Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

WATER SUPPLY CHECKLIST

PROJECT INFORMATION
Project name:
Prepared by:
Checked by:

Date:

GENERAL NOTES

 N/
A
Description Remarks

Calculations shall be prepared before any design work

After selecting the Mechanical capacity for equipment, electrical data has
the first priority and to be handed over to electrical Department

All architectural plans shall be revised form Mechanical point of view as


soon as it is received from the Architect.

All requirements, Design stages shall be according to the prepared


calculations

Shaft coordination shall be done with other MEP systems.

MEP REQUIREMENTS CHECKLIST

 N/A Description Remarks

Fire Water tanks Location and Capacity


Fire Water Tank as per QCD requirements

Fire water tank is 2 compartment

Type of the tanks shall be specified (GRP, Concrete, Sectional) means of


access, proper ventilation, equalizing valves, overflow pipe, vents, water
level indicator and drainage system. Fire tanks shall be provided with
complete appurtenances for maintenance purposes, drains, overflow
pipe, water level indicator, tank access, vents, etc. Ensure the tank has two
equal compartments, all pumps are taking suction from both tank and each
pump can be isolated for testing.
Fire Water tanks & Fire Pump room
Mechanical Pump room shall have as a separate detail with scale of 1:50

Fire Pump room area to be carefully determined according to QCD


requirements and the equipment inside (Main electric pump, diesel pump,
and jockey pump, bulk tank, etc.…)

Tank compartments served by the pump room shall have a common wall

Pump room level shall be lower than the Water tank by 20 cm minimum (for
tank drainage).

Clear height between the water level and the pump room bottom of slab 1 m
minimum (for access door and overflow line).

Pump room shall have double leaf door opening to outside.

Doha – Qatar,
Tel: + 974 4441 2659, Fax: +974 4441 2659 Page |1
Website: www.dmg-eg.com
Filling line for Firefighting tanks shall have the same size as KAHRAMAA tie
in Pipe.

Fire tanks shall have the following:


 Drain pit ( usually 600X600X200mm)
 Suction Pipe c/w anti-vortex plat
 Tank drain
 Tank Over flow
 Filling line (c/w float valve and shall be near to the access opening)
 Vent pipe
 Level indicator
 Test and drain pipe

Dimension of the room to verify adequate housing of the fire pump and
related fittings, valves, headers and related equipment complying with NFPA
20 & 22.

Sprinklers inside the fire pump room (if installed below ground level) and
shall be rated as Extra Hazard Group 2.

Sequence of operations for the fire pump and Schedule of Equipment

A testing line shall be provided with flow meter and isolating valve.
Provide details of each component.

Provide a pump room layout with section and elevation detail relative to the
fire water tank. Ensure at least 0.8 meter clearance in every side of the
pumps for maintenance work space.

Ensure that distance between pump flange and suction elbow/tee flange is
greater than 10 diameter as per NFPA 20.

Provide bulk tank calculation for diesel pump.

 N/A Description Remarks

Plan and shafts requirements


Check ZCS and risers location.

Doha – Qatar,
Tel: + 974 4441 2659, Fax: +974 4441 2659 Page |2
Website: www.dmg-eg.com
DETAILED DESIGN CHECKLIST

 N/A Description Remarks

Pipe Materials
Underground main piping shall be HDPE.

Exposed pipes and pipes running inside shafts shall be black steel
Cover page
As per FF cover page file

Legend and Symbols shall be modified to contain only items in the


project.

Notes Must be read Carefully to match the project.

Technical schedule shall be prepared for All projects, showing:


1-fire tank schedule indicating the following: area, effective height,
volume, capacity, duration, construction type (steel, concrete), location,
accessories.
2- All types of fire pumps indicating the type of pump, capacity, head
and power requirements.
3-Fire Extinguishers schedule indicating the class (A,B,C,D,K) capacity
(lbs./ kg / gal), type (ABC, dry /wet chemical, CO, foam or others),
description (wheeled, cartridge), rating in terms of A:B:C) and tagging
(i.e. FE-1, FE-2).
Standard Details
Check that all project standard details are matching and shown
(sprinklers, landing valve, fire hose reel, clean agent, fire extinguisher
etc...)

Check text size to be readable when printed (even the DWG. Is N.T.S)

Design Criteria
Plan
Check location of ZCS and fire risers.

Drain pipe is installed for ZCS (test and drain valve) connected to
separate drain riser.

Pipe sizes shall be according to NFPA 13

Sprinklers will be distributed as per NFPA 13 with taking in


consideration maximum and minimum distance between sprinkler and
wall and sprinklers with each other.

Check false ceiling depth for using double layer sprinkler.

Side wall sprinkler will be installed in elevator pit, stairs and ramps.

Sprinkler will be installed in garbage chute.

Branch lines shall not exceed eight sprinklers.

For toilets area 5m2 or higher sprinkler will be installed as per NFPA13.

In case of office building or commercial building OS&Y gate valve c/w


tamper switch will be installed at the entrance of office or retail.

Check ZCS components (OS&Y, CH.V, P.G, F.S, T&D valve).

Doha – Qatar,
Tel: + 974 4441 2659, Fax: +974 4441 2659 Page |3
Website: www.dmg-eg.com
Testing connection for the most remote area will be installed.

Landing valve will be taken from stand pipe riser or combined riser
(before ZCS).

Landing valve is installed in order of priority :


(1) Firefighting lobby (2) smoke stop lobby (3) inside staircase
and comply with NFPA 14.

Fire hose reel is taken after ZCS.

Fire hose reel is distributed in corridor or lobbies provided that each one
cover 30m.

Alarm gong is placed at the entrance of the building and is connected to


alarm check valve in fire pump room.

Fire extinguisher (dry chemical powder) is used for stores, telecom and
electric rooms in floors.

Fire extinguisher (wet chemical powder) and fire blanket (4x4) ft. is used
for kitchens and pantries.

 N/A Description Remarks

Clean agent Details


Details shall be prepared for ALL projects ( small and large projects)

Foam system is used for generator room and bulk tank.

FM200 is used for fire command center , main telecom ,LV (main
electric) ,MV and TX rooms in case of TX in under ground
Riser Diagram
Riser Diagram shall be prepared for ALL projects (small and large
projects)

Check Riser Diagram text height shall be readable (even if it is NTS)

Riser Diagram shall show all branches and shall have the same order of
the plan as possible.

PRESENTATION CHECKLIST

 N/A Description Remarks

All used blocks shall be as per FF CAD standard file.

All Layers (pipes, text, leader, etc...) shall be as per FF CAD standard file.

All text shall be using Multi leader with properties as per FF CAD standard
file.

All text with boundaries shall be as per FF CAD standard file.

Text size shall be read at layout as 2.5 regardless the viewport scale.

All blocks, pipes, fittings, etc... shall have a proper scaling and dimension
( plan and Schematic)

Tanks & equipment shall have tag numbers same as equipment schedule.

Doha – Qatar,
Tel: + 974 4441 2659, Fax: +974 4441 2659 Page |4
Website: www.dmg-eg.com
SUBMISSION TO CIVIL DEFENCE

 N/A Description Remarks

Documents.

Cover page shall be as per FF cover page FF CAD standard files.

CAD & PDF drawing.

Elite Calculations (most demand & most remote, Hydraulic Calculation


Summary & Isometric Drawings).

Clean agent calculations.

Comments reply after revision 0

Doha – Qatar,
Tel: + 974 4441 2659, Fax: +974 4441 2659 Page |5
Website: www.dmg-eg.com

You might also like