Professional Documents
Culture Documents
2007 Analyses of Underground Structures Crossing An Active Fault in Coronado
2007 Analyses of Underground Structures Crossing An Active Fault in Coronado
D. Young
Hatch Mott MacDonald, Pleasanton, California, USA
ABSTRACT: The City of Coronado, California, has initiated the design for the State Route 75/282 Trans-
portation Corridor Project. This project includes the design of approximately 5700 feet (1740 m) long twin road
tunnels. The shallow, 32 –6 (9.9 m) finished diameter, tunnels will be crossing the seismically active Coronado
Fault. A cut-and-cover box structure or twin bored tunnels lined with precast segmental concrete linings, have
been considered as options in the area of the fault crossing. Assessment of the structural behaviour of these
options during fault rupture consisted of the development of finite difference (bored tunnels) and finite ele-
ment (cut-and-cover boxes) analytical models. Both types of models reflected non-linear stress-strain ground
behaviour. The results of the design analyses have shown that it is possible to assess the structural behaviour of
underground structures under severe ground displacement conditions using numerical analysis and to develop
structural solutions.
1 INTRODUCTION
445
Table 1. Design ground motion levels. Table 2. Maximum fault rupture design parameters in the
main zone.
Designation FEE SEE
Lateral (Along Strike) Sub-vertical
Return period 150 years Not Displacement (Along Dip)
applicable Scenario (1 inch = 25.4 mm) displacement
PGA 0.17 g 0.57 g
PPV 7.8–8.3 inches/ 26.3 inches/ Right lateral 22 inches 11.75 inches
second second Left lateral 14 inches 11.75 inches
Free field shear strain 0.04% 0.28%
Notes: PGA: Peak Ground Acceleration, PPV: Peak Particle Table 3. Maximum displacements in secondary zone –
Velocity, 1 inch = 25.4 mm footwall (hanging wall similar).
Sub-vertical
typically at or near the plastic limit, and the over con-
Lateral (Along Strike) (Along Dip)
solidation ratio of these materials is typically in the Scenario displacement displacement
range of 2.5 to 2.9.
The Bay Point Formation sands are medium dense Right lateral 11 inches 5.9 inches
to very dense, with an effective friction angle typcally Left lateral 7 inches 5.9 inches
ranging from 33 to 38 degrees.
Groundwater exists 10 to 15 feet (3.0 to 4.5 m)
below ground surface, and depth to invert varies from
40 feet (12 m) for the cut-and-cover option to 100 feet
(30 m) for the bored tunnel option.
Site seismicity and geologic hazards were assessed
by Kleinfelder (2006). Three faults, the Coronado,
Silver Strand, and Spanish Bight Faults, have been
identified in and around the project area but only the
Coronado fault crosses the proposed tunnel structures,
as shown on Figure 1.
The project is being designed for a Functional
Evaluation Earthquake (FEE) event and a Safety Eval-
Figure 2. Hanging wall and Foot wall.
uation Earthquake (SEE) event. As the anticipated
lifetime of the project is on the order of 100 years, The lateral design offsets were estimated by deter-
the FEE will conform to the 150-year return period ministic methods. The two fault rupture lateral and
event. The SEE event is similar to the maximum cred- vertical displacements for the SEE are outlined on
ible earthquake. The maximum moment magnitude for Table 2 below for the main zone and in Table 3 for
the SEE is 7.0. A summary of proposed design seis- the secondary zones. A graphic depicting a hanging
mic ground motion levels for the SR75/282 Project is wall and foot wall is shown on Figure 2.
provided on Table 1. Return period and peak ground Lateral displacements occur in the same direction
acceleration (PGA) values are provided in the table as the strike of the fault which intersects the tunnel at
as well as peak particle velocity (PPV) and free field an angle of 78 degrees. The dip of the Coronado Fault
shear strains that consider near source effects. was observed to be 70 degrees. (Kleinfelder, 2006).
The fault is only expected to rupture in the SEE event. 4.1 Tunnel structure properties and geometry
It will rupture through the soil to the ground surface
Geometry of the planned tunnels and assumptions that
in an oblique sense of movement, with displacement
were built into the analytical models were as follows:
spread over a fault zone thickness of 2 feet (600 mm).
Displacement values for design are described in terms • External tunnel diameter: 36.5 feet (11.12 m)
of vector components along strike and down dip. • Lining thickness: 1.5 feet (457 mm)
The primary fault rupture occurs along the 2 foot • Ring length 5 feet (1.52 m)
(600 mm) wide zone that can occur anywhere within a • Number of segments in a ring: 6 + a key
70 foot (20 m) wide zone along the alignment. In addi- • Spacing between the twin tunnels 62.5 feet
tion to primary rupture, secondary fault rupture would (19.05 m) center-to-center
occur within a zone 50 feet (15 m) in each direction • Lining modulus of elasticity 4354 ksi (30000 MPa)
outside of the primary zone. (uncracked concrete)
446
150 feet
and n is the number of radial joints and I is the moment
300 feet of inertia of the solid section of the lining. The formula
has been derived under the assumption that the radial
joints are uniformly distributed along the ring circum-
60 feet
ference. Typically, with the key segment being much
smaller than the rest of the segments the radial joints
adjacent to the key are much closely spaced than the
100 feet rest of the radial joints and thus the two joints adjacent
to the key were conservatively considered as one joint.
In order to preserve the true axial load stiffness of
the lining the following calculations had to be per-
formed where tm is the lining thickness in the model,
t is the actual thickness of the lining, Em is the modulus
of elasticity of the lining in the model, E is the actual
modulus elasticity of the lining and A is the actual
lining area per unit length:
Figure 3. FLAC3D model.
447
Figure 4. Case 2 tunnel ring displacements (x10). Figure 6. Case 3 soil block displacements (x10).
Moment [lbsf.ft/ft]
-1200000
-1000000
-800000
Axial Force [lbsf/ft]
18" #8@8
-600000
My Ny
-400000
-200000
-400000 -200000 0 200000 400000
0
200000
Figure 5. Case 3 tunnel ring displacements (x10). Figure 7. Capacity and loads, linear elastic lining hoop
direction, case 2.
• The system was brought to equilibrium, while the
gap was allowed to close.
• In the next phase, the fault offset displacement displacement is gradual, extending beyond the model
pressures have been gradually applied to the bound- limits and smoothes out the abrupt ground displace-
aries of the model while concurrent solving of the ment. Case 1 results were intermediate between these
model towards equilibrium was performed. Once two extremes.
the prescribed displacements at the model bound-
aries were reached the model was brought into the 4.6.1 Post processing
final equilibrium. A moment-axial force interaction curve was developed
• A similar gradual loading process was applied to
for the precast lining assuming the reinforcement of
model the SEE shaking. A free field strain of 0.34% about 1% in each direction. Values of axial loads and
was applied gradually along the boundaries of the corresponding moments were read from all elements
model, perpendicularly to the tunnel direction thus representing the tunnel lining in the model and plotted
imposing ovaling deformations. against the capacity curves.
• Non-linear material simulation of the concrete lin-
ing was performed.
4.6.2 Lining as linear elastic material
As the first step in the evaluation, the lining rings were
4.6 Observations from the analyses
conservatively assumed to be a linear elastic material.
Figure 4 shows that for Case 2 the tunnel dis- This would correspond to uncracked lining. Figure 7
placements follow the ground displacements. Fig- shows the critical curve for Case 2 connectivity
ure 5 shows that for Case 3, however, the tunnel assumption.
448
Lining M - N and Load Case 2 with Concrete/Steel Non-
linearity Hoop Direction
Moment [lbsf.ft/ft]
-1200000
-1000000
-800000
Axial Force [lbsf/ft]
18" #8@8
-600000
My Ny
-400000
Figure 9. Box geometry.
-200000
-400000 -200000 0 200000 400000
0
200000
449
5.3 Analyses results
Figure 11 shows the resulting box displacement. The
results also showed that with providing the special
joints the effect of the fault rupture was actually
secondary to the effects of the ground shaking.
6 CONCLUSIONS
Y
X
Z Load 4 : Displacement
5.2 Modeling sequence in StaadPro Dean,A.,Young D.J., and Kramer G.E. 2006.The Use and Per-
formance of Precast Concrete Tunnel Linings in Seismic
A two stage modeling sequence was used to cir- Areas. Proceedings of the 10th IAEG Congress, Notting-
cumvent some of the StaadPro loading modeling ham, United Kingdom: Paper No 679, Geological Society
limitations. Publishing House
Soil shear strains causes by ground shaking were Kleinfelder, Inc., 2006. Final Preliminary Engineering
Geotechnical Investigation, Volume I&II, State Route
applied as an additional, racking, displacement derived
75 and 282 Transportation Corridor Project Report,
from the calculated soil shear strain and the ratio of the Coronado, California.
ground and structure stiffness. Muir Wood, A M. 1975. The circular tunnel in elastic ground.
Consideration has been given to using compressible Geotechnique 25 No 1:115–127.
material around the box structure to reduce the forces USGS 2000, The web site of the U.S. Geological Survey,
on the structure due to ground movements. http://www.usgs.gov/
450