.
Special emphasis had been placed on an excellent dedusting
system and a dust-free transfer of material, respectively.
The take-up system consists of a take-up carriage which is
connected to two counterweights by two tension ropes. Between the 0 1000 2000 3000 4000 5000 6000 7000 8000 9000
take-up carriage and the counterweights the ropes run through a so- Abstand vom Aufgabepunkt Atocongo in m
called “Capstan Brake”, which artificially increases the counterweight in Figure 13. Belt tension in the upper and lower strand.
case of an emergency stop. This artificial counterweight increase
prevents the counterweight from bouncing up during these dynamic The following loading conditions have been calculated:
processes and an extreme decrease of the belt traction forces at
critical points can thus be Upper strand and lower strand loaded
Upper strand and lower strand empty
DIMENSIONING OF THE PIPE CONVEYOR Upper strand loaded in ascending sections only
Upper strand loaded in descending sections only
Detailed calculations to determine the belt tensile forces and drive
rating were carried out for the design of the Pipe Conveyor on the For a conveying system as long and as complex as the Cementos
basis of the specified route. First of all it was necessary to define all Lima Pipe Conveyor System with the different loading conditions, a
the sub-sections accurately with respect to length, gradient, vertical dynamic calculation is required in order to ensure a safe design. Belt
and horizontal curves with radius and angle. Table 3 lists some traction forces, strains on and speed of short belt sections in short time
important design data of this Pipe Conveyor. intervals in transitional phases (start-up and slowdown) are calculated.
The results of the dynamic calculations show whether the distance of 8.2 km between centers makes it the longest Pipe
selected take-up system is appropriate and reveal the maximum Conveyor in the world. The Pipe Conveyor, which has 15 horizontal
movements of the take-up pulley, the occurring forces and speeds of and 20 vertical curves and which can transport two different bulk
the belt etc. materials simultaneously in opposite directions, came into operation at
the end of 2007 and was accepted by the client in January 2008 after a
successful 24-hours performance test. This presentation starts by
describing the situation and provides interesting information about the
planning, design, installation and commissioning of the Pipe Conveyor.