Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 16

MENYEDIA TENAGA KERJA, MEMBEKAL PERALATAN, MENGHANTAR, MEMASANG, MENGUJIJALAN DAN LA

RETROFIT ANAEROBIK REAKTOR DI LOJI BIOGAS PASOH, SIMPANG PERTANG, NEGER

Item

A. PRELIMINARIES
A.1 Insurance
Provide necessary insurances required under contract:-
a) Contractor All Risk
b) Third Party Liability
c) Workmen Compensation
(Insured Period : Construction period + 1 year defect. Liability period + 6 months)

A.2 Local Authorities Submission And Approval


To provide, submit and seek for Government Authority approval:-
i. DOE
ii. DOSH
iii. BOMBA (notification confined space work)
(Copy of submission and approval letter must submit to Engineer)

A.3 Temporary Site Office & Buildings


Provide, maintain and remove Portable Office Cabin for site office usage, document
storage and management.

A.4 Worker Accomodation & Storage


Establish worker's living quarters, stores, site facilities and removal upon completion
work. This include survey and first aid outfit.

A.5 Mobilization And Demobilization Transport


Allow for mobilization and demobilization of transport to and from site to all plant,
equipments and labour necessary for the execution of the works including all duties and
insurances, etc. and providing for the temporary crossing and drainage necessary for
proper execution of works.

A.6 Safety & Health


Provide safety precautions to ensure the health and safety of Contractor's staff and
labour. This include providing personal protection equipment (PPE), medical kit,
portable fire extinguisher etc. based on HIRARC assessment.

A.7 Site Safety and Health Supervisor


The employment of competent Site Safety and Health Supervisor for the entire duration
of the construction period to be stationed at site. This include report to summarize
occurences, accidents and safety performance.

A.8 Authoruzed Gas Tester Personel (AGT)


The employment of competent authorized gas tester to ensure tank in safe condition to
work. This include carry out air testing for toxic, flammable gas and fumes and oxygen
adequacy before access to the confined area of work.

A.9 Leak Test


Provide test to verify welding condition and check leakage for each unit tank.
TOTAL SECTION A

B. RETROFIT BIOREACTOR 1 (R1)


B.1 Remove & Terminate Gas Pipeline
B.2 Cut,
Cleanremove & Clearand Tank terminate
ContentReactor 1 gas pipeline till main gas pipeline. The gas pipeline
terminate
Dispose using 8 inch
any liquid, sludge, ID stud
solidend flange
or any for HDPE
content c/wthe
inside accessories.
3,600mt tank to assigned area
B.3 Scaffolding
with
Erect, radius of 300 meter from site.
B.4 Crane maintain and dismantle suitable scarffolding for temporary working platform
including
Provide 1 access
unit and egress
20tonne cranearound tank. & installation work. The price include
B.5 Demolish
-transportation, Rooftop
Tank Dimension : &
ID Top
X Platefor
Height :
demolish
19.1m
Prepare insurance, driver, and dieselXand
12.8m
other related item. and demolish rooftop &
B.6 - Scaffoldworkforces,
Replace : L X Wequipments
vol.Plate
Top X H : 60m X 1.5mtransportations
X 12.8m to remove
top
To supply, portionfabricate,
bioreactor 1 to theand
transport designed
replacearea
MS with radiustank
1 portion of 500 meter
plate fromfrom
top.site.
Any
TOTAL SECTION B
facilities mount on top late will install back. Tank spesification:
- Material : MS plate (5' X 20' X 6mm thk) c/w 3 layer anti rust paint
C. -RETROFIT Tank Diameter
HOLDING : 19.2m
TANK (HT)
- 1 portion = 8 plate
C.1 Clean
Refer to & Clear
drawing Tank ………Content
C.2 Dispose
Scaffolding any liquid, sludge, solid or any content inside the 800mt tank to assigned area
with
Erect, radius of 300 meter from site.
C.3 Crane maintain and dismantle suitable scarffolding for temporary working platform
including
Provide access
1 unit and egress around
20tonne crane for demolish tank. & installation work. The price include
C.4 -Demolish Tank Work
Dimension : ID X Height : 15.54m X 7.1m
transportation,
Prepare insurance, driver, and
diesel and other related item. and demolish top
C.5 -Replace Scaffoldworkforces,
vol. : L X
Top Portion Tank W equipments
X H : 50m X 1.5m transportations
X 7m to remove
portion
To & 20ft
supply, X 6ft bottom
fabricate, transportplate
andatreplace
holdingMStank (HT) to the
2 portion tankdesigned area
plate from within
top. Tankradius
C.6 Replace
of 500 Tank
meter C-Channel
from site.
spesification:
To supply, fabricate,
C.7 -Replace Material Bottom
: MS plate Platetransport
Tankthk)and
(6mm
replace 2" X 4" MS C-channel around top plate tank.
c/w 3 layer anti rust paint
Refer
To to drawing
supply, fabricate, ………
- Dimension Tank : D transport
X h = 50ft and replace 20ft
X 22ft X 6fftSECTION
TOTAL X 9mm MS C plate at bottom tank.
Tank spesification:
- 1 portion tank plate height = 6ft
-Refer Material : MS plate
to drawing ……… (9mm thk) c/w 3 layer anti rust paint
D. -RETROFIT Dimension Tank : DTANK
SETTLING X h = 50ft X 22ft
Refer to drawing ………
D.1 Clean & Clear Tank Content
D.2 Dispose
Scaffolding any liquid, sludge, solid or any content inside the 560mt tank to assigned area
with
Erect, radius of 300 meter from site.
D.3 Crane maintain and dismantle suitable scarffolding for temporary working platform
including
Provide 1 access
unit and egresscranearound tank. & installation work. The price include
D.4 Demolish
-transportation, Top 20tonne
Tank Dimension Portion
: ID X Height
for demolish
: 15.54m X 7.1m
Prepare insurance, driver, and diesel and other related item. and demolish rooftop &
D.5 -ReplaceScaffoldworkforces,
: L X Wequipments
vol.Portion
Top X H : 50m X 1.5mtransportations
Tank X 7m to remove
top
To portionfabricate,
supply, bioreactor 2 to theand
transport designed
replacearea
MSwith radiustank
2 portion of 500 meter
plate fromfrom
top.site.
Tank
D.6 Replace Tank C-Channel
spesification:
To supply,
D.7 -Install New:fabricate,
Material Spiral
MS plate
transport and replace MS 2 portion tank plate from top. Tank
Stairs
(6mm thk) c/w 3 layer anti rust paint
spesification:
Supply, fabricate, transport and replace 1.5m height spiral stair mount on top plate as
D.8 --Overflow
Dimension
Material Tank
Pipe
: MS : D X h = 50ft
plate (6mm thk)Xc/w22ft3 layer anti rust paint
per
-To 1 drawing
portion ………..
tank
supply, fabricate, plate height
transport = 6ft
and install 6 inch ID HDPE overflow
-Material
Dimension
Refer
Tank
: GI expanded
toholder
drawing
: D
………
X h = 50ft X 22ft
mesh (3' width) TOTAL SECTION D pipe c/w accessories
&
- 1pipe
portion tank forplate
each 1.0m.
height = 6ft
Refer to drawing ………

E CONTIGENCY

CONTI
GRAN
NG, MENGUJIJALAN DAN LAIN-LAIN KEPERLUAN BAGI KERJA
SIMPANG PERTANG, NEGERI SEMBILAN

Qty Unit Amount


Rate [RM]
[RM]

1 L.Sum 2,000.00 2,000.00

1 L.Sum 2,000.00 2,000.00

1 L.Sum 4,000.00 4,000.00 http://quantitysurveyoronline.com.my/materials-prices.html

1 L.Sum 1,900.00 1,900.00 http://quantitysurveyoronline.com.my/materials-prices.html

1 L.Sum 10,000.00 10,000.00

1 L.Sum 3,000.00 3,000.00

9 Man-month 3,500.00 31,500.00 http://quantitysurveyoronline.com.my/materials-prices.html

1 L.sum 20,000.00 20,000.00 Based previous contract record

3 nos. 3,000.00 9,000.00


83,400.00

1 L.Sum 250.00 250.00


1 L.Sum 30,000.00 30,000.00
1,200 m3 35.00 42,000.00 http://quantitysurveyoronline.com.my/materials-prices.html
14 days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
1 nos. 55,000.00 55,000.00
1 nos. 80,000.00 80,000.00
218,450.00

1 L.Sum 50,000.00 50,000.00


525 m3 35.00 18,375.00 http://quantitysurveyoronline.com.my/materials-prices.html
14 days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
1 L.Sum 30,000.00 30,000.00
2 portion 60,000.00 120,000.00
50 m 30.00 1,500.00 http://quantitysurveyoronline.com.my/materials-prices.html
2 nos. 4,500.00 9,000.00
240,075.00

1 L.Sum 50,000.00 50,000.00


525 m3 35.00 18,375.00 http://quantitysurveyoronline.com.my/materials-prices.html
14 days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
1 nos. 40,000.00 40,000.00
3 portion 60,000.00 180,000.00
50 m 30.00 1,500.00 http://quantitysurveyoronline.com.my/materials-prices.html
4 m 1,500.00 6,000.00
10 m 100.00 1,000.00
308,075.00

TOTAL 850,000.00

CONTIGENCIES -
GRAND TOTAL 850,000.00
aterials-prices.html

aterials-prices.html

aterials-prices.html
aterials-prices.html
aterials-prices.html

aterials-prices.html
aterials-prices.html

aterials-prices.html

aterials-prices.html
aterials-prices.html

aterials-prices.html
Item

A. PRELIMINARIES
A.1 Insurance

A.2 Local Authorities Submission And


Approval

A.3 Temporary Site Office & Buildings

A.4 Worker Accomodation & Storage

A.5 Mobilization And Demobilization


Transport

A.6 Safety & Health

A.7 Site Safety and Health Supervisor

A.8 AGT

A.9 Leak Test


A.10
TOTAL SECTION A

B. RETROFIT BIOREACTOR 1 (R1)


B.1 Remove & Terminate Gas Pipeline
B.2 Clean & Clear Tank Content
B.3 Scaffolding
B.4 Crane
B.5 Demolish Rooftop & Top Plate
B.6 Replace Top Plate

TOTAL SECTION B

C. RETROFIT HOLDING TANK (HT)


C.1 Clean & Clear Tank Content
C.2 Scaffolding
C.3 Crane
C.4 Demolish Work

C.5 Replace Top Portion Tank

C.6 Replace Tank C-Channel


C.7 Replace Bottom Plate Tank
TOTAL SECTION C

D. RETROFIT SETTLING TANK


D.1 Clean & Clear Tank Content
D.2 Scaffolding
D.3 Crane
D.4 Demolish Top Portion

D.5 Replace Top Portion Tank

D.6 Replace Tank C-Channel


D.7 Install New Spiral Stairs
D.8 Overflow Pipe
TOTAL SECTION E

E CONTIGENCY
E.1 Replace Bottom Plate (Settling Tank)
E.2 Replace 2nd Bottom Plate
E.3 (Settling Tank)C-Channel (reactor 1)
Replace Tank
E.4 Clear Dumping Site
Description Qty

Provide necessary insurances required under contract:- 1


a) Contractor All Risk
b) Third Party Liability
c) Workmen Compensation
(Insured Period : Construction period + 1 year defect. Liability period + 6 months)

To provide, submit and seek for Government Authority approval:- 1


i. DOE
ii. DOSH
iii. BOMBA (notification confined space work)
(Copy of submission and approval letter must submit to Engineer)

Provide, maintain and remove Portable Office Cabin for site office usage, document storage 1
and management.
Establish worker's living quarters, stores, site facilities and removal upon completion work. 1
This include survey and first aid outfit.
- Quarters / homestay / hotel (RM40/night @ 30 days) 6
- Travel daily (RM0.15 @ 20km/day @ 25working days) 6
Allow for mobilization and demobilization of transport to and from site to all plant, 1
equipments and labour necessary for the execution of the works including all duties and
insurances, etc. and providing for the temporary crossing and drainage necessary for proper
execution of works.

Provide safety precautions to ensure the health and safety of Contractor's staff and labour. 1
This include providing personal protection equipment (PPE), medical kit, portable fire
extinguisher etc. based on HIRARC assessment.

The employment of competent Site Safety and Health Supervisor for the entire duration of 9
the construction period to be stationed at site. This include report to summarize occurences,
accidents and safety performance.

The employment of competent authorized gas tester to ensure tank in safe condition to work. 1
This include carry out air testing for toxic, flammable gas and fumes and oxygen adequacy
before access to the confined area of work.

Provide test to verify welding condition and check leakage for each unit tank. 3

TOTAL SECTION A

Cut, remove and terminate Reactor 1 gas pipeline till main gas pipeline. The gas pipeline 1
terminate
Dispose any using 8 inch
liquid, ID stud
sludge, solidend flange
or any for HDPE
content c/wthe
inside accessories.
3,600mt tank to assigned area with 1
radius of 300 meter from site.
Erect, maintain and dismantle suitable scarffolding for temporary working platform including 1,200
access
Provideand egress
1 unit around
20tonne tank.
crane for demolish & installation work. The price include 14
-transportation,
Tank Dimension : ID X
insurance,Height : 19.1m
driver, dieselXand
12.8m
other related item. and demolish rooftop & top
-Prepare
Scaffoldworkforces,
vol. : L X Wequipments
X H : 60m X and
1.5mtransportations
X 12.8m to remove 1
portion bioreactor 1 to the designed area with radius of 500 meter from site.
- Lorry with driver, 6 wheels 8 tonne; with driver 14
- Worker; RM100.00/man.day (6 worker) 14
To supply, fabricate, transport and replace MS 1 portion tank plate from top. Any facilities 1
mount
MS plate on top late will install back. Tank spesification: 5,107
-- Material :: MS
πD =plate (6mm=thk) c/w 3 layer anti rust paint
- Ukur
Tank
lilit RM95.00/man.day
Worker;
Diameter
π(19.2m)
: 19.2m
60.3186m
(6 worker) 30
- Plate height & thk : 1.8m X 6mm
-- 1 portion
Plate weight tank: 60.3186m
plate height = 6ft XSECTION
XTOTAL
1.8m B
6mm X 7840kg/m3 = 5,107.29kg
Refer to drawing ………

Dispose any liquid, sludge, solid or any content inside the 800mt tank to assigned area with 1
radius of 300 meter
Erect, maintain from site. suitable scarffolding for temporary working platform including
and dismantle 525
access
Provideand 1 unitegress around
20tonne tank.
crane for demolish & installation work. The price include 14
-transportation,
Tank Dimension : ID X Height
insurance, : 15.54m
driver, X 7.1m
diesel and other related item. and demolish top portion &
-Prepare
Scaffoldworkforces,
vol. : L X Wequipments
X H : 50m X and 1.5mtransportations
X 7m to remove 1
20ft
- Lorry X 6ft
with bottom
driver,plate at holding
6 wheels tankwith
8 tonne; (HT)driver
to the designed area within radius of 500 meter 14
from site.
- Worker; RM100.00/man.day (6 worker) 14
To supply, fabricate, transport and replace MS 2 portion tank plate from top. Tank 2
spesification:
MS plate (1 portion) 10,214
-- Material :: MS
πD =plate
Ukur lilitRM95.00/man.day (6mm=thk)
π(15.5m) 50m c/w 3 layer anti rust paint
Worker;
-- Dimension (6 worker) 30
Plate height & thk : 1.8m X 6mm22ft
Tank : D X h = 50ft X
-To
-1 portion
supply,
Plate weight tank: 50m
plateXtransport
fabricate, height
1.8m X=6mm6ft
and replace 2" X 4"=MS
X 7840kg/m3 C-channel around top plate tank.
5,107.29kg 50
Refer
Refer to
to
-ToPortion drawing
drawing
replace : ………
………
2 portion
supply, fabricate, transport and replace 20ft X 6fft X 9mm MS plate at bottom tank. Tank 2
spesification: TOTAL SECTION C
- Material : MS plate (9mm thk) c/w 3 layer anti rust paint
- Dimension Tank : D X h = 50ft X 22ft
Refer to drawing ………
Dispose any liquid, sludge, solid or any content inside the 560mt tank to assigned area with 1
radius of 300 meter
Erect, maintain from site. suitable scarffolding for temporary working platform including
and dismantle 525
access
Provideand 1 unitegress around
20tonne tank.
crane for demolish & installation work. The price include 14
-transportation,
Tank Dimension : ID X
insurance, Height : 15.54m
driver, X 7.1m
diesel and other related item. and demolish rooftop & top
-Prepare
Scaffoldworkforces,
vol. : L X Wequipments
X H : 50m X and1.5mtransportations
X 7m to remove 1
portion bioreactor 2 to the designed
- Lorry with driver, 6 wheels 8 tonne; with driver area with radius of 500 meter from site. 14
- Worker; RM95.00/man.day (6 worker) 14
To supply, fabricate, transport and replace MS 2 portion tank plate from top. Tank 3
spesification:
MS plate (1 portion) 15,321
-- Material :: MS
πD =plate
Ukur lilitRM95.00/man.day (6mm=thk)
π(15.5m) 50m c/w 3 layer anti rust paint
Worker;
-- Dimension (6 worker) 30
Plate height & thk : 1.8m X 6mm22ft
Tank : D X h = 50ft X
-- 1
To portion
supply,
Plate weight tank: 50m
plateXtransport
fabricate, height
1.8m X=6mm6ft
and replace 2" X 4"=MS
X 7840kg/m3 C-channel around top plate tank.
5,107.29kg 50
Refer
Refer to
to drawing
drawing
- Portionfabricate, ………
………
replace : transport
2 portion and replace 1.5m height spiral stair mount on top plate as per
Supply, 4
drawing ………..
To supply, fabricate, transport and install 6 inch ID HDPE overflow pipe c/w accessories & pipe 10
Material
holder for: GI expanded
each 1.0m. mesh (3' width)
TOTAL SECTION E

TOTAL

To supply, fabricate, transport and replace 20ft X 6fft X 9mm MS plate at bottom tank. Tank 8
spesification:
To supply, fabricate, transport and replace 20ft X 6fft X 9mm MS plate at bottom tank. Tank 8
-spesification:
Material : MS plate (9mm thk) c/w 3 layer anti rust paint
-To
-Refer
supply, fabricate,
Dimension
Material Tank
: MS : D transport
plate X h = 50ft
(9mm
and
thk)Xc/w
replace 2" X 4" MS C-channel around top plate tank.
22ft
3 layer anti rust paint
50
--Clear to
Total drawing
plate (1 ………
portion)
and transfer : (50m X 7.6m)/ = 380to the deisgned area.
Dimension Tank :solid
D X hin=the
50ftdumping
X 22ft pond 24,150
Refer to drawing ………
- Total plate (1 portion) : (50m X 7.6m)/ = 380 CONTIGENCIES
Refer to drawing ………
GRAND TOTAL
Unit Amount
Rate [RM]
[RM]

L.Sum 2,000.00 2,000.00

L.Sum 2,000.00 2,000.00

L.Sum 4,000.00 4,000.00 http://quantitysurveyoronline.com.my/materials-prices.html

L.Sum http://quantitysurveyoronline.com.my/materials-prices.html

month 1,500.00 9,000.00


month 75.00 450.00
L.Sum 10,000.00 10,000.00

L.Sum 3,000.00 3,000.00

Man-month 3,500.00 31,500.00 http://quantitysurveyoronline.com.my/materials-prices.html

L.sum 20,000.00 20,000.00 Based previous contract record

nos. 3,000.00 9,000.00

90,950.00

L.Sum 200.00 200.00


L.Sum 30,000.00 30,000.00
m3 35.00 42,000.00 http://quantitysurveyoronline.com.my/materials-prices.html
days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
nos. -
day 600.00 8,400.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 600.00 8,400.00 http://quantitysurveyoronline.com.my/materials-prices.html
nos. -
kg 5.00 25,535.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 570.00 17,100.00 http://quantitysurveyoronline.com.my/materials-prices.html
142,835.00

L.Sum 30,000.00 30,000.00


m3 35.00 18,375.00 http://quantitysurveyoronline.com.my/materials-prices.html
days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
L.Sum
day 600.00 8,400.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 600.00 8,400.00 http://quantitysurveyoronline.com.my/materials-prices.html
portion
kg 5.00 51,070.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 570.00 17,100.00 http://quantitysurveyoronline.com.my/materials-prices.html
m 30.00 1,500.00 http://quantitysurveyoronline.com.my/materials-prices.html
nos. 3,000.00 6,000.00
152,045.00

L.Sum 30,000.00 30,000.00


m3 35.00 18,375.00 http://quantitysurveyoronline.com.my/materials-prices.html
days 800.00 11,200.00 http://quantitysurveyoronline.com.my/materials-prices.html
nos.
day 600.00 8,400.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 570.00 7,980.00 http://quantitysurveyoronline.com.my/materials-prices.html
portion
kg 5.00 76,605.00 http://quantitysurveyoronline.com.my/materials-prices.html
day 570.00 17,100.00 http://quantitysurveyoronline.com.my/materials-prices.html
m 30.00 1,500.00 http://quantitysurveyoronline.com.my/materials-prices.html
m 1,500.00 6,000.00
m 110.00 1,100.00
178,260.00

TOTAL 564,090.00

nos. 3,000.00 24,000.00 Actual damage hardly to identified due to:-


nos. 3,000.00 24,000.00 a) sludge
Actual at fill in
damage tank to identified due to:-
hardly
b) Last test report on 13 March 2021.
a) sludge at fill in tank
m 30.00 1,500.00
b) Last test report on 13 March 2021.
m3 5.00 120,750.00
CONTIGENCIES 49,500.00
GRAND TOTAL 789,875.00
Settling Size

ukur lilit C 47.87787 m 157.0796 ft W 1.8288 m 6 ft


height h 6.7056 m 22 ft 160 L 6.096 m 20 ft
diameter D 15.24 m 50 ft Thk 0.006 m 0.25 ft
radius r 7.62 m 25 ft 0.06689 m3
volume v 1223.2 m3 43196.9 524.4191 kg
2600 rm
tank portion heght 4.5 no 4.957867 rm/kg
27
22.5 7.1 23.29396
5.176436
CRANE
Plate thickness (t) a. Max Weight = kg
6 mm 30 ton
0.006 m
b. Period = 2 month

H= 6 ft c. Price = RM15,000.00 /month


1.8288 m = RM30,000.00

SCAFFOLDING
D= 15.2 m a. Price = RM35,000.00

Mild Steel Density (ρ) 7,840 kg/m3


Mild Steel Price (P) RM7.00 /kg
Sand Blasting Work RM0.00 /m2 CUCI TANGKI
Painting Work (2 Side) RM0.00 /m2 Cuci Tangki = RM8.00 /m3

TOP PLATE a. Tank Capacity = 3600 m3


a. Ukur Lilit = πD b. Price = RM28,800.00
= 48 m2
Labour Work + Equiment
b. Plate = (a)*H*t RM80.00 / head/day
= 48 1.8288 0.006
= 0.52 m3 g. Head = 5 head
h. Period = 1 month
c. Weight = (b)*ρ = 30 days
= 4,107.97 kg i. Price = RM12,000.00

d. Price = (c )*P STAIRS


= RM28,755.77

SAND BLASTING & PAINTING


e. Area = (a)*H
= 87.3292386023 m2
Channel = 150 X 75 X 9.36
f. Price = RM0.00 Mild Steel Price (P) RM8.00 /kg
Mild Steel Density (ρ) 7,850 kg/m3
S H= 12.8 m
Labour Work + Equiment
RM80.00 / head/day ϴ= 45 °

g. Head = 5 head a. Slope, S = H/(Sin ϴ)


h. Period = 1 month = 19.13 m
= 30 days
i. Price = RM12,000.00 b. Weight = 358.10 kg
c. Price = RM2,864.80
GRAND TOTAL = RM40,755.77
0.2 m
0.61 m
t= 6 mm
d. Plate = 0.11 m3
e. Weight = 900.99 kg
f. Price = RM7,207.92

Pipe price RM120.00 /m

g. Up Stairs = 64 step
h. height = 64 m
i. Weight = 599.04 kg
j. Price = RM4,792.32
k. Pipe handrill = RM2,295.52

Gand Price Stair = RM17,160.56

RAILING

MS plate
1m 2 mm

19.1 m

Channel = 150 X 75 X 9.36


Horizontal
a. Ukur Lilit = 60.00 m
b. Volume = 0.061 m3
c. Weight = 478.57 kg
d. Price = RM3,828.57

Vertical
a. Point = 60
b. Volume (1) = 0.001 m3
Volume = 0.061 m3
c. Weight = 478.57 kg
d. Price = RM3,828.57

Handrill
a. Price = RM6,600

GRAND HANDRILL = RM14,257.63