Professional Documents
Culture Documents
Material Requirement Planning
Material Requirement Planning
2
MASTER PRODUCTION SCHEDULE (MPS)
The master schedule deals with end items and is a major input to the MRP process.
The aggregate plan provides the general range of operation; the master scheduler must
3
FROM APP TO MPS
4
ROLE OF TIME FENCES
5
MATERIAL REQUIREMENTS PLANNING
The logic that ties production functions together from a material planning and control
view
6
MRP – SYSTEM STRUCTURE
MRP
system
inputs
MRP
system
outputs
7
PRODUCT DEMAND SOURCES
Aggregate production plan – the firm’s strategy for meeting demand in the future,
implemented through the master production schedule (MPS)
8
BILL OF MATERIALS
9
BOM EXAMPLE
Product A – Product A
the end item consists of
2 B and 3 C
Product C consists of
Product B 2 F, 5 G, and
consists of 4H
1 D and 4 E
10
BOM – STRUCTURES & HIERARCHY
Higher levels (lower
numbers) refer to end
products.
Source: Link 12
INVENTORY STATUS RECORDS
Basic
information
describing
the item
Information
about part
availability
Additional
information
that may be
useful
13
MRP – EXPLOSION PROCESS
The requirements for end items are retrieved from
the master schedule.
•These are referred to as “gross requirements” by the MRP program.
14
MRP – EXPLOSION PROCESS (CONTD.)
15
MRP EXAMPLE – AMPERE, INC.
Meters are of two basic types for different voltage and amperage ranges.
Some subassemblies are sold separately for repair or for changeovers.
The schedule is then checked for feasibility, and the schedule is modified if
necessary.
16
FUTURE REQUIREMENTS – METERS (A,B) & SUBASSEMBLY (D)
17
PRODUCT STRUCTURE & INVENTORY DATA
18
MRP PLANNING SCHEDULE
19
MRP – ANOTHER EXAMPLE
20
MRP – ANOTHER EXAMPLE (2)
22
MRP – ANOTHER EXAMPLE (4)
23
LOT SIZING IN MRP SYSTEMS
Determination of lot
sizes in an MRP
Economic order
system is a Lot-for-lot (L4L)
quantity (EOQ)
complicated and
difficult problem.
Lot Sizing
Lot sizes – the part Strategies
quantities issued in
the planned order
receipt and planned Least total cost Least unit cost
(LTC) (LUC)
order release
sections of an MRP
schedule
24
LOT FOR LOT (L4L)
Produces exactly
Sets planned orders what is needed each
to exactly match the week with none
net requirements. carried over into
future periods.
25
ECONOMIC ORDER QUANTITY (EOQ)
27
COMPARISON – L4L & EOQ
Lot-
for-
Lot
EOQ
28
LEAST TOTAL COST
Least total cost method (LTC) – a dynamic lot-sizing technique that
calculates the order quantity by comparing the carrying cost and
the setup costs for various lot sizes and then selects the lot in which
these are most nearly equal
29
LEAST TOTAL COST - CALCULATIONS
30
LEAST UNIT COST
31
LEAST UNIT COST - CALCULATIONS
32
LOT SIZING – ANOTHER EXAMPLE
33
LOT SIZING – LOT FOR LOT
34
LOT SIZING – EOQ
35
LOT SIZING – LTC
36
LOT SIZING – LTC ORDERS
37
LOT SIZING – LUC
38
LOT SIZING – LUC ORDERS
39
LOT SIZING – DECISION
40
41