Maya Apartment ( 2P+10 Floor)_10 Month RCC Schedule

Structural Drawings Schedule For RCC Date


Task Name Duration Start Finish
RCC WORKS 307 09-Mar-22 09-Jan-23 Sub Structure
Excavation 10 09-Mar-22 19-Mar-22 General Notes, Typical Sections 11-Mar-22
Sub Structure - Footing Foundation 66 20-Mar-22 24-May-22 Foundation Layout & Footing Schedule 13-Mar-22
Super Structure 230 25-May-22 09-Jan-23 Super Structure
1st Floor Slab 20 25-May-22 13-Jun-22 1st Floor Slab Layout & Column,Beam Schedule with Sections 25-Apr-22
2nd Floor Slab 18 14-Jun-22 01-Jul-22 2nd Floor Slab Layout & Column,Beam Schedule with Sections 15-May-22
3rd Floor Slab 18 02-Jul-22 19-Jul-22 3rd Floor Slab Layout & Column,Beam Schedule with Sections 02-Jun-22
4th Floor Slab 18 20-Jul-22 06-Aug-22 4th Floor Slab Layout & Column,Beam Schedule with Sections 20-Jun-22
5th Floor Slab 18 07-Aug-22 24-Aug-22 5th Floor Slab Layout & Column,Beam Schedule with Sections 08-Jul-22
6th Floor Slab 18 25-Aug-22 11-Sep-22 6th Floor Slab Layout & Column,Beam Schedule with Sections 26-Jul-22
7th Floor Slab 18 12-Sep-22 29-Sep-22 7th Floor Slab Layout & Column,Beam Schedule with Sections 13-Aug-22
8th Floor Slab 18 30-Sep-22 17-Oct-22 8th Floor Slab Layout & Column,Beam Schedule with Sections 31-Aug-22
9th Floor Slab 18 18-Oct-22 04-Nov-22 9th Floor Slab Layout & Column,Beam Schedule with Sections 18-Sep-22
10th Floor Slab 18 05-Nov-22 22-Nov-22 10th Floor Slab Layout & Column,Beam Schedule with Sections 06-Oct-22
Terrace Slab 18 23-Nov-22 10-Dec-22 Terrace Slab Layout & Column,Beam Schedule with Sections 24-Oct-22
Mumty & OHT Slab 30 11-Dec-22 09-Jan-23 Mumty & OHT Slab Layout & Column,Beam Schedule with Sections 11-Nov-22