Professional Documents
Culture Documents
AY1920 EG114101 Teaching Materials
AY1920 EG114101 Teaching Materials
RC Buildings
Reinforced Concrete (R.C.)
Concrete
1 of 18
Chapter 1. RC Buildings
Load Compression in
upper fibres
Load Compression in
upper fibres
Reinforcement
Reinforcing bars (rebar) are made of high carbon steel. They are manufactured by
hot rolling and therefore also known as ‘Hot rolled steel bar”. Two types of rebar
are used for construction:
A plain round steel bars is made of mild steel. It is classified as Grade 250. It
means that the characteristic yield stress shall not be less then 250 MPa. Common
nominal sizes (bar diameter in mm) are: 10, 12 and 16. Plain round steel bars are
2 of 18
Chapter 1. RC Buildings
named with a prefix ‘R’. For example, R10 denotes a plain round steel bar of 10
mm diameter.
A deformed high tensile steel bar is rolled on the surface with ribs to increase the
bond strength with concrete. It is classified as grade 500. Common nominal sizes
are: 10, 12, 16, 20, 25, 32 and 40. They are named with a prefix ‘T’. (Formerly it
is name as high yield steel bar with a prefix ‘Y’.)
Beam
Wall Superstructure
Column
Floor slab
Substructure
Foundation
Columns are vertical members which carry the loads from beams and transfer
the loads down to the foundations.
Column
Secondary beams
Beams are horizontal member supporting floor slabs. They are further
subdivided into main beam and secondary beam.
Main beams span between columns and transfer the loads placed upon them to
the columns.
Secondary beams span between main beams and transfer their loadings to the
main beams. Their primary function is to reduce the spans of the floor slabs.
Floor slabs provide platforms on which people can circulate and furniture can
be placed.
Walls – wall can be classified into external walls and internal walls:
External walls are the envelope of the building to exclude rain, wind, sunlight,
etc.
Internal walls (partitions) are used to subdivide the floor space in a storey of
different uses.
Some walls also help to take loadings.
4 of 18
Chapter 1. RC Buildings
R.C. Beam
When a beam is subjected to loading, the upper part of the beam will be in
compression while the lower part is in tension.
Therefore, main reinforcements should be placed at the bottom side to resist
tension.
Top bars are often used as carriers for links.
For heavily loaded beams, top bars also help to resist compressive stress.
Even though compressive and tensile strengths of the beam are not exceeded,
cracks may still appear in the web of the beam near the supports. These cracks
are in fact shear failure lines at an angle of approximately 45 to the horizontal,
and sloping downward toward to the supports.
P P
Crushing
Flexural cracks
Shear crack R
R
Crack Pattern of Loading a R.C. Beam
Shearing stress may be resisted by bent up bars at 45 to the horizontal and
positioned to cut the anticipated shear failure plane at right angles. These are
in fact the main bars from the bottom of the beam which are no longer required
to resist tension which can be bent up to the top and carried to the support.
5 of 18
Chapter 1. RC Buildings
A
Links at close centres Links at nominal centres Links at close centres
02 02
03
01 01 01
Main bars 01 Top bars 02 Link 03 Section
A
A-A
Typical R.C. Beam Reinforcement (without bent up bar)
Even where shear resistance is not required, nominal links are provided in
beams for hanging up the top bars. They also help to minimize shrinkage
cracks of the concrete and confine the compression bars from buckling.
For cantilever beams, main bars should be placed at the top as tension is
appeared at the top of the beam.
Main bars
Link
Bottom bars
Fixed
support
Typical Reinforcement Details of Cantilever Beam
6 of 18
Chapter 1. RC Buildings
R.C. Column
Reaction to beams upon the column, as the beam deflects it tends to pull the
column towards itself thus inducing bending in the column.
Wind loading acting on high-rise buildings, the columns on the windward side
may be subject to tension.
P P
Wind
Columns
in tension
The minimum number of the main bars in a column should not be less than four
for rectangular columns and six for circular columns.
7 of 18
Chapter 1. RC Buildings
main
bar
B B
Section A - A Section B - B
Typical R.C. Column Reinforcement
R.C. Slabs
Slabs are spanning members and they behave very similar to beams.
Main bars should be placed at the bottom side of the slab to resist sagging.
Normally, top reinforcement is not required except for heavily loaded slabs.
However, a hogging moment will occur above supports which necessitating top
reinforcements.
For cantilever slab such as canopies, the main bars shall be place near the top of
the slab to resist top tensile stresses.
The slab thicknesses of most domestic buildings are about 100 mm to 150 mm.
8 of 18
Chapter 1. RC Buildings
There are three basic forms of floor slab systems:
Beam and slab system
Flat slab system
Slab
Ribbed slab system
Beam
Beams
Columns
Beam & slab spanning two-ways Beam & slab spanning one-way
9 of 18
Chapter 1. RC Buildings
Middle strip
Slabs
Drop panel
Waffle slab
A ribbed slab is also known as waffle slab or honeycomb floor (or roof).
It is cast over lightweight moulds or pans made of glass fibre, or polypropylene.
Ribs in both longitudinal and transverse directions are formed in close centres
and tied with each others.
Ribbed slabs can resist great bending moment in both longitudinal and
transverse directions.
They are used for large span slabs and require less concrete and less
reinforcement than other slab systems.
Slab
Ribs
Column
Waffle slab
10 of 18
Chapter 1. RC Buildings
R.C. Walls
External walls
An external R.C. wall should contain a mat of reinforcement in each of two faces.
The horizontal reinforcement of each mat should be evenly spaced in the outer layer
to contain the vertical compression bars. Additional horizontal restraining links
should be provided.
Restraining links
Shear walls
Shear walls are thick R.C. walls to increase the lateral stability of a building.
Strong wind tries to cause a high-rise building frame to sway. Shear walls are
ideally suited for bracing tall buildings because of their very high in-plane
stiffness and strength. Therefore, shear wall is also known as ‘wind wall’.
Shear walls also carry gravity loadings. They replace part of or even all
columns. Shear walls are arranged as external walls and partitions. Grouped
shear wall may also be used to form services cores, elevator shaft and stairwells.
11 of 18
Chapter 1. RC Buildings
Concrete when first mixed is a fluid. Formwork is the temporary moulds for casting
concrete members where the fresh concrete can be placed to retain its shape, size and
position as it sets.
Formwork materials
Timber plank
Various sizes of timber planks are available but the most common one used in
Hong Kong is 2” x 4” (50 mm x 100 mm) planks.
Plywood
Most common type of plywood used in Hong Kong is 4’ x 8’ x 3/4” (1.2 m x 2.4
m x 19 mm) 7 plies plywood.
Some plywood is resin coated (sealed plywood). It is more expensive but the
board life is extended (typically 5 to 10 reuses) and it gives good concrete finish.
Soffit form
Bearers of suitable size shall be placed on top of the U-heads / prop cap plate.
Bearers shall be fixed by wedges / nails centrally to prevent eccentricity and
dislodgement.
Joists shall be placed at suitable centres on top and at right angle to the bearers.
Plywood can then be placed on top of the joists and fixed by nails.
Joist
Plywood
Bearer
Fork head
Soffit form
14 of 18
Chapter 1. RC Buildings
Column Form
Clamps
Studs
Plywood panel
Plan Front view
Timber Column Formwork
Beam Form
This is basically a three sided box supported and propped in the correct position
and to the desired level.
The beam formwork also has to resist lateral hydrostatic pressure of the wet
concrete, sufficient braces shall be provided.
15 of 18
Chapter 1. RC Buildings
A Side panel
Slab soffit form
Raking strut
Shutter
Stud
Kicker
Joist
Bearer
Soffit panel
Fork head
Falsework
Wall formwork
A
Plywood panel
Wall tie
Stud
Double walings
Steel bars are cut to correct lengths, bent to desired shapes and then fixed to positions
with steel wires.
A 5 R10-04-100 B 5 R10-04-100
6 R10-04-200
03 03 2T 10 03
03 03
01 01 01 02 01
02 02
Section A-A 2 T20-01 & 1 T16-02 Section B-B
A B
Legend
total number of bars in the group centre to centre spacing
5 R10 -04-100
150
17 of 18
Chapter 1. RC Buildings
Hooks and Bends
To prevent bond failure hooks or bends can be used at the ends of bars.
Bend sand Hooks for R-bars Bends and Hooks for T-bars
(Source: R. Chudley)
Concrete Cover
Concrete cover is the thickness of concrete measured from the concrete surface
to the outer face of the reinforcing bar.
The concrete cover provides corrosion protection and fire protection to the steel.
Normally, concrete cover is between 20 to 40 mm.
In very severe condition concrete cover may be increased to 100 mm.
18 of 18
Chaper 2. Earthwork, Substructure, Foundation and ELS
Very few sites are level and therefore re-shaping works have to be carried out before
any construction work can be taken place.
cut
formation level
formation level
fill
fill
1 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Excavation
There are various kinds of excavation plants. Suitable choices of plants increase the
efficiency and reduce the cost.
Backactor / Backhoe
2 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Bulldozer
Mainly designed for excavating, spreading or pushing soil from one position to
another.
Excavation is carried out by lowering the mould board or blade into the soil and
pushing the soil in front of the machine.
Other tasks:
clearing vegetation
stripping topsoil
excavating and opening up pilot roads
maintaining haul roads
as tractor for towing other plants
3 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Multipurpose Excavator
Both backhoe and loader shovel attached in one machine. It is also known as
backhoe loader.
Multi-function.
Useful in confined site.
The two components cannot be operated at the same time.
Road Lorry
Backhoe Loader
Road Lorries
4 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
5 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Rock Excavation
The techniques of breaking and excavating rock or other hard material depend on the
type of material, the quantity involved and the conditions on site. Such techniques
include:
Pneumatic breakers
Pneumatic breakers may be used to break the rock into small fragments. The power
supply to this type of breaker is from an air compressor. Small pneumatic breakers
are hand-held while giant breakers are hung on excavators.
Holes of 25 – 150 mm can be formed in rocks by rock drilling methods. The rocks
can then be further broken down by explosives.
There are basically two methods of producing holes in rock. These are:
Rotary-percussive drilling
Rotary drilling
6 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Rotary-percussive drilling
For hard rocks, the rotary-percussive drilling method is often favoured because the
rig is light and provides good rates of penetration up to 50 m deep and 150 mm
diameter. The method is used for blast holes, rock anchors, grouting holes, etc.
In rotary-percussive drilling the drill bit is supplied with both a percussive and a
relatively slow rotary action. The broken rock fragments are flushed out with either
compressed air or water. Various types of bits are available for different conditions:
For larger diameters boreholes, or when boring to greater depths and accuracy are
required, or where soil or soft rock are encountered, rotary drilling methods are
preferred.
Rotary drilling relies on a high feed thrust applied down the drill stem, to force the
edges of the bit into the rock surface. High torque and rotation of the drill shaft then
7 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
cause cracking and chipping, and rock fragments are broken away. Flushing of the
drill hole may be carried out with water or compressed air. Various bits are available
for different conditions:
Drag bit
Roller bits
Blasting
8 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Filling
Fill materials
Earthwork fill materials may consist of soil, rock, or inert construction and
demolition material.
Inert construction and demolition material shall mean rock, rubble, earth, soil,
concrete, asphalt, brick, tile and masonry generated from construction and demolition
works.
Fill material shall also be capable of being compacted to form stable areas of fill.
Compaction
Earthwork fill materials when deposited are normally loose and bulked. It is
therefore necessary to compact the materials so as to prevent softening, dislodgment
and settlement of the earth.
Fill material shall be compacted in layers to a stable condition. The thickness of each
layer shall be 150 mm to 300 mm which depends of the capacity of the compaction
plant used. The amount of compaction attained is measured by “dry density” of the
fill. Generally, the fill material shall be compacted to obtain a relative compaction of
at least 95% of the “maximum dry density” of that material.
9 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Compaction plants
Vibrating Rollers
Beside the weight of the machine, vibration greatly improves compaction
performance.
They are suitable for compacting granular soil
Various size available:
- manually guided tandem roller (1 tonne baby roller)
- up to 20 tonnes vibrating roller (effective compaction thickness: 300 mm)
Vibrating plate
manually guided
for light compaction
useful in utility trenches, confined space
and awkward situations
maximum compaction thickness: 150mm
Vibrating plate
10 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Power Rammers
manually operated
suitable for compacting soil in narrow
trenches and around foundations
effective compacted depth about 200mm
Power rammer
(Source: Masalta)
11 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Substructure
Substructures are structures below ground. Foundations and basements are the
most common type of substructures.
Shallow Foundation
Shallow foundations are found at a depth of less than 3 m below the finished
ground level.
Pad footing
12 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Strip Foundation
Columns
FRONT
VIEW
Blinding
concrete
PLAN
Strip foundation
Strip foundations are used to transfer the load from a wall, or from a
succession of closely spaced piers or columns, to the ground.
They consist of a continuous ribbon-shaped strip formed of reinforced
concrete. Main bars are placed transversely to resist bending while
longitudinal bars are used for the continuity of the strip foundation and to
bridge soft spots in the soil.
13 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Raft foundation
Solid slab rafts are suitable for lightly loaded structures such as small houses.
A solid slab raft consists of a reinforced concrete slab, usually slightly larger
than the area of the building. Reinforcement in the form of a mesh fabric is
provided on both the top and bottom faces of the slab.
Columns
Raft slab
Ground level
Blinding
Concrete
Ground beams
Beam and slab raft foundation
Combined foundation
15 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Shallow foundations
16 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Shallow basement
A basement can be defined as a storey with a floor which at some point is more
than 1.2 m below the highest level or ground adjacent to the outside walls.
The structural walls of a basement below ground level are in fact retaining walls
which have to offer resistance to the soil and ground water pressures as well as
assisting to transmit the superstructure loads to the foundations.
There are various kinds of methods for basement construction and maintaining
the stability of the ground. The choice depends on the nature of ground
condition and the depth of basement.
Open Excavations
Temporary support is often needed to the sides of the excavation for stability. These
temporary members can be intrusive when the actual construction works of the
basement is carried out. One method is to use battered excavation sides that cut back
to a safe angle of repose thus eliminating the need for temporary support.
This method is suitable for shallow basement only because the extra volume of
soil needed to be excavated increases rapidly with depth increased. Another
limitation is that large amount of free space around the site must be available.
The term ‘cofferdam’ can be defined as a structure, usually temporary, built for the
purpose of excluding water or soil sufficiently to permit construction to proceed
without excessive pumping, and to support the surrounding ground.
There are a lot of methods and materials for forming cofferdams. Among which steel
sheet piling cofferdam is the most common one in Hong Kong. It has the following
advantages:
a. Steel sheet piles have high structural strength
b. They can be driven deep into most types of ground.
c. Cofferdams can be constructed to a depth of about 15 m below existing ground
level.
d. The sheet pile interlocks provide an almost completely watertight enclosure.
e. The sheet piles can be withdrawn and reused.
18 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Sheet piles are normally driven into the ground by drop hammers or vibration
hammers to form an enclosure prior to excavation. To ensure that the sheet
piles are pitched and installed vertically a driving trestle or guide frame is used.
When excavation is taken place inside the cofferdam, adequate support must be
provided for the lateral stability.
19 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
This method is suitable for a depth up to 5 m. After the sheet piles has been driven
around the perimeter of the site to form an enclosure, the centre of the basement is
excavated down to the formation level but leaving a wedge of soil at the perimeter to
support the cofferdam. Raking struts are installed to support the cofferdam. Finally
the wedge of soil is trimmed away.
battered slope
base slab
waling
20 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
21 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Sheet piles
To be backfilled
and compacted
in layers
After the sheet piles have been driven around the perimeter to form an enclosure,
the centre of the cofferdam is excavated to about 1m below the first bracing
level.
Holes at suitable spacings and in the same level are drilled into the ground at an
inclination of 30-45 below the horizontal penetrating through the sheet piles.
Prestressing wires are inserted in to the holes and the ends are grouted with
cement grout.
Walings and anchorage heads are installed and the wires are prestressed to hold
the cofferdam.
The process is repeated for the subsequent bracing levels until down to the final
formation level.
This method is suitable for wide and deep basement. It also provides a clear working
area within the cofferdam. However its use is often limited by the site boundary.
23 of 66
Cofferdam support with ground anchors
Chaper 2. Earthwork, Substructure, Foundation and ELS
Piled Foundation
Classification of Piles
End bearing piles - they act as columns carrying the loads through the
overlaying weak subsoils to a firm stratum on which the pile toes rest.
Friction piles - they transfer the loads by the adhesion or friction action of
the soil around the perimeter of the pile shaft.
Replacement Piles - a shaft (or hole) is excavated and the soil replaced with
concrete to form a pile. This type of pile is called a replacement pile.
25 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Displacement piles are preformed piles made in a factory, transported to the site, and
then driven into the ground. They are also called ‘preformed piles’ or ‘driven piles’.
Preformed piles may be made of reinforced concrete or steel.
Displacement piles are generally driven into the ground by one of the following
methods:
1. Percussion
2. Vibration
Percussive driving
Piles are driven into the ground by the impact of heavy pile hammers. There are
several types of pile hammers:
a. Drop hammer
b. Diesel hammer
(These two types of piles are now obsolete.)
c. Hydraulic Hammer
be up to 18 tonnes. The stroke height is about 1-2 m. The blow rate depends on the
stroke height and ranges from 40 to 100 blows per minutes.
Most hydraulic hammers are equipped with silencers nowadays. They produce less
noise than diesel hammers and they do not emit exhaust fumes. They are suitable for
hard drive.
27 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Piling rigs
A piling rig has the function of guiding the pile at its correct alignment from the stage
of first pitching in position to its final penetration. It also carries the hammer and
maintains it in position co-axially with the pile.
Pile helmet
(Source: Jufri & Wellman)
Pile helmet
Helmets (Source: R. Chudely)
The head of displacement piles must be protected from damage during driving. The
protection consists of resilient packing which is held in position by a steel helmet.
The resilient packing distributes the impact load from the piling hammer evenly on to
the pile head.
The helmet should fit loosely around the pile, so that the pile may rotate slightly
without inducing torsion on the pile.
28 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
In the past, most of precast concrete piles were square in cross sections. They can be
made of either of normal reinforced concrete or prestressed concrete. Their bearing
capacity ranged between 800-1500 KN.
In 1980s, precast concrete piles in H.K. became tubular because of the development
of a manufacturing technology. This type of pile is prestressed and the concrete is
compacted by centrifugal spinning process. The spinning process effectively
compacts the zero slump concrete and produces a hollow tube without the need of a
former. They are then steam cured in an autoclave under high steam pressure and
high temperature in order to obtain a minimum concrete compressive strength of
about 80 MPa within three days.
The outside diameters of the piles are about 400-600 mm and in lengths of up to 12
m. They have a nominal bearing capacity in the range up to 3500 KN.
Each pile length has integral steel joint plates (end plates) cast onto ends of the pile.
Lengthening is done by a full penetration butt welding of the end plates.
The disadvantages of these piles are that they produce great noise and vibration
during the installation of these piles. Moreover, most Hong Kong soils are coarse,
containing boulders and rocks which are not too suitable for large diameter
displacement piles.
29 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Two main types of hollow steel piles: tubular and box sections. Box piles are
normally driven with closed ends (now obsolete) with internal drop hammers. Open
ended tubes can be driven with vibration hammers. Hollow Steel piles have a high
resistance to lateral loading and buckling and good energy-absorbing properties.
They are particular suitable for structures subjected to lateral and impact loading such
as jetties and dolphins.
Steel H-pile
Steel H-pile is strong and tough. The displacement of the soil is little compared with
other types of displacement piles. It is widely used in HK.
Driving steel piles generally do not require pile shoes. In hard conditions, the toe of
the pile may be strengthened. Strengthening may be carried out by welding steel
plates or angles to the toe of the pile. Preformed pile shoes for H-piles are also
available. In ground conditions where boulders exist, Oslo point may be used.
H-pile point
Strengthening by (Source: Housing Department)
welding of angles Oslo Point
(Source: Tomlinson) (Source: Tomlinson)
30 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Lengthening
Corrosion Protection
The surfaces of steel piles to which protective coatings will be applied shall be
prepared by blast cleaning.
31 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
32 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Measurement of set
‘Set’ related to the ultimate bearing capacity of the pile can be determined by pile
driving formulae by considering the parameters of the pile, the soil and the ground
condition. There are many pile driving formulae, among which the Hiley formula is
the most commonly used one.
Measurement of Set
33 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Advantages
1. Where large numbers of piles are to be installed in easy driving conditions, it can
be more economic.
2. Projection above ground level advantageous to marine structures.
3. The pile can be inspected for quality and soundness before driving.
4. Construction operations not affected by ground water.
5. Not liable to ‘squeezing’ or ‘necking’.
1. Transporting the complete length of pile through narrow and/or congested streets
may be difficult.
2. The driving process, which is generally percussion, can cause unacceptable noise
and vibrations.
3. Pile driving hour is limited by environmental regulations.
4. May break during driving, causing delays and replacement charges.
5. Displacement of soil during driving may damage adjacent structure or cause up
lifting of adjacent piles.
6. Cannot be driven in very large diameters.
7. Cannot be driven in conditions of low headroom.
34 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Replacement Pile
Rotary boring
Rotary boring involves a drilling rig which may be mounted on a mobile crane or a
truck. The drilling rig consists of a telescopic or extendable kelly bar on which a
boring tool is attached.
1. Cheshire auger – The auger has only a few helix turns. It has
to go up and down repeatly to cut the soil and bring the spoil
to the ground surface.
2. Continuous auger (flight auger) – It has a long helix. The
spoil is continuously brought to the ground surface by the
spiral motion. However, the drilling rig must provide
sufficient torque to overcome the great friction.
3. Drilling bucket – It is designed to withstand the high torque
forces developed during penetration of dense strata. The spoil
is temporarily stored in the bucket to reduce the friction
created. The frequency of up and down motions can also be
reduced as compared with that of the Cheshire auger.
4. Coring bucket – It is used to raise a solid core of rock.
5. Chisel - It is used break through boulder or rock.
36 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Grab boring
Virtually the rope can be of infinite length. The depth of a borehole can be over a
hundred meters by grab boring. Most boreholes are circular in cross section but can
be rectangular by using a rectangular grab.
When boulders are encountered, they can be broken by free falling a rock chisel on to
it. The rock fragments are then removed by the grab. Chisel and grab are often used
alternately to break through obstructions.
A down the hole drill (DTH) is a large size hammer drill. It is equipped with a button
bit that can drill holes into rock with diameters up to 750 mm and to depths of several
hundred meters.
Pneumatic Hammer
Button bit 38 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
A reverse circulation drilling rig can drill at a fast rate in a wide range of ground
conditions including rocks. In Hong Kong, it is commonly use to form the bed rock
sockets for bored piles.
The Reverse circulation drill sits on the temporary steel casing while operating. The
Compressed air is injected through the air delivery pipe and discharge at the base of
the hollow drill stem. The rising column of air and water at the centre of the drill
stem lifts the soil and rock fragments which have been loosened by the drilling bit.
(It is termed as air lifting. Air lifting is also commonly used to clean the bottom of a
bored pile before concreting.)
39 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
40 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Bell-out
The base of a bored pile can be enlarged to three times the shaft diameter to increase
the bearing capacity of the pile. The method is known as under-reaming which is
done by a belling bucket.
The belling bucket is lowered to the bottom a borehole by a kelly bar with the cutter
in retracted position. It is then rotated by the kelly bar and the cutter is jacked out to
form the bell.
Self-supported (unsupported)
For small diameter bored piles and in stable soils, the borehole may remain
unsupported without collapsing. However, a borehole without support is not
recommended in Hong Kong.
The oscillator consists of a collar clamp and a pair of hydraulic jacks. The collar
clamp grips the casing. The two hydraulic jacks extend and retract repeatly in
opposite phrases. This oscillation motion helps to cut the soil by the casing shoe and
sink the casing into to ground.
The steel casing is usually thick and expensive and will be retrieved after the
borehole is concreted. The casing oscillators (or vibrator hammer) the can be used to
withdraw the casing. In a long pile the casing may be stuck by the concrete and the
extraction becomes difficult. Moreover, temporary steel casings which are in contact
42 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
with concrete shall be withdrawn before the initial set of the concrete has taken place.
Otherwise, it shall be left in place.
To overcome this problem, it is advisable to extract the casing in stages, i.e., the
casing is extracted as concreting progresses upwards. However, it is important that a
sufficient concrete pressure head shall be maintained within the steel casing to ensure
that the pressure from external soil and ground water would not cause necking of the
pile. Extraction of
casing
Earth and
ground
water
pressure
Fresh
concrete
pressure
Permanent casing
Sometimes a permanent casing will be lowered into a temporary cased borehole. The
permanent casing is made of light gauge corrugated steel sheet. It is much cheaper
than the thick temporary casing.
The permanent casing prevents the expensive temporary casing being stuck by the
fresh concrete. It also reduces the risk of necking of the pile after extraction of the
temporary casing and prevents the fresh concrete being contaminated by soil and
ground water. Corrugated steel casings are often used in long piles and in difficult
grounds such as reclaimed land.
43 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Bentonite is a kind of clay. When mixed with the correct amount of water bentonite
slurry produces thixotropic properties, it gives a liquid behaviour when agitated and a
gel structure when undisturbed.
During boring, the borehole is filled with bentonite slurry. The boring action stirs the
slurry so it remains liquid state. But the slurry penetrates slightly into the subsoil and
forms a soft gel or so called 'filter cake' at the interface of the excavation sides.
Hydrostatic pressure caused by the slurry thrusting on the 'filter cake' that prevents
the borehole from collapse. This method is not suitable for soil with high
permeability.
Bored pile
Bored pile is perhaps the most popular type of pile in Hong Kong currently. The
maximum diameter can be over 3 m and the pile length can be over 100 m. It can be
designed to carry loads up to 30000 kN.
There are various techniques for boring pile shafts and supporting them. The choices
of the methods and their combinations depend on the ground condition and the pile
design. Some typical examples are as follows:
Procedure
1. Pitch a temporary steel casing in the correct position and drive it into the ground
with a casing oscillator.
2. Bore within the casing with a hammer grab. Boring shall not go beyond the
bottom of the casing to prevent collapse of the borehole.
44 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
3. If rocks or boulders are encountered, use a chisel to break them and then use the
grab to remove the fragments.
4. Extend the steel casing and drive it into the ground if necessary.
5. Repeat steps 2 to 4 until the founding rock is reached.
6. Place a reverse circulation drill on top of the steel casing. Form the socket of
desired depth into the bed rock with a roller cutter. The debris is removed by air
lifting.
7. Remove the RCD. (Lower a permanent casing into the borehole.)
8. Lower the reinforcement cage into the borehole.
9. Check the rate of ingress of ground water. If it does not exceed 0.3 L/s, place
high slump concrete into the shaft immediately after it is pumped dry.
Otherwise, fill the shaft with tremie concrete.
10. Extract the temporary steel casing as the concreting is progress upward. When
the concrete level reaches the desired lever, the piling process is completed.
Boring supported with temporary casing Boring supported with bentonite slurry
45 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Procedure
1. Pitch a steel collar casing in the correct position and drive it into the ground with
a vibration hammer.
2. Fill bentonite slurry within the casing and excavate the borehole with a hammer
grab.
3. Maintain the slurry level to about 500 mm below the top of the casing during the
whole piling process.
4. If rocks or boulders are encountered, use a chisel and the grab alternately to
break the rocks and remove the fragments.
5. Repeat steps 2 to 4 until the founding rock is reached.
6. Use the chisel and the grab alternately to form a socket in the rock.
7. Lower the reinforcement cage into the borehole through the slurry.
8. Insert an air lift pipe to the bottom of the borehole. Clean the bottom of the
borehole with air lifting. Slurry loaded with soil particles shall be pumped to a
settling tank, stained and recycled.
9. Fill the pile shaft with tremie concrete. Displaced slurry shall be retrieved.
10. Stop concreting with the concrete reaches 1 m above the cut-off level. Remove
the collar casing and the piling is completed.
Barrette
By definition, a barrette is exactly the same as a bored pile supported with bentonite
slurry. However, a barrette is often referred as a pile in rectangular cross section. Its
46 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
formation is the same as that of a bored pile except that four concrete guide walls are
used instead of the collar casing. The guide walls are about 150 mm thick, arranged
as a topless and bottomless box with internal dimension the same as the barrette
section.
48 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Minipile (Micropile)
Minipiles are defined as piles having a diameter of less than 300 mm. Generally they
range in shaft diameter from 50 to 250 mm, with working loads in the range of 50 to
500 kN. There are many ways of forming minipiles. A typical method currently used
in Hong Kong is:
1. Drill a borehole of about 150 mm diameter with a rotary drilling rig and line the
borehole with a steel casing.
2. Grout the borehole with cement slurry from the bottom of the hole.
3. Insert the pile reinforcement into the casing. Normally it consists of 2-4 numbers
of T40 or T50 bars.
(The steel casing is left in place to enhance corrosion protection.)
The principal use of minipiles is for underpinning work or in steep slope where large
piling machine cannot access.
49 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Concreting by trunking
In boreholes where the rate of ingress of water does not exceed 0.3 L/s, the piles shall
be dried immediately before concrete is placed. Then the concrete can be placed
using a readily workable mix (slump 100 mm , which is self-compacting but does
not segregate) through a trunking.
Procedure:
Erect the tremie pipe (with hopper) vertically and resting on the bottom of the
pile shaft.
Place a traveling plug (formed with foamed plastic in plastic bag) into the tremie
pipe.
Feed high slump concrete into the hopper to push the traveling plug downward.
When the plug reaches the bottom, slightly raise the tremie pipe to let the plug
and the concrete to flow out.
Continuously feed fresh concrete into the tremie pipe. Pump away displaced
water/bentonite slurry.
Raise and remove sections of the tremie pipe progressively to maintain the
concrete flow rate, but keeping at least 3 m embedment of the tremie pipe in the
concrete.
Continue concreting until the concrete level reaches 750 mm above the cut-off
level.
50 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
51 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
1. Soil or rock removed in boring can be inspected for comparison with site
investigation data.
2. Can be installed in very large diameters.
3. Can be installed in very long length.
4. End enlargements up to three diameters are possible
5. Can be installed without appreciable noise or vibration.
6. Can be installed in conditions of very low headroom.
7. No risk of ground heave.
1. Drilling a number of piles in group can cause loss of ground and settlement of
adjacent structures.
2. Squeezing or ‘necking’ may occur in soft ground that reduces the bearing
capacity of the pile.
52 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Diaphragm Walls
Diaphragm walling describes the construction of continuous concrete walls into the
ground. The process, sometimes called the slurry trench method, involves the
excavation of a narrow trench to the required depth which supported with bentonite
slurry. The trench is then filled with concrete to form the wall.
1. A perimeter trench, 1 to 1.5 m deep and with a width equal to the wall
thickness plus 300 mm is excavated.
2. The trench is lined on both sides with 150 mm thick in-situ concrete. (The
linings provide a guide for the grab and protect the top of the excavation from
collapse.)
3. The wall is divided into to panels. The width of each panel is about 4.5 to 7 m.
The sequence of construction for the panels is in an alternatively way. That is,
an intermediate panel is excavated after panels on its both sides have been cast.
4. The trench is then filled with bentonite slurry from a large storage tank before
excavation. Excavation is done by a grab. During excavation, it is important
to maintain the slurry level at about 0.5 m below the top of the trench. (The
function of the bentonite is to prevent the ingress of water and soil into the
trench.) Excavation is continued until the founding is reached.
5. Stop end pipes of diameter equal the wall thickness are placed at both ends of
the panel. A reinforcement cage is lowered through the bentonite and panel is
cast with tremie concrete. The displaced bentonite is recovered, strained to
remove the soil particles and then stored for future use.
6. When the concrete has set, the stop end pipes are removed. Semi-circular
sockets are formed which provide key for the adjacent panels.
7. Further panels of the diaphragm wall are then formed in a similar manner until
the wall is completed.
53 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
54 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
It is to construct the basement in the downward direction to the final levels of the
basement. The sequence of work is as follows:-
1. Construct the permanent basement wall using diaphragm wall or soldier piles
wall.
2. Construct bored piles with temporary steel casings as the foundation of the
basement. The cut-off level of the piles is at the final basement level.
3. Place steel columns inside the steel casings of the bore piles from the foundation
level up to the ground level.
4. Backfill the shafts with granular material to hold the steel columns.
5. Construct the ground floor slab supported on the steel columns and the
diaphragm walls. (This slab provides a working platform for superstructure
construction and acts as the lateral support for the basement excavation.) Access
opening in this slab shall be provided for further excavation.
6. Excavate beneath the ground floor slab down to next basement floor soffit.
7. Cut the steel casing, remove the gravel and expose the steel column.
8. Cast the second basement slab. (The slab is connected to the columns with shear
studs and connected the diaphragm wall with dowels)
9. Repeat the process for the successive basement floors until down to the final
basement slab.
55 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Steel column on
top of bored pile
56 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Pile Test
Sonic Test
A non-destructive test is based on the principle of measuring the velocity of
propagation of vibrations between a transmitter and a receiver which are both placed
inside the pile.
57 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Vibration Test
This is one kind of non-destructive test and no preparation work is required during
construction. It is carried out by placing an electro-dynamic vibrator on the centre of
the prepared pile head. The vibrator imposes a sinusoidal force of constant amplitude
to the pile. A velocity transducer records the movement of the head of the pile caused
by the vibration. The pile concrete condition and the length are then measured from
the geometry of the curve.
58 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
59 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Koden Test
KODEN test is a pile test for testing the size of bell-out of large diameter bored pile.
Before using this test, all bell-out have to be checked by sending of diver down to the
bottom of the pile for inspection, and actually the diver was working in the very
dangerous environment such as unsupported soil, extremely deep level etc.
KODEN test utilizes the principle of ultrasonic wave travel from sensor to the wall of
drilled hole and reflect to the sensor through the bentonite slurry or water as a media.
Wave travelling time varies with size of the hole so it can be interpreted to reflect
characteristics of the hole accordingly. Equipment consists of two parts, i.e. recorder
unit and winch unit. Recorders unit controls the operation and record the test result.
On the other hand, winch unit lowers the probe with sensor down the hole for
ultrasonic reflection. KODEN test is quick and easy to perform. Installation of test
equipment is not so complicated. Test result can be obtained immediately after the
test and the result is simple to be analyzed.
However, there are still some limitations for this test:
1. Test cannot be performed in dry hole as it needs liquid as a media for ultrasonic
wave transmission.
2. Density media must not exceed 1200 kg / m³
3. Data cannot be stored electronically in computer.
60 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
The test can gives very accurate results and detailed analysis can be carried out.
However, the cost is very high and the test itself is time consume. Also, it cannot be
applied to every pile on site.
61 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
The pile to receive the jack and the instrumentation. This is done by cutting off or
building up the head of the pile to the necessary elevation, and by capping the head
appropriately to produce a clean horizontal bearing surface.
Before carrying out the load test, the engineer will state the working load and the test
load, and he will describe the different stages of loading in the test. Most
specification gives the test load as twice the working load. The test load is applied in
increments of about 25% of the working load, until the working load is reached.
Smaller increments are added thereafter until the specified limit is reached.
Loading tests are usually carried out in a cycle. Each stage of the loading test or
increment of load is applied as smoothly and quickly as possible. Readings of load,
time and settlement are taken when loading commences, and at intervals as the load
increases. Each increment of load is allowed to remain until settlement has ceased.
Similarly, unloading of each incremental load must not commence until recovery has
ceased.
Most Hong Kong specifications require that after unloading, the maximum test load
be applied again in one operation, and be maintained for a minimum period of 72
hours.
Graphs of load against time, load against settlement, and settlement against time are
then plotted. These graphs are used to determine if the pile has satisfied the
requirements of the specification.
where Pb = safe bearing capacity of sub-soil strata at the tip of the pile (kN/m2). This
can be calculated from the appropriate soil parameters obtained by site investigation.
1. Kentledge
2. Hydraulic Jack
3. Main Girders
4. Grillage
5. Dial Gauge
63 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Generally, four dial gauges are fixed parallel to the pile axis and
equidistant from the centre of the pile. The dial gauges should be
able read to an accuracy of 0.01 mm.
6. Reference Beam
64 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
Main Girder
65 of 66
Chaper 2. Earthwork, Substructure, Foundation and ELS
66 of 66
Chapter 3. Precast Concrete
Precasting means casting a concrete member at a place other than where it will be
used and then moving it to the place where it will be installed.
Precast yard
Most precast units are produced in factories or casting yards. Fundamental factors
that contribute to the success of a factory/casting yard for the precasting include:
proximity to the place where the precast unit will be installed
sufficient area for the storage of materials, bending and fabrication of steel
reinforcement, casting, curing and storage of finished products
land price or rent
good access such as road, rail or pier
availability and cost of materials and labour supply
availability plants such as batching plants and lifting facilities
Fabrication of reinforcement
Reinforcement fixing is labour intensive on site. For precasting, mechanization is
possible for the fabrication of reinforcement because of mass production.
Cutting, bending and fixing the
reinforcement can have high
degree of automation. The
reinforcement can also be fixed by
spot welding. (Normally,
welding for T-bars is not permitted
on site as poor temperature control
on welding lowers the strength of
Automatic rebar fabrication machine
high tensile steel.)
1 of 10
Chapter 3. Precast Concrete
Prestressing
The technique ‘prestressing’ greatly improve the strength of precast units. Usually,
pre-tensioning is used for precasting. Sometimes, post-tensioning is also used for
non-standard units or where curved tendons are required.
Concrete moulds
Steel moulds are usually used for precasting which have the following advantages:
˙ easy assembling and demoulding
˙ durable - can be reused up to a thousand times for percasting works
˙ hard and smooth surfaces of
the moulds can be cleaned
easily and give good
concrete finishes
Compaction of concrete
External vibrators - which mounted on the moulds reduce the labour works for
compacting the concrete.
Hydraulic pressing - which can be employed to compact low slump concrete of small
precast units, such as paving blocks and concrete drainage pipes. The units
can also be demoulded immediately without breaking.
Accelerated curing
3 of 10
Chapter 3. Precast Concrete
Since precast concrete unites are bulk and heavy, lifting equipments are required for
the lifting. Lifting fittings should also be cast into units for easy handling.
lifting hooks
4 of 10
Chapter 3. Precast Concrete
Lifting devices
There are various applications of precast concrete, and the precast units can be
installed by different methods.
5 of 10
Chapter 3. Precast Concrete
Precast Slab
6 of 10
Chapter 3. Precast Concrete
Hollow core slabs may be simply supported on beams or load bearing wall.
To resist hogging moment at the support, steel dowel are can be provided.
Dowel
Min. 75mm
External Wall
Façade Panel is the most widely used precast concrete wall in Hong Kong.
Various installed methods had been used.
Building
structural Joint filled
frame with cement
grout Cast with
insitu
concrete
7 of 10
Chapter 3. Precast Concrete
Design for Manufacture and Assembly (DfMA) is a design approach that emphases
the ease of manufacture and efficiency of assembly of construction components. It
enables off-site manufacturing for on-site assembly, which can reduce on-site
construction processes.
8 of 10
Chapter 3. Precast Concrete
Structural parts other than prefabricated components still need to be built using
conventional construction methods.
Interior decoration and laying of pipes, etc., could only be carried out
thereafter.
9 of 10
Chapter 3. Precast Concrete
10 of 10
Chapter 4 Structural Steelwork
Universal Beam
1 of 17
Chapter 4 Structural Steelwork
Joist
˙ Joists are rolled with 8° tapered flanges.
˙ They provide a useful range of sections smaller than those
in the universal beam
Structural Tee
˙ Structural tees may be cut from
universal beams or universal columns.
1.6 Angle
There are two types of structural steel
angles :
˙ equal leg angles
˙ unequal leg angles
Equal leg angle Unequal leg angle
Hollow Sections
˙ Available hollow sections are round, square and rectangular.
˙ Hollow sections are specified by their size and thickness.
2 of 17
Chapter 4 Structural Steelwork
Fabrication
Fabrication is carried out in a fabrication workshop, where the steel sections undergo
the following stages of treatments:
1. The steel sections are first cleaned to remove dirt, mill-scales and any corrosion
by sand blasting. They are then painted with a priming coat of paint within 2
hours.
2. The sections are cut to the correct length by sawing or cropping.
3. Holes are drilled or punched on the workpiece for bolted connections. Sometimes
the edge of a workpiece is machined for welded connections.
4. Jointing accessories (fittings), such as angle cleats, plates, bases, etc., are
manufactured by drilling, punching and cropping machines at the same time.
5. To reduce the site works, the main components and the fittings are then assembled
into modules. The size of each module should be convenience for lifting and
transportation.
6. The components are then transferred to the dispatch bay to await transport to site.
Fabrication Workshop
3 of 17
Chapter 4 Structural Steelwork
Connection
˙ Steelwork can be connected by bolting or welding
Bolting connection
Black bolt
˙ Black bolts are made of mild steel, unpolished and the least expensive.
˙ They are used in clearance hole, i.e. the hole diameter is 2 mm larger than
the bolt, or 3 mm larger if the bolt diameter is 24 mm or above.
H.S.F.G bolt
4 of 17
Chapter 4 Structural Steelwork
Welding Connection
Methods of welding
Gas welding
˙ In gas welding, an oxy-acetylene flame provides the heat needed to melt the
steel interfaces and the weld metal.
Types of Welds
Fillet Welds
˙ Fillet welds are used to join
plates at an angle (usually
90) to each other.
Butt Weld
˙ Before butt welding, the ends of the work pieces have to be machined to
receive the weld.
˙ The work pieces are then butt against each other and are welded together.
Erection
Universal
clolumn
Fillet weld
Cement
grout
6 of 17
Chapter 4 Structural Steelwork
7 of 17
Chapter 5 Prestressed Concrete
The well known properties of concrete are that it has high compressive strength and
low tensile strength. Consider a beam of plain concrete carrying a load, the beam
deflects slightly and then fails abruptly as the load increases. We can expect this
happen at a relatively small load.
1 / 15
Chapter 5 Prestressed Concrete
Advantages
Disadvantages
3 / 15
Chapter 5 Prestressed Concrete
Single Wire
Single wires have diameters ranging from 3 to 7 mm, and are in coils up to 500 m.
Strand
Strands are made up of several small diameter wires, twisted around a straight central
wire. The most commonly used strand is seven-wire strand and is available in sizes
from 8 mm to 18 mm nominal diameter.
Compacted Strand
To reduce the percentage of voids in the cross-section of normal strand, the strand can
be drawn through a die which compresses it. So, for the same ‘nominal’ diameter,
the amount of steel is higher, thus enabling a larger force to be exerted.
Pre-tensioning
The equipment used for pre-tensioning consists of abutments, barrels and wedges,
and hydraulic prestressing jack. Abutments provide reaction points for the
hydraulic prestressing jack to stress the tendons and anchorage points of the tendons.
A barrel has a tapered hole into which two or three pieces of steel wedges are fitted.
The wedges have serrated teeth to grip the tendon.
Procedure of Pre-tensioning
1. Stressing (Tensioning)
The concrete mould with the reinforcement cage, if any, is placed between the
abutments.
The tendons are threaded through the mould and anchored to one of the
abutments with barrels and wedges.
At the opposite abutment, the tendons are stressed with a hydraulic jack, which
needs regularly checked and calibrated, to the predetermined tension and then
securely anchored them on the abutment.
2. Concreting
Concrete is placed in the moulds and the tendons are embedded by the concrete.
3. Curing
The casting is then usually steam-cured for 24 hours to obtain the desired
characteristic strength.
4. De-tensioning
When the concrete has achieved sufficient strength, the tendons are released from
the abutments gradually; the prestressing force is transferred to the concrete
through the bond that now exists between the tendons and the concrete.
Applications of Pre-tensioning
Post-tensioning
In post-tensioning the concrete is cast around ducts in which the stressing tendons can
be housed and the stressing is carried out after the concrete has hardened.
Tendon Ducts
Tendon Ducts
Tendon ducts can be made of corrugated steel or plastic. Plastic ducts offer better
corrosion protection, and provide reduced duct friction. However, they are more
expensive.
Although the ducts can be made to very long length, normally they are supplied in
standard lengths. Special care should be taken when joining ducts to ensure that no
mortar can get into the duct during concreting.
8 / 15
Chapter 5 Prestressed Concrete
Anchorage
Anchorages are units used in post-tensioning for the transfer of the prestressing
forces to the concrete. They can be further subdivided into stressing anchorages and
dead-end anchorages.
9 / 15
Chapter 5 Prestressed Concrete
In most cases stressing an anchorage is installed at one end of the concrete member
while at the opposite end a dead end anchorage is used. In very long structures
especially with ducts with multiple curvatures stressing anchorages are installed at
both ends of the concrete member.
10 / 15
Chapter 5 Prestressed Concrete
Procedure of Post-tensioning
Placing tendons
Tendons are housed in tendon ducts and the ducts are fixed in their
predetermined alignment, level and profile. (Sometimes the tendons are
threaded through the ducts after concreting.)
The tendon ducts shall be securely tied to the reinforcement to prevent
dislodgment during concreting.
Concreting
In situ concrete is cast. It is then cured as normal reinforced concrete.
Stressing (Tensioning)
11 / 15
Chapter 5 Prestressed Concrete
4.2.4 Grouting
Sheathing is flushed with water before grout injection and the remaining water to
be removed by oil free compressed air. The ducts are grouted with cement
grout through the grout holes/tubes to protect the tendons from corrosion.
12 / 15
Chapter 5 Prestressed Concrete
13 / 15
Chapter 5 Prestressed Concrete
Application of Post-tensioning
14 / 15
Chapter 5 Prestressed Concrete
Post-tensioning in Buildings
Post-tensioning in Bridges
Ground anchor
Ground Anchor
15 / 15
Chapter 6 Bridge and Tunnel Construction
Bridge components:
Type of Bridges:
Beam Bridge
A beam bridge is a horizontal beam supported by piers. The vertical dead load and
vehicular traffic pushes down the beam with top edge under compression and bottom edge
in tension.
Single span beam bridges rarely span more than 100 m whereas a continuous beam could
span over multiple spans for crossing a larger horizontal distance.
Different types concrete deck girder bridges had been used in Hong Kong. Their designs
are now obsolete but many bridges are still servicing us. They include:
1. Solid slab bridge with inverted T beam
2. Box beam bridge
3. Pseudo-Box M beam bridge
4. M beam bridge with top slab construction
Page 2 of 41
Chapter 6 Bridge and Tunnel Construction
Since 1980s, U-beam Bridge has become the prevailing one used in Hong Kong. The U-
beams are lifted by cranes and supported longitudinally between piers. The beams are
placed parallel to each other with suitable spacing to suit wide carriageway width of multi-
traffic lanes.
The decks are usually simply supported on piers. They can also be made continuous by
exposed reinforcement connection or post-tensioning.
The limitations in the length and weight of precast units under transportation will only allow
spans of not more than 30m in use.
Page 3 of 41
Chapter 6 Bridge and Tunnel Construction
There are various kinds of methods for constructing box girder bridges.
This is a traditional method. Falsework is erected between piers and abutments. Formwork
is placed on top the falsework and the bridge is cast insitu. When the entire girder (or one
span) is complete, the temporary supports can be removed.
The temporary support requires that the locations for the supports be clear and stable.
Often the ground is not sufficiently stable and it is necessary to construct foundations for the
temporary supports. The assembly and removal of temporary supports requires lots of
equipment and labour. Therefore, it is economical for low level bridges.
Page 4 of 41
Chapter 6 Bridge and Tunnel Construction
This method is suitable for bridges with constant depth and straight alignment or bridges
with constant circular alignment and superelevation.
Page 5 of 41
Chapter 6 Bridge and Tunnel Construction
Cantilevering
The forward end of the bridge will be in cantilever. A light truss of steel or aluminium is
affixed to the forward end as a ‘launching nose’ to reduce the cantilever length before it
reaches the next pier. In addition, temporary props between piers can also be employed to
reduce the span of temporary cantilevering
Page 6 of 41
Chapter 6 Bridge and Tunnel Construction
Balancing
Since it is not feasible to cast the two segments exactly simultaneously, a step-by-step
sequence is adopted, in which one segment is cast on one side, then the next one on the
other side. This puts bending moments in the pier; the unbalanced load is the load of the
segment plus any construction equipment. Temporary towers with vertical prestressing or
counterweights can provided the balancing.
Page 7 of 41
Chapter 6 Bridge and Tunnel Construction
This method is commonly employed for large span bridges such as bridges crossing rivers
or channels.
In this scheme, the bridges are formed by joining precast segments. Launching girders are
used which are large trusses that are placed longitudinally over the bridge structure.
Page 8 of 41
Chapter 6 Bridge and Tunnel Construction
For Full Span Erection Method, the depths of the box girders are in constant depth. The
actual construction procedures can have several variants:
1. All the segments of a span are be assembled on the ground and joined by post-
tensioning. The whole group is lifted up by a heavy-duty crane then placed on top of
the bridge piers.
2. Erection girders are placed on top of the piers. Bridge segments are hung beneath the
girders or placed on top of them. The segments are aligned and joined together by
post-tensioning to form a complete span. The girders are then set forward for the
construction of the next span.
Page 9 of 41
Chapter 6 Bridge and Tunnel Construction
Truss Bridges
A truss is an open structure comprising many small rods joined together. They can support
a large amount of weight and span great distances. Most truss bridges have one set of truss
on each side of the roadway. Typical Span Length of a truss bridge ranges from 40m -
500m.
Warren Truss
A Warren truss can be identified by the presence of many equilateral or isosceles triangles
formed by the web members which connect the top and bottom chords. For smaller spans,
no vertical members are used lending the structure a simple look. For longer spans vertical
members are added providing extra strength.
Page 10 of 41
Chapter 6 Bridge and Tunnel Construction
Pratt Truss
Pratt trusses are identified by their diagonal members which, except for the very end ones,
all slant down and toward the center of the span. Except for those diagonal members near
the center, all the diagonal members are subject to tension forces only while the shorter
vertical members handle the compressive forces. This allows for thinner diagonal members
resulting in a more economic design.
Howe Truss
The Howe truss is the opposite of the Pratt truss. The diagonal members face in the
opposite direction and handle compressive forces. This makes it very uneconomic design
for steel bridges and its use is rarely seen
Page 11 of 41
Chapter 6 Bridge and Tunnel Construction
Arch Bridges
The arch profile is aesthetically pleasing and it provides a structure which eliminates tensile
stresses in spanning an open space. This is useful because several of the available building
materials such as stone, cast iron and concrete are strong in compression but are weak when
tension.
Concrete arches
Spandrel-filled arch bridge - The arch spandrel is closed by two retaining walls and the
interior is filled with earth. The roadway is placed directly on the fill. It is obsolete
now due to its heavy masonry structure self weight and short span limitation. However,
many spandrel-filled arch bridge are still serving us.
Open spandrel arch - The roadway is supported above the arch by columns and girders.
This type of bridges is best suited to deep gorges with steep rocky banks which
provides efficient natural abutment to receive the heavy thrust exerted by the arch.
Tied Arch
Constructing an arch bridge can be tricky, since the structure is completely unstable until
the two spans meet in the middle.
Erection on Falsework
Page 13 of 41
Chapter 6 Bridge and Tunnel Construction
Cantilever Method
Full span erection
Often conditions under the bridge are not suitable for the use of temporary supports. This
can happen when the valley or ravine is too deep, the flow of a river is too rapid, or
environmental reasons prevent the use of temporary supports under the bridge. The whole
span of an arch can be prefabricated in a fabrication yard. It is then moved to the site, lifted
up and put in place by heavy-duty cranes.
Page 14 of 41
Chapter 6 Bridge and Tunnel Construction
The cable stayed bridge is specially suited in the span range of 400 to 1000 m. The main
components of a cable stayed bridge are:
towers or pylons
inclined cables, and
deck.
Bridge deck
The bridge decks are often of steel or composite materials (concrete deck + steel girders).
Concrete decks are heavy but have the advantage of resisting the compressive load induced
by the sloping cables and against the heavy wheel loads of the road traffic. Steel decks are
much lighter but requires expensive stiffening parts to resist compressive load and wheel
loads.
The Kap Shui Mun Bridge The Stone Cutter Island Bridge
(Source: Highways Department)
Page 15 of 41
Chapter 6 Bridge and Tunnel Construction
Each stay cable is made up of about 50 to 110 nos. of 7-wire strands. The strands are in
turn wrapped externally with a HDPE coating. They may made up on site from drums of
wire strand, or delivered to site as complete factory produced stays.
Construction Procedures
Page 16 of 41
Chapter 6 Bridge and Tunnel Construction
Page 17 of 41
Chapter 6 Bridge and Tunnel Construction
Suspension Bridges
The suspension bridge is currently the solution for spans in excess of 1000 m.
The components of a suspension bridge are
1. Bridge Pylons Bridge pylon / tower
2. Anchorages Suspender
(Source: Highways Department)
3. Main cables
4. Suspenders Bridge deck
5. Bridge deck Anchorage Main cable
Page 18 of 41
Chapter 6 Bridge and Tunnel Construction
Bridge Pylon
A bridge pylon may be made of steel or reinforced concrete. A cable saddle is installed on
the top of the pylon to support the main cable.
An anchorage is very massive concrete block at which the end of the main cable is securely
anchored.
The overall diameter of the main cable may be over 1 m. Clearly, a cable of this size cannot
be delivered and strung from anchorage to anchorage across the tower tops in one piece.
Page 19 of 41
Chapter 6 Bridge and Tunnel Construction
The cable may be installed strand by strand. Each strand is taken across the sea by barge
and then lifted to tower top. The strands are then finally compressed and clamped together
to form the main cable.
Alternatively, the main cable can be installed by aerial spinning method. The initial strands
were taken across the sea channel by barge and lifted to the tower top. Later strands were
placed by ‘high lining’ based on the previously installed strands. Main cable of Tsing Ma
Bridge, for example, is divided into 97 strands each composed of 368 high tensile steel
wires. Each cable was further compacted into a circular shape and bound with temporary
strapping.
.
Page 20 of 41
Chapter 6 Bridge and Tunnel Construction
Page 21 of 41
Chapter 6 Bridge and Tunnel Construction
Cast steel cable bands are then fitted, clamped into position by tightening bolts. The cable
bands were placed at about 20m interval, which served also as the support for the suspender
cable that hanged the bridge deck underneath.
The most common method of forming the deck for a suspension bridge is by joining
prefabricated steel truss segments. Each segment is prefabricated in workshop and
transported by barge to right beneath the main cable. It is then lifted up and hung by the
suspenders. Segment to segment is jointed by welding and bolting and eventually a
continuous deck is formed.
Page 22 of 41
Chapter 6 Bridge and Tunnel Construction
Page 23 of 41
Chapter 6 Bridge and Tunnel Construction
Tunnel Construction
Introduction
Type of Tunnels
There are many types of tunnels and can be classified in many ways:
Classified by Example of tunnels
The shapes of tunnel linings are usually determined by their purpose, ground
conditions, construction method and/or lining materials.
Page 24 of 41
Chapter 6 Bridge and Tunnel Construction
Rectangular shape
Rectangular shaped tunnels are usually adopted by the cut and cover method. It is
particular suitable for pedestrian and highway tunnels. Precast concrete box units
may be used to speed up the construction works. On the other hand, multi-lane
submerged highway tunnels are often in rectangular shape.
Circular shape
A circular shape tunnel has the greatest cross-sectional area to perimeter ratio. They
are often associated with TBM or the shield tunnelling methods.
Page 25 of 41
Chapter 6 Bridge and Tunnel Construction
Permanent linings are required in most tunnels, always in soft ground and frequently
in rock. They are required for two purposes: structurally to retain the earth and water
pressure, and operationally to provide an internal surface appropriate to the function
of the tunnel.
Brickwork, blockwork and masonry had been used for tunnel lining but now they are
obsolete.
Insitu concrete
Insitu concrete lining is frequently in rock tunnelling where the roof is able to stay
unsupported temporary. Specially designed travelling formwork is used for casting
the concrete.
Page 26 of 41
Chapter 6 Bridge and Tunnel Construction
Preformed segments
Preformed segments may be made of cast iron, steel or normal reinforced concrete.
This type of lining usually comes with TBM or shield tunnelling methods.
The segments are jointed together by bolting and the joints are sealed with neoprene
gasket. Sometimes the joints are also caulked with rubberised bituminous strips.
Voids behind the preformed segments are filled by bentonite cement grout.
Page 27 of 41
Chapter 6 Bridge and Tunnel Construction
Sprayed Concrete
Sprayed concrete linings usually compose of rock bolts, wire mesh, steel ribs and a
thin layer or sprayed concrete. This kind of lining is rather flexible than other types
of linings. The use of sprayed concrete lining is usually associated with the Drill &
Blast method.
Page 28 of 41
Chapter 6 Bridge and Tunnel Construction
Open Cut
Open cut method often refers to excavation with battered sides such that no lateral
support is required. In its simplest form, a trench is excavated, the tunnel structure is
built, the trench is backfilled and the surface is restored. Precast tunnel units can also
be employed to speed up to construction process.
The major problem of this method is the procession of land so that it is not too
suitable in urban areas. Moreover, it is only suitable for shallow tunnels only because
with increased depth, direct costs of trench excavation and backfilling increase
rapidly.
The construction process of cut and cover method is very similar to that of open cut
method except that the excavation sides are vertical and temporary supported are
provided.
The main problems associated with cut and cover method are the stability of the soft
ground, impact on the existing underground services & utilities and traffic disruption
in urban areas.
Page 29 of 41
Chapter 6 Bridge and Tunnel Construction
Temporary steel decks may be used to maintain the traffic while the construction
works proceeds underneath. This method is also only suitable for high level tunnels.
Pre-Deck Method
Same as the open-cut method, the pre-deck method is suitable for high level tunnels.
The tunnel walls are constructed by the diaphragm walling method first and then the
upper surface of the ground is removed. The upper deck of the tunnel is cast
supported on the diaphragms. It is then backfilled and the road surface is reinstated.
Now the tunnel excavation can started from both ends of the tunnel without the fear
of collapse and with minimum disturbance to traffic and services.
Page 30 of 41
Chapter 6 Bridge and Tunnel Construction
This method can be used for the installation of pipes from 150 mm to 4 m diameter,
or box section up to 7 x 4 m, but it is mainly employed on the larger diameter pipes of
over 1 m.
This method is very suitable for installing services under roads and railway
embankments without creating disturbance to traffic.
The method consists of forming pits at both ends of the proposed tunnel. A thrust
wall is constructed to provide jacking reaction and pipe segments are jacked into the
soil.
Pipe Jacking
For small diameter pipes, bullet-shaped solid metal heads are fixed to the leading end
of the pipe, which is jacked into the ground displacing the earth.
For tunnels of diameter 1 m or above, the leading pipe is fitted with a steel shield to
aid the driving process. The shield provides protection under which the workers
Page 31 of 41
Chapter 6 Bridge and Tunnel Construction
excavate the tunnel face. New pipe segments are added from the starting pit and
jacked forward one by one until the pipe length reaches the opposite pit.
Micro TBM
liquefied by mixing with bentonite slurry and removed by pump and pipeline.
For large diameter pipes or for long pipes, the friction will be very great and it creates
problems in providing suitable jacking reaction. A method to counteract the friction
is the introduction of intermediate jacks. The intermediate jacks are fixed on steel
sleeves which are installed at suitable intervals along the pipe length. The line is then
jacked forward in a caterpillar fashion. In addition, bentonite slurry can be
introduced from the rear of the driving shield as lubricant to reduce the friction.
Page 32 of 41
Chapter 6 Bridge and Tunnel Construction
The technique of shield tunnelling method is very similar to pipe jacking method,
except that prefabricated segments are used for lining and are installed right behind
the shield.
When tunnelling in water bearing ground, ground water infiltration will create
problems. The ground water can be excluded by the introduction of compressed air.
This method is especially suitable for excluding water from fine silts or soft clays.
Compressed air also provides a counterbalancing force against the inward pressure
thus reducing risk of collapsing of the tunnel face.
A great deal of air may leak through the tunnel wall and face. To prevent excessive
loss of pressure, caulking should be done. One method is to cover the tunnel face
with polythene sheeting when the exaction is not carrying out. An alternative method
is to spray the tunnel face with bentonite slurry. The method is more convenience
and more effective for fine soil.
The appropriate working pressure is about 200 kN/m2 (2 bar), but sometimes as high
as 3.4 bar is used. When working compressed air environment, air will dissolved into
Page 33 of 41
Chapter 6 Bridge and Tunnel Construction
our blood. . Air bubble may form and block our blood stream if decompression
procedure is not strictly followed before leaving the compressive air environment
after work.
To avoid the need of miners working in compressed air and to eliminate the risk of
collapse of tunnel face, tunnel boring machines (TBM) are developed for such
purpose.
TBM
Page 34 of 41
Chapter 6 Bridge and Tunnel Construction
This method is suitable in medium to strong rock. By jack hammers, blast holes are
drilled on the tunnel face. Explosives are loaded in the blast holes and then blasting
is taken place.
R.C. tunnel lining can be cast by using travelling formwork, or more often, the tunnel
lining is formed by sprayed concrete.
There are various methods of attacking the rock face. The choice depends on the size
and shape of tunnel and the available equipment.
Page 35 of 41
Chapter 6 Bridge and Tunnel Construction
Submerged Tunnel
The first cross harbour tunnel in Hong Kong is made of steel but reinforced concrete
ones are preferred now. Reinforced concrete tubes are not only cheaper than steel
ones, but can be more easily made in rectangular cross sections, which were more
suitable for multi-lane road tunnels. In addition, they can be constructed rather long
to reduce the numbers of sinking and jointing operation.
Tunnels units are pre-fabricated in a dry dock. The dry dock is usually an excavated
basin beside seashore at a depth several meters below water level.
Besides the structural frame, fittings and accessories are installed onto the units.
These include: lifting lugs, temporary support jacks, bearing plates & gaskets, ballast
tanks, bulkheads, locating nibs, a control tower and a survey tower.
Page 36 of 41
Chapter 6 Bridge and Tunnel Construction
Trench preparation
While the tunnel units are pre-fabricated in the dry dock, a trench on the seabed for
laying the tunnels units will be prepared at the same time. The trench may be
excavated by dredging or by grabbing. The sides of the trench are usually sloped
back to a stable angle.
To ensure the stability of the tunnel units on the seabed, the foundation of the tunnel
units shall be prepared. There are two methods for the preparation of the foundation:
Screeding method, and
Sand jetting method
Screeding Method
Seabed leveller
Granular trench bedding materials are laid on the trench bed and then smoothed by a
leveller.
Page 37 of 41
Chapter 6 Bridge and Tunnel Construction
Control
Transit
Survey Tower
Winch
Tower
Floating
Pontoon
Trench on
Seabed
Concrete
Jacking
Pad
The open ends of the units will be closed with watertight temporary steel bulkheads
to enable them to float. The floodgate of the casting basin is opened to let the
seawater flowing in. The unit is then floated and towed to its final position.
The unit can be laid by fixed-leg platform, or more often nowadays by floating
pontoons. In the later case, two pontoons are placed on top of the tunnel unit to be
sunk. There are transit winches on the pontoons for adjusting the position of the
pontoons. The wires from the winches are tied to heavy concrete block anchors on
the seabed. The sinking operation starts with water ballasting of the unit so that 2%
negative buoyancy is established for sinking. Its position under water is carefully
controlled by means of the surveying tower.
Page 38 of 41
Chapter 6 Bridge and Tunnel Construction
Jointing
At an end of each tunnel units, there are a bulkhead with a locating nib, and a Gina
gasket or a steel bearing plate installed. The unit is lowered slowly until the locating
nibs are engaged. Now the moving of the unit is taken over by hydraulic jacks.
The jacks pulled the newly sunk unit towards its neighbour until sufficient contact
pressure is established between the Gina gasket and the bearing plate. This initial
compression provides an isolation of the water inside the gap from the outside.
Page 39 of 41
Chapter 6 Bridge and Tunnel Construction
Thereafter the water is discharged from the joint. The unbalanced hydrostatic
pressure on the further end of the new unit will press the units tightly together.
The bulkheads at the joints are then removed. The waterproofing of the joint is
further reinforced by installing an omega seal and covered with a steel plate by
welding. Finally the joint is filled with concrete or cement grout.
Sand Jetting
If the tunnel bedding is placed by sand jetting, the sand and water are mixed and
pumped down from a barge through deliver pipes to nozzles beneath the tunnel unit
which are placed at 4 to 8 m intervals. Following the sand jetting bentonite/cement
grout may be injected into the sand foundation for additional reinforcement.
Page 40 of 41
Chapter 6 Bridge and Tunnel Construction
Backfilling
Selected backfill comprising of granular material which will compact naturally under
water is placed to mid-way of the tunnel depth.
General fill or granular fill material which would not cause damages to the tunnel
waterproofing is placed on top until a cover of at least 2 m for the tunnel unit is
attained. Rock armour should also be provided near the shore for protection of tunnel
from damages by vessels.
Page 41 of 41