Download as pdf or txt
Download as pdf or txt
You are on page 1of 47

Economics of Machining

Machining Economics

1
Cost Components of Production

• handling cost/piece
Economics of Machining

• tooling cost/piece
• tool setting and changing cost/piece
• machining cost/piece

2
Economics of Machining

Cost per piece

3
4

Min Cp

Vopt
Minimum cost
R
Cost of Production

V
3

2 4–31–Cost
––Cost
Cost
RCost
– of tool
ofof
ofmachining
Total changing
handling
tooling
Cost
Time Components of Production

• machining time/piece
Economics of Machining

• handling time/piece
• tool setting and changing time/piece

4
Economics of Machining

Time per piece

2
Min Tp
3
R
Minimum time

Vopt
Rate of Production

Maximum
production
1

V
5

Time
changing
21–3–Non-productive
–Tool
RMachining
– Total time
timetime
Economics of Machining

Minimum
Economics of Machining

cost
Production rate
Cost per piece

Maximum
Hi-E production
range

Vcp Vtp
V
6
Cost of Production

machining cost/piece
Economics of Machining

+ tool setting cost/piece


Unit cost (Cp)
+ tooling cost/piece

+ handling cost/piece

7
Cost of Production
machining cost/piece =
Economics of Machining

8
Cost of Production
tool setting cost/piece =
Economics of Machining

9
Cost of Production
tooling cost/piece =
Economics of Machining

Solid tool Insert

10
Cost of Production
handling cost/piece =
Economics of Machining

 Does not depend on cutting speed

 Constant

11
Cost of Production
Therefore, overall machining cost or production cost per
piece ,
Cp = Cm*tm + Cm*ts*(tm/T) + Ce*(tm/T) + Cm*th
Economics of Machining

……(1)
where,
Cm = Machining cost per unit time
tm = Machining time
ts = Tool setting time
T = Tool life
Ce = Tool cost per edge
th = Tool handling time

12
Cost of Production
Since,
Machining time (tm) = ( π*d*l/ 1000*f*v)
Economics of Machining

Also from Tool life equation, VTn = C ( a constant)


Therefore by equation (1), Cp becomes

13
Economics of Machining Cost of Production

14
Economics of Machining Cost of Production

15
Economics of Machining Rate of Production

machining time/piece
Time of Prodn. (Rp) + tool setting time/piece

+ handling time/piece

16
Economics of Machining Rate of Production

17
Economics of Machining Rate of Production

18
Economics of Machining Rate of Production

19
Economics of Machining Rate of Production

20
b) Tool costs:
 brazed tools – initial cost = Rs.80/-; grinding
time – 5 min/edge; tool changing time = 2
min; 9 grinds/tool before salvage.
 Throw-away inserts: cost – Rs.300; tool
change time = 1.5 min; cutting edges = 8
i. Plot the cost/piece as a function of cutting speed
and hence find the cutting speed for minimum
cost for each case.
ii. Compute and compare the tool life for minimum
cost/piece for maximum production rate both for
brazed and inserted type cutting tools.
21
Cost of Production
Extended Taylor’s tool life equation:
Economics of Machining

22
Economics of Machining Cost of Production

23
Economics of Machining Cost of Production

24
Economics of Machining Cost of Production

25
Economics of Machining Cost of Production

26
Economics of Machining Cost of Production

27
Economics of Machining Cost of Production

28
Economics of Machining Cost of Production

29
Economics of Machining Cost of Production

30
Economics of Machining Cost of Production

31
Economics of Machining Rate of Production

32
Economics of Machining Rate of Production

33
Economics of Machining Rate of Production

34
Economics of Machining Rate of Production

35
Economics of Machining Rate of Production

36
Exercise Problems
Pb.: A large batch of steel shafts are to be rough turned to 76 mm
diameter for 300 mm length at a feed of 0.25 mm/rev. A solid
HSS type tool is to be used and appropriate constant in Taylor’s
tool life equation for the conditions employed are as follows: n =
Economics of Machining

0.25; measured tool life at the cutting speed of 245 m/min is 60


sec. The initial cost of the machine was Rs. 1,50,000/- and is to
be amortized in 5 years. The operator’s wages are Rs. 20/hour
and the operator and machine overheads are 100%. Tool
changing and resetting time on the machine is 300 sec and the
cost of regrinding the tool is Rs.10/-. The initial cost of the tool is
Rs.50/- and it can be ground 10 times. Non productive time for
each component is 120 sec. Obtain optimum speed for minimum
cost of production and hence obtain the tool life; rate of
production and the cost of producing the component.

37
Exercise Problems
Pb.: A 200 mm long and 300 mm diameter bar is
turned on a lathe with feed = 0.25 mm/rev.
The operating cost is 5 paise/min while the
Economics of Machining

tool cost is Rs. 1/edge. Tool changing time is


1 min. The requirements are such that either
of the two tool materials X or Y can be used.
Compare the machining cost per component
whilst operating under most economical
conditions for the two materials.
Material ‘X’  VT0.1 = 67
Material ‘Y’  VT0.1 = 90
38
Exercise Problems
Pb.: A 100 mm long 35 mm diameter bar is to be
turned at a feed of 0.26 mm/rev. The
Economics of Machining

operating cost is Rs. 10/min. and the tool


cost is Rs. 75/edge. The tool changing time
is 4 min. A carbide tool is used with two
cutting fluids for which the tool life
equations are given below:
Cutting fluid ‘X’  VT0.22 = 67
Cutting fluid ‘Y’  VT0.32 = 67

39
Exercise Problems
A tool used in a turning operation is of the brazed
carbide tip type. Its cost is Rs. 450/- and on the average,
it can be reground 10 times. The cost of regrinding is
Economics of Machining

Rs. 45/-. The lathe cost is Rs.2 lakhs, used 8 hrs/day, 5


days/week and 50 weeks/year. Its cost is to be amortized
over 10 years. The machine overheads are 100%. The
operator’s wages are Rs. 20/hr. and the operator’s
overheads are 100%. Tool life equation is VT0.25 = 7,
where V is in m/sec and T is the tool life in sec. the tool
changing time is 4 min, and the handling time per
component is 5 min. The workpiece with 50 mm
diameter and 400 mm length is machined at the rate of
0.25 mm/rev. Calculate minimum production cost and
hence obtain minimum production time.
40
Exercise Problems
Pb.: A 200 mm long and 65 mm diameter bar is to be
turned at a feed of 0.15 mm/rev. The operating
cost is Rs. 0.50/min. and the tool cost is Rs.
Economics of Machining

10/edge. The tool changing time is 2 min. Assume


weight of workpiece as 0.14 kg. The following two
workpiece materials have been used.:
Material ‘X’ (cost Rs.100/kg)  VT0.10 = 67
Material ‘Y’ (cost Rs.120/kg)  VT0.16 = 90
Calculate tool life and optimum cutting velocities
for min. cost with no consideration for material
cost; and maximum production rate criteria for
both the w/p materials. State which material
should be chosen for total minimum cost.
41
Exercise Problems
Pb.: A tool used in a turning operation is of brazed
type. Cost of the tool is Rs. 100 and on average, it
can be reground 10 times. The cost of each
Economics of Machining

regrinding is Rs.5/-. The lathe cost is to be


amortized over 10 years and the machine
overheads are 100%. The lathe cost is Rs.2,00,000
and is used 8 hrs/day, 5 days/week and 50
weeks/yr. The tool life relationship is VT0.25 = 400.
Tool changing time is 4 min, handling time per
component is 5 min, cutting distance per
component is 200 m. Calculate minimum
production cost and time.

42
Exercise Problems
Pb.: Illustrate in a sketch graph the economic factors
involved in metal cutting and show that cutting
Economics of Machining

speed has an optimum value.


When finish turning a 50 mm diameter, 130 mm
long bore in a high-tensile steel at a feed of 0.13
mm/rev. The tool life equation was VT0.12 = 146.
The cost of regrinding the tool was Rs. 8 and the
tool changing time was 10 min. If the inclusive
cost of operating the machine is Rs. 13.5/hr,
determine (a) the economic machining time per
component, (b) the number of components to be
produced between tool changes.
43
Exercise Problems
Pb.:An automatic lathe is to be used to machine brass
components 75 mm long X 50 mm diameter using a
depth of cut 1.25 mm. Select the speed that
Economics of Machining

minimizes the machining cost and calculate the


corresponding tool life. Also estimate the cutting
speed for minimum tool life of production. Assume:
Labor + overhead rate Cm = Rs. 5/hr.
Reconditioning cost of the tool edge = Rs 0.25/edge
Loading and unloading time of the work = 15 Sec.
Tool change time = 5 min.
Tool life relationship: VT0.25 = 300
44
Exercise Problems
Pb.: A 1.0 m long cut is to be given on a 100 mm
diameter steel bars on an engine lathe. The depth of
cut is 6 mm and the feed rate is 0.5 mm/rev. the
Economics of Machining

following cost data are available for this operation:


machine labor: Rs.20/hr; machine burden rate:
400% of labor; tool cost: Rs. 180; tool changing
time: 2 min.; regrinds available: 5/tool; grinding
time: 6 min/edge; tool grinding labor: Rs.30/hr;
tool grinding burden: 500% of labor; loading time:
5 min/component; Tool life equation: VT0.25 = 200.
Obtain optimum speed for minimum cost of
production and hence obtain the tool life, rate of
production and the cost producing a component.
45
Exercise Problems
Pb.: A 200mm long and 30 mm diameter bar is to
be turned on a lathe with a feed rate of 0.25
mm/rev. The rpm is 200. The operating cost is
Economics of Machining

5 paise/min while the tool cost is Rs. 1/edge.


The design provisions indicate that either of
the following two materials may be used.
State which material should be chosen for
minimum cost.
Material cost/kg tool life eqn.
X Rs. 2.00 VT0.10 = 67
Y Rs. 3.00 VT0.16 = 90
46
Exercise Problems
Pb.: A 600 mm long cut is to be made on a 150 mm dia
bar on a lathe with a depth of cut of 1.5 mm and
feed of 0.25 mm/rev. The tool life equation is VT 0.25
Economics of Machining

= 475. For the above operation, two types of tools


may be used: (i) brazed tool and (ii) throw away
carbide inserts. The following cost data have been
collected:
(a) Machine costs: machining cost = Rs 1/hr;
machine overhead = 100%; grinding cost =
Rs.1.5/hr; grinding machine overhead = 200%;
idle time = 5 min.

Contd….
47

You might also like