TASK RISK ASSESSMENT

Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:


Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

TASK RISK ASSESSMENT SUMMARY

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 1 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

S. No Description of Task steps Remarks


1 Mobilization of Plant / Equipment

2 Offloading / Rigging and Slinging

3 Stacking and storage of material

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 2 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

1 Mobilization of  Unauthorized Property damage.  Ensure that all the required 3 C M  Effective and Site 1 C L OSHAD
Plant / access. Personnel injury. permits are received from continuous Engineer/ COP 34.0
Equipment  Collision with supervision to be Authorised Safe use
concerned authory such as Supervisor Lifting
moving vehicles. ensured always.
Etislat, AADC etc. prior to Equipment
 Old and Damaged  Flashing lights shall and Lifting
commence mobilize. be placed suitably to
plant. accessories
 Poor
 Ensure the approval of ACG warn drivers during
communication; and MUS and inform them night
 Untrained work about the mobilization date  All personnel will
wear the Mandatory COP 22.0
force and time. Barricading
PPE (Safety Helmet,
 Un protected  All the permits shall be kept of Hazards,
Safety Glasses,
work force OSHAD.
Heat stress on site. Coverall, and safety
 Ensure the approved shoes) along with PPE
 Manual Handling specific to their task.
 Scattered method statment and risk
materials in the assessment.
area.  Ensure the demarkation of
plot limit.
 Ensure that the equipment
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 3 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

intended to mobilize are


according to the
requirements of Musanada
and comply the HSE
requirments.
 The plant shall be inspected
by competent logistic and HSE
personnel prior to commence
on site.
 All personnel must be
inducted.
 Ensure the scope of work and
specific risk assessment are
communicated through Tool
Box Talk.
 Correct PPE must be used for
the job (hard hat, high visibility

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 4 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

vest, and safety shoes).


 Ensure close supervision and
competent team while
offloading and stacking of
materials.
 Driver must have valid UAE
license.
 Adequate light shall be
provided if work in night.
 Sufficient & suitable safe
methods of access and egress
for the delivery vehicles.
 Ensure lifting permit and
Appointed person and rigger
while offloading with crane.
 Storage areas shall be
barricaded and display the

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 5 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

signages.
 Ensure suitbale access / egress.

2 Offloading /  Incompetent - Fall of materials  Ensure the crane is approved 3 C M  Mandatory and Site 2 A L OSHAD
Rigging and operator, rigger, by HSE and logistic team of optional PPE’s shall Engineer/ COP 34.0
- Personal Injury
Slinging Flagman. main contractor and be used at all times. Authorized Safe use
- Property damage  Continuous Supervisor Lifting
(Use of Mobile  Unsuitable consultant.
Crane) - Fatality monitoring is Equipment
selection of lifting  Ensure the lifting plan and required and Lifting
equipment like lifting permits. accessories
mobile crane,  Ensure the clear distance and
Boom loader etc. anti-collision system in crane
 Unstable and to avoid the contact between COP 22.0
improper ground two cranes in case of using two Barricading
conditions fall of crane. Check the overhead line of Hazards,
materials, sharp OSHAD.
 Ensure the Red Helmet and
objects of vest for Rigger and clearly
material, mention on the vest “RIGGER”
ergonomics, slip  TOOL BOX TALK and pre-
trip fall. adverse starting briefing prior to start
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 6 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

environment the activities.


conditions.  The ground should be suitable
for the task.
 The operator and rigger
(flagman man) should be
competent and third party
certified.
 Co-ordination between riggers
and crane operator.
 Lifting must be stopped if the
load exceeds the admissible
limits.
 The equipment used for the
operation should be third party
certified.
 The area should be barricaded
and un authorized entry to the
area must be restricted and

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 7 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

sign boards
 Specific Lifting plan to be
prepared and submitted to
consultant for approval.
 Work should be stopped in the
adverse weather conditions
such as rain, fog and more than
38 kilometers wind speed.
 Proper PPEs should be used for
the task.
 The area must be free from
scattered materials and proper
housekeeping must be
ensured at the site.
 Ensure proper Tag Line for
lifting of load.
 Ensure the availibility of
Appointed perosn and rigger

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 8 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

all the time while using crane.


 Ensure the flash on the boom
of crane.
 Always follow OSHAD COP 34.0
safey use of lifting and lifting
accessories.

3 Stacking and  Improper  Personal Injury  Lazourdy will off-load and 2 D L  Continuous Site 1 C L OSHAD
Storage of stacking and store its material at Arabtech Engineer/ COP 49.
 Property monitoring is required
Materials Authorized Compressed
storing on damage designated.
Supervisor Gass and Air
unstable ground  Ensure the exclusion zone once
area. stacked the material to stop
OSHAD
 Scattered the the unauthorized access. COP 34.0
material on the  Stacking and storing of Safe use
way material must be done as per Lifting
 Stacking with Consultant and Eployor Equipment
and Lifting
more then requirements. accessories
required height.  Ensure suitable plants for

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 9 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

 Stacking on stacking of steel materials.


uneven surface.  Proper Crane and boom loader
to be used for stacking and
storing of materials.

 Materials not to block the


access or egress.
 Proper signage to avoid
unwanted contact with other
site users.
 Supervision to be informed
when materials arrive to the
work place and to dictate
where materials will be
stacked/stored.
 Ensure proper storage of
acetylene, propane and oxygen
as per OSHAD – COP 49.0
Compressed Gases and Air.
 Store the chemical in
S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 10 of 11
TASK RISK ASSESSMENT
Construction of Staff accommodation in Al Dhafra City – Al Ghuwaifat Date: Performer Dept:
Brief Description
(Mobilization and offloading of materials)
TASK DETAILS 28.08.2021 CIVIL
Location / Equipment Al Dhafra City – Al Ghuwaifat, UAE
Tag ID
Ahmed R A Review date: TRA No: LAZ-TRA-CSA-002-
Name: M. Ziad Nissar Ahmed Abdul Rahim
Hamdan 00
TRA TEAM
Project 27-02-2022
MEMEBERS Designation: HSE-Eng. QA/QC Ali Alathba
Manager Rev #: 00
Company: LAZOURDAY LAZOURDAY LAZOURDAY LAZOURDAY
BASELINE ADDITIONAL CONTROL RESP. RESIDUAL REFERENCES
RISK MEASURES / ACTIONS PARTY RISK
STEP DESCRIPTION OF CONSEQUENCES CONTROL MEASURES
HAZARDS
NO. TASK STEP
R
S P S P R
R

designated area and shall


be under the shade.

Preparation by: Lazourdy Approval by: DEC


Prepared by: HSE-Eng Reviewed by Contractor: PM Approved by: Consultant/ HSE Engineer

Name: Nisar Ahmed Name: M. Ziad Abbadi Name:

Sign: Sign: Sign:

S: Severity, P: Probability, R: Risk. Risk Rating (High, Medium to Low) 1-Negligible , 2-Marginal, 3-Critical,4-Sever, 5- Catastrophic
A-Improbable , B-Remote , C-Occasional , D-Probable , E-Frequent

Page No. 11 of 11