DAILY REPORT

JATIGEDE HEPP PROJECT 2 x 55 MW


Monday / March 21, 2022

I. CIVIL WORKS
1. Upper Headrace Tunnel Area
a. Adit 3 Area
- Upstream Activity :
● Cleaning Area

- Downstream Activity :
● Backfill Grouting in Block S40-S39(PT.0+464.000 - PT.0+446.000)

- Labour :
1 Person Site Engineer (Chinese)
1 Person Security
1 Person Worker (Chinese)
10 People Worker (local)
1 Person Water Pump Operators

- Equipment :
● Welding Machine : 1
● Grouting Machine : 1
● All Equipment Standby

b. Adit 2 Area
- Activity :
● Breaker the soil for install H-beam 125
● Dewatering

- Labour :
1 Person Site Engineer (Chinese)
1 Person Skilled (Chinese)
8 People Worker (local)
1 Person Hse
1 Person Security

- Equipment :
● Waterpump : 4
● Truck Mixer : 1
● Concrete Pump : 1

2. Horizontal Penstock Tunnel Area


- Horizontal Penstock (Downstream) Area :
● Dewatering

- Labour :
● 1 Person Supervise (Chinese)
● 1 Person HSE (local)
● 1 Person Worker (Local)

- Equipment :
● Water pump : 4

- Horizontal Penstock (Upstream) Area :


● Mucking after Blasting
● Dewatering

- Labour :
● 1 Persons HSE (local)
● 1 Person Worker (Chinese)
● 15 People Worker (Local)
● 1 Person Operator Crane (local)
● 1 Person Driver (Local)

- Equipment :
● Water pump : 16
● Fan Blower (15kw) : 1
● Mini Excavator : 1
● Dump Truck : 1
● Drilling Machine : 1

3. Upper Surge Shaft


- Activity :
● No Activity

- Labour :
● 1 Person Supervisor (Chinese)

4. Tailrace Tunnel and Open Channel


a. Tailrace Open Channel
- Activity :
● Pouring Concrete Cyclopean Reight and Left Wall Stage 6 (v=18m³)
● Cleaning Area

b. Tailrace Outlet
- Activity :
● Pouring Concrete Slab
V = 16 m3

- Labour :
● 1 Person Supervisor (Chinese)
● 4 Persons Worker (Chinese)
● 23 People Worker (Local)
● 2 Persons Operator Pump
● 1 Person Electrical

- Equipment :
● Dump Truck : 1
● Excavator : 1
● Water Pump : 3
● Welding Machine : 1
● Concrete Pump : 1
● Truck Mixer : 1
● Concrete Vibrator : 1
5. Regulating DAM
- Activity :
● There’s No Activity at The Other Area

- Labour :
● 1 Person Security

- Equipment :
● All Equipment Standby

6. Power House
- Activity :
● Cutting and curing silica concrete at assembly bay El. 100,26
● Preparation of toilet facilities at substation control building
● Repair plastering and putty powder at canteen outer wall
● Security fence works at switchyard
● Asphalt waterproofing membrane at canteen roof El. 105,80 (2nd layer)

- Labour :
● 1 Person Supervisor (Chinese)
● 1 Person Assistant Supervisor (Chinese)
● 3 Persons Skilled (Chinese)
● 30 People Worker (Local)
● 12 People Multifab worker
● 1 Persons Operator (Local)
● 1 Person HSE Civil (Local)

- Equipment :
● Welding Machine : 2
● Excavator : 1

7. QA/QC Civil Works


a. Batching Plant
- Activity :
● Monitoring sampling fresh concrete type A (C-30) slab concrete left levee
outlet structure tailrace tunnel
● Monitoring sampling fresh concrete type B (C-20) with silica second concrete
the floor power house
● Monitoring sampling fresh concrete type A (C-30) wall concrete temporary
supporting collapse horizontal penstock tunnel

- Labour :
● 1 Person Engineer (Chinese)
● 3 People Assistant Lab (Local)

b. Laboratory Civil
- Activity :
● Monitoring Compression strength test age 28 days of wet shotcrete sampled
supporting temporary collapse horizontal penstock tunnel
● Monitoring Compression strength test age 7 days of concrete sampled type B
(C-20) slope concrete #17 tailrace open chanel
● Monitoring Compression strength test age 7 days of concrete sampled type A
(C-30) slab concrete right levee outlet structure tailrace tunnel
● Monitoring Compression strength test age 28 days of concrete sampled type
B(C-20) drainage ditch concrete right levee Downstream Regulating Dam

- Labour :
● 1 Person Engineer (Chinese)
● 3 People Assistant Lab (Local)

8. Parakan Kondang Access Road


- Activity :
● Repair Crack with Mortar

- Labour :
● 1 Person Engineer (Chinese)
● 6 People Worker (Local)

9. Others Condition
a. Weather
- Morning : Sunny
- Noon : Cloudy
- Afternoon : Cloudy

b. Supervisor on Duty
● Puthi G Novanti
● Ujang Suryana
● Riki Kurniawan
● Gilang Yulianto
● Adi Maulana
● Andrew Bryano Kermite
● Adlin F Bangun
● Dhynna Annisa B
● M Ihsan
● A Habibullah Bayumarta
● Insani Qori Aina
● Agung Anugrahito
● Telly Catur
● Rifky Prabowo
● Dirga Wahyu
● Farid Faris
● Andry Reinhad
10.Documentation Photograph

1. Upper Headrace Tunnel


a. Adit III

Backfill Grouting in Block S40-S39(PT.0+464.000 - PT.0+446.000)


b. Adit II

Breaker the soil for install H-beam 125


1. Horizontal Penstock Tunnel
a. Downstream

No Activity
2. Surge Shaft

No Activity
3. Tailrace Open Channel

Pouring Concrete Slab (v=16m³)


Pouring Concrete Cyclopean Reight and Left Wall Stage 6 (v=18m³)
4. Regulating DAM

No Activity
5. Power House

Silica concrete placement class B at assembly bay El. 100,20 – 100,26 with
estimate ±7,00 cu.m
Preparation of toilet facilities at substation control building
Repair plastering and putty powder at canteen outer wall
Security fence works at switchyard

Install formwork for cement mortar facing (t = 3 cm) at Silo #1 El. 66,00 –
72,50
6. Parakan Kondang Access Road

Repair Crack
7. QA/QC Civil Works
a. Batching Plant

Monitoring sampling fresh concrete type A (C-30) slab concrete left levee
outlet structure tailrace tunnel
Monitoring sampling fresh concrete type B (C-20) slope concrete #17 stage
6th left & right levee tailrace open chanel
Monitoring sampling fresh concrete type B (C-20) with silica fume second
concrete the floor power house
b. Laboratory Civil

Monitoring Compression strength test age 7 days of concrete sampled type


A (C-30 slab concrete left levee outlet structure tailrace tunnel
Monitoring Compression strength test age 28 days of concrete sampled type
A (C-30) coloumb concrete second stage outlet structure tailrace tunnel
Monitoring Compression strength test age 28 days of concrete sampled type
B (C-20) drainage ditch concrete right levee Downstream Regulating Dam
CONSTRUCTION SUPERVISION TEAM
JATIGEDE HEPP PROJECK (2x55 MW)

DAILY REPORT

DAY / DATE : Monday / 21 March 2022

Contractor : SINOHYDRO-PP

Owner : PT PLN (Persero) UIP JBT I

Consultant : PT PLN ENJINIRING


Contruction Activities

NO Location Activities Remark

1 Switchyard Area - Continue wiring of cable of new CT at SST bay Switchyard

- Wiring of cable of protection panel & control panel at Electrical


Substation and Control
Room Substation Control Building
2 Building / Diesel
- Wiring of cable of panel at Emergency Diesel Building
Generator Building
- Replace the switch with DC powered dan wiring termination

Power House EL 100.2 /


- Installation of conduit and lighting at Auxiliary Powerhouse El.
3 Assembly Bay / Outdoor
100.20
Area

4 Power House EL 104.50 No Activities

5 Power House EL 93.50 No Activities

6 Silo 1 No Activities

- Installation of fire alarm box at Silo 2 Powerhouse El. 77.00


- Continuity control/instrument cable at Silo 2 El. 77.00 and
7 Silo 2 72.50
- Wiring of cable at Silo 2 Powerhouse El. 72.50
- Installation of conduit pipe at Silo 2 El. 72.50

8 Silo 3 No Activities

Workshop / Warehouse /
9 No Activities
Regulating Dam / Tailrace

Inspection Activities

NO Location Activities Remark

- Individual test : SST ( PI test) at Switchyard


1 Switchyard Area - Individual Test : Insulation resistance and voltage ratio all tap
changer at SST

Substation and Control


2 Building / Diesel No Activities
Generator Building

Power House EL 100.2 /


3 Assembly Bay / Outdoor No Activities
Area

4 Power House EL 104.50 No Activities

5 Power House EL 93.50 No Activities

6 Silo 1 No Activities

7 Silo 2 No Activities

8 Silo 3 No Activities

9 Power House No Activities

Workshop / Warehouse /
10 No Activities
Regulating Dam
Documentation

Individual Test : Insulation resistance


Individual test : SST ( PI test) at Continue wiring of cable of new CT at
and voltage ratio all tap changer at
Switchyard SST bay Switchyard
SST

Individual Test : Insulation resistance


Individual test : SST ( PI test) at Continue wiring of cable of new CT at
and voltage ratio all tap changer at
Switchyard SST bay Switchyard
SST
Documentation

Installation of fire alarm box at Silo 2 Wiring of cable at Silo 2 Powerhouse El. Installation of conduit pipe at silo 2 el
Powerhouse El. 77.00 72.50 72.50

Installation of fire alarm box at Silo 2 Wiring of cable at Silo 2 Powerhouse El. Installation of conduit pipe at silo 2 el
Powerhouse El. 77.00 72.50 72.50
Documentation

Wiring of cable of protection panel &


Wiring of cable of panel at Replace the switch with DC powered
control panel at Electrical Room
Emergency Diesel Building dan wiring termination
Substation Control Building

Wiring of cable of protection panel &


Wiring of cable of panel at Replace the switch with DC powered
control panel at Electrical Room
Emergency Diesel Building dan wiring termination
Substation Control Building
Documentation

Installation of conduit and lighting at Continuity control/instrument cable at


Auxiliary Powerhouse El. 100.20 Silo 2 El. 77.00 and 72.50

Installation of conduit and lighting at Continuity control/instrument cable at


Auxiliary Powerhouse El. 100.20 Silo 2 El. 77.00 and 72.50