APron 6, Design & Procurement

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

KKIA - AFU - BL ...Classic Schedule Layout...

04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Expansion of Apron no.6 and Related Facilities Updated 28-Feb-2014 439 13-Jan-14 A 15-Jan-17

Design & Engineering 118 01-Feb-14 A 21-Jun-15

Civil 118 01-Feb-14 A 21-Jun-15


Pavement 118 01-Feb-14 A 21-Jun-15
Scope Layout 74 01-Feb-14 A 20-Jul-14 A
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 26-Apr-14 A 01-Jul-14 A
Development of Design to 100% Design Completion (By Contractor) 20 26-Apr-14 A 10-Jun-14 A 100%
Submission 100% Design (By Contractor) 0 10-Jun-14 A 100%
100% Design - Design Review (By Authority) 8 11-Jun-14 A 30-Jun-14 A 100%
Approval 100% Design 0 01-Jul-14 A 100%
Shop Drawings 10 01-Jul-14 A 20-Jul-14 A
Development of Shop Drawings and Submit for Approval 4 01-Jul-14 A 10-Jul-14 A 100%
Submission Sop Drawings (By Contractor) 0 10-Jul-14 A 100%
Review Sop Drawings and Approval 6 11-Jul-14 A 20-Jul-14 A 100%
Approval Shop Drawings 0 20-Jul-14 A 100%
Phasing Plan 93 01-Feb-14 A 21-Jun-15
Development of Design 70% 56 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Site Access and Security Fencing Layout and details 8 28-Feb-15 20-Mar-15
Shop Drawings 8 28-Feb-15 20-Mar-15
Development of Sop Drawings and Submit for Approval 3 28-Feb-15 06-Mar-15 0%
Submission Sop Drawings (By Contractor) 0 06-Mar-15 0%
Review Sop Drawings and Approval 6 07-Mar-15 20-Mar-15 0%
Approval Shop Drawings 0 20-Mar-15 0%
Demolition Layout 110 01-Mar-14 A 01-Jun-15
Development of Design 70% 36 01-Mar-14 A 30-May-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Mar-14 A 30-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-May-14 A 100%
70% Design - Design Review (By Authority) 8 02-May-14 A 29-May-14 A 100%
Approval 70% Design 0 30-May-14 A 100%
Development of Design 100% 28 28-Feb-15 08-May-15
Development of Design to 100% Design Completion (By Contractor) 20 28-Feb-15 18-Apr-15 0%
Submission 100% Design (By Contractor) 0 18-Apr-15 0%
100% Design - Design Review (By Authority) 8 19-Apr-15 08-May-15 0%
Approval 100% Design 0 08-May-15 0%
Shop Drawings 10 09-May-15 01-Jun-15
Development of Sop Drawings and Submit for Approval 4 09-May-15 18-May-15 0%
Submission Sop Drawings (By Contractor) 0 18-May-15 0%
Review Sop Drawings and Approval 6 19-May-15 01-Jun-15 0%
Approval Shop Drawings 0 01-Jun-15 0%
Pavement Layouts 74 01-Feb-14 A 20-Jul-14 A
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 26-Apr-14 A 01-Jul-14 A
Development of Design to 100% Design Completion (By Contractor) 20 26-Apr-14 A 10-Jun-14 A 100%
Submission 100% Design (By Contractor) 0 10-Jun-14 A 100%
100% Design - Design Review (By Authority) 8 11-Jun-14 A 30-Jun-14 A 100%
Approval 100% Design 0 01-Jul-14 A 100%
Shop Drawings 10 01-Jul-14 A 20-Jul-14 A
Development of Sop Drawings and Submit for Approval 4 01-Jul-14 A 10-Jul-14 A 100%
Submission Sop Drawings (By Contractor) 0 10-Jul-14 A 100%
Review Sop Drawings and Approval 6 11-Jul-14 A 20-Jul-14 A 100%
Approval Shop Drawings 0 20-Jul-14 A 100%
Finished Contour Grading Plans 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%

Page 1 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%


Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Pavement Sections & Details 74 01-Feb-14 A 20-Jul-14 A
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 26-Apr-14 A 01-Jul-14 A
Development of Design to 100% Design Completion (By Contractor) 20 26-Apr-14 A 10-Jun-14 A 100%
Submission 100% Design (By Contractor) 0 10-Jun-14 A 100%
100% Design - Design Review (By Authority) 8 11-Jun-14 A 30-Jun-14 A 100%
Approval 100% Design 0 01-Jul-14 A 100%
Shop Drawings 10 01-Jul-14 A 20-Jul-14 A
Development of Sop Drawings and Submit for Approval 4 01-Jul-14 A 10-Jul-14 A 100%
Submission Sop Drawings (By Contractor) 0 10-Jul-14 A 100%
Review Sop Drawings and Approval 6 11-Jul-14 A 20-Jul-14 A 100%
Approval Shop Drawings 0 20-Jul-14 A 100%
Finished Spot Levels 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Profiles 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Pavement Markings Layout and Details 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Storm Drainage 106 01-Feb-14 A 21-Jun-15
Drainage Layouts 98 01-Feb-14 A 01-Jun-15
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A

Page 2 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 28-Feb-15 08-May-15
Development of Design to 100% Design Completion (By Contractor) 20 28-Feb-15 18-Apr-15 0%
Submission 100% Design (By Contractor) 0 18-Apr-15 0%
100% Design - Design Review (By Authority) 8 19-Apr-15 08-May-15 0%
Approval 100% Design 0 08-May-15 0%
Shop Drawings 10 09-May-15 01-Jun-15
Development of Sop Drawings and Submit for Approval 4 09-May-15 18-May-15 0%
Submission Sop Drawings (By Contractor) 0 18-May-15 0%
Review Sop Drawings and Approval 6 19-May-15 01-Jun-15 0%
Approval Shop Drawings 0 01-Jun-15 0%
Drainage Profiles 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Drainage Sections & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 28-Feb-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Structural 93 01-Jun-14 A 21-Jun-15
Utilities Buildings Setting Out 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Foundation Layout & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%

Page 3 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Approval Shop Drawings 0 21-Jun-15 0%


Roof Layout 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Substructure Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Ground Floor Layout 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Super Structure Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Architectural 93 01-Jun-14 A 21-Jun-15
Floor Plans 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%

Page 4 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%


Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Elevations 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Finishing Schedule 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Doors / Windows Schedules 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Sections& Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
External works 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15

Page 5 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%


Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
U/G Utilities Civil Works 93 01-Jun-14 A 21-Jun-15
Duct Banks Layout 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Manholes Schedules & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Duct Bank Profiles / Sections 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Apron Services Pits Layouts, Sec tions and details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Equipment - Foundation Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%

Page 6 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Approval 100% Design 0 28-May-15 0%


Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Electrical & Communication 93 01-Jun-14 A 21-Jun-15
Electrical & Communication 93 01-Jun-14 A 21-Jun-15
Aircraft Stands - Equipment Layouts 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Single Line Diagrams 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Low Voltage / Low Current - Layouts 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Control Rooms - Single line diagram 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Power Supply - Connection & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15

Page 7 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%


Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Grounding - Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Communication and Control - Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Guidance signs - Layouts and Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Flood Light - Layout and Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Power Supply Layouts and details- Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%

Page 8 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Approval 70% Design 0 19-Mar-15 0%


Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Airfield Ground Lighting - Light Arrangments 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Ligthting Fixtures Layout - Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Low Current System - Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Special Systems 93 01-Jun-14 A 21-Jun-15
Summary Of Special System (Design & Engineering) Part 93 01-Jun-14 A 21-Jun-15 51.07%
VDGS - Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Public Address System 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15

Page 9 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fire Alarm System 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Staff Information Display System 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
I/O Backbone Fiber Optic - Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Aviation Fuel Control system 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%

Page 10 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

UPS System 93 01-Jun-14 A 21-Jun-15


Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
BMS 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Mechanical 106 01-Feb-14 A 21-Jun-15
Mechanical 106 01-Feb-14 A 21-Jun-15
Utilities Relocation 93 01-Feb-14 A 21-Jun-15
Development of Design 70% 56 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fuel Relocation - Layout 98 01-Feb-14 A 01-Jun-15
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 28-Feb-15 08-May-15
Development of Design to 100% Design Completion (By Contractor) 20 28-Feb-15 18-Apr-15 0%
Submission 100% Design (By Contractor) 0 18-Apr-15 0%
100% Design - Design Review (By Authority) 8 19-Apr-15 08-May-15 0%
Approval 100% Design 0 08-May-15 0%
Shop Drawings 10 09-May-15 01-Jun-15
Development of Sop Drawings and Submit for Approval 4 09-May-15 18-May-15 0%
Submission Sop Drawings (By Contractor) 0 18-May-15 0%
Review Sop Drawings and Approval 6 19-May-15 01-Jun-15 0%
Approval Shop Drawings 0 01-Jun-15 0%
Fuel Relocation - Profiles 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%

Page 11 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%


Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fuel Relocation - Details 98 01-Feb-14 A 01-Jun-15
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 28-Feb-15 08-May-15
Development of Design to 100% Design Completion (By Contractor) 20 28-Feb-15 18-Apr-15 0%
Submission 100% Design (By Contractor) 0 18-Apr-15 0%
100% Design - Design Review (By Authority) 8 19-Apr-15 08-May-15 0%
Approval 100% Design 0 08-May-15 0%
Shop Drawings 10 09-May-15 01-Jun-15
Development of Sop Drawings and Submit for Approval 4 09-May-15 18-May-15 0%
Submission Sop Drawings (By Contractor) 0 18-May-15 0%
Review Sop Drawings and Approval 6 19-May-15 01-Jun-15 0%
Approval Shop Drawings 0 01-Jun-15 0%
Fire Fighting system - Layout & Details - Buildings 106 01-Feb-14 A 21-Jun-15
Development of Design 70% 68 01-Feb-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fuel Hydrant System - Layout & Details 74 01-Feb-14 A 20-Jul-14 A
Development of Design 70% 36 01-Feb-14 A 25-Apr-14 A
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 26-Apr-14 A 01-Jul-14 A
Development of Design to 100% Design Completion (By Contractor) 20 26-Apr-14 A 10-Jun-14 A 100%
Submission 100% Design (By Contractor) 0 10-Jun-14 A 100%
100% Design - Design Review (By Authority) 8 11-Jun-14 A 30-Jun-14 A 100%
Approval 100% Design 0 01-Jul-14 A 100%
Shop Drawings 10 01-Jul-14 A 20-Jul-14 A
Development of Sop Drawings and Submit for Approval 4 01-Jul-14 A 10-Jul-14 A 100%
Submission Sop Drawings (By Contractor) 0 10-Jul-14 A 100%
Review Sop Drawings and Approval 6 11-Jul-14 A 20-Jul-14 A 100%
Approval Shop Drawings 0 20-Jul-14 A 100%
Fuel Hydrant System - Instrumentation 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fuel Hydrant System - Cathodic Protection 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15

Page 12 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%


Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Sewage System Layout & Details - Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Potable Water Supply & Details - Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
HVAC System - Buildings 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Submittals General, Material & Procurement 439 13-Jan-14 A 15-Jan-17

General 121 13-Jan-14 A 31-Jul-14 A


Site Access & Security Plan 17 10-Jul-14 A 31-Jul-14 A
Prepare and Submit Document Submittal 6 10-Jul-14 A 20-Jul-14 A 100%
Review Document Submittal and Approve 6 20-Jul-14 A 25-Jul-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Document Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Document Submittal Approved 0 30-Jul-14 A 100%
Start Construction of Site Access 0 31-Jul-14 A 100%
Pre-Qualification of Designer 13 10-Jul-14 A 30-Jul-14 A
Prepare and Submit Document Submittal 2 10-Jul-14 A 20-Jul-14 A 100%
Review Document Submittal and Approve 6 20-Jul-14 A 25-Jul-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Document Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Document Submittal Approved 0 30-Jul-14 A 100%
QA/QC Plan 108 13-Jan-14 A 30-Jul-14 A
Review Document Submittal and Approve 0 13-Jan-14 A 100%
Prepare and Submit Document Submittal 0 13-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Document Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Document Submittal Approved 0 30-Jul-14 A 100%
PROJECT HEALTH, SAFETY & ENVIRONMENTPLAN 110 13-Jan-14 A 30-Jul-14 A
Review Document Submittal and Approve 0 13-Jan-14 A 100%
Prepare and Submit Document Submittal 0 13-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Document Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%

Page 13 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Document Submittal Approved 0 30-Jul-14 A 100%


Pre-Qualification of Sub-Contractors 108 13-Jan-14 A 30-Jul-14 A
Review Document Submittal and Approve 0 13-Jan-14 A 100%
Prepare and Submit Document Submittal 0 13-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Document Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Document Submittal Approved 0 30-Jul-14 A 100%
Civil 439 13-Jan-14 A 15-Jan-17
Pavement 365 13-Jan-14 A 15-Jan-17
Aggregates Source - Quality check 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
CTB Mix Design 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
PCC Mix Design 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
Blinding Concrete Mix Design 22 20-Mar-15 14-May-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Preparation for 1st Delivery 6 01-May-15 14-May-15 0%
1st Delivery 0 14-May-15 0%
Structural Concrete Mix Design 22 20-Mar-15 14-May-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Preparation for 1st Delivery 6 01-May-15 14-May-15 0%
1st Delivery 0 14-May-15 0%
Plain Dowel 100 13-Jan-14 A 23-Mar-15
Review Material Submittal and Approve 0 13-Jan-14 A 100%
Prepare and Submit Material Submittal 0 13-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 0 13-Jan-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 0 13-Jan-14 A 100%
Material Submittal Approved 0 13-Jan-14 A 100%
Purchase and Procurement Process 6 09-Mar-15 23-Mar-15 0%
1st Delivery 0 23-Mar-15 0%
JOINT SEALANT FOR CONCRETE & ASPHALT PAVEMENT 96 13-Jan-14 A 13-Mar-15
Review Material Submittal and Approve 0 13-Jan-14 A 100%
Prepare and Submit Material Submittal 0 13-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 0 13-Jan-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 0 13-Jan-14 A 100%
Material Submittal Approved 0 13-Jan-14 A 100%
Purchase and Procurement Process 6 28-Feb-15 13-Mar-15 0%
1st Delivery 0 13-Mar-15 0%
Subbase 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
CABC 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%

Page 14 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Material Submittal Approved 0 10-Apr-15 0%


Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
Asphalt Base Course Mix Design 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
Bitumen 60/70 22 28-Feb-15 24-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 6 11-Apr-15 24-Apr-15 0%
1st Delivery 0 24-Apr-15 0%
Tack Coat 19 28-Feb-15 16-Apr-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Preparation for 1st Delivery 2 11-Apr-15 16-Apr-15 0%
1st Delivery 0 16-Apr-15 0%
Asphalt Crack Relief Layer Mix Design 22 24-Mar-15 19-May-15
Prepare and Submit Material Submittal 6 24-Mar-15 07-Apr-15 0%
Review Material Submittal and Approve 6 07-Apr-15 21-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 21-Apr-15 28-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 28-Apr-15 05-May-15 0%
Preparation for 1st Delivery 6 05-May-15 19-May-15 0%
Material Submittal Approved 0 05-May-15 0%
1st Delivery 0 19-May-15 0%
Prime Coat 19 11-Apr-15 29-May-15
Prepare and Submit Material Submittal 6 11-Apr-15 25-Apr-15 0%
Review Material Submittal and Approve 6 25-Apr-15 09-May-15 0%
Incorporate the engineer's comments and Resubmit 3 09-May-15 16-May-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 16-May-15 23-May-15 0%
Preparation for 1st Delivery 2 23-May-15 29-May-15 0%
Material Submittal Approved 0 23-May-15 0%
1st Delivery 0 29-May-15 0%
Asphalt Surface Course Mix Design 22 03-Apr-15 29-May-15
Prepare and Submit Material Submittal 6 03-Apr-15 17-Apr-15 0%
Review Material Submittal and Approve 6 17-Apr-15 01-May-15 0%
Incorporate the engineer's comments and Resubmit 3 01-May-15 08-May-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 08-May-15 15-May-15 0%
Preparation for 1st Delivery 6 15-May-15 29-May-15 0%
Material Submittal Approved 0 15-May-15 0%
1st Delivery 0 29-May-15 0%
Pavement Sealant 22 08-Apr-15 03-Jun-15
Prepare and Submit Material Submittal 6 08-Apr-15 22-Apr-15 0%
Review Material Submittal and Approve 6 22-Apr-15 06-May-15 0%
Incorporate the engineer's comments and Resubmit 3 06-May-15 13-May-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 13-May-15 20-May-15 0%
Purchase and Procurement Process 6 20-May-15 03-Jun-15 0%
Material Submittal Approved 0 20-May-15 0%
1st Delivery 0 03-Jun-15 0%
Curing Compound 29 23-Mar-15 03-Jun-15
Prepare and Submit Material Submittal 6 23-Mar-15 06-Apr-15 0%
Review Material Submittal and Approve 6 06-Apr-15 20-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Apr-15 27-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Apr-15 04-May-15 0%
Purchase and Procurement Process 12 04-May-15 03-Jun-15 0%
Material Submittal Approved 0 04-May-15 0%
1st Delivery 0 03-Jun-15 0%
Joint Filler Boards 29 28-Mar-15 08-Jun-15
Prepare and Submit Material Submittal 6 28-Mar-15 11-Apr-15 0%
Review Material Submittal and Approve 6 11-Apr-15 25-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 25-Apr-15 02-May-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 02-May-15 09-May-15 0%
Purchase and Procurement Process 12 09-May-15 08-Jun-15 0%
Material Submittal Approved 0 09-May-15 0%
1st Delivery 0 08-Jun-15 0%
Pavement marking 35 28-May-16 23-Aug-16
Prepare and Submit Material Submittal 6 28-May-16 11-Jun-16 0%

Page 15 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Review Material Submittal and Approve 6 11-Jun-16 25-Jun-16 0%


Incorporate the engineer's comments and Resubmit 3 25-Jun-16 02-Jul-16 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 02-Jul-16 09-Jul-16 0%
Purchase and Procurement Process 18 09-Jul-16 23-Aug-16 0%
Material Submittal Approved 0 09-Jul-16 0%
1st Delivery 0 23-Aug-16 0%
Fencing 37 15-Oct-16 15-Jan-17
Prepare and Submit Material Submittal 6 15-Oct-16 29-Oct-16 0%
Review Material Submittal and Approve 6 29-Oct-16 12-Nov-16 0%
Incorporate the engineer's comments and Resubmit 3 12-Nov-16 19-Nov-16 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 19-Nov-16 26-Nov-16 0%
Purchase and Procurement Process 20 26-Nov-16 15-Jan-17 0%
Material Submittal Approved 0 26-Nov-16 0%
1st Delivery 0 15-Jan-17 0%
Structure 242 13-Jan-14 A 12-Sep-15
Waterproofing 53 03-May-15 12-Sep-15
Prepare and Submit Material Submittal 6 03-May-15 16-May-15 0%
Review Material Submittal and Approve 6 17-May-15 30-May-15 0%
Incorporate the engineer's comments and Resubmit 3 31-May-15 06-Jun-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 07-Jun-15 13-Jun-15 0%
Material Submittal Approved 0 13-Jun-15 0%
Purchase and Procurement Process 36 14-Jun-15 11-Sep-15 0%
1st Delivery 0 12-Sep-15 0%
Damproofing 124 06-Nov-14 A 12-Sep-15
Prepare and Submit Material Submittal 6 06-Nov-14 A 19-Nov-14 A 100%
Review Material Submittal and Approve 6 17-May-15 30-May-15 0%
Incorporate the engineer's comments and Resubmit 3 31-May-15 06-Jun-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 07-Jun-15 13-Jun-15 0%
Material Submittal Approved 0 13-Jun-15 0%
Purchase and Procurement Process 36 14-Jun-15 11-Sep-15 0%
1st Delivery 0 12-Sep-15 0%
Steel Reinforcement 130 22-Oct-14 A 12-Sep-15
Prepare and Submit Material Submittal 6 22-Oct-14 A 30-Oct-14 A 100%
Review Material Submittal and Approve 6 02-Nov-14 A 08-Nov-14 A 100%
Incorporate the engineer's comments and Resubmit 3 08-Nov-14 A 14-Nov-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 14-Nov-14 A 16-Nov-14 A 100%
Material Submittal Approved 0 16-Nov-14 A 100%
Purchase and Procurement Process 36 20-Nov-14 A 11-Sep-15 20%
1st Delivery 0 12-Sep-15 0%
Sealants 35 17-Jun-15 12-Sep-15
Prepare and Submit Material Submittal 6 17-Jun-15 30-Jun-15 0%
Review Material Submittal and Approve 6 01-Jul-15 14-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 15-Jul-15 21-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 22-Jul-15 28-Jul-15 0%
Material Submittal Approved 0 28-Jul-15 0%
Purchase and Procurement Process 18 29-Jul-15 11-Sep-15 0%
1st Delivery 0 12-Sep-15 0%
MASTERFLEX 477 ELASTOMERIC POLYURETHANE JOINT SEALANT 139 13-Jan-14 A 26-Mar-14 A
Prepare and Submit Material Submittal 0 13-Jan-14 A 100%
Review Material Submittal and Approve 6 14-Jan-14 A 16-Jan-14 A 100%
Incorporate the engineer's comments and Resubmit 3 16-Jan-14 A 18-Jan-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 18-Jan-14 A 20-Jan-14 A 100%
Material Submittal Approved 0 09-Feb-14 A 100%
Purchase and Procurement Process 18 10-Feb-14 A 26-Mar-14 A 100%
1st Delivery 0 26-Mar-14 A 100%
Storm Drainage 132 10-Jul-14 A 27-Jun-15
RC Pipes 65 10-Jul-14 A 11-Mar-15
Prepare and Submit Material Submittal 6 10-Jul-14 A 20-Jul-14 A 100%
Review Material Submittal and Approve 6 20-Jul-14 A 27-Jul-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Material Submittal Approved 0 27-Jul-14 A 100%
Purchase and Procurement Process 48 01-Nov-14 A 11-Mar-15 90%
1st Delivery 0 11-Mar-15 0%
Manholes Covers & Frames / Gratings 129 10-Aug-14 A 27-Jun-15
Prepare and Submit Material Submittal 6 10-Aug-14 A 23-Aug-14 A 100%
Review Material Submittal and Approve 6 24-Aug-14 A 06-Sep-14 A 100%
Incorporate the engineer's comments and Resubmit 3 07-Sep-14 A 13-Sep-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 13-Sep-14 A 19-Sep-14 A 100%
Material Submittal Approved 0 20-Sep-14 A 100%
Purchase and Procurement Process 48 22-Sep-14 A 27-Jun-15 0%
1st Delivery 0 27-Jun-15 0%
GRP - Slot Drains 93 03-Aug-14 A 23-Mar-15
Prepare and Submit Material Submittal 6 03-Aug-14 A 12-Aug-14 A 100%
Review Material Submittal and Approve 6 12-Aug-14 A 18-Aug-14 A 100%
Incorporate the engineer's comments and Resubmit 3 18-Aug-14 A 24-Aug-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Aug-14 A 27-Aug-14 A 100%
Material Submittal Approved 0 27-Aug-14 A 100%

Page 16 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Purchase and Procurement Process 48 01-Sep-14 A 23-Mar-15 80%


1st Delivery 0 23-Mar-15 0%
Architechural 89 22-Jun-15 29-Jan-16
CMU 89 22-Jun-15 29-Jan-16
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 72 03-Aug-15 29-Jan-16 0%
1st Delivery 0 29-Jan-16 0%
Paint 53 22-Jun-15 31-Oct-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 36 03-Aug-15 31-Oct-15 0%
1st Delivery 0 31-Oct-15 0%
Doors 89 22-Jun-15 29-Jan-16
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase, Procurement Process, & Manufacturing 72 03-Aug-15 29-Jan-16 0%
1st Delivery 0 29-Jan-16 0%
Windows 89 22-Jun-15 29-Jan-16
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase, Procurement Process, & Manufacturing 72 03-Aug-15 29-Jan-16 0%
1st Delivery 0 29-Jan-16 0%
Flooring 89 22-Jun-15 29-Jan-16
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 72 03-Aug-15 29-Jan-16 0%
1st Delivery 0 29-Jan-16 0%
Mechanical 210 22-May-14 A 27-Oct-15
FHS - (Pressure Transmitter) 89 28-Feb-15 07-Oct-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 72 11-Apr-15 07-Oct-15 0%
1st Delivery 0 07-Oct-15 0%
FHS - (Welding Material) 149 07-Jun-14 A 13-Jun-15
Prepare and Submit Material Submittal 6 07-Jun-14 A 10-Jun-14 A 100%
Review Material Submittal and Approve 6 10-Jun-14 A 15-Jun-14 A 100%
Incorporate the engineer's comments and Resubmit 3 15-Jun-14 A 16-Jun-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 16-Jun-14 A 18-Jun-14 A 100%
Material Submittal Approved 0 18-Jun-14 A 100%
Purchase and Procurement Process 24 22-Jun-14 A 13-Apr-15 25%
1st Delivery 0 13-Jun-15 0%
FHS - (Coating and Wrapping material) 153 01-Jun-14 A 13-Jun-15
Prepare and Submit Material Submittal 6 01-Jun-14 A 08-Jun-14 A 100%
Review Material Submittal and Approve 6 08-Jun-14 A 10-Jun-14 A 100%
Incorporate the engineer's comments and Resubmit 3 10-Jun-14 A 16-Jun-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 16-Jun-14 A 18-Jun-14 A 100%
Material Submittal Approved 0 18-Jun-14 A 100%
Purchase and Procurement Process 72 22-Jun-14 A 28-May-15 50%
1st Delivery 0 13-Jun-15 0%
FHS - (Temperature Transmitter) 89 28-Feb-15 07-Oct-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 72 11-Apr-15 07-Oct-15 0%
1st Delivery 0 07-Oct-15 0%
FHS - Pipes Fittings 97 10-Jul-14 A 26-Mar-15
Prepare and Submit Material Submittal 6 10-Jul-14 A 20-Jul-14 A 100%

Page 17 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Review Material Submittal and Approve 6 20-Jul-14 A 27-Jul-14 A 100%


Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Material Submittal Approved 0 27-Jul-14 A 100%
Purchase and Procurement Process 48 28-Jul-14 A 26-Mar-15 78%
1st Delivery 0 26-Mar-15 0%
FHS - Pipes 97 10-Jul-14 A 26-Mar-15
Prepare and Submit Material Submittal 6 10-Jul-14 A 20-Jul-14 A 100%
Review Material Submittal and Approve 6 20-Jul-14 A 27-Jul-14 A 100%
Incorporate the engineer's comments and Resubmit 3 25-Jul-14 A 30-Jul-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 25-Jul-14 A 30-Jul-14 A 100%
Material Submittal Approved 0 27-Jul-14 A 100%
Purchase and Procurement Process 48 28-Jul-14 A 26-Mar-15 78%
1st Delivery 0 26-Mar-15 0%
FHS - Pits 153 01-Jun-14 A 13-Jun-15
Prepare and Submit Material Submittal 6 01-Jun-14 A 08-Jun-14 A 100%
Review Material Submittal and Approve 6 05-Jun-14 A 10-Jun-14 A 100%
Incorporate the engineer's comments and Resubmit 3 10-Jun-14 A 16-Jun-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 12-Jun-14 A 18-Jun-14 A 100%
Material Submittal Approved 0 18-Jun-14 A 100%
Purchase and Procurement Process 72 22-Jun-14 A 28-May-15 50%
1st Delivery 0 13-Jun-15 0%
FHS - High Points & Low Points Assembly 185 22-May-14 A 26-Aug-15
Prepare and Submit Material Submittal 6 22-May-14 A 01-Jun-14 A 100%
Review Material Submittal and Approve 6 01-Jun-14 A 05-Jun-14 A 100%
Incorporate the engineer's comments and Resubmit 3 07-Jun-14 A 11-Jun-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 09-Jun-14 A 30-Jun-14 A 100%
Purchase and Procurement Process 72 28-Feb-15 26-Aug-15 0%
Material Submittal Approved 0 28-Feb-15 0%
1st Delivery 0 26-Aug-15 0%
FHS - Hydrant Pit Valves Assembly 155 22-May-14 A 13-Jun-15
Prepare and Submit Material Submittal 6 22-May-14 A 01-Jun-14 A 100%
Review Material Submittal and Approve 6 04-Jun-14 A 07-Jun-14 A 100%
Incorporate the engineer's comments and Resubmit 3 08-Jun-14 A 14-Jun-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 14-Jun-14 A 18-Jun-14 A 100%
Material Submittal Approved 0 18-Jun-14 A 100%
Purchase and Procurement Process 72 22-Jun-14 A 13-Jun-15 50%
1st Delivery 0 13-Jun-15 0%
FHS - DBB Valves (Double Block & Bleed Valves) 141 06-Jul-14 A 13-Jun-15
Prepare and Submit Material Submittal 6 06-Jul-14 A 09-Jul-14 A 100%
Review Material Submittal and Approve 6 09-Jul-14 A 12-Jul-14 A 100%
Incorporate the engineer's comments and Resubmit 3 12-Jul-14 A 14-Jul-14 A 100%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 14-Jul-14 A 16-Jul-14 A 100%
Material Submittal Approved 0 16-Jul-14 A 100%
Purchase and Procurement Process 82 26-Jul-14 A 29-May-15 56%
1st Delivery 0 13-Jun-15 0%
FHS - Shock Absorber Accumulator 89 28-Feb-15 07-Oct-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 72 11-Apr-15 07-Oct-15 0%
1st Delivery 0 07-Oct-15 0%
FHS - Pressure Reducing Valves 89 28-Feb-15 07-Oct-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 72 11-Apr-15 07-Oct-15 0%
1st Delivery 0 07-Oct-15 0%
FHS - Pressure Releif Valves 53 28-Feb-15 09-Jul-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 36 11-Apr-15 09-Jul-15 0%
1st Delivery 0 09-Jul-15 0%
FHS - Hydrocarbon Detector 89 28-Feb-15 07-Oct-15
Prepare and Submit Material Submittal 6 28-Feb-15 13-Mar-15 0%
Review Material Submittal and Approve 6 14-Mar-15 27-Mar-15 0%
Incorporate the engineer's comments and Resubmit 3 28-Mar-15 03-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 04-Apr-15 10-Apr-15 0%
Material Submittal Approved 0 10-Apr-15 0%
Purchase and Procurement Process 72 11-Apr-15 07-Oct-15 0%

Page 18 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

1st Delivery 0 07-Oct-15 0%


FHS - Cathodic Protection 65 20-Mar-15 28-Aug-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 48 01-May-15 28-Aug-15 0%
1st Delivery 0 28-Aug-15 0%
HVAC - Split / AHU's / FCU 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
PVC Pipes and Fittings 73 20-Mar-15 17-Sep-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 31-Jul-15 14-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 14-Aug-15 21-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 21-Aug-15 28-Aug-15 0%
Purchase and Procurement Process 8 28-Aug-15 17-Sep-15 0%
Material Submittal Approved 0 28-Aug-15 0%
1st Delivery 0 17-Sep-15 0%
GRP Pipes and Fittings 29 07-Jul-15 17-Sep-15
Prepare and Submit Material Submittal 6 07-Jul-15 21-Jul-15 0%
Review Material Submittal and Approve 6 21-Jul-15 04-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 04-Aug-15 11-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 11-Aug-15 18-Aug-15 0%
Purchase and Procurement Process 12 18-Aug-15 17-Sep-15 0%
Material Submittal Approved 0 18-Aug-15 0%
1st Delivery 0 17-Sep-15 0%
Pre-insulated Pipes and Fittings 53 08-May-15 17-Sep-15
Prepare and Submit Material Submittal 6 08-May-15 22-May-15 0%
Review Material Submittal and Approve 6 22-May-15 05-Jun-15 0%
Incorporate the engineer's comments and Resubmit 3 05-Jun-15 12-Jun-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 12-Jun-15 19-Jun-15 0%
Purchase and Procurement Process 36 19-Jun-15 17-Sep-15 0%
Material Submittal Approved 0 19-Jun-15 0%
1st Delivery 0 17-Sep-15 0%
Insulation material 41 07-Jun-15 17-Sep-15
Prepare and Submit Material Submittal 6 07-Jun-15 21-Jun-15 0%
Review Material Submittal and Approve 6 21-Jun-15 05-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 05-Jul-15 12-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 12-Jul-15 19-Jul-15 0%
Purchase and Procurement Process 24 19-Jul-15 17-Sep-15 0%
Material Submittal Approved 0 19-Jul-15 0%
1st Delivery 0 17-Sep-15 0%
Pumps 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Plumbing Accessories 29 07-Jul-15 17-Sep-15
Prepare and Submit Material Submittal 6 07-Jul-15 21-Jul-15 0%
Review Material Submittal and Approve 6 21-Jul-15 04-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 04-Aug-15 11-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 11-Aug-15 18-Aug-15 0%
Purchase and Procurement Process 12 18-Aug-15 17-Sep-15 0%
Material Submittal Approved 0 18-Aug-15 0%
1st Delivery 0 17-Sep-15 0%
Electrical and Communication 89 20-Mar-15 27-Oct-15
Medium Voltage Cables 53 20-Mar-15 29-Jul-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 36 01-May-15 29-Jul-15 0%
1st Delivery 0 29-Jul-15 0%
Substations 65 20-Mar-15 28-Aug-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%

Page 19 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%


Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 48 01-May-15 28-Aug-15 0%
1st Delivery 0 28-Aug-15 0%
Transformers 65 20-Mar-15 28-Aug-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 48 01-May-15 28-Aug-15 0%
1st Delivery 0 28-Aug-15 0%
Airfield Ground Lighting / Guidance Signs/AFL cable 77 20-Mar-15 27-Sep-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 60 01-May-15 27-Sep-15 0%
1st Delivery 0 27-Sep-15 0%
400 Hz Converters/PITS/Cables 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
ALCMS 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Flood Lights 65 20-Mar-15 28-Aug-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 48 01-May-15 28-Aug-15 0%
1st Delivery 0 28-Aug-15 0%
Switch Boards 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Panel boards 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Automatic transfer Switch 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
MCC's 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%

Page 20 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

LV Generator 89 20-Mar-15 27-Oct-15


Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
MV Switch Gears 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Lighting Fixtures 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
Receptacles / Switches 89 20-Mar-15 27-Oct-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 72 01-May-15 27-Oct-15 0%
1st Delivery 0 27-Oct-15 0%
LV Cables 53 20-Mar-15 29-Jul-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 36 01-May-15 29-Jul-15 0%
1st Delivery 0 29-Jul-15 0%
Grounding Pits and accessories 53 20-Mar-15 29-Jul-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 36 01-May-15 29-Jul-15 0%
1st Delivery 0 29-Jul-15 0%
PVC Conduits 33 20-Mar-15 09-Jun-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 16 01-May-15 09-Jun-15 0%
1st Delivery 0 09-Jun-15 0%
Rigid Conduits 33 20-Mar-15 09-Jun-15
Prepare and Submit Material Submittal 6 20-Mar-15 02-Apr-15 0%
Review Material Submittal and Approve 6 03-Apr-15 16-Apr-15 0%
Incorporate the engineer's comments and Resubmit 3 17-Apr-15 23-Apr-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 24-Apr-15 30-Apr-15 0%
Material Submittal Approved 0 30-Apr-15 0%
Purchase and Procurement Process 16 01-May-15 09-Jun-15 0%
1st Delivery 0 09-Jun-15 0%
Special Systems 78 22-Jun-15 03-Jan-16
Summary Of Special System (Submittals & Procurement ) Part 78 22-Jun-15 03-Jan-16 0%
(VDGS) Units 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
I.P Telephony sets 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%

Page 21 of 22 TASK filter: WBS.


KKIA - AFU - BL ...Classic Schedule Layout... 04-Mar-15 17:19
Activity Name Original Duration Start Finish Activity %
Complete

Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%


Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
PAS Equipment 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
(FAS) Units 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
FIDS Work station 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
Digital Control and Monitoring Units & Cabling 65 22-Jun-15 30-Nov-15
Prepare and Submit Material Submittal 6 22-Jun-15 05-Jul-15 0%
Review Material Submittal and Approve 6 06-Jul-15 19-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 20-Jul-15 26-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 27-Jul-15 02-Aug-15 0%
Material Submittal Approved 0 02-Aug-15 0%
Purchase and Procurement Process 48 03-Aug-15 30-Nov-15 0%
1st Delivery 0 30-Nov-15 0%
I/O BACKBONE FIBER OPTIC CABLING 65 25-Jun-15 04-Dec-15
Prepare and Submit Material Submittal 6 25-Jun-15 09-Jul-15 0%
Review Material Submittal and Approve 6 09-Jul-15 23-Jul-15 0%
Incorporate the engineer's comments and Resubmit 3 23-Jul-15 30-Jul-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 30-Jul-15 06-Aug-15 0%
Purchase and Procurement Process 48 06-Aug-15 04-Dec-15 0%
Material Submittal Approved 0 06-Aug-15 0%
1st Delivery 0 04-Dec-15 0%
AVIATION FUEL MONITORING & CONTROL SYSTEM Units 65 05-Jul-15 14-Dec-15
Prepare and Submit Material Submittal 6 05-Jul-15 19-Jul-15 0%
Review Material Submittal and Approve 6 19-Jul-15 02-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 02-Aug-15 09-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 09-Aug-15 16-Aug-15 0%
Purchase and Procurement Process 48 16-Aug-15 14-Dec-15 0%
Material Submittal Approved 0 16-Aug-15 0%
1st Delivery 0 14-Dec-15 0%
(UPS) 65 15-Jul-15 24-Dec-15
Prepare and Submit Material Submittal 6 15-Jul-15 29-Jul-15 0%
Review Material Submittal and Approve 6 29-Jul-15 12-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 12-Aug-15 19-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 19-Aug-15 26-Aug-15 0%
Purchase and Procurement Process 48 26-Aug-15 24-Dec-15 0%
Material Submittal Approved 0 26-Aug-15 0%
1st Delivery 0 24-Dec-15 0%
BUILDING MANAGEMENT SYSTEM Units & Cabling 65 25-Jul-15 03-Jan-16
Prepare and Submit Material Submittal 6 25-Jul-15 08-Aug-15 0%
Review Material Submittal and Approve 6 08-Aug-15 22-Aug-15 0%
Incorporate the engineer's comments and Resubmit 3 22-Aug-15 29-Aug-15 0%
Review Material Submittal and Approve "After Incorporate the engineer's comments and Resubmit" 3 29-Aug-15 05-Sep-15 0%
Purchase and Procurement Process 48 05-Sep-15 03-Jan-16 0%
Material Submittal Approved 0 05-Sep-15 0%
1st Delivery 0 03-Jan-16 0%

Page 22 of 22 TASK filter: WBS.