Updated SOW REV 07
Updated SOW REV 07
2. WORK SCHEDULE 2
3. SCOPE OF WORK 2
4. RESOURCES 3
7. GENERAL REQUIREMENTS 5
8. CONTRACT PAYMENT 7
9. ENCLOSURES/ATTACHMENTS 8
2. WORK SCHEDULE:
2.1. The start date of this contract January 1, 2021 (01/01/2021)
2.2. The period of the contract shall be three years from starting date of this contract.
3. SCOPE OF WORK
This scope of work together with relevant drawings, documents, and applicable Saudi
Aramco Engineering Standards constitute the project basis for installation of a new
Divider Wall for sea water canal at plant 35 in Ras Tanura Refinery.
Sea water canal is identified as one of the critical assets. Failure of a critical asset may
lead to a business interruption. Currently, 2,132 ft (650 meters) long portion of divider
wall located between the sea water intake and return is showing concrete deterioration
and rebar corrosion.
To extend useful service life of the sea water canal system without operational
interruption; the proposal is to fabricate a precast concrete wall panels and anchoring
them in place using divers. This scheme will eliminate the need to divert or control
water level in the canal, allowing construction to proceed un-interrupted.
3.1. Drawings
Following is the list of sketches and drawings included with this package.
Drawing No. Title
CIVIL-SK-01 Sea Water Canal – Plan Showing Overall Scope
CIVIL-SK-02 Sea Water Canal - Section & General Notes
CIVIL-SK-03 New Divider Wall – At Intake / Return
CIVIL-SK-04 New Divider Wall – At Settling Basin
CIVIL-SK-05 New Divider Wall – At Low Headroom Pipe Crossing
CIVIL-SK-06 Hilti RE-500 Installation Instructions
Unless noted otherwise, all design and engineering work shall be performed by Contractor
in accordance with the latest edition in effect of the following industry codes, standards
and specifications
Page | 2
3.3.1. Refer to CIVIL-SK-01 for Sea Water Canal layout and overall scope of the NEW
wall
3.3.2. CONTRACTOR shall perform topographic survey and develop require
engineering work to obtain the as-built condition of the divider wall, including
wall height measured from both sides, wall thickness at top, wall thickness at
the base, and alignment.
3.3.3. Based on the as-built conditions, CONTRACTOR shall prepare precast
concrete panels fabrication drawings. The attached drawings (SK-03, 04, and
05) show the panel thickness, minimum reinforcement and proposed anchorage
detail with maximum of 1 meter long of each pre-cast panel . Contractor shall
not increase the wall thickness without first getting approval from Saudi Aramco
representative. All other details can be adjusted as needed. Final drawings
showing dimensions, reinforcements, anchoring detail of the new wall to
Saudi Aramco: Company General Use
Page | 3
Page | 4
3.3.25. Saudi Aramco inspection representative shall witness and approve all
concrete pouring and tests.
3.3.26. CONTRACTOR shall provide testing result for mix the concrete to Saudi
Aramco for review and approval .
3.3.27. CONTRACTOR shall provide red line drawings for the installed precast walls.
The markings have to be done in sketch CIVIL-SK-01.
4. RESOURCES:
4.1. Resources To Be Supplied By The CONTRACTOR:
4.1.1. Manpower:
4.1.1.1. CONTRACTOR shall supply all management, supervision, skilled labor,
technical and professional services, scheduling, reporting,
transportation and handling for all personnel, equipment and materials
to carry-out the Work as per the scope of work, applicable Codes,
SAUDI ARAMCO Engineering Procedures and Engineering Standards to
the satisfaction of SAUDI ARAMCO.
4.1.1.2. CONTRACTOR shall supply certified divers equipped with all diving
equipment and tools that ensure safe handling and execution
throughout the execution for this project .
4.1.2. Materials:
4.1.2.1. CONTRACTOR shall provide materials required for this project are
listed below. All the material shall be supplied by the Contractor. The
Contractor is also responsible for construction equipment, and all consumable
items such as screws, tape, paint brushes, etc… to complete this project.
Page | 6
7. GENERAL REQUIREMENTS
7.1. General
7.1.1. The terms and conditions of SAUDI ARAMCO Contract shall be applied. The
CONTRACTOR shall read the Contract and comply with all rules & stipulations.
7.1.2. The CONTRACTOR shall coordinate with SAUDI ARAMCO Representative in
order to start, execute and complete the work in safe and secure environment.
7.1.3. The CONTRACTOR shall comply with the government and SAUDI ARAMCO
policies, regulations and guidelines at all time.
7.1.4. CONTRACTOR shall comply with safety rules governed by “SAUDI ARAMCO
Safety Handbook” at all time.
Page | 8
8. CONTRACT PAYMENT
8.1. The CONTRACTOR shall submit his bid as per below breakdown:
Approved by:
Naimi, Mouhnad A, ESU SUPVR.
Refinery Maintenance Department /
Utility Division
______________________________
Page | 10