Professional Documents
Culture Documents
2A. TRA For Al Ghuwaifat Project
2A. TRA For Al Ghuwaifat Project
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 1 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
4 Work at height.
Using of scaffold platform and mobile scaffold tower
7 Manual Handling
8 Housekeeping
9 Excavation work
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 2 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
1 Mobilization of Unauthorized Property damage. Ensure that all the required 3 C M Effective and Site 1 C L OSHAD
Plant / access. Personnel injury. permits are received from continuous Engineer/ COP 34.0
Equipment Collision with supervision to be Authorised Safe use
concerned authory such as Supervisor Lifting
moving vehicles. ensured always.
Etislat, AADC etc. prior to Equipment
Old and Damaged Flashing lights shall and Lifting
commence mobilize. be placed suitably to
plant. accessories
Poor
Ensure the approval of ACG warn drivers during
communication; and MUS and inform them night
Untrained work about the mobilization date All personnel will
wear the Mandatory COP 22.0
force and time. Barricading
PPE (Safety Helmet,
Un protected All the permits shall be kept of Hazards,
Safety Glasses,
work force OSHAD.
Heat stress on site. Coverall, and safety
Ensure the approved shoes) along with PPE
Manual Handling specific to their task.
Scattered method statment and risk
materials in the assessment.
area. Ensure the demarkation of
plot limit.
Ensure that the equipment
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 3 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 4 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 5 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
signages.
Ensure suitbale access / egress.
2 Offloading / Incompetent - Fall of materials Ensure the crane is approved 3 C M Mandatory and Site 2 A L OSHAD
Rigging and operator, rigger, by HSE and logistic team of optional PPE’s shall Engineer/ COP 34.0
- Personal Injury
Slinging Flagman. main contractor and be used at all times. Authorized Safe use
- Property damage Continuous Supervisor Lifting
(Use of Mobile Unsuitable consultant.
Crane) - Fatality monitoring is Equipment
selection of lifting Ensure the lifting plan and required and Lifting
equipment like lifting permits. accessories
mobile crane, Ensure the clear distance and
Boom loader etc. anti-collision system in crane OSHAD-
Unstable and to avoid the contact between SF_COP 36
improper ground two cranes in case of using two Plant &
Equipment.
conditions fall of crane. Check the overhead line
materials, sharp Ensure the Red Helmet and
objects of vest for Rigger and clearly
material, mention on the vest “RIGGER” COP 22.0
Barricading
ergonomics, slip TOOL BOX TALK and pre-
of Hazards,
trip fall. adverse starting briefing prior to start
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 6 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 7 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
sign boards
Specific Lifting plan to be
prepared and submitted to
consultant for approval.
Work should be stopped in the
adverse weather conditions
such as rain, fog and more than
38 kilometers wind speed.
Proper PPEs should be used for
the task.
The area must be free from
scattered materials and proper
housekeeping must be
ensured at the site.
Ensure proper Tag Line for
lifting of load.
Ensure the availibility of
Appointed perosn and rigger
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 8 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
3 Stacking and Improper Personal Injury Lazourdy will off-load and 2 D L Continuous Site 1 C L OSHAD
Storage of stacking and store its material at Arabtech Engineer/ COP 49.
Property monitoring is required
Materials Authorized Compressed
storing on damage designated.
Supervisor Gass and Air
unstable ground Ensure the exclusion zone once
area. stacked the material to stop
OSHAD
Scattered the the unauthorized access. COP 34.0
material on the Stacking and storing of Safe use
way material must be done as per Lifting
Stacking with Consultant and Eployor Equipment
and Lifting
more then requirements. accessories
required height. Ensure suitable plants for
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 9 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
Page No. 10 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
4 Work at height. Fall of person, Personal serious Ensure competent supervision 4 D H Ensure design drawing for Operation 1 C M OSHAD-SF-
fall of scaffolding injuries, is available always. scaffold if the height is team COP 23.0
Using of scaffold work at
structure, Property damage, Lazourdy must use the more than 10 meters.
and mobile height
Electrocution, scaffolding erected by
scaffold tower fall of material, Follow.
fatality. competent scaffolders and
overhead power OSHAD-SF-
lines inspected by competent COP-26.0
scaffold inspector. Scaffolding
Inspection shall be repeated at
OSHAD-SF-
least every 7 days and also COP 37.0
following any alteration / Ladders
change.
Supervisor will remove the
green tag once the scaffolding
is not in use and will keep the
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 11 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
red tag.
All scaffolders must be clearly
identifiable and the wording
‘SCAFFOLDER’ must be clearly
printed on their coveralls
Full body harness with double
lanyard is used for the job shall
be inspected on monthly basis
and ensure the colour code.
Ensure the register log of
Safety harness and scaffold
and maintained regulalry.
Ensure the daily TOOL BOX
TALK & Pre-start briefing prior
to commence the work and
shall sign by all workers.
The inspection must be
recorded in a scaffold register
which must be kept onsite &
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 12 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
Page No. 13 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 14 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 15 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 16 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
6 Ergonomics & Use of tools Property Provide awareness on the 2 B M Continuous Engineers I C L OSHAD-SF-
Improper use of during damage and proper use of tools and monitoring and and COP 20.0
Supervisors Safety in
hand tools installation Personal harm ergonomic issues. supervision of
design.
activity •Stress Worn out tools shall not be activities to be
Exposure to used & damaged tools must performed
vibration be replaced
Ensure that workers shall be
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 17 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
7 Manual Handling Slip of object Personnel harm Ensure to use the kerb lifter 3 C M Close supervision is Site 1 B L OSHAD
Heavier loads while fixing the kerbstone and maintained. Engineers COP 14.0
Back injury and Manual
than your lifting shall be lift with tw0 Ensure to
Supervisors Handling
capacity use the cotton gloves while First Aid and
mixing the mortar 3/8 with certified First Aider
Improper hold /
cement. will be present
grip
Always follow the manual
handling procedures.
T.B.T will be conducted before
starting the task.
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 18 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
8 Housekeeping Slip, trip & fall Personal Injury Ensure to keep the waste 2 D L Continuous Engineers 1 C L OSHAD
Manual handling BINS on site and shall be and COP 14.0
monitoring is required
supervisors Manual
disposed with approved
Handling
center of waste management
OSHAD_SF
contractor. _COP-54
Separate BINS to be kept for waste
food waste and conduct the management
awareness training for .
workers for disposal of
different waste.
Ensure trained and
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 19 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
experienced workers,
Ensure to use slip resistant
chemical for floor cleaning.
Waste should be segregated
Waste should be removed on
a daily basis & housekeeping
should be done before after
and whenever required
9 Excavation work Overhead Damaged of Contractor shall ensure to 4 D H Ensure site lighting and Engineers 2 C M OSHAD-SF-
power line. underground or asssess the excavation work by suitable access. and COP 29.0
Unsuaitable competent person prior to supervisors Excavation
overhead poer
ground. commence. work.
line.
Underground Ensure the exclusion zone and
Electric shock. suitable signage prior to
services.
Inadequate Personal injury commence the work.
equipment and Insufficient Conduct the daily TBT & PSB
plant. ogygenc before the work and sign by all
Unskilled and involved people.
experience Ensure to receive all required
operator. permits from concerned
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 20 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 21 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 22 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
Page No. 23 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 24 of 25
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(All Activity of the Project)
TASK DETAILS 21.09.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002A-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 22-03-2022
MEMEBERS Designation: HSE-Eng. QA/QC Site Foreman
Manager Rev #: 01
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent
Page No. 25 of 25