PLANILLA DE AVANCE DE OBRA N° 3

Correspondiente al periodo comprendido entre el 15 - Marzo - 2022 y el 23 - Marzo - 2022


PROYECTO: CONSTRUCCION CANCHA MUNICIPAL COLQUENCHA
Moneda: BOLIVIANO

VOLUMEN ORDENES PRECIO


ÍTEM DESCRIPCIÓN UND. CONTRATADO DE CAMBIO UNITARIO
3 OBRA FINA
8 FACHADA FLOTANTE M2 23.00 0.00 89.147
9 PISO DE PORCELANATO (AREA COMUN) M2 10.00 0.00 299.279
10 BOTAGUAS DE H°A° ML 20.66 0.00 123.004
11 CASTIGADO C/ CEMENTO M2 20.00 0.00 105.619
SUBTOTAL OBRA FINA
TOTAL VOLUMEN EJECUTADO MONTO EJECUTADOS %
CONTRATADO ANTERIOR ACTUAL ACUMULADO ANTERIOR ACTUAL ACUMULADO AVANCE

2,050.38 0.00 23.00 23.00 0.00 2,050.38 2,050.38 100.00 %


2,992.79 0.00 10.00 10.00 0.00 2,992.79 2,992.79 100.00 %
2,541.26 6.88 13.78 20.66 846.27 1,695.00 2,541.27 100.00 %
2,112.38 10.00 10.00 20.00 1,056.19 1,056.19 2,112.38 100.00 %
1,902.46 7,794.36 9,696.82
TOTAL 1,902.46 7,794.36 9,696.82 23.50 %
ANTICIPO 6,692.94 1,558.87 8,251.81
LÍQUIDO PAGABLE -4,790.48 6,235.49 1,445.01