application with its plans and statements shall be deemed to have been

sanctioned.
6.7.4 Once the plan has been scrutinized and objections have been pointed out, the
owner giving notice shall modify the plan, comply with the objections raised
and resubmit it. No new objections may generally be raised when they are
resubmitted after compliance of earlier objections. The prints of Plans
submitted for final approval shall not contain any mistakes. The Authority
shall grant or refuse the Commencement Certificate/Building Permission
within 60 days from the days of resubmission. If objections raised by authority
is not complied within 60 days original application shall stand cancelled and
fresh proposal should be submitted with requisite fees.

6.8 Revocation of Permission


6.8.1 In addition to the provisions of section 51 of the Maharashtra Regional and
Town Planning Act, 1966, the Authority may revoke any building permission
issued under the provisions of these regulations, wherever there has been any
false statement or any misrepresentation of material fact in the application on
which the building permission was based, and the whole work shall be treated
as unauthorized.
In the case of revocation of permission based on false statements or any
material misrepresentation of fact in the application, no compensation would
be payable.

7. PROCEDURE DURING CONSTRUCTION:-


7.1 Neither the granting of the permission nor the approval of the drawings and
specifications, nor inspections made by the Authority during erection of the
building shall in any way relieve the owner of such building from full
responsibility for carrying out the work in accordance with the requirements
of the regulations.
7.2 Notice for Commencement of Work – Within one year from the date of
issue of building permission, the owner shall commence the work for which
the building permission has been issued. The owner shall give notice to the
Authority of the intention to start work on the building site in the Pro forma
given in Appendix F along with N.A. order issued by the District Collector.
The owner shall commence the work after 7 days from the date of receipt of

30