PT UNILEVER OLEOCHEMICAL INDONESIA

SUNSHINE PROJECT
ANCILLARY FACILITIES TENDER

Item Description

A Tenderer shall allow herein the cost related to the items as described in "Scope of
Works", "Conditions of Contract for Construction (General Conditions, Appendix
to Tender and Particular Conditions)" and elsewhere within this Tender Documents.

B Project Management, Construction/Site Management, Site Supervision and all other


necesary support personnel. Mobilisation, Maintainance and Demobilisation of Contractor's Temporary/Site
Facilities such as construction access and etc.

C Temporary Utilities (power, lighting, gases, waste disposal/sewage etc.)


necessary for the timely, safe and proper execution of the Works, including
(but not limited to) all necessary installation, maintenance, removal/reinstatement
upon completion, liaison with local athorities, payment of all fees, charges etc.
as applicable. Communication Facilities, including (but not limited to) all necessary equipment
(including intrinsically safe where required), licences, liaison with local authorities,
fees/charges, or the like.

D Health, Safety and Environmental Facilities, including (but not limited to) all necessary
personnel protective equipment (PPE) with Client requirement, safety harness,
induction of workers, training, incentive/reward schemes, drug testing, or the like
(including slope stability enhancement). Scaffolding, Access Equipment or the like
(other than already included as direct costs within the unit rates). Erection shall
be supervised by registered competent safety personnel.
COVID-19 PANDEMIC PROTOCOL TO BE FOLLOWED AS PER CLIENT REQUIREMENT

E Housekeeping, including wash ramp and all necessary personnel, equipment,


containers, removal from site, safe disposal etc. Security, including (but not limited to)
all necessary personnel, administration, time-keeping systems for Contractor's temporary structures,

fences, and the like.


Cut pile to be disposed in authorized disposal external yard

F Documentation (other than already included as direct costs within the unit rates),
including (but not limited to) all necessary personnel (management already included
above), storage facilities (fire-safe where appropriate), equipment (including
reprographic equipment), database management, or the like.
Progress Monitoring, Control and Reporting, including (but not limited to) daily site
records, progress reports, work schedules, or the like.

G As-built drawings, diagrams, documents, or the like, including endorsement of


Licensed Surveyor or certification by relevant authority, submission to the Engineer in
three (3) sets of hard copy and three (3) sets of soft copy in USB upon completion
of the Works.
INCLUDING CIVIL, STRUCTURAL & ELECTRICAL AS BUILT DRAWINGS

H Surveying Work (including setting out/level of the works and etc.) by Licensed Surveyor.
Topography Survey (to locate and identify all existing structures built on-site (e.g. storage tanks,
pipe-rack, abandoned piles on-site, etc.) and transpose the information to AutoCAD drawing in
*.dwg format, submit to the Employer and Engineer in both native softcopy (in flash drive) and hardcopy
(in color in A1 size paper)
PILING SET OUT DRAWINGS AND STRUCTURAL FABRICATION DRAWING

I Insurances
Contractors' All Risks (CAR)
Workmen's Compensation (WC) - contractor to quote

J Contract Document's Stamp Duty Fee "Notaris" (three (3) copies)

K Any other items not mentioned above, but need to be priced in to fullfill the
requirements as stipulated within this Tender Documents: -

1) Mobilization and demobilization of the eguipment and workers

2)

3)

4) Site Security and IMB

5)

--- END ---


PT UNILEVER OLEOCHEMICAL INDONESIA
SUNSHINE PROJECT SECTION 2
ANCILLARY FACILITIES TENDER ANCILLARY BUILDING - CIVIL & STRUCTURAL
24th Dec 2021

Unit Price (IDR)


No Description Unit Quantity Subtotal (IDR)
Supply Install

ANCILLARY BUILDING (12.00 m x 28.20 m)

A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)


i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm
Excavation of soft clay & silty soil including disposal from site to contractors
own dump area and replaced with PCC and engineered soil fill with Lot 1.00 -
compaction earth safe bearing capacity >200 N/mm² .
Soil top up - Granular Subbase (Sirtu) fill 600mm thickness Compacted m3 408.00 -
Throughly with 95% CBR.
Surveying final earth level for elevation, record result and built-in drawing the Ls 1.00 -
locations.

B EXCAVATION
Excavate, get out, part return, fill in, well ram, remainder load and cart away
from site, level, grade and ram bottom, trim sides and including planking
and strutting for foundation, ground beam and ground slab
Under Footing Foundation m3 65.10 -
Under Ground Beam & Retaining Wall m3 31.86 -
Under Concrete Trench m3 124.65 -

C Refill Soil
Under Ground Beam & Retaining Wall m3 305.64 -
Under Ground Slab m3 146.16 -

D Levelling & Compaction


Under Footing Foundation m2 48.10 -
Under Ground Beam & Retaining Wall m2 61.90 -
Under Ground Slab m2 365.58 -
Under Concrete Trench m2 86.67 -

E 50mm thick lean concrete Grade K-100 blinding for: -


Foundation, Pilecap, Stump Column, Ground Slab & Structure
Under Footing Foundation m2 48.10 -
Under Ground Beam & Retaining Wall m2 61.90 -
Under Ground Slab m2 365.58 -
Under Concrete Trench m2 86.67 -

F BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Footing Foundation kg 2,236.50 -
Ground Beam & Retaining Wall kg 3,848.00 -
Ground Slab kg 4,560.84 -
Column GroundFloor kg 2,083.97 -
Beam & Fascia First Floor kg 4,368.60 -
First Floof Slab kg 5,739.12 -
colomn First Floor kg 737.46 -
Roof Beam & Fascia kg 2,961.36 -
Roof Slab kg 2,437.56 -
Trench kg 3,844.80 -

G FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Footing Foundation m2 41.30 -
Ground Beam & Retaining Wall m3 267.80 -
Ground Slab m4 10.53 -
Column GroundFloor m5 148.80 -
Beam & Fascia First Floor m6 268.11 -
First Floor Slab m7 402.48 -
colomn First Floor m8 52.56 -
Roof Beam & Fascia m9 181.62 -
Roof Floor Slab m10 202.14 -
Trench m12 603.72 -

H CONCRETING
PT UNILEVER OLEOCHEMICAL INDONESIA
SUNSHINE PROJECT SECTION 2
ANCILLARY FACILITIES TENDER ANCILLARY BUILDING - CIVIL & STRUCTURAL
24th Dec 2021

Unit Price (IDR)


No Description Unit Quantity Subtotal (IDR)
Supply Install
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Footing Foundation m3 11.30 -
Ground Beam & Retaining Wall m3 22.80 -
Ground Slab m3 41.57 -
Column GroundFloor m3 12.67 -
Beam & Fascia First Floor m3 25.42 -
First Floor Slab m3 44.37 -
colomn First Floor m3 4.20 -
Roof Beam & Fascia m3 17.10 -
Roof Floor Slab m3 22.10 -
Trench m3 34.20 -

I CONCRETE STAIRCASE
Reinforcement Bar kg 316.80 -
Formwork m2 33.60 -
Grade K300 Reinforced Concrete m3 3.00 -

J FINISHING WORKS
1 Wall (Brick Wall) m2 783.60 -
2 Wall Plastering m2 1,567.20 -
3 Wall Skim Coat (Sika Wall 181 Skim Coat) m2 1,960.80 -
4 Internal & External Wall Painting m2 1,912.00 -
6 Aluminium Louver Door, Size 2,2 x 2,5 m unit 2.00 -
7 Aluminium Louver Door, Size 1,1 x 2,5 m unit 8.00 -
8 Aluminium Louver, Size 3,0 x 0,5 m unit 12.00 -
9 Glass Window, Size 3,0 x 1,25 m unit 2.00 -
10 Meeting Room Door, Size 1,8 x 2,1 m unit 1.00 -
11 Toilet Door, Size 0,8 x 2,1 m unit 3.00 -
12 Wash basin c/w accessories (Wastafel Toto LW 246 J) set 1.00 -
13 setting Closet c/w accessories (Closet Duduk Toto CW 422) set 2.00 -
14 Parameter Fencing, Size 1,9 m (BRC Fence ) lot 1.00 -
15 Fencing Door, Size 1,0 x 1,9m unit 2.00 -
16 Stair Railing unit 2.00 -
17 Steel Grating for Trench m' 66.00 -
18 Water Tap (Toto T205MB) nos 3.00 -
19 Wall tiles & Floor tiles (Keramik 40x40 Platinum) m2 54.00 -
20 Ceiling at 1st floor m2 165.60 -

K OTHERS

Other item not mentioned in the schedule of works but deemed necessary for
the proper completion of the works :
1
2
3

SUBTOTAL SECTION 2 -
Unit Price (IDR)
No Description Unit Quantity
Supply Install

LOADING BAY

A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)


i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm

Excavation of soft clay & silty soil including disposal from site to Lot 1.00
contractors own dump area and replaced with PCC and engineered
soil fill with compaction earth safe bearing capacity >200 N/mm² .
Soil top up - Granular Subbase (Sirtu) fill 600mm thickness m3 144.00
Compacted Throughly with 95% CBR.
Surveying final earth level for elevation, record result and built-in Ls 1.00
drawing the locations.

B EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Pile Cap, size 700x700 mm m3 16
Road Slab, Size 16800x15000 m3 97
Road Slab, Size 13800x15000 m3 75

C LEVELLING & COMPACTION


Pile Cap, size 700x700 mm m2 20
Road Slab, Size 16800x15000 m2 323
Road Slab, Size 13800x15000 m2 248

D LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 20
Road Slab, Size 16800x15000 m2 269
Road Slab, Size 13800x15000 m2 248

E BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Slab & Structure
Pile Cap, size 700x700 mm kg 1,778
Road Slab, Size 16800x15000 kg 4,032
Road Slab, Size 13800x15000 kg 3,108
Slab, Size 1800x15000 kg 426
Slab, Size 1800x12000 kg 346
kg 198

F FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 33
Road Slab, Size 16800x15000 m2 16
Road Slab, Size 13800x15000 m2 14
Slab, Size 1800x15000 m2 12
Slab, Size 1800x12000 m2 10
Permanent Stoper m2 19

G CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Pile Cap, size 700x700 mm m3 6
Road Slab, Size 16800x15000 m3 65
Road Slab, Size 13800x15000 m3 50
Slab, Size 1800x15000 m3 10
Slab, Size 1800x12000 m3 8
Permanent Stoper m3 2

H STEEL STRUCTURE
Unit Price (IDR)
No Description Unit Quantity
Supply Install
Column 200x150x10 mm (HB 200x200x8x12) kg 3,667
Beam 200x150x10 mm (WF 200x100x5.5x8) kg 3,085
Unequal Angle 125x75x8 mm kg 703
Chequed Plat 4mm thick m2 58
Hollow 100x100x3,8 mm kg 1,954
Hollow 100x50x3,8mm kg 2,004
Sagrod dia.10 mm x 1,2 m nos 112
Wind Bracing dia. 16 mm x 9 m set 5
Metal Sheat Roof Lysaght Spandek Optima 0,4 mm Colorbond m2 378
Steel Staircase unit 2

I OTHERS

Other item not mentioned in the schedule of works but deemed


necessary for the proper completion of the works :
1
2

SUBTOTAL SECTION 3
Subtotal (IDR)

-
-
-

-
-
-

-
-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
Subtotal (IDR)
-
-
-
-
-
-
-
-
-
-

-
Unit Price (IDR)
No Description Unit Quantity Subtotal (IDR)
Supply Install

A EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Drain, Size 600 x 600 mm m3 60 -
Drain, Size 450 x 450 mm m3 330 -
Junction box, Size 90 x 900 mm m3 38 -

B LEVELLING & COMPACTION


Drain, Size 600 x 600 mm m2 60 -
Drain, Size 450 x 450 mm m2 367 -
Junction box, Size 90 x 900 mm m2 38 -

C LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Drain, Size 600 x 600 mm m2 60 -
Drain, Size 450 x 450 mm m2 367 -
Junction box, Size 90 x 900 mm m2 38 -

D BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Drain, Size 600 x 600 mm kg 1,732 -
Drain, Size 450 x 450 mm kg 10,195 -
Junction box, Size 90 x 900 mm kg 125 -

E FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Drain, Size 600 x 600 mm m2 227 -
Drain, Size 450 x 450 mm m2 1,376 -
Junction box, Size 90 x 900 mm m2 130 -

F CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -

Foundation, Pilecap, Stump Column, Ground Slab & Structure

Drain, Size 600 x 600 mm m3 20 -


Drain, Size 450 x 450 mm m3 132 -
Junction box, Size 90 x 900 mm m3 20 -

Heavy Duty Grating, Size 450 x 600 mm unit 38 -


Unequal Angle, Sise 3"x 2' x 8 mm
Flat Bar 2,5x 8 mm
Rebar dia 20 mm

Weeping hole every 100 cm nos 309 -


PVC pipe dia 4"

G OTHERS

Other item not mentioned in the schedule of works but deemed


necessary for the proper completion of the works :
1
2
3

SUBTOTAL SECTION 4 -
PT UNILEVER OLEOCHEMICAL INDONESIA
SUNSHINE PROJECT SECTION 5
ANCILLARY FACILITIES TENDER ELECTRICAL WORKS
23th Dec 2021

Unit Rate (IDR) Subtotal


Item Description Unit Quantity
Supply Installation (IDR)

A EQUIPMENT

1 Supply, Delivery, Unload & Install Main Lighting Panel lot 1 Rp -

B CABLE FEEDER

Supply, delivery, layying & termination of power & control cables c/w
1 accessories to the following user:-

Cable from New MSB to Main Lighting Panel


with cable 0.6/1Kv CU/PVC/SWA/PVC 4C X 95 mm2 m 17 Rp -
NYY 1 X 50 mm2 m 19 Rp -
Brass Type Cable Gland Water Proof, IP67 c/w Shroud LS 1 Rp -

C Supply & Installation of Lighting/ Fitting Feature (Anciliary Building)

1 TL8 LED Tube MR Fittings, ( 2 X 16W ) c/w supports & Accessories nos 20 Rp -
with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

2 TL8 LED Tube Weather Proof Fittings, ( 2 X 16W ) c/w supports & Accessories nos 38 Rp -
with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

3 LED Downlight, ( 14W ) c/w supports & Accessories nos 4 Rp -


with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

4 LED Floodlight Weather Proof ( 250w )) c/w supports & Accessories nos 1 Rp -
with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

5 LED Emergency Light c/w supports & Accessories nos 2 Rp -


with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

6 LED Keluar Sign c/w supports & Accessories nos 9 Rp -


with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5 mm2

7 one gang one way Switch c/w supports & Accessories nos 11 Rp -

two gang one way switch c/w supports & Accessories nos 8 Rp -

Notes:
a) Cable Brand: JJ LAPP/Suppreme
b) Cable Gland: Raychem/Peppers/Schlemmer
c) Manufacture Lamp Local: Philips , NIG LITE

D Supply & Installation of Socket Outlet (Anciliary Building)

1 Socket Outlet 16A 1P+N+E c/w supports & Accessories nos 11 Rp -


with cable 0.6/1Kv CU/PVC/PVC 3C X 4mm2

2 Underdesk Socket Outlet 16A 1P+N+E c/w supports & Accessories nos 6 Rp -
with cable 0.6/1Kv CU/PVC/PVC 3C X 4mm2

3 Floor Socket Outlet 16A 1P+N+E c/w supports & Accessories nos 4 Rp -
with cable 0.6/1Kv CU/PVC/PVC 3C X 4mm2
PT UNILEVER OLEOCHEMICAL INDONESIA
SUNSHINE PROJECT SECTION 5
ANCILLARY FACILITIES TENDER ELECTRICAL WORKS
23th Dec 2021

Unit Rate (IDR) Subtotal


Item Description Unit Quantity
Supply Installation (IDR)

Note: a) SSO Brand: Schneider, b) Conduit PVC H impact Brand:Clipsal, EGA


c) Cable Brand: JJ LAPP/Suppreme

E Supply & Installation Air Conditioner and Mechanica Ventilation


(Anciliary Building)

1 Air Conditioner Floor Standing 5.5 HP 380 Volt include Remote Control c/w nos 5 Rp -
supports & Accessories
with cable 0.6/1Kv CU/PVC/PVC 5C X 4mm2
Brand: Daikin

2 Air Conditioner Wall Mounted 3 HP 220 Volt include wire Remote Control c/w nos 5 Rp -
supports & Accessories
with cable 0.6/1Kv CU/PVC/PVC 4C X 6mm2
Brand: Daikin

3 Air Conditioner Wall Mounted 2.5 HP 220 Volt include Remote Control c/w nos 2 Rp -
supports & Accessories
with cable 0.6/1Kv CU/PVC/PVC 4C X 4mm2
Brand: Daikin

4 Air Conditioner Wall Mounted 1 HP 220 Volt include Remote Control c/w nos 1 Rp -
supports & Accessories
with cable 0.6/1Kv CU/PVC/PVC 4C X 4mm2
Brand: Daikin

5 Exhaust Fan 2632m3/h 220 Volt include Adjustable Thermostat c/w supports nos 2 Rp -
& Accessories
with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5mm2
Brand: Kruger

6 Exhaust Fan 454m3/h 220 Volt include Adjustable Thermostat c/w supports & nos 1 Rp -
Accessories
with cable 0.6/1Kv CU/PVC/PVC 3C X 2.5mm2
Brand: Kruger
Notes:
a) Cable Brand: JJ LAPP/Suppreme
b) Cable Gland: Raychem/Peppers/Schlemmer

F Grounding System For (Anciliary Building)

Supply and Installation of Down conductor with CU Cover & Stick Rood dia
5/8'' c/w joint connection & accessories to Equipment as shown/specified in
1 the drawings/specification for the following equipment:-

Grounding Point point 6 Rp -

2 50mm X 3mm Bare Copper Tape (conceal/Underground) LS 1 Rp -

3 Copper Earth Bar c/w Bracket & Accessories, min 8 terminal nos 5 Rp -
(Fixing by countersunk wood screw 1 1/2 X No12 and No.12 wall plug)
Note: Based Plate made of plastic

nos 6 Rp -
4 Heavy Duty Concrete Earth Chamber, 300mm (W) X 300mm (L) X 200mm (D)
Accessories Such cable log, clamp, bracket and others to necessary to
5 complete works as per specification and drawing LS 1 Rp -
PT UNILEVER OLEOCHEMICAL INDONESIA
SUNSHINE PROJECT SECTION 5
ANCILLARY FACILITIES TENDER ELECTRICAL WORKS
23th Dec 2021

Unit Rate (IDR) Subtotal


Item Description Unit Quantity
Supply Installation (IDR)

G Supply & Installation of Cable Ladder HDG Thickness 1.6mm

1 Cable Ladder LS 1 Rp -
2 Cover LS 1 Rp -
3 Support and Hanger LS 1 Rp -
Brand: Elpro, Anugerah Hutama Mandiri

H Others

1 Cable Marking & Tagging LS 1 Rp -

2 Testing & Commissioning LS 1 Rp -

I OTHERS

Other item not mentioned in the schedule of works but deemed necessary
for the proper completion of the works :

SUBTOTAL SECTION 5 Rp -
WEEKLY REPORT
SUNSHINE PROJECT

PEMILIK : PT. UNILEVER OLEOCHEMICAL INDONESIA


PROYEK : ANCILLARY FACILITIES
PEKERJAAN : CIVIL
LOKASI : SEI MANGKEI
PELAKSANA : PT. ERA KARYA KONSTRUKSI NUSANTARA
Minggu : II
Tanggal : 21 Januari s/d 27 Januari 2022

Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

PRELIMINARY
A Tenderer shall allow herein the cost related to the items as described in "Scope of Lot 1.00 0.1086% 0.00 0.0000% 0.14 0.0155% 0.14 0.0155%
Works", "Conditions of Contract for Construction (General Conditions, Appendix
to Tender and Particular Conditions)" and elsewhere within this Tender Documents.

B Project Management, Construction/Site Management, Site Supervision and all other Lot 1.00 0.6514% 0.00 0.0000% 0.50 0.3257% 0.50 0.3257%
necesary support personnel. Mobilisation, Maintainance and Demobilisation of Contractor's
Temporary/Site Facilities such as construction access and etc.

C Temporary Utilities (power, lighting, gases, waste disposal/sewage etc.) Lot 1.00 0.3257% 0.00 0.0000% 0.14 0.0465% 0.14 0.0465%
necessary for the timely, safe and proper execution of the Works, including
(but not limited to) all necessary installation, maintenance, removal/reinstatement
upon completion, liaison with local athorities, payment of all fees, charges etc.
as applicable. Communication Facilities, including (but not limited to) all necessary equipment
(including intrinsically safe where required), licences, liaison with local authorities,
fees/charges, or the like.

D Health, Safety and Environmental Facilities, including (but not limited to) all necessary Lot 1.00 0.9546% 0.00 0.0000% 0.14 0.1364% 0.14 0.1364%
personnel protective equipment (PPE) with Client requirement, safety harness,
induction of workers, training, incentive/reward schemes, drug testing, or the like
(including slope stability enhancement). Scaffolding, Access Equipment or the like
(other than already included as direct costs within the unit rates). Erection shall
be supervised by registered competent safety personnel.
COVID-19 PANDEMIC PROTOCOL TO BE FOLLOWED AS PER CLIENT REQUIREMENT

E Housekeeping, including wash ramp and all necessary personnel, equipment, Lot 1.00 0.1086% 0.00 0.0000% 0.14 0.0155% 0.14 0.0155%
containers, removal from site, safe disposal etc. Security, including (but not limited to)
all necessary personnel, administration, time-keeping systems for Contractor's temporary structures,
fences, and the like.
Cut pile to be disposed in authorized disposal external yard

F Documentation (other than already included as direct costs within the unit rates), Lot 1.00 0.1086% 0.00 0.0000% 0.14 0.0155% 0.14 0.0155%
including (but not limited to) all necessary personnel (management already included
above), storage facilities (fire-safe where appropriate), equipment (including
reprographic equipment), database management, or the like.
Progress Monitoring, Control and Reporting, including (but not limited to) daily site
records, progress reports, work schedules, or the like.

G As-built drawings, diagrams, documents, or the like, including endorsement of Lot 1.00 0.2171% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Licensed Surveyor or certification by relevant authority, submission to the Engineer in
three (3) sets of hard copy and three (3) sets of soft copy in USB upon completion
of the Works.
INCLUDING CIVIL, STRUCTURAL & ELECTRICAL AS BUILT DRAWINGS
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

H Surveying Work (including setting out/level of the works and etc.) by Licensed Surveyor. Lot 1.00 0.2171% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Topography Survey (to locate and identify all existing structures built on-site (e.g. storage tanks,
pipe-rack, abandoned piles on-site, etc.) and transpose the information to AutoCAD drawing in
*.dwg format, submit to the Employer and Engineer in both native softcopy (in flash drive) and hardcopy
(in color in A1 size paper)
PILING SET OUT DRAWINGS AND STRUCTURAL FABRICATION DRAWING

I Insurances
Contractors' All Risks (CAR)
Workmen's Compensation (WC) - contractor to quote Lot 1.00 0.2171% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

J Contract Document's Stamp Duty Fee "Notaris" (three (3) copies) Lot 1.00 0.0651% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

K Any other items not mentioned above, but need to be priced in to fullfill the
requirements as stipulated within this Tender Documents: -

1) Mobilization and demobilization of the eguipment and workers Lot 1.00 0.2171% 0.00 0.0000% 0.14 0.0310% 0.14 0.0310%

ANCILLARY BUILDING (12.00 m x 28.20 m)


A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)
i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm
- Excavation of soft clay & silty soil including disposal from site to contractors own dump area Lot 1.00 1.9048% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
and replaced with PCC and engineered soil fill with compaction earth safe bearing capacity >200 N/mm² .
- Soil top up - Granular Subbase (Sirtu) fill 600mm thickness Compacted Throughly with 95% CBR. m3 408.00 3.4110% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
- Surveying final earth level for elevation, record result and built-in drawing the locations. Ls 1.00 0.4343% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

B EXCAVATION
Excavate, get out, part return, fill in, well ram, remainder load and cart away
from site, level, grade and ram bottom, trim sides and including planking
and strutting for foundation, ground beam and ground slab
Under Footing Foundation m3 65.10 0.1838% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Beam & Retaining Wall m3 31.86 0.0899% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Concrete Trench m3 124.65 0.3519% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

C Refill Soil
Under Ground Beam & Retaining Wall m3 305.64 0.4314% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Slab m3 146.16 0.2063% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

D Levelling & Compaction


Under Footing Foundation m2 48.10 0.0261% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Beam & Retaining Wall m2 61.90 0.0336% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Slab m2 365.58 0.1985% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Concrete Trench m2 86.67 0.0471% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

E 50mm thick lean concrete Grade K-100 blinding for: -


Foundation, Pilecap, Stump Column, Ground Slab & Structure
Under Footing Foundation m2 48.10 0.0747% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Beam & Retaining Wall m2 61.90 0.0961% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Ground Slab m2 365.58 0.5676% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Under Concrete Trench m2 86.67 0.1346% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

F BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Footing Foundation kg 2236.50 0.8013% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Ground Beam & Retaining Wall kg 3848.00 1.3787% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

Ground Slab kg 4560.84 1.6341% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Column GroundFloor kg 2083.97 0.7467% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Beam & Fascia First Floor kg 4368.60 1.5652% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
First Floof Slab kg 5739.12 2.0563% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
colomn First Floor kg 737.46 0.2642% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Beam & Fascia kg 2961.36 1.0610% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Slab kg 2437.56 0.8734% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Trench kg 3844.80 1.3776% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

G FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Footing Foundation m2 41.30 0.1569% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Ground Beam & Retaining Wall m3 267.80 1.0177% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Ground Slab m4 10.53 0.0400% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Column GroundFloor m5 148.80 0.5655% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Beam & Fascia First Floor m6 268.11 1.0188% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
First Floor Slab m7 402.48 1.5295% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
colomn First Floor m8 52.56 0.1997% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Beam & Fascia m9 181.62 0.6902% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Floor Slab m10 202.14 0.7682% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Trench m12 603.72 2.2942% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

H CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Footing Foundation m3 11.30 0.4049% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Ground Beam & Retaining Wall m3 22.80 0.8169% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Ground Slab m3 41.57 1.4894% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Column GroundFloor m3 12.67 0.4540% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Beam & Fascia First Floor m3 25.42 0.9108% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
First Floor Slab m3 44.37 1.5898% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
colomn First Floor m3 4.20 0.1505% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Beam & Fascia m3 17.10 0.6127% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Roof Floor Slab m3 22.10 0.7918% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Trench m3 34.20 1.2254% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

I CONCRETE STAIRCASE
Reinforcement Bar kg 316.80 0.1135% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Formwork m2 33.60 0.1313% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Grade K300 Reinforced Concrete m3 3.00 0.1075% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

J FINISHING WORKS
1 Wall (Brick Wall) m2 783.60 2.5524% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
2 Wall Plastering m2 1567.20 2.5524% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
3 Wall Skim Coat (Sika Wall 181 Skim Coat) m2 1960.80 0.7877% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
4 Internal & External Wall Painting m2 1912.00 1.4532% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
6 Aluminium Louver Door, Size 2,2 x 2,5 m unit 2.00 0.3583% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
7 Aluminium Louver Door, Size 1,1 x 2,5 m unit 8.00 0.7166% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
8 Aluminium Louver, Size 3,0 x 0,5 m unit 12.00 0.5863% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
9 Glass Window, Size 3,0 x 1,25 m unit 2.00 0.2443% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
10 Meeting Room Door, Size 1,8 x 2,1 m unit 1.00 0.1231% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
11 Toilet Door, Size 0,8 x 2,1 m unit 3.00 0.1532% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
12 Wash basin c/w accessories (Wastafel Toto LW 246 J) set 1.00 0.0217% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
13 setting Closet c/w accessories (Closet Duduk Toto CW 422) set 2.00 0.1173% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
14 Parameter Fencing, Size 1,9 m (BRC Fence ) lot 1.00 2.1715% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

15 Fencing Door, Size 1,0 x 1,9m unit 2.00 0.0217% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
16 Stair Railing unit 2.00 0.6080% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
17 Steel Grating for Trench m' 66.00 3.7263% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
18 Water Tap (Toto T205MB) nos 3.00 0.0326% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
19 Wall tiles & Floor tiles (Keramik 40x40 Platinum) m2 54.00 0.2638% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
20 Ceiling at 1st floor m2 165.60 0.5933% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

LOADING BAY

A TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700)


i) Current Plot Elevation: -47.100. ii) Top-up Soil: 600mm
Excavation of soft clay & silty soil including disposal from site to contractors own dump area Lot 1.00 0.5602% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
and replaced with PCC and engineered soil fill with compaction earth safe bearing capacity >200 N/mm² .
Soil top up - Granular Subbase (Sirtu) fill 600mm thickness Compacted Throughly with 95% CBR. m3 144.00 1.2039% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Surveying final earth level for elevation, record result and built-in drawing the locations. Ls 1.00 0.2714% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

B EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Pile Cap, size 700x700 mm m3 16.32 0.0461% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 m3 96.80 0.2733% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 m3 74.52 0.2104% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

C LEVELLING & COMPACTION


Pile Cap, size 700x700 mm m2 20.30 0.0110% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 m2 322.68 0.1752% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 m2 248.40 0.1348% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

D LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 20.28 0.0315% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 m2 268.90 0.4175% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 m2 248.40 0.3857% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

E BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Slab & Structure
Pile Cap, size 700x700 mm kg 1778.40 0.6372% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 kg 4032.00 1.4446% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 kg 3108.00 1.1136% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x15000 kg 426.24 0.1527% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x12000 kg 346.32 0.1241% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
kg 197.76 0.0709% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

F FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Slab & Structure
Pile Cap, size 700x700 mm m2 32.90 0.1250% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 m2 15.84 0.0602% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 m2 13.80 0.0524% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x15000 m2 12.12 0.0461% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x12000 m2 9.96 0.0378% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Permanent Stoper m2 19.44 0.0739% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

G CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Pile Cap, size 700x700 mm m3 5.76 0.2064% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 16800x15000 m3 64.56 2.3132% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Road Slab, Size 13800x15000 m3 49.68 1.7800% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x15000 m3 9.72 0.3483% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Slab, Size 1800x12000 m3 7.80 0.2795% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Permanent Stoper m3 1.94 0.0695% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

H STEEL STRUCTURE
Column 200x150x10 mm (HB 200x200x8x12) kg 3667.20 1.9351% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Beam 200x150x10 mm (WF 200x100x5.5x8) kg 3085.20 1.5543% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Unequal Angle 125x75x8 mm kg 703.20 0.4123% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Chequed Plat 4mm thick m2 57.60 1.2918% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Hollow 100x100x3,8 mm kg 1953.60 1.1454% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Hollow 100x50x3,8mm kg 2004.00 1.1967% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Sagrod dia.10 mm x 1,2 m nos 112.00 0.0580% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Wind Bracing dia. 16 mm x 9 m set 5.00 0.0633% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Metal Sheat Roof Lysaght Spandek Optima 0,4 mm Colorbond m2 378.00 1.8633% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Steel Staircase unit 2.00 0.4343% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

STORM DRAIN

A EXCAVATION
Excavate for foundation at any depth, get out, part return, fill in,
well ram, remove surplus excavated material from site to
Contractor's own dump
Drain, Size 600 x 600 mm m3 60.48 0.1707% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm m3 330.48 0.9329% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Junction box, Size 90 x 900 mm m3 38.40 0.1084% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

B LEVELLING & COMPACTION


Drain, Size 600 x 600 mm m2 60.48 0.0328% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm m2 367.20 0.1993% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Junction box, Size 90 x 900 mm m2 38.40 0.0208% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

C LEAN CONCRETE
50mm thick lean concrete Grade K-100 blinding for: -
Slab & Structure
Drain, Size 600 x 600 mm m2 60.48 0.0939% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm m2 367.20 0.5701% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Junction box, Size 90 x 900 mm m2 38.40 0.0596% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

D BAR BENDER
Mild steel round bars or high tensile deformed bar
reinforcement, irrespective of diameter, to concrete for: -
Drain, Size 600 x 600 mm kg 1731.60 0.6204% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm kg 10195.20 3.6529% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Junction box, Size 90 x 900 mm kg 124.80 0.0447% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

E FORM WORKS
Sawn formwork as described above or below ground at
any height and any location (including floor opening) for: -
Drain, Size 600 x 600 mm m2 226.80 0.8619% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm m2 1376.40 5.2304% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Kontrak Progres
Minggu Lalu Minggu Ini Sampai Minggu Ini
No Uraian Pekerjaan Satuan Keterangan
Volume Bobot (%)
Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

Junction box, Size 90 x 900 mm m2 129.60 0.4925% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

F CONCRETING
K-300 reinforced concrete, placing, vibrating, finishing
and curing for r.c structure, placed below or above ground
at any height, any thickness and any location for: -
Foundation, Pilecap, Stump Column, Ground Slab & Structure
Drain, Size 600 x 600 mm m3 20.16 0.7223% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Drain, Size 450 x 450 mm m3 132.24 4.7381% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Junction box, Size 90 x 900 mm m3 20.40 0.7309% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%

Heavy Duty Grating, Size 450 x 600 mm unit 38.00 0.6684% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
Unequal Angle, Sise 3"x 2' x 8 mm
Flat Bar 2,5x 8 mm
Rebar dia 20 mm

Weeping hole every 100 cm nos 309.00 0.1342% 0.00 0.0000% 0.00 0.0000% 0.00 0.0000%
PVC pipe dia 4"

Total 100.0000% 0.0000% 0.5862% 0.5862%

Prepare By : Checked By : Approved By :

Riomo Silalahi
TIME SCHEDULE - ANCILLARY FACILITIES (PT. UNILEVER OLEOCHEMICAL INDONESIA)
Special Economic Zones (SEZ), Block M.N.R.S, HUTA VI, Sei Mangkei
Bosar Maligas - Simalungun, North Sumatera 21183

NO. ITEM BOBOT Januari Feb-22 Mar-22 Apr-22


PROGRESS Week Week Week
3 4 1 2 3 4 1 2 3 4 1 2 3 4
A PRELIMINARY
1 Preliminary Works 3.1912% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279% 0.2279%
100.0000%

B ANCILLARY BUILDING (12.00 m x 28.20 m)


1 TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700) 5.7501% 0.9583% 0.9583% 0.9583% 0.9583% 0.9583% 0.9583%
2 EXCAVATION 0.6256% 0.2085% 0.2085% 0.2085% 88.5650%
3 Refill Soil 0.6377% 0.1275% 0.1275% 0.1275% 0.1275% 0.1275%
4 Levelling & Compaction 0.3052% 0.0610% 0.0610% 0.0610% 0.0610% 0.0610%
5 50mm thick lean concrete Grade K-100 blinding for: - 0.8730% 0.1455% 0.1455% 0.1455% 0.1455% 0.1455% 0.1455%
77.1300%
6 BAR BENDER 11.7586% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690% 1.0690%
7 FORM WORKS 8.2806% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528% 0.7528%
8 CONCRETING 8.4461% 1.6892% 1.6892% 1.6892% 1.6892% 1.6892%
9 CONCRETE STAIRCASE 0.3523% 0.1762% 0.1762%
10 FINISHING WORKS 17.0836% 64.2416%
4.2709% 4.2709% 4.2709% 4.2709%

C LOADING BAY
1 TOP UP SOIL (PTUOI Site Elevation ±0.00 = equal to 47.700) 2.0355% 0.4071% 0.4071% 0.4071% 0.4071% 0.4071%
52.8647%
2 EXCAVATION 0.5297% 0.2648% 0.2648%
3 LEVELLING & COMPACTION 0.3210% 0.1605% 0.1605%
4 LEAN CONCRETE 0.8347% 0.4173% 0.4173%
43.2603%
5 BAR BENDER 3.5431% 0.8858% 0.8858% 0.8858% 0.8858%
6 FORM WORKS 0.3954% 0.1977% 0.1977%
7 CONCRETING 4.9968% 2.4984% 2.4984%
33.8173%
8 STEEL STRUCTURE 9.9543% 1.2443% 1.2443% 1.2443% 1.2443% 1.2443% 1.2443% 1.2443% 1.2443%

26.8727%
D STORM DRAIN
1 EXCAVATION 1.2121% 0.6060%
21.5923%
0.6060%
2 LEVELLING & COMPACTION 0.2530% 0.1265% 0.1265%
3 LEAN CONCRETE 0.7236% 15.9259% 0.3618% 0.3618%
4 BAR BENDER 4.3180% 1.4393% 1.4393% 1.4393%
11.8488%
5 FORM WORKS 6.5848% 2.1949% 2.1949% 2.1949%
8.2251%
6 CONCRETING 6.9939% 3.4970% 3.4970%
4.6014%
1.1863%

TOTAL 100.0000% 1.1863% 3.4151% 3.6237% 3.6237% 4.0771% 5.6664% 5.2804% 6.9446% 9.4430% 9.6044% 11.3769% 12.8884% 11.4350% 11.4350%
CUMULATIVE 1.1863% 4.6014% 8.2251% 11.8488% 15.9259% 21.5923% 26.8727% 33.8173% 43.2603% 52.8647% 64.2416% 77.1300% 88.5650% 100.0000%
ACTUAL 0.0000% 0.5862%
DEVIATION

Note : The schedule is valid if the good weaher.

Proposed by, Known by, Approved by, Approved by,

Riomo Silalahi, ST Agus Salim Jadi, ST, MT


Site Manager PT. EKKN Project Coordinator PT. EKKN PT. UNILEVER OLEOCHEMICAL INDONESIA
STRUKTUR ORGANISASI
PT. ERAKARYA KONSTRUKSI NUSANTARA
ANCILLARY FACILITIES PROJECT - PT. UNILEVER OLEOCHEMICAL INDONESIA

PROJECT MANAGER
AGUS SALIM JADI
PHOTO
0852 7075 0370

ADMINISTRASI K3
M.A.HAFIZ
PHOTO
0822 7239 0032

SITE MANAGER ASS. SITE MANAGER


RIOMO SILALAHI FERY PARDOSI
PHOTO PHOTO
0813 7675 8878 0853 6214 0010

SPV LOGISTIC TEKNISI SURVEYOR DRAFTER


HERI LUTHFI TOMI RAHMAD/NICO M. ALI
PHOTO PHOTO PHOTO PHOTO PHOTO
0853 7100 6016 0852 7786 3474 0813 9797 7564 NO.HP 0857 1416 4651
PT. ERAKARYA KONSTRUKSI NUSANTARA
WEATHER REPORT
Periode 21 Januari sd 27 Januari 2022

Hours
Date
07'00-08'00 08'00-09'00 09'00-10'00 11'00-12'00 12'00-13'00 13'00-14'00 14'00-15'00 15'00-16'00 16'00-17'00 17'00-18'00
21-Jan-22

22-Jan-22

23-Jan-22 H

24-Jan-22

25-Jan-22

26-Jan-22

27-Jan-22

Legend :
H

Rain Sunny Cloudy Holiday

Medan, 27 Januari 2022


Dibuat Oleh :
PT. ERA KARYA KONSTRUKSI NUSANTARA
Riomo Silalahi
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 21-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7
8
9
10
11
12
13
14
15 Job List
16 Description Volume %
17 Pengerjaan Dokumen
18 Induction Pekerja
19

Total Worker 6 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 21-Jan-22

Induction Pekerja

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 22-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7 Amansyah Skill
8 Mesdi Skill
9 Hardi Skill
10 Ahmadi Skill
11 Andi Helper
12 Hari Mukti Helper
13
14
15 Job List
16 Description Volume %
17 Pengerjaan Dokumen
18 Pemasangan Pagar Seng
19

Total Worker 12 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 22-Jan-22

Pemasangan Pagar Seng

Pemasangan Pagar Seng

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 24-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7 Amansyah Skill
8 Mesdi Skill
9 Ahmadi Skill
10
11
12
13
14
15 Job List
16 Description Volume %
17 Pembuatan Pagar Seng
18
19

Total Worker 9 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 24-Jan-22

Pemasangan Pagar Seng

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 25-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7 Amansyah Skill
8 Mesdi Skill
9 Ahmadi Skill
10
11
12
13
14
15 Job List
16 Description Volume %
17 Pemasangan Bedeng Kerja
18 Pemasangan Bedeng Fabrikasi
19

Total Worker 9 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 25-Jan-22

Pemasangan Bedeng Kerja dan Fabrikasi

Pemasangan Bedeng Kerja dan Fabrikasi

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 26-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7
8
9
10
11
12
13
14
15 Job List
16 Description Volume %
17 Pemasangan Pagar Seng
18
19

Total Worker 6 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 26-Jan-22

Pemasangan Pagar Seng

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY REPORT MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 27-Jan-22

Workers Materials Equipment


NO
Name Position Type of Materials Quantity Type of Equipment Quantity

1 Riomo Silalahi Site Manager Kayu Kereta sorong 3


2 Fery Pardosi Supervisor Triplek Mesin Potong Triplek 1
3 Masyhuril Akmalul Hafiz Safety Officer Seng Mesin Las 1
4 M. Luthfi Logistic Cutting Well 2
5 M. Ali Drafter
6 Heri Foreman
7 Amansyah Skill
8 Mesdi Skill
9 Ahmadi Skill
10
11
12
13
14
15 Job List
16 Description Volume %
17 Pemasangan Bedeng Kerja
18 Pemasangan Bedeng Fabrikasi
19

Total Worker 9 Orang

WHETHER CONDITION PROBLEMS DURING CONSTRUCTION


Morning Cerah
Afternoon Cerah
Evening Cerah WORK PLAN TOMORROW
Night
Total Rain Level
Total Hour Raining

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date
ANCILLARY FACILITIES DAILY PROGRESS DOKUMENTATION MONTH Jan-22
Project :Ancillary Facilities No

Location :9 HA
Contractor :EKKN Date 27-Jan-22

Pemasangan Bedeng Kerja dan Fabrikasi

Pemasangan Bedeng Kerja dan Fabrikasi

Prepared by : Approved by :
Name : Name
Signature : Signature
Date : Date