This weekly safety report summarizes safety metrics and work hours for a construction project from August 5-11, 2019. There were 10 workers who worked a total of 342 hours during this period. The project has gone 39 consecutive work days without an accident. Daily work hour logs are provided for each worker from August 3-8.
This weekly safety report summarizes safety metrics and work hours for a construction project from August 5-11, 2019. There were 10 workers who worked a total of 342 hours during this period. The project has gone 39 consecutive work days without an accident. Daily work hour logs are provided for each worker from August 3-8.
This weekly safety report summarizes safety metrics and work hours for a construction project from August 5-11, 2019. There were 10 workers who worked a total of 342 hours during this period. The project has gone 39 consecutive work days without an accident. Daily work hour logs are provided for each worker from August 3-8.
Office : Jl. Deltasari Indah AX-19, Wedoro, Waru, Sidoarjo JawaTimur, Indonesia 61256 Telp : 031-7427299 Fax : 031-7427299 Web : www.bintangwahanatata.com Email: pt.bintangwahanatata@gmail.com SAFETY RECORD PeriodeMinggu : PERIODE : 05 AGT 2019 - 11 AGT 2019 Weekly Period JumlahTenagaKerja : 10 ORANG Number Of Workers Jumlah Jam KerjadariAwalProyek : 342 JAM Total Work Hours From Project Start JumlahHariKerjatanpaKecelakaan : 39 HARI Total Work Days Without Accident SAFETY SCORE : 180 HARI 39 HARI TARGET REALISASI
START AWAL PROYEK : 1 JULI 2018
FINISH PROYEK : 20 DESEMBER 2019 TODAY DATE :11 AGUSTUS 2019
PERHITUNGAN JAM KERJA
05 AGUSTUS 2019 : 08.00 – 16.00 ( 7 JAM ) 06 AGUSTUS 2019 : 08.00 – 18.00 ( 9 JAM ) 07 AGUSTUS 2019 : 08.00 – 18.00 ( 9 JAM ) 08 AGUSTUS 2019 : 08.00 – 18.00 ( 9 JAM ) 09 AGUSTUS 2019 : 08.00 – 22.00 ( 12 JAM ) 10 AGUSTUS 2019 : 08.00 – 18.00 ( 9 JAM )