Activity Name Original Duration Start Finish Activity %
Complete
Expansion of Apron no.6 and Related Facilities Updated 28-Feb-2014 439 13-Jan-14 A 15-Jan-17
Development of Design to 70% Design Completion (By Contractor) 28 01-Feb-14 A 01-Apr-14 A 100%
Submission 70% Design (By Contractor) 0 01-Apr-14 A 100%
70% Design - Design Review (By Authority) 8 02-Apr-14 A 25-Apr-14 A 100%
Approval 70% Design 0 25-Apr-14 A 100%
Development of Design 100% 28 28-Feb-15 08-May-15
Development of Design to 100% Design Completion (By Contractor) 20 28-Feb-15 18-Apr-15 0%
Submission 100% Design (By Contractor) 0 18-Apr-15 0%
100% Design - Design Review (By Authority) 8 19-Apr-15 08-May-15 0%
Approval 100% Design 0 08-May-15 0%
Shop Drawings 10 09-May-15 01-Jun-15
Development of Sop Drawings and Submit for Approval 4 09-May-15 18-May-15 0%
Submission Sop Drawings (By Contractor) 0 18-May-15 0%
Review Sop Drawings and Approval 6 19-May-15 01-Jun-15 0%
Approval Shop Drawings 0 01-Jun-15 0%
Drainage Profiles 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Drainage Sections & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 28-Feb-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Structural 93 01-Jun-14 A 21-Jun-15
Utilities Buildings Setting Out 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Foundation Layout & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Fire Alarm System 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Staff Information Display System 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
I/O Backbone Fiber Optic - Layouts & Details 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%
Aviation Fuel Control system 93 01-Jun-14 A 21-Jun-15
Development of Design 70% 56 01-Jun-14 A 19-Mar-15
Development of Design to 70% Design Completion (By Contractor) 28 01-Jun-14 A 01-Aug-14 A 100%
Submission 70% Design (By Contractor) 0 01-Aug-14 A 100%
70% Design - Design Review (By Authority) 8 28-Feb-15 19-Mar-15 0%
Approval 70% Design 0 19-Mar-15 0%
Development of Design 100% 28 20-Mar-15 28-May-15
Development of Design to 100% Design Completion (By Contractor) 20 20-Mar-15 08-May-15 0%
Submission 100% Design (By Contractor) 0 08-May-15 0%
100% Design - Design Review (By Authority) 8 09-May-15 28-May-15 0%
Approval 100% Design 0 28-May-15 0%
Shop Drawings 10 29-May-15 21-Jun-15
Development of Sop Drawings and Submit for Approval 4 29-May-15 07-Jun-15 0%
Submission Sop Drawings (By Contractor) 0 07-Jun-15 0%
Review Sop Drawings and Approval 6 08-Jun-15 21-Jun-15 0%
Approval Shop Drawings 0 21-Jun-15 0%