Professional Documents
Culture Documents
Install CH 3
Install CH 3
1
Outline
Design Procedures
2
Terminology and definitions
Ampacity: current carrying capacity of electric
conductors expressed in amperes.
Appliance: utilization equipment.
Branch circuit: the circuit conductor between the
final over current device protecting the circuit
and the outlet(s).
Demand factor: the ratio of the maximum demand
of a system, or part of a system, to the total
connected load of a system or the part of the system
under consideration.
3
Feeder: all circuit conductors between the service
equipment, or the generator switchboard of an
isolated plant, and the final branch circuit over
current device.
Ground: a conductor connection, whether intentional
or accidental, between an electric circuit or
equipment and the earth, or to some conducting body
that serves in place of the earth.
Lighting outlet: an outlet intended for direct
connection of a lamp holder, a light fixture, or a
pendant cord terminating in a lamp holder.
4
Outlet: a point on the wiring system at which
current is taken to the utilization equipment
Receptacle: a contact device installed at the outlet
for the connection of a single attachment plug.
Service: the conductor and equipment for
delivering energy from electric supply system to the
wiring system of the premises served.
Switch board: a large panel, frame or assembly of
panels on which are mounted, on the face or
back or both, switches, over current and other
protective devices, buses, any usual instruments.
5
Wiring Design Criteria
Flexibility:- Able to change to suit new conditions or situations
for the provision for expansion.
branch circuitry,
Feeders
Panels/distribution boards
7
Design procedures
steps involved in the electrical wiring design of
any facility.
A. Determine the type and rating of all client furnished
equipments.
8
The electrical loads which can be estimated are:
i. Lighting.
9
Household loads/appliances
10
Cont…
D. Decide the point of service entrance:- type of service run
(1 phase or 3 phase), service voltage, metering location, and
building utilization voltage.
11
Cont…
G. In your plan Locate all electrical apparatus including
receptacles, switches, motors, and other power consuming
apparatus and signal apparatus such as phone outlets,
speakers, microphones, TV outlets, fire and smoke detectors,
and so on.
12
Cont…
I. Prepare the panel schedule (table). This table shows the load
distribution over the three phases and the type of load which is
connected on each circuit.
13
Cont…
14
Branch Circuit Design
Branch circuits are circuits that supplies power from the
distribution board(DB) to the outlets.
It is the circuit conductor between the final overcurrent
device and the outlet(s).
Protective devices:- Fuses, MCBs, Main switch,
15
Cont…
The final circuits can be:
16
Residential wiring system
Guidelines
a. The NEC requires to supply a load of 3w/sq ft in the
building, excluding unfinished spaces such as porches,
garages, and basements.
17
Cont…
c. The NEC requires that at least one 20-amp circuit supply
to be set for laundry outlets.
d. Do not combine receptacles and switches into a single
outlet except where convenience of use dictates high
mounting of receptacles.
e. Circuit the lighting and receptacles so that each room has
parts of at least two circuits.
f. Supply at least one receptacle in the bathroom and one
outside the house.
g. Provide switch control for closet lights (private or
individual).
18
Cont…
h. In bedrooms supply two duplex outlets at each side of the
bed location to accommodate electric blanket, clocks,
radios, lamps, and other such appliances.
19
Non-residential wiring
Guidelines
(a) Schools:-
Lecture Hall
Laboratory
Shop
Assembly
Office
Gymnasium
Swimming Pools
Photographic Labs
20
Cont…
so it is not possible to generalize on branch circuit design
considerations except for the following
22
(b) Office Space
one outlet for every 40 sq ft, or one outlet for every 10 linear
ft of wall space, In larger office spaces, provide one outlet
every 100 to 125 sq ft.
23
(c) Stores.
In stores, good practice requires at least one convenience
outlet receptacle for every 300 sq ft in addition to outlets
required for loads such as lamps, show windows, and
demonstration appliances
24
Load Tabulation
Arranging facts or figures of loads.
While circuiting the loads, a panel schedule is drawn up
which lists:
The circuit numbers
25
Cont…
In calculating panel loads,
(a) Each specific appliance, device, lighting fixture , or other
load is taken at its nameplate rating
26
Schedule for lighting panel
27
Building regulations for switches and sockets
Socket outlets must be mounted at a height above the floor
or work surface so as to minimize the risk of mechanical
damage.
32
The main switchboard shown in the figure below
constitutes a combination of service equipment and feeder
switchboard.
33
34
A residential system power riser diagram
The service entrance cable runs from the local utility
company to the meter socket
35
Riser diagram of a commercial system
• LP-lighting subpanels,
• RP-receptacle panel board
• EP-Emergency panel board
36
Example
Assume a single floor of an office building 10 m X 20 m. Calculate the
required number of panels, circuits for lighting.
Solution
Office space- illumination=300lux from table (EBCS-10)
Total wattage=51*40=2040W
38
Cont…
Receptacles:
we simply take into account the furniture, electronic
equipments that located in that room and the functions of
rooms.
Let’s take total number of receptacles =6(mostly 6
receptacles supplying from one branch ckt ) So, one branch
ckt for socket is required.
39
Cont…
The total no of circuits for lighting plus receptacles
is 2 + 1 = 3 ckts
Total of 4 ckts.
40
Next class
41
Cable Size Design procedure
The correct choice of cable size for any installation
is dependent upon
42
Steps for selection of cable size
1. Determine the design current Ib.
𝐏
Three phases: Ib =
𝟑∗𝐕𝐋
44
If an item of equipment has a pF and ɳ , it will have been
taken into account. Hence:
𝐏
Single phase: Ib =
𝐕𝐩𝐡 ∗𝐏𝐅∗ 𝛈
𝐏
Three phase: Ib =
𝟑∗𝐕𝐋 ∗𝐏𝐅∗ 𝛈
45
(2) Nominal setting of protection:
having determined Ib , we must now select the nominal
setting of protection In, such that In>Ib. This value may be
taken from IEE regulations.
47
48
ii. Grouping (Cg)
When cables are grouped together they impart heat to each
other.
Therefore the more cables there are, the more heat they will
generate, thus increasing the temperature of each cable.
IEEE regulation also gives factors for such groupings of the
same cable sizes.
For the standard values of Cg, see A.1, A.2 and A.3 from
page 85-87 of EBCS-10
49
iii. Protection by BS 3036 fuse and circuit conditions
(Cc )
BS 3036 fuses have a high fusing current In and, as a result,
50
iv. Thermal Insulation (Ci)
Since the purpose of such materials is to limit the transfer of
heat, they will clearly affect the ability of a cable to
dissipate the heat build up within it when in contact with
them.
51
Length of Cable (mm)
in Thermal Insulation Derating Factor(up to
10mm2)
50 0.89
100 0.81
200 0.68
400 0.55
>=500 0.50
52
(4) Current carrying capacity
For each of the above factors , there is a correction factor
(CF) which derates cable current capacity or conversely
increases cable size.
In
Iz
cg c a ci
53
(5) Choice of cable size
Having established Iz of the cable to be used, it now remains
to choose a cable to suit that value.
Cable Sizes,
54
(6) Voltage drop
It is the voltage difference between the voltage measured at
DB and the voltage reaching the load.
for three-phase 400V, the voltage drop should not exceed 20 55V.
According to IEE regulations,
𝒎𝑽
𝑽𝒅 = ∗ 𝑰𝒃 ∗ 𝑳
𝟏𝟎𝟎𝟎
OR Vd = (mV/Am)* I b* L
Vd = voltage drop
Am = amper meter
I b = design current
From table B.2 voltage drop for 4mm2 conductor size = 11mv/A
60
If BS 3036 fuse is chosen for protection, this fuse type requires
correction factor of 0.725.
In = 32 Amp
i. Therefore the required cable rating will be :
Iz = In/CF CF- Correction Factors.
Ca = 1.03, Cf = 0.725
Required cable rating Iz = 32 Amp/1.03 * 0.725= 42.85 Amp.
From Table B.1, 10mm2 conductor carries 57 A. Take 10mm
diameter conductor.
ii. Testing for Voltage drop = (mV/A.m) * Ib * l
actual Voltage drop on cable = 4.4 mv/Am * 30.13A * 10 m
1.326 V
Maximum allowable voltage drop = 3% of 230 V = 6.9V.
61
Since the actual voltage drop is less than the allowable
maximum voltage drop, selected size is 10 mm2.
Observe the conductor size difference in using Circuit
breaker and fuses
62
output kw
eff .
input 3 VI cos
b) I
18.65kw
48.77 A
3 400 0.8 0.69
50 A circuit-breaker of type BS 3871 can use for protection.
then, In = 50 Amp
Load current will be :
→ Iz = In/CF : =Ca = 1( from Table A.4)
Then,
→ Iz = 50 A
Choose 16 mm2cable which is capable of carrying 52 A
63
Testing for Voltage drop:
Maximum voltage drop=2.5% of 400V= 2.5*400/100=10V.
Voltage drop on the cable = (mV/Am) * Ib * L
= 2.3* 48.77 * 100
= 11.22 V which is beyond the allowable
voltage drop.
So,
choose the next cable size, which is 25mm2.
Voltage drop for 25 mm2 = 1.7 * 48.77 * 100 = 8.29 V
Therefore selected size is 25 mm2.
64
when, 50 A BS 3036 fuse can used for protection from table
→ In = 50 A
→ Load current Iz = In / CF = In / Cf
→ Iz = 50 A / 0.725 = 68.966 A
66