WEEKLY REPORT

SUNSHINE PROJECT

PEMILIK : PT. UNILEVER OLEOCHEMICAL INDONESIA


PROYEK : ANCILLARY FACILITIES
PEKERJAAN : CIVIL
LOKASI : SEI MANGKEI
PELAKSANA : PT. ERA KARYA KONSTRUKSI NUSANTARA
Minggu : V
Tanggal : 11 Februari s/d 17 Februari 2022

Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

PRELIMINARY
A Tenderer shall allow herein the cost related to the items as described in "Scope of Lot 1,00 0,1086% 0,29 0,0310% 0,71 0,0776% 1,00 0,1086%
Works", "Conditions of Contract for Construction (General Conditions, Appendix
to Tender and Particular Conditions)" and elsewhere within this Tender Documents.

B Project Management, Construction/Site Management, Site Supervision and all other Lot 1,00 0,6514% 0,64 0,4188% 0,36 0,2327% 1,00 0,6514%
necesary support personnel. Mobilisation, Maintainance and Demobilisation of Contractor's
Temporary/Site Facilities such as construction access and etc.

C Temporary Utilities (power, lighting, gases, waste disposal/sewage etc.) Lot 1,00 0,3257% 0,29 0,0931% 0,21 0,0698% 0,50 0,1629%
necessary for the timely, safe and proper execution of the Works, including
(but not limited to) all necessary installation, maintenance, removal/reinstatement
upon completion, liaison with local athorities, payment of all fees, charges etc.
as applicable. Communication Facilities, including (but not limited to) all necessary equipment
(including intrinsically safe where required), licences, liaison with local authorities,
fees/charges, or the like.

D Health, Safety and Environmental Facilities, including (but not limited to) all necessary Lot 1,00 0,9546% 0,29 0,2727% 0,21 0,2046% 0,50 0,4773%
personnel protective equipment (PPE) with Client requirement, safety harness,
induction of workers, training, incentive/reward schemes, drug testing, or the like
(including slope stability enhancement). Scaffolding, Access Equipment or the like
(other than already included as direct costs within the unit rates). Erection shall
be supervised by registered competent safety personnel.
COVID-19 PANDEMIC PROTOCOL TO BE FOLLOWED AS PER CLIENT REQUIREMENT

E Housekeeping, including wash ramp and all necessary personnel, equipment, Lot 1,00 0,1086% 0,29 0,0310% 0,07 0,0078% 0,36 0,0388%
containers, removal from site, safe disposal etc. Security, including (but not limited to)
all necessary personnel, administration, time-keeping systems for Contractor's temporary structures,
fences, and the like.
Cut pile to be disposed in authorized disposal external yard

F Documentation (other than already included as direct costs within the unit rates), Lot 1,00 0,1086% 0,29 0,0310% 0,07 0,0078% 0,36 0,0388%
including (but not limited to) all necessary personnel (management already included
above), storage facilities (fire-safe where appropriate), equipment (including
reprographic equipment), database management, or the like.
Progress Monitoring, Control and Reporting, including (but not limited to) daily site
records, progress reports, work schedules, or the like.

G As-built drawings, diagrams, documents, or the like, including endorsement of Lot 1,00 0,2171% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Licensed Surveyor or certification by relevant authority, submission to the Engineer in
three (3) sets of hard copy and three (3) sets of soft copy in USB upon completion
of the Works.
INCLUDING CIVIL, STRUCTURAL & ELECTRICAL AS BUILT DRAWINGS
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

H Surveying Work (including setting out/level of the works and etc.) by Licensed Surveyor. Lot 1,00 0,2171% 0,00 0,0000% 0,30 0,0651% 0,30 0,0651%
Topography Survey (to locate and identify all existing structures built on-site (e.g. storage tanks,
pipe-rack, abandoned piles on-site, etc.) and transpose the information to AutoCAD drawing in
*.dwg format, submit to the Employer and Engineer in both native softcopy (in flash drive) and hardcopy
(in color in A1 size paper)
PILING SET OUT DRAWINGS AND STRUCTURAL FABRICATION DRAWING

I Insurances
Contractors' All Risks (CAR)
Workmen's Compensation (WC) - contractor to quote Lot 1,00 0,2171% 0,14 0,0310% 0,07 0,0155% 0,21 0,0465%

J Contract Document's Stamp Duty Fee "Notaris" (three (3) copies) Lot 1,00 0,0651% 0,14 0,0093% 0,86 0,0558% 1,00 0,0651%

K Any other items not mentioned above, but need to be priced in to fullfill the
requirements as stipulated within this Tender Documents: -

1) Mobilization and demobilization of the eguipment and workers Lot 1,00 0,2171% 0,29 0,0620% 0,07 0,0155% 0,36 0,0776%

ANCILLARY BUILDING (12.00 m x 28.20 m)


A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)
i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm
- Excavation of soft clay & silty soil including disposal from site to contractors own dump area Lot 1,00 1,9048% 0,30 0,5714% 0,70 1,3334% 1,00 1,9048%
and replaced with PCC and engineered soil fill with compaction earth safe bearing capacity >200 N/mm² .
- Soil top up - Granular Subbase (Sirtu) fill 600mm thickness Compacted Throughly with 95% CBR. m3 408,00 3,4110% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
- Surveying final earth level for elevation, record result and built-in drawing the locations. Ls 1,00 0,4343% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

B EXCAVATION
Excavate, get out, part return, fill in, well ram, remainder load and cart away
from site, level, grade and ram bottom, trim sides and including planking
and strutting for foundation, ground beam and ground slab
Under Footing Foundation m3 65,10 0,1838% 31,00 0,0875% 19,00 0,0536% 50,00 0,1411%
Under Ground Beam & Retaining Wall m3 31,86 0,0899% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Concrete Trench m3 124,65 0,3519% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

C Refill Soil
Under Ground Beam & Retaining Wall m3 305,64 0,4314% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Ground Slab m3 146,16 0,2063% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

D Levelling & Compaction


Under Footing Foundation m2 48,10 0,0261% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Ground Beam & Retaining Wall m2 61,90 0,0336% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Ground Slab m2 365,58 0,1985% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Concrete Trench m2 86,67 0,0471% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

E 50mm thick lean concrete Grade K-100 blinding for: -


Foundation, Pilecap, Stump Column, Ground Slab & Structure
Under Footing Foundation m2 48,10 0,0747% 0,00 0,0000% 20,61 0,0320% 20,61 0,0320%
Under Ground Beam & Retaining Wall m2 61,90 0,0961% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Ground Slab m2 365,58 0,5676% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Under Concrete Trench m2 86,67 0,1346% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

F BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Footing Foundation kg 2236,50 0,8013% 670,95 0,2404% 500,00 0,1791% 1170,95 0,4195%
Ground Beam & Retaining Wall kg 3848,00 1,3787% 1154,40 0,4136% 0,00 0,0000% 1154,40 0,4136%
Ground Slab kg 4560,84 1,6341% 1368,25 0,4902% 0,00 0,0000% 1368,25 0,4902%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

Column GroundFloor kg 2083,97 0,7467% 625,19 0,2240% 0,00 0,0000% 625,19 0,2240%
Beam & Fascia First Floor kg 4368,60 1,5652% 1310,58 0,4696% 0,00 0,0000% 1310,58 0,4696%
First Floof Slab kg 5739,12 2,0563% 1721,74 0,6169% 0,00 0,0000% 1721,74 0,6169%
colomn First Floor kg 737,46 0,2642% 221,24 0,0793% 0,00 0,0000% 221,24 0,0793%
Roof Beam & Fascia kg 2961,36 1,0610% 888,41 0,3183% 0,00 0,0000% 888,41 0,3183%
Roof Slab kg 2437,56 0,8734% 731,27 0,2620% 0,00 0,0000% 731,27 0,2620%
Trench kg 3844,80 1,3776% 1153,44 0,4133% 0,00 0,0000% 1153,44 0,4133%

G FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Footing Foundation m2 41,30 0,1569% 20,00 0,0760% 10,00 0,0380% 30,00 0,1140%
Ground Beam & Retaining Wall m2 267,80 1,0177% 40,00 0,1520% 25,00 0,0950% 65,00 0,2470%
Ground Slab m2 10,53 0,0400% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Column GroundFloor m2 148,80 0,5655% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Beam & Fascia First Floor m2 268,11 1,0188% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
First Floor Slab m2 402,48 1,5295% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
colomn First Floor m2 52,56 0,1997% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Roof Beam & Fascia m2 181,62 0,6902% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Roof Floor Slab m2 202,14 0,7682% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Trench m2 603,72 2,2942% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

H CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Footing Foundation m3 11,30 0,4049% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Ground Beam & Retaining Wall m3 22,80 0,8169% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Ground Slab m3 41,57 1,4894% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Column GroundFloor m3 12,67 0,4540% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Beam & Fascia First Floor m3 25,42 0,9108% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
First Floor Slab m3 44,37 1,5898% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
colomn First Floor m3 4,20 0,1505% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Roof Beam & Fascia m3 17,10 0,6127% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Roof Floor Slab m3 22,10 0,7918% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Trench m3 34,20 1,2254% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

I CONCRETE STAIRCASE
Reinforcement Bar kg 316,80 0,1135% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Formwork m2 33,60 0,1313% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Grade K300 Reinforced Concrete m3 3,00 0,1075% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

J FINISHING WORKS
1 Wall (Brick Wall) m2 783,60 2,5524% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
2 Wall Plastering m2 1567,20 2,5524% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
3 Wall Skim Coat (Sika Wall 181 Skim Coat) m2 1960,80 0,7877% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
4 Internal & External Wall Painting m2 1912,00 1,4532% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
6 Aluminium Louver Door, Size 2,2 x 2,5 m unit 2,00 0,3583% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
7 Aluminium Louver Door, Size 1,1 x 2,5 m unit 8,00 0,7166% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
8 Aluminium Louver, Size 3,0 x 0,5 m unit 12,00 0,5863% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
9 Glass Window, Size 3,0 x 1,25 m unit 2,00 0,2443% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
10 Meeting Room Door, Size 1,8 x 2,1 m unit 1,00 0,1231% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
11 Toilet Door, Size 0,8 x 2,1 m unit 3,00 0,1532% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
12 Wash basin c/w accessories (Wastafel Toto LW 246 J) set 1,00 0,0217% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
13 setting Closet c/w accessories (Closet Duduk Toto CW 422) set 2,00 0,1173% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
14 Parameter Fencing, Size 1,9 m (BRC Fence ) lot 1,00 2,1715% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
15 Fencing Door, Size 1,0 x 1,9m unit 2,00 0,0217% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
16 Stair Railing unit 2,00 0,6080% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

17 Steel Grating for Trench m' 66,00 3,7263% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
18 Water Tap (Toto T205MB) nos 3,00 0,0326% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
19 Wall tiles & Floor tiles (Keramik 40x40 Platinum) m2 54,00 0,2638% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
20 Ceiling at 1st floor m2 165,60 0,5933% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

LOADING BAY

A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)


i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm
Excavation of soft clay & silty soil including disposal from site to contractors own dump area Lot 1,00 0,5602% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
and replaced with PCC and engineered soil fill with compaction earth safe bearing capacity >200 N/mm² .
Soil top up - Granular Subbase (Sirtu) fill 600mm thickness Compacted Throughly with 95% CBR. m3 144,00 1,2039% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Surveying final earth level for elevation, record result and built-in drawing the locations. Ls 1,00 0,2714% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

B EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Pile Cap, size 700x700 mm m3 16,32 0,0461% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 m3 96,80 0,2733% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 m3 74,52 0,2104% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

C LEVELLING & COMPACTION


Pile Cap, size 700x700 mm m2 20,30 0,0110% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 m2 322,68 0,1752% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 m2 248,40 0,1348% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

D LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 20,28 0,0315% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 m2 268,90 0,4175% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 m2 248,40 0,3857% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

E BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Slab & Structure
Pile Cap, size 700x700 mm kg 1778,40 0,6372% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 kg 4032,00 1,4446% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 kg 3108,00 1,1136% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x15000 kg 426,24 0,1527% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x12000 kg 346,32 0,1241% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
kg 197,76 0,0709% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

F FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 32,90 0,1250% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 m2 15,84 0,0602% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 m2 13,80 0,0524% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x15000 m2 12,12 0,0461% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x12000 m2 9,96 0,0378% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Permanent Stoper m2 19,44 0,0739% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

G CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Pile Cap, size 700x700 mm m3 5,76 0,2064% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 16800x15000 m3 64,56 2,3132% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Road Slab, Size 13800x15000 m3 49,68 1,7800% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x15000 m3 9,72 0,3483% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Slab, Size 1800x12000 m3 7,80 0,2795% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Permanent Stoper m3 1,94 0,0695% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

H STEEL STRUCTURE
Column 200x150x10 mm (HB 200x200x8x12) kg 3667,20 1,9351% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Beam 200x150x10 mm (WF 200x100x5.5x8) kg 3085,20 1,5543% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Unequal Angle 125x75x8 mm kg 703,20 0,4123% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Chequed Plat 4mm thick m2 57,60 1,2918% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Hollow 100x100x3,8 mm kg 1953,60 1,1454% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Hollow 100x50x3,8mm kg 2004,00 1,1967% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Sagrod dia.10 mm x 1,2 m nos 112,00 0,0580% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Wind Bracing dia. 16 mm x 9 m set 5,00 0,0633% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Metal Sheat Roof Lysaght Spandek Optima 0,4 mm Colorbond m2 378,00 1,8633% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Steel Staircase unit 2,00 0,4343% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

STORM DRAIN

A EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Drain, Size 600 x 600 mm m3 60,48 0,1707% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Drain, Size 450 x 450 mm m3 330,48 0,9329% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Junction box, Size 90 x 900 mm m3 38,40 0,1084% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

B LEVELLING & COMPACTION


Drain, Size 600 x 600 mm m2 60,48 0,0328% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Drain, Size 450 x 450 mm m2 367,20 0,1993% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Junction box, Size 90 x 900 mm m2 38,40 0,0208% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

C LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Drain, Size 600 x 600 mm m2 60,48 0,0939% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Drain, Size 450 x 450 mm m2 367,20 0,5701% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Junction box, Size 90 x 900 mm m2 38,40 0,0596% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

D BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Drain, Size 600 x 600 mm kg 1731,60 0,6204% 519,48 0,1861% 0,00 0,0000% 519,48 0,1861%
Drain, Size 450 x 450 mm kg 10195,20 3,6529% 3058,56 1,0959% 0,00 0,0000% 3058,56 1,0959%
Junction box, Size 90 x 900 mm kg 124,80 0,0447% 37,44 0,0134% 0,00 0,0000% 37,44 0,0134%

E FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Drain, Size 600 x 600 mm m2 226,80 0,8619% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Drain, Size 450 x 450 mm m2 1376,40 5,2304% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Junction box, Size 90 x 900 mm m2 129,60 0,4925% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

F CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Drain, Size 600 x 600 mm m3 20,16 0,7223% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Drain, Size 450 x 450 mm m3 132,24 4,7381% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Junction box, Size 90 x 900 mm m3 20,40 0,7309% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%

Heavy Duty Grating, Size 450 x 600 mm unit 38,00 0,6684% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
Unequal Angle, Sise 3"x 2' x 8 mm
Flat Bar 2,5x 8 mm
Rebar dia 20 mm

Weeping hole every 100 cm nos 309,00 0,1342% 0,00 0,0000% 0,00 0,0000% 0,00 0,0000%
PVC pipe dia 4"

Total 100,0000% 6,6900% 2,4832% 9,1732%

Prepare By : Checked By : Approved By :

Riomo Silalahi
TIME SCHEDULE - ANCILLARY FACILITIES (PT. UNILEVER OLEOCHEMICAL INDONESIA)
Special Economic Zones (SEZ), Block M.N.R.S, HUTA VI, Sei Mangkei
Bosar Maligas - Simalungun, North Sumatera 21183

NO. ITEM BOBOT Januari Feb-22 Mar-22 Apr-22


PROGRESS Week Week Week
3 4 1 2 3 4 1 2 3 4 1 2 3 4
A PRELIMINARY
1 Preliminary Works 3,1912% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279% 0,2279%
100,0000%

B ANCILLARY BUILDING (12.00 m x 28.20 m)


1 TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700) 5,7501% 0,9583% 0,9583% 0,9583% 0,9583% 0,9583% 0,9583%
2 EXCAVATION 0,6256% 0,2085% 0,2085% 0,2085% 88,5650%
3 Refill Soil 0,6377% 0,1275% 0,1275% 0,1275% 0,1275% 0,1275%
4 Levelling & Compaction 0,3052% 0,0610% 0,0610% 0,0610% 0,0610% 0,0610%
5 50mm thick lean concrete Grade K-100 blinding for: - 0,8730% 0,1455% 0,1455% 0,1455% 0,1455% 0,1455% 0,1455%
77,1300%
6 BAR BENDER 11,7586% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690% 1,0690%
7 FORM WORKS 8,2806% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528% 0,7528%
8 CONCRETING 8,4461% 1,6892% 1,6892% 1,6892% 1,6892% 1,6892%
9 CONCRETE STAIRCASE 0,3523% 0,1762% 0,1762%
10 FINISHING WORKS 17,0836% 4,2709% 64,2416%
4,2709% 4,2709% 4,2709%

C LOADING BAY
1 TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700) 2,0355% 0,4071% 0,4071% 0,4071% 0,4071% 0,4071% 52,8647%
2 EXCAVATION 0,5297% 0,2648% 0,2648%
3 LEVELLING & COMPACTION 0,3210% 0,1605% 0,1605%
4 LEAN CONCRETE 0,8347% 0,4173% 0,4173%
43,2603%
5 BAR BENDER 3,5431% 0,8858% 0,8858% 0,8858% 0,8858%
6 FORM WORKS 0,3954% 0,1977% 0,1977%
7 CONCRETING 4,9968% 2,4984% 2,4984%
33,8173%
8 STEEL STRUCTURE 9,9543% 1,2443% 1,2443% 1,2443% 1,2443% 1,2443% 1,2443% 1,2443% 1,2443%

26,8727%
D STORM DRAIN
1 EXCAVATION 1,2121% 0,6060% 0,6060%
21,5923%
2 LEVELLING & COMPACTION 0,2530% 0,1265% 0,1265%
3 LEAN CONCRETE 0,7236% 15,9259% 0,3618% 0,3618%
4 BAR BENDER 4,3180% 11,8488%
1,4393% 1,4393% 1,4393%
5 FORM WORKS 6,5848% 9,1732% 2,1949% 2,1949% 2,1949%
8,2251%
6 CONCRETING 6,9939% 6,6900% 3,4970% 3,4970%
4,6014%
1,1863%
0,0000% 0,5862% 1,3345%

TOTAL 100,0000% 1,1863% 3,4151% 3,6237% 3,6237% 4,0771% 5,6664% 5,2804% 6,9446% 9,4430% 9,6044% 11,3769% 12,8884% 11,4350% 11,4350%
CUMULATIVE 1,1863% 4,6014% 8,2251% 11,8488% 15,9259% 21,5923% 26,8727% 33,8173% 43,2603% 52,8647% 64,2416% 77,1300% 88,5650% 100,0000%
ACTUAL 0,0000% 0,5862% 1,3345% 6,6900% 9,1732%
DEVIATION -1,1863% -4,0153% -6,8906% -5,1588% -6,7527%

Note : The schedule is valid if the good weaher.

Proposed by, Known by, Approved by, Approved by,

Riomo Silalahi, ST Agus Salim Jadi, ST, MT


Site Manager PT. EKKN Project Coordinator PT. EKKN PT. UNILEVER OLEOCHEMICAL INDONESIA
DAILY PROGRESS

Date : Jumat, 11 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLD CLD CLR CLR CLR CLR CLD CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks

Man Power Dokumentasi


No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 0 8
2 Fery Pardosi (SPV) 08:00 17:00 8 0 8
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 0 8
4 M. Luthfi (Logistik) 08:00 17:00 8 0 8
5 M. Ali Akbar (Drafter) 08:00 17:00 8 0 8
6 Heri (Foremen) 08:00 17:00 8 0 8
7 Amansyah (Tukang) 08:00 17:00 8 0 8
8 Mesdi (Tukang) 08:00 17:00 8 0 8
9 Andika (Tukang) 08:00 17:00 8 0 8
10 Hari Mukti (Tukang) 08:00 17:00 8 0 8
11 Ahmadi (Tukang) 08:00 17:00 8 0 8
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 88 0 88
Las Day Cumulative : 88
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 11 21 52%
2 Fabrikasi Besi Pile Cap 3 21 14%
3
4
5
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi
DAILY PROGRESS

Date : Sabtu, 12 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLD CLR CLR CLR CLR CLD CLD CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks

Man Power Dokumentasi


No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 8 16
2 Fery Pardosi (SPV) 08:00 17:00 8 8 16
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 8 16
4 M. Luthfi (Logistik) 08:00 17:00 8 8 16
5 M. Ali Akbar (Drafter) 08:00 17:00 8 8 16
6 Heri (Foremen) 08:00 17:00 8 8 16
7 Amansyah (Tukang) 08:00 17:00 8 8 16
8 Mesdi (Tukang) 08:00 17:00 8 8 16
9 Andika (Helper) 08:00 17:00 8 8 16
10 Hari Mukti (Tukang) 08:00 17:00 8 8 16
11 Ahmadi (Tukang) 08:00 17:00 8 8 16
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 88 88 176
Las Day Cumulative : 176
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 11 21 52%
2 Fabrikasi Besi Pile Cap 6 21 29%
3
4
5
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi
DAILY PROGRESS

Date : Senin, 14 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLD CLR CLR CLR CLR CLR CLD CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks

Man Power Dokumentasi


No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 16 24
2 Fery Pardosi (SPV) 08:00 17:00 8 16 24
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 16 24
4 M. Luthfi (Logistik) 08:00 17:00 8 16 24
5 M. Ali Akbar (Drafter) 08:00 17:00 8 16 24
6 Heri (Foremen) 08:00 17:00 8 16 24
7 Amansyah (Tukang) 08:00 17:00 8 16 24
8 Mesdi (Tukang) 08:00 17:00 8 16 24
9 Andika (Helper) 08:00 17:00 8 16 24
10 Hari Mukti (Tukang) 08:00 17:00 8 16 24
11 Ahmadi (Tukang) 08:00 17:00 8 16 24
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 88 176 264
Las Day Cumulative : 264
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 13 21 62%
2 Fabrikasi Besi Pile Cap 8 21 38%
3
4
5
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi
DAILY PROGRESS

Date : Selasa, 15 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLR CLR CLR CLR CLR CLR CLR CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks

Man Power Dokumentasi


No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 24 32
2 Fery Pardosi (SPV) 08:00 17:00 8 24 32
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 24 32
4 M. Luthfi (Logistik) 08:00 17:00 8 24 32
5 M. Ali Akbar (Drafter) 08:00 17:00 8 24 32
6 Heri (Foremen) 08:00 17:00 8 24 32
7 Amansyah (Tukang) 08:00 17:00 8 24 32
8 Mesdi (Tukang) 08:00 17:00 8 24 32
9 Andika (Helper) 08:00 17:00 8 24 32
10 Hari Mukti (Tukang) 08:00 17:00 8 24 32
11 Ahmadi (Tukang) 08:00 17:00 8 24 32
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 88 264 352
Las Day Cumulative : 352
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 15 21 71%
2 Fabrikasi Besi Pile Cap 9 21 43%
3
4
5
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi
DAILY PROGRESS

Date : Rabu, 16 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLR CLR CLR CLR CLR CLR CLR CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks
18.00 19.00 20.00 21.00 22.00
Man Power Dokumentasi
No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 32 40
2 Fery Pardosi (SPV) 08:00 17:00 8 32 40
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 32 40
4 M. Luthfi (Logistik) 08:00 17:00 8 32 40
5 M. Ali Akbar (Drafter) 08:00 17:00 8 32 40
6 Heri (Foremen) 08:00 17:00 8 32 40
7 Amansyah (Tukang) - - 0 32 32
8 Mesdi (Tukang) 08:00 22.00 13 32 45
9 Andika (Helper) 08:00 17:00 8 32 40
10 Hari Mukti (Tukang) 08:00 17:00 8 32 40
11 Ahmadi (Tukang) 08:00 17:00 8 32 40
12 Arif (Helper) 08:00 17:00 8 32 40
13 Eli (Helper) 08:00 17:00 8 32 40
14 Irgi (Helper) 08:00 17:00 8 32 40
15 Helmi (Tukang) 17:00 22.00 5 0 5
16 Rio (Helper) 17:00 22.00 5 0 5
17 Andi (Helper) 17:00 22.00 5 0 5
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 124 448 572
Las Day Cumulative : 572
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 15 21 71%
2 Fabrikasi Besi Pile Cap 11 21 52%
3 Lantai Kerja Pile Cap 3 21 14%
4
5
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi
DAILY PROGRESS

Date : Kamis, 17 Februari 2022 Wheather : Clear Cloud Rain


Project Name : Sunshine Ancillary Facilities Shift : Day Night
Day CLD CLD CLR CLR CLR CLD CLD CLD CLD CLD
Rainfall Periode
Night
Working Hours
Activity Description 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 Remarks

Man Power Dokumentasi


No Position From To Work s/by Tot. Hrs
1 Riomo Silalahi (SM) 08:00 17:00 8 40 48
2 Fery Pardosi (SPV) 08:00 17:00 8 40 48
3 Masyhuril A. Hafiz (HSE) 08:00 17:00 8 40 48
4 M. Luthfi (Logistik) 08:00 17:00 8 40 48
5 M. Ali Akbar (Drafter) 08:00 17:00 8 40 48
6 Heri (Foremen) 08:00 17:00 8 40 48
7 Amansyah (Tukang) 08:00 17:00 8 32 40
8 Mesdi (Tukang) 08:00 17:00 8 45 53
9 Andika (Helper) 08:00 17:00 8 40 48
10 Hari Mukti (Tukang) 08:00 17:00 8 40 48
11 Ahmadi (Tukang) 08:00 17:00 8 40 48
12 Arif (Helper) 08:00 17:00 8 40 48
13 Eli (Helper) 08:00 17:00 8 40 48
14 Irgi (Helper) 08:00 17:00 8 40 48
15 Helmi (Tukang) 0 5 5
16 Rio (Helper) 0 5 5
17 Andi (Helper) 0 5 5
18
19
20
21
22
23
24
25
26
27
28
29
30
Total Hour 112 572 684
Las Day Cumulative : 684
Work Equipment
No Material/Alat Kerja Qty Unit
1 Mesin Las 1 Unit
2 Mesin Circle 1 Unit
3 Cutting Wheel 1 Unit
4 Kereta Sorong 2 Unit
5
6
7
8
9
10
Volume Activity
No Progress Actual Cumulatif Qty Progress
1 Penggalian Pile Cap 15 21 71%
2 Fabrikasi Besi Pile Cap 15 21 71%
3 Lantai Kerja Pile Cap 3 21 14%
4 Fabrikasi Bekisting Pile Cap 4 21 19%
5 Bowplank Loading Bay
6
7
8
9
10
Heavy Equipment
No Equipment Qty Unit Remark
1
2

Reported By :
PT. ERAKARYA KONSTRUKSI NUSANTARA

Riomo Silalahi