GREDOR NIGERIA LIMITED INSTALLATION OF JUNCTION BOX AT THE SNG/NGC/WAPCO

ROW  
WORK PLAN

Activity ID Activity Name Original Remaining Duration % Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q


Duration Duration Complete J JJ J JJ J JJ J JJ J JJ J JJ J JJ

IJB INSTALLATION OF JUNCTION BOX AT THE SNG/NGC/WAPCO ROW 4 4 0% 02-Jul-21 05-Jul-21 05-Jul-21, IJB INSTALLATION OF JUNCTION BOX AT THE SNG/NGC/WAPCO ROW
IJB10 Procurement of bond box 1 1 0% 02-Jul-21 02-Jul-21 Procurement of bond box
IJB20 Procurement of materials for the fabrication of bond box stand 1 1 0% 02-Jul-21 02-Jul-21 Procurement of materials for the fabrication of bond box stand
IJB30 Fabrication of stand 1 1 0% 03-Jul-21 03-Jul-21 Fabrication of stand
IJB40 Mobilization of CP team to site 1 1 0% 04-Jul-21 04-Jul-21 Mobilization of CP team to site
IJB50 Procurement of Laterite and refilling of sink ROW 1 1 0% 05-Jul-21 05-Jul-21 Procurement of Laterite and refilling of sink ROW
IJB60 Installation of bond box 1 1 0% 05-Jul-21 05-Jul-21 Installation of bond box
IJB70 Casting of base of bond box 1 1 0% 05-Jul-21 05-Jul-21 Casting of base of bond box
IJB80 Demobilization 1 1 0% 05-Jul-21 05-Jul-21 Demobilization

Actual Level of Effort Critical Remaining Work Page 1 of 1 INSTALLATION OF JUNCTION BOX AT THE SNG/NGC/WAP...
Actual Work Milestone
Date Revision Checked Approved
02-Jul... IFA OLAKUNLE BABALOLA FELIX OWUMI