Laporan Harian (21 March 2022)
Laporan Harian (21 March 2022)
I. CIVIL WORKS
1. Upper Headrace Tunnel Area
a. Adit 3 Area
- Upstream Activity :
● Cleaning Area
- Downstream Activity :
● Backfill Grouting in Block S40-S39(PT.0+464.000 - PT.0+446.000)
- Labour :
1 Person Site Engineer (Chinese)
1 Person Security
1 Person Worker (Chinese)
10 People Worker (local)
1 Person Water Pump Operators
- Equipment :
● Welding Machine : 1
● Grouting Machine : 1
● All Equipment Standby
b. Adit 2 Area
- Activity :
● Breaker the soil for install H-beam 125
● Dewatering
- Labour :
1 Person Site Engineer (Chinese)
1 Person Skilled (Chinese)
8 People Worker (local)
1 Person Hse
1 Person Security
- Equipment :
● Waterpump : 4
● Truck Mixer : 1
● Concrete Pump : 1
- Labour :
● 1 Person Supervise (Chinese)
● 1 Person HSE (local)
● 1 Person Worker (Local)
- Equipment :
● Water pump : 4
- Labour :
● 1 Persons HSE (local)
● 1 Person Worker (Chinese)
● 15 People Worker (Local)
● 1 Person Operator Crane (local)
● 1 Person Driver (Local)
- Equipment :
● Water pump : 16
● Fan Blower (15kw) : 1
● Mini Excavator : 1
● Dump Truck : 1
● Drilling Machine : 1
- Labour :
● 1 Person Supervisor (Chinese)
b. Tailrace Outlet
- Activity :
● Pouring Concrete Slab
V = 16 m3
- Labour :
● 1 Person Supervisor (Chinese)
● 4 Persons Worker (Chinese)
● 23 People Worker (Local)
● 2 Persons Operator Pump
● 1 Person Electrical
- Equipment :
● Dump Truck : 1
● Excavator : 1
● Water Pump : 3
● Welding Machine : 1
● Concrete Pump : 1
● Truck Mixer : 1
● Concrete Vibrator : 1
5. Regulating DAM
- Activity :
● There’s No Activity at The Other Area
- Labour :
● 1 Person Security
- Equipment :
● All Equipment Standby
6. Power House
- Activity :
● Cutting and curing silica concrete at assembly bay El. 100,26
● Preparation of toilet facilities at substation control building
● Repair plastering and putty powder at canteen outer wall
● Security fence works at switchyard
● Asphalt waterproofing membrane at canteen roof El. 105,80 (2nd layer)
- Labour :
● 1 Person Supervisor (Chinese)
● 1 Person Assistant Supervisor (Chinese)
● 3 Persons Skilled (Chinese)
● 30 People Worker (Local)
● 12 People Multifab worker
● 1 Persons Operator (Local)
● 1 Person HSE Civil (Local)
- Equipment :
● Welding Machine : 2
● Excavator : 1
- Labour :
● 1 Person Engineer (Chinese)
● 3 People Assistant Lab (Local)
b. Laboratory Civil
- Activity :
● Monitoring Compression strength test age 28 days of wet shotcrete sampled
supporting temporary collapse horizontal penstock tunnel
● Monitoring Compression strength test age 7 days of concrete sampled type B
(C-20) slope concrete #17 tailrace open chanel
● Monitoring Compression strength test age 7 days of concrete sampled type A
(C-30) slab concrete right levee outlet structure tailrace tunnel
● Monitoring Compression strength test age 28 days of concrete sampled type
B(C-20) drainage ditch concrete right levee Downstream Regulating Dam
- Labour :
● 1 Person Engineer (Chinese)
● 3 People Assistant Lab (Local)
- Labour :
● 1 Person Engineer (Chinese)
● 6 People Worker (Local)
9. Others Condition
a. Weather
- Morning : Sunny
- Noon : Cloudy
- Afternoon : Cloudy
b. Supervisor on Duty
● Puthi G Novanti
● Ujang Suryana
● Riki Kurniawan
● Gilang Yulianto
● Adi Maulana
● Andrew Bryano Kermite
● Adlin F Bangun
● Dhynna Annisa B
● M Ihsan
● A Habibullah Bayumarta
● Insani Qori Aina
● Agung Anugrahito
● Telly Catur
● Rifky Prabowo
● Dirga Wahyu
● Farid Faris
● Andry Reinhad
10.Documentation Photograph
No Activity
2. Surge Shaft
No Activity
3. Tailrace Open Channel
No Activity
5. Power House
Silica concrete placement class B at assembly bay El. 100,20 – 100,26 with
estimate ±7,00 cu.m
Preparation of toilet facilities at substation control building
Repair plastering and putty powder at canteen outer wall
Security fence works at switchyard
Install formwork for cement mortar facing (t = 3 cm) at Silo #1 El. 66,00 –
72,50
6. Parakan Kondang Access Road
Repair Crack
7. QA/QC Civil Works
a. Batching Plant
Monitoring sampling fresh concrete type A (C-30) slab concrete left levee
outlet structure tailrace tunnel
Monitoring sampling fresh concrete type B (C-20) slope concrete #17 stage
6th left & right levee tailrace open chanel
Monitoring sampling fresh concrete type B (C-20) with silica fume second
concrete the floor power house
b. Laboratory Civil
DAILY REPORT
Contractor : SINOHYDRO-PP
6 Silo 1 No Activities
8 Silo 3 No Activities
Workshop / Warehouse /
9 No Activities
Regulating Dam / Tailrace
Inspection Activities
6 Silo 1 No Activities
7 Silo 2 No Activities
8 Silo 3 No Activities
Workshop / Warehouse /
10 No Activities
Regulating Dam
Documentation
Installation of fire alarm box at Silo 2 Wiring of cable at Silo 2 Powerhouse El. Installation of conduit pipe at silo 2 el
Powerhouse El. 77.00 72.50 72.50
Installation of fire alarm box at Silo 2 Wiring of cable at Silo 2 Powerhouse El. Installation of conduit pipe at silo 2 el
Powerhouse El. 77.00 72.50 72.50
Documentation