EXPANSION & DEVELOPMENT OF APRON-6 Long Lead Material Schedule Data Date 22-Jan-15

Activity ID Activity Name Duration Planned Planned Actual Actual Planned Actual % 2015 2016 2017
Start Finish Start Finish % Complete J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M JJul
676 25-May-14 26-Feb-16 22-Jun-14 A 27-Apr-16
Complete
0% 0%
Expansion of Apron no.6 and Related Facilities Updated 22-Jan-2014...
Submittals General, Material & Procurement 676 25-May-14 26-Feb-16 22-Jun-14 A 27-Apr-16 0% 0%

Civil 479 25-May-14 18-Oct-15 01-Sep-14 A 23-Dec-15 0% 0%


Storm Drainage 181 25-May-14 18-Jan-15 01-Sep-14 A 21-May-15 0% 0%
RC Pipes 120 25-May-14 21-Sep-14 01-Nov-14 A 02-Feb-15 0% 0%
PC4720 Purchase and Procurement Process 120 25-May-14 21-Sep-14 01-Nov-14 A 02-Feb-15 100% 90%
Manholes Covers & Frames / Gratings 120 21-Sep-14 18-Jan-15 22-Sep-14 A 21-May-15 0% 0%
PC4790 Purchase and Procurement Process 120 21-Sep-14 18-Jan-15 22-Sep-14 A 21-May-15 100% 0%
GRP - Slot Drains 120 25-May-14 21-Sep-14 01-Sep-14 A 14-Feb-15 0% 0%
PC4860 Purchase and Procurement Process 120 25-May-14 21-Sep-14 01-Sep-14 A 14-Feb-15 100% 80%
Architechural 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
CMU 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
PC5350 Purchase and Procurement Process 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
Doors 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
PC5490 Purchase, Procurement Process, & Manufacturing 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
Windows 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
PC5560 Purchase, Procurement Process, & Manufacturing 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
Flooring 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
PC5630 Purchase and Procurement Process 180 22-Apr-15 18-Oct-15 27-Jun-15 23-Dec-15 0% 0%
Mechanical 568 07-Aug-14 09-Nov-15 22-Jun-14 A 10-Jan-16 0% 0%
FHS - (Pressure Transmitter) 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 0% 0%
PC700 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 79.44% 0%
FHS - (Coating and Wrapping material) 180 01-Sep-14 27-Feb-15 22-Jun-14 A 21-Apr-15 0% 0%
PC1080 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 22-Jun-14 A 21-Apr-15 79.44% 50%
FHS - (Temperature Transmitter) 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 0% 0%
PC1150 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 79.44% 0%
FHS - Pipes Fittings 120 27-Aug-14 24-Dec-14 28-Jul-14 A 17-Feb-15 0% 0%
PC1290 Purchase and Procurement Process 120 27-Aug-14 24-Dec-14 28-Jul-14 A 17-Feb-15 100% 78%
FHS - Pipes 120 27-Aug-14 24-Dec-14 28-Jul-14 A 17-Feb-15 0% 0%
PC1360 Purchase and Procurement Process 120 27-Aug-14 24-Dec-14 28-Jul-14 A 17-Feb-15 100% 78%
FHS - Pits 180 01-Sep-14 27-Feb-15 22-Jun-14 A 21-Apr-15 0% 0%
PC1430 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 22-Jun-14 A 21-Apr-15 79.44% 50%
FHS - High Points & Low Points Assembly 180 01-Sep-14 27-Feb-15 22-Jan-15 20-Jul-15 0% 0%
PC1500 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 22-Jan-15 20-Jul-15 79.44% 0%
FHS - Hydrant Pit Valves Assembly 180 01-Sep-14 27-Feb-15 22-Jun-14 A 07-May-15 0% 0%
PC1640 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 22-Jun-14 A 07-May-15 79.44% 50%
FHS - DBB Valves (Double Block & Bleed Valves) 205 07-Aug-14 27-Feb-15 26-Jul-14 A 22-Apr-15 0% 0%
PC1710 Purchase and Procurement Process 205 07-Aug-14 27-Feb-15 26-Jul-14 A 22-Apr-15 81.95% 56%
FHS - Shock Absorber Accumulator 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 0% 0%
PC1780 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 79.44% 0%
FHS - Pressure Reducing Valves 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 0% 0%
PC1850 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 79.44% 0%
FHS - Hydrocarbon Detector 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 0% 0%
PC2060 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 05-Mar-15 31-Aug-15 79.44% 0%
FHS - Cathodic Protection 120 31-Oct-14 27-Feb-15 25-Mar-15 22-Jul-15 0% 0%
PC2200 Purchase and Procurement Process 120 31-Oct-14 27-Feb-15 25-Mar-15 22-Jul-15 69.17% 0%
HVAC - Split / AHU's / FCU 180 14-May-15 09-Nov-15 14-Jul-15 10-Jan-16 0% 0%
PC2270 Purchase and Procurement Process 180 14-May-15 09-Nov-15 14-Jul-15 10-Jan-16 0% 0%
Pumps 180 01-Sep-14 27-Feb-15 25-Mar-15 20-Sep-15 0% 0%
PC2620 Purchase and Procurement Process 180 01-Sep-14 27-Feb-15 25-Mar-15 20-Sep-15 79.44% 0%
Electrical and Communication 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
Substations 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 0% 0%
PC2830 Purchase and Procurement Process 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 100% 0%
Transformers 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 0% 0%
PC2900 Purchase and Procurement Process 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 100% 0%
Airfield Ground Lighting / Guidance Signs/AFL cable 150 25-May-14 21-Oct-14 25-Mar-15 21-Aug-15 0% 0%

Remaining Level of Effort Remaining Work Milestone Page 1 of 2

Actual Work Critical Remaining Work


EXPANSION & DEVELOPMENT OF APRON-6 Long Lead Material Schedule Data Date 22-Jan-15

Activity ID Activity Name Duration Planned Planned Actual Actual Planned Actual % 2015 2016 2017
Start Finish Start Finish % Complete J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M JJul
PC2970 Purchase and Procurement Process 150 25-May-14 21-Oct-14 25-Mar-15 21-Aug-15
Complete
100% 0%
400 Hz Converters/PITS/Cables 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3040 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
ALCMS 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3110 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Flood Lights 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 0% 0%
PC3250 Purchase and Procurement Process 120 25-May-14 21-Sep-14 25-Mar-15 22-Jul-15 100% 0%
Switch Boards 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3320 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Panel boards 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3390 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Automatic transfer Switch 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3460 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
MCC's 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3530 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
LV Generator 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3600 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
MV Switch Gears 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3670 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Lighting Fixtures 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3740 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Receptacles / Switches 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 0% 0%
PC3810 Purchase and Procurement Process 180 25-May-14 20-Nov-14 25-Mar-15 20-Sep-15 100% 0%
Special Systems 252 19-Jun-15 26-Feb-16 19-Aug-15 27-Apr-16 0% 0%
A5780 Summary Of Special System (Submittals & Procurement ) Part 252 19-Jun-15 26-Feb-16 19-Aug-15 27-Apr-16 0% 0%
(VDGS) Units 120 31-Jul-15 27-Nov-15 30-Sep-15 28-Jan-16 0% 0%
PC4510 Purchase and Procurement Process 120 31-Jul-15 27-Nov-15 30-Sep-15 28-Jan-16 0% 0%
I.P Telephony sets 120 10-Aug-15 07-Dec-15 10-Oct-15 07-Feb-16 0% 0%
PC4580 Purchase and Procurement Process 120 10-Aug-15 07-Dec-15 10-Oct-15 07-Feb-16 0% 0%
PAS Equipment 120 20-Aug-15 17-Dec-15 20-Oct-15 17-Feb-16 0% 0%
PC4650 Purchase and Procurement Process 120 20-Aug-15 17-Dec-15 20-Oct-15 17-Feb-16 0% 0%
(FAS) Units 120 30-Aug-15 27-Dec-15 30-Oct-15 27-Feb-16 0% 0%
PC7390 Purchase and Procurement Process 120 30-Aug-15 27-Dec-15 30-Oct-15 27-Feb-16 0% 0%
FIDS Work station 120 09-Sep-15 06-Jan-16 09-Nov-15 08-Mar-16 0% 0%
PC7460 Purchase and Procurement Process 120 09-Sep-15 06-Jan-16 09-Nov-15 08-Mar-16 0% 0%
Digital Control and Monitoring Units & Cabling 120 19-Sep-15 16-Jan-16 19-Nov-15 18-Mar-16 0% 0%
PC7530 Purchase and Procurement Process 120 19-Sep-15 16-Jan-16 19-Nov-15 18-Mar-16 0% 0%
I/O BACKBONE FIBER OPTIC CABLING 120 29-Sep-15 26-Jan-16 29-Nov-15 28-Mar-16 0% 0%
PC7600 Purchase and Procurement Process 120 29-Sep-15 26-Jan-16 29-Nov-15 28-Mar-16 0% 0%
AVIATION FUEL MONITORING & CONTROL SYSTEM Units 120 09-Oct-15 05-Feb-16 09-Dec-15 07-Apr-16 0% 0%
PC7670 Purchase and Procurement Process 120 09-Oct-15 05-Feb-16 09-Dec-15 07-Apr-16 0% 0%
(UPS) 120 19-Oct-15 15-Feb-16 19-Dec-15 17-Apr-16 0% 0%
PC7740 Purchase and Procurement Process 120 19-Oct-15 15-Feb-16 19-Dec-15 17-Apr-16 0% 0%
BUILDING MANAGEMENT SYSTEM Units & Cabling 120 29-Oct-15 25-Feb-16 29-Dec-15 27-Apr-16 0% 0%
PC7810 Purchase and Procurement Process 120 29-Oct-15 25-Feb-16 29-Dec-15 27-Apr-16 0% 0%

Remaining Level of Effort Remaining Work Milestone Page 2 of 2

Actual Work Critical Remaining Work