Professional Documents
Culture Documents
Synchronicity of Global Construction Cost Indexes
Synchronicity of Global Construction Cost Indexes
net/publication/331410932
CITATIONS READS
7 1,835
5 authors, including:
Some of the authors of this publication are also working on these related projects:
Building information modeling (BIM) on chain: From ‘stocks’ of model files to ‘flows’ of semantic trees View project
A derivative-free optimization (DFO) approach to architectural symmetry detection from 3D point clouds View project
All content following this page was uploaded by Xing Jinding on 01 April 2019.
Access to this document was granted through an Emerald subscription provided by emerald-
srm:485131 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald
for Authors service information about how to choose which publication to write for and submission
guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company
manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as
well as providing an extensive range of online products and additional customer resources and
services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the
Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for
digital archive preservation.
Synchronicity
Synchronicity of global of global CCIs
construction cost indexes
Ruixi Zhang
Research Center for Construction Economics and Management,
Chongqing University, Chongqing, China
Jinding Xing Received 10 February 2018
School of Construction Management and Real Estate, Revised 4 July 2018
Accepted 20 August 2018
Faculty of Built Environment, Chongqing University, Chongqing, China
Kunhui Ye
School of Construction Management and Real Estate,
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Abstract
Purpose – The purpose of this paper is to examine the features and tendency of cost indices in the global
construction setting.
Design/methodology/approach – Data from 22 countries/regions are collected and analyzed using
maximum variance formulation and Kendall rank correlation coefficient.
Findings – It is found that global construction cost indexes (CCIs) have commonly maintained a steady
increase for decades, and the CCIs synchronize with each other. Overall synchronicity and synchronicity of
different countries pairs have increased with time significantly.
Research limitations/implications – The major limitation, however, is the availability of data: only
22 regions/countries are examined, the distribution of these regions/countries is imbalanced between different
continents and various indices are adopted around the world, of which statistical methods are not same.
Practical implications – The implication is that a better perception of CCIs enables contractors to have a
robust estimation for bidding prices and to improve the efficiency of construction projects management.
The research findings also provide a useful reference for those countries that have not established
construction cost indices databases to forecast the tendency of domestic construction industries.
Originality/value – This paper contributes to the overall body of knowledge by presenting the co-movement
of global CCIs and measuring the changes of CCI synchronicity with time and in different countries pairs.
Keywords Construction, Estimating, Competitiveness, Vibration, International practice, Bidding,
Construction cost index, Synchronicity
Paper type Research paper
Introduction
International construction is one of the most attractive businesses that contractors expect to
operate in the present era of globalization. According to the Engineering News-Record, the
overseas contract revenue of top 225 international contractors has increased rapidly over
Engineering, Construction and
Architectural Management
The authors are grateful to Chongqing University for financing this research project under the Fundamental © Emerald Publishing Limited
0969-9988
Research Funds for the Central Universities, No. 2018 CDJSK 03 PT 16 and cqu2017hbrc2B10. DOI 10.1108/ECAM-02-2018-0045
ECAM the years from 2005 to 2016. With the pace of globalization, entering the international
construction market and exploring business overseas have been instrumental for
contractors to achieve business growth (Deng et al., 2014). Therefore, in addition to
multitudinous competitors from developed countries such as the USA, UK, Japan and
European countries, a growing multitude of contractors from developing countries are
involved in the international construction industry (Low and Jiang, 2003).
International construction is characterized with social and political instability, a high
possibility of investment failure and considerable market turbulence (Ye et al., 2009). Cost
overruns, schedule delays and enterprise bankruptcy may appear if contractors fail to manage
international construction business in due ways (Yildiz et al., 2014). Recent studies on many
completed projects have been conducted with a snapshot of this (Mulva and Dai, 2012;
Grau and Back, 2015). For instance, Mulva and Dai (2012) found that nearly 70 percent of 975
projects completed between 1996 and 2011 suffered from cost and schedule deviation (negative
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
or positive) in excess of 10 percent; only 5 percent of them actualized authorized cost and
expected completion time with slight deviations. These kinds of unsatisfactory performance
may be attributed to fragile perceptions of construction cost which will further cause the
closing actual cost to surpass the preliminary estimate (Hassim et al., 2018). On the one hand,
there are observations of “the winner’s curse,” which signify that construction cost variability
is an overwhelming risk associated with contractors’ profit and owners’ budget (Ashuri and
Lu, 2010). Hence, contractors have to handle any challenges of construction cost as far as they
could. On the other hand, a vast majority of global construction projects are more complicated
than usual in cost management. As stated by Smith (2016), the need to establish cross-national
regular patterns for construction cost management has been unprecedentedly germane.
In the discipline of construction management and economics, construction cost indices
(CCIs) are examined mainly for the purpose of making short- and long-term forecast of market
trends in an individual country (Grau and Back, 2015; Xu and Moon, 2011; Ashuri and
Lu, 2010). In appraising the paucity of relevant examination in the international setting,
the aim of this study is to examine CCIs with the intention of identifying their common
features on a global scale. The examination favors individuals/entities to realize the nature of
international construction business. In addition, a comprehensive perception of CCIs across
different countries/regions facilitates international construction contractors to manage cost
risks, form solid groundworks for project performance assessment and formulate competition
strategies (Ye et al., 2014). The remainder of this paper is organized with five sections. The
theoretical background of the research is discussed in the second section. The third section
describes the research activities. Results of the data analysis are outlined in the fourth section.
The last one summarizes research findings, implications of the findings and limitations.
Conceptual background
Construction cost indexes
Since their applications in the field of purchasing power measurement, index number
methods have gained much popularity in the discipline of economics (Guerrero-de-Lizardi,
2013). An index number would be derived by calculating a large amount of data for a
defined variable. The derived indices are useful to mirror relative changes in value added by
a variable or a set of related variables (Molugaram and Rao, 2017), and they may vary
in a spatial or temporal dimension with the changes of prices or economic activities
(Langston, 2014; O’Neill, 2015). In the construction context, a cost index (or CCIs) is a
weighted aggregate price index for constant quantities of workforce, materials and
equipment that are necessary for construction activities (Hassanein and Khalil, 2006).
The role of CCIs in domestic construction markets is two-faceted, namely, a baseline for
estimating the amount of construction cost at the project level, and an indicator for general
change of construction cost at the industrial level.
The applications of CCIs span widely from informing decision making, estimating Synchronicity
construction cost, preparing budgets in earlier stages of construction projects to life-cycle of global CCIs
cost planning, management and control (Xu and Moon, 2011). According to the Department
for Business Innovation and Skills in Britain, users of built facilities rely heavily on cost
indices to operate day-to-day business. Most of them are able to recognize potential major
disruptions to works if alternatives become unsuitable. In reverse, without an accurate
estimation of CCIs, contractors may encounter thorny problems such as schedule delays,
cost overruns and insolvencies especially on those construction projects that have high
variability of construction cost (Ashuri and Lu, 2010). CCIs are thus widely adopted
in the architecture, engineering and construction sector to gauge construction cost trends
(Touran and Lopez, 2006; Xu and Moon, 2011). Furthermore, CCIs can assist contractors to
compare cost or price for a limited quantity of goods or services over a period of time
(Williams, 1994; Trefor, 1994), and behind a set of CCIs may contractors’ general
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Synchronicity of CCIs
Economic links between cities, states, regions and countries are fueled by globalization as
evidenced by the integration of international production chains (Vitsounis et al., 2014).
Such kinds of economic links are stretching the borders of society, and they have stimulated
widespread concerns over the synchronization of industries. Synchronization, which
basically means “moving at the same rate and exactly together” (House, 1987), refers to the
development patterns of business cycles or the co-movement of growth rates through time.
In the mainstream of economics, researchers claim that the trade fluctuation across borders
as well as the synchronization of business cycles pushes economic entities to grow
simultaneously (Chan and Hameed, 2006). Likewise, synchronicity is the similarity of
movement in these patterns over time (Patrick and Aaron, 2011).
The gaps of CCIs between developed and developing countries can be narrowed for a few
reasons (Ke et al., 2013). First, economic synchronicity is determined in part by the factors of
international trade, capital flows and multinational corporations that prompt different
economic entities to grow in same directions (Patrick and Aaron, 2011). International trade
has been a dominant force that causes construction businesses to develop in similar
manners ( James and Daniel, 2008). Recent years have witnessed that a large number of
construction firms from less-developed countries explore businesses overseas to escape
from strong business competition in their home markets (Li et al., 2013). Second,
synchronicity of CCIs is embodied with the close linkages of construction to other sectors
including finance, technologies, management, materials and labor (Raftery et al., 1998). The
internationalization of construction firms has been further advanced by the accumulation of
enterprise resources and advanced management skills that mirror the progress of
knowledge (Oluwatayo and Amole, 2012). Last but not least, rapid urbanization in
developing countries attracts contractors or consultants of developed countries to flood in
from all over the world, and nowadays international construction firms have more
opportunities than before to impact local construction productivity.
the pace of economic growth (Taylor and Bowen, 1987; Touran and lopez, 2006). In addition,
previous research has shown that both GDP and consumer price index have positive
relationships with CCIs (Shahandashti, 2014), but CCIs correlate to prime loan rate in a
negative way (Ashuri and Shahandashti, 2012). Furthermore, some other factors such as
producer price index, economic conditions and energy price index are often combined to
examine the variation of CCIs over a period of time (Shahandashti, 2014; Ashuri and
Shahandashti, 2012).
At the level of industry, materials price and volatilities of workforce pose CCIs to
fluctuate ( Joukar and Nahmens, 2015; Touran and Lopez, 2006). There is a highly positive
relationship between employment rate and CCI (Shahandashti, 2014). The interaction
between construction demand and supply requires contractors to charge different prices for
construction activities. For instance, the proliferation of housing demands will be followed
with a larger supply of construction services (Williams, 1994), and the resultant changes of
construction costs. As delineated by Skitmore (1987), the relationship between new
construction demand and price level is positive. In this strand, housing demands must be a
determinant of CCIs. Nevertheless, this may not always be the case because housing scale
does not significantly correlate with CCIs (Shane et al., 2009). Whilst the industry capacity
has effects on price movement (Taylor and Bowen, 1987), the level of construction cost is
affected by building approval and fixed capital formation in buildings in the short or long
run ( Joukar and Nahmens, 2015; Ashuri and Shahandashti, 2012).
Other factors related to the project level comprise investment intention, architects’ new
commission, new construction orders and penalties as a result from delays (Renata and
Marek, 2015; Ashuri et al., 2012). In addition, construction costs are determined by
construction works, scope, expected volume of work, progress payment and construction
technologies ( Joukar and Nahmens, 2015; Shane et al., 2009; Touran and Lopez, 2006).
Methodology
Maximum variance formulation (MVF)
Principal component analysis is a statistical tool to project data onto a lower dimensional
linear space, of which the dimensions are called principal components (Volosovych, 2011).
The first principal component approach satisfies the research purpose and matches the
quality of multiple samples in this study. Therefore, it is used to derive a reference curve to
reflect the overall trend of global CCIs. The first principal component can be extracted by
means of MVF as demonstrated widely in the field of signal processing. The principle of
signal processing is that signal has larger variance, while noise has smaller variance.
By locating signals in a two-axis coordinate system, smaller variances on a certain axis are
considered to be caused by noise. This method transforms the observed signals into
principal components, and retains variance in the data set.
Previous studies have disclosed that MVF is an appropriate method to analyze historic price Synchronicity
data especially on the occasion when a variety of countries, regions and industries are of global CCIs
examined (Pukthuanthong and Roll, 2009). Linear dimensionality reduction by means of MVF
is built on leading eigenvectors of data covariance (Yun et al., 2012). If cost indices of all samples
have high relevance, CCIs for a country/region can be treated as a signal based on the
principle of maximum variance theory. Thus, the reference curve could be extracted
successfully. Considering a data set of observations {ccii}, where i ¼ 1, …, n, and n is the
number of all samples. Assumed {ccii} is a Euclidean vector with dimensionality j ( j ¼ 1, …, k),
CCI for sample i at time j is cciij.
Before detecting the relationships between CCIs, it is very important to conduct
Kaiser–Meyer–Olkin (KMO) test in the study to ensure that the data fit MVF (Bayo and
López-Castellanos, 2016). Setting cost indices per country over the period of time as a
sample, a linear correlation coefficient is derived as follows:
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
PP 2
i a j r ij
KMO ¼ P P P P ; (1)
i a j r ij þ
2 2
i a j pij
where rij and pij is Pearson correlation coefficient and partial correlation coefficient of
ccii and ccij, respectively. The value of KMO is between 0 and 1, and according to Kaiser and
Rice (1974), a KMO value of more than 0.9 represents very suitable for analysis, 0.8 means
fit, 0.7 means general, 0.6 means not appropriate and below 0.5 is extremely inappropriate
in general.
Then, in accordance with the first principal component, all data should be projected onto
a one-dimensional space (M ¼ 1) while the variance of the projected data is maximized.
The direction of this space is defined using a j-dimensional vector u, which is a unit vector so
that uTu ¼ 1. Each data point of CCIi is then projected into a scalar value uTCCIi, where
CCIi is defined as follows (Bishop, 2006):
1X k
CCI ij ¼ cciij cciij : (2)
k j¼1
1X n 2
uT CCI ¼ uT Su: (3)
n i¼1
To maximize uTSu, a standard result for a positive semi-definite matrix such as S is that the
product’s maximum possible value is the largest eigenvalue (λ1) of the matrix, which occurs
when u is the corresponding eigenvector. Then, the coefficient of the characteristic equation
of the global CCIs (GCCI) can be given by:
u
GCCI ¼ pffiffiffiffiffi CCI T ; (4)
l1
pffiffiffiffiffi
where the sum of elements in vector u= l1 equals 1.
as follows:
qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
Pk 2
j¼1 cciij GCCIj
gi ¼ qffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
Pk ffi : (6)
2
j¼1 GCCI j
The closer the coefficient g to 0 is, the smaller the deviation degree is.
where Sirt is expressed in negative values for the convenience of identifying the curves of
synchronicity directly. The closer the Sirt value to 0, the larger the time series synchronicity,
and the higher the similarity of CCI curves will be. As Kalemli-Ozcan et al. (2013) pointed
out, Sirt is not influenced by the volatility of samples, which allows this study to outline the
co-movement of CCI curves.
Construction cost Japan Residential The deflator for each component is calculated by the Official Statistics
deflators buildings (monthly/ Laspeyres type formula with the weights based on the ratios of Japan
quarterly/yearly) of materials and labor cost by kind of construction work to
the total cost of construction
Construction cost Denmark; Spain; France; Italy; Lithuania; Residential The construction cost index is to show the development of Eurostat
index Finland; Portugal; German; Austria; The buildings costs incurred by the contractor or producer to carry out the Statistics
Netherlands; Norway; Turkey; UK (quarterly) construction process including labor, materials, plant and
overheads
Construction and China Residential Costs of building materials, labor and machinery are all Shenzhen
installation buildings (monthly) taken into account based on the construction market Construction
engineering cost Engineering Cost
index Network
Construction price Canada Apartment building Changes in contractors’ selling prices of new apartment Statistics Canada
index (quarterly/yearly) building construction and major sub-trade group (structural,
architectural, mechanical and electrical)
Mauritius Residential Prices of a representative selection of basic inputs (labor, Statistics
buildings (monthly/ plant, materials and transport) into the construction work Mauritius
quarterly/yearly)
America Single-family The price index excludes the value of land and other non- United States
houses (monthly) construction costs Census Bureau
Construction Uganda Residential The prices for the whole construction sector covering Uganda Bureau of
sector index buildings material prices, wage rates and equipment hire rates Statistics
(quarterly)
Input to the house Australia Residential houses It includes all inputs, fittings and fixtures which form an Australian
construction (quarterly) integral part of the structures of detached house buildings Bureau of
industry Statistics
Tender price index Singapore Residential The calculation method of the index is the same as that of the Building and
buildings and Royal Institute of Chartered Institute of construction costs. It Construction
commercial office is mainly influenced by production factors such as labor Authority
(quarterly) costs, materials costs, machinery and equipment use fees
Hong Kong Building works Architectural
(quarterly) Services
Department
Note: Due to data availability in China, Installation Engineering Cost Index of Shenzhen city is adopted as an alternative
Synchronicity
of global CCIs
global construction
Table I.
Typical CCIs in the
market
ECAM changes of cost in construction markets. The main types of CCIs including building cost
index, output price index and tender price index are adopted to present the trends of
construction cost in the international construction industry. For simplicity, these types of
indices mentioned above are called “CCI” in this paper.
Quarterly data from 2006Q1 to 2015Q3 are collected for 20 countries/regions, while data
from China and the USA are monthly and must be transformed into quarterly one for
simplicity of comparison. The countries listed in Table I are included due to data
availability. A few missing data are inputted using linear interpolation. As a result, 22
countries/regions from Europe, Asia, America, Africa and Oceania are gathered.
CCIs of all samples are re-calculated by setting the first quarterly data of reference year
(2006) to be 100 for unification. Seasonal fluctuations are smoothed by following US Census
Bureau X-12-ARIMA procedure (Mink et al., 2015). X-12-ARIMA has been widely used to
seasonally adjust the economic time series, and it provides procedures to examine the
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
time series’ trading day effects, holiday effects and some other calendar effects. Further
information about X-12-ARIMA can be find in X-12-ARIMA Reference Manual. The results
are shown in Figure 1.
Figure 1 demonstrates that most of the CCI curves sustain upturn trends of growth, and
their volatility appears to be in a synchronous way. For instance, both Hong Kong and
Turkey had a distinctive growth of CCIs, but the growth was relatively vague in European
countries. Most of the CCI curves were subject to much fluctuation during the period of
2008–2009, and thereafter fell down distinctively by 5–30 percent. Compared to other
entities, Hong Kong and Mauritius had a sharp decrease in CCI curves. These characteristics
are aligned with previous studies, which show that construction markets of different nations
may be fluctuating simultaneously as they have some determinants in common (e.g. global
financial crisis) (Edey, 2009; Ozdemir and Kilic, 2011). KMO test is applied to further reveal
the high linear correlation between 22 samples with a KMO value of 0.881, which suggests
that the correlation is strong and MVF can be used to outline the reference curve.
(a) (b)
240
Construction Cost Index
200 130
120
160
110
120
100
2
3
Q
0Q
7Q
8Q
9Q
Q
07
08
11
13
14
10
12
13
14
1
0
20
20
20
20
20
20
20
20
20
20
20
20
20
Overall Partial
USA Canada Hong Kong Japan China Singapore Denmark
Using Equation (4), CCIs are calculated and the results are shown in Table II. CCIs for all
samples are plotted in Figure 2. As shown in the figure, the reference curve sustains rising
over the past years, and it concurs with the trends of cost index curves of sampled
countries/regions.
In order to measure the extent to which the reference curve represents all of the CCI
curves, the eigenvalues λ are calculated.PVariances explained by the first principal
component are given, namely, d ¼ lmax = 20 i¼1 li ¼ 92:4% (λi ¼ 1, 2, …, 22). The results
suggest that the proportion of variance explained by the reference curve is as high as
92.4 percent. Thus, the reference curve is acceptable to reflect the overall trends of cost
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Sample Points
260
Reference Curve
240
Construction Cost Index
220
200
180
160
140
120
100
1
Figure 2.
7Q
8Q
9Q
0Q
Q
12
13
14
0
Curves of construction
20
20
20
20
20
20
20
cost indices
Time (quarter)
ECAM Global trend
140
120
110
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
100
3
3
Figure 3.
Q
Q
06
07
08
08
09
10
11
11
12
13
14
14
15
Overall trend of
20
20
20
20
20
20
20
20
20
20
20
20
20
global CCIs
Time (quarterly)
rapid growth of construction cost in the global construction industry (Vol, 2006).
Despite this, the increase of construction cost was a little bit beyond imagination. As shown
in Figure 3, the curve had a sharp increase before 2008 and dropped down thereafter
within one year. A gradual growth after the downturn year is thus confirmed. This echoes
with the views of Grogan (2011) that uptrend of global construction cost is inevitable as
driven by inflation.
Figure 4 mirrors the quarter-on-quarter growth rate of global CCIs. As shown in this
figure, the fluctuation range is between −2 and 4 percent, and it had been gentle over the
past years. A significant upward development before and after the second quarter of 2008 is
revealed. In effect, the growth rate suddenly fell down about 0.6 percent at that breakpoint.
The maximum growth rate reached to 3.24 percent in the first quarter of 2008, and rapidly
dropped to a minimum of −1.99 percent within three quarters. The growth feature of global
CCIs from 2008 to 2009 shows a significant volatility in the global market, which concurs
4%
Quarter-on-quarter growth rate
3%
2%
Growth Rate (%)
1%
0%
–1%
–2%
–3%
4
20 1
20 4
20 3
20 2
20 1
20 4
20 3
20 2
1
Figure 4.
Q
Q
06
07
08
09
09
10
11
12
12
13
14
15
Quarter-on-quarter
20
20
20
20
significantly since the third quarter of 2008. The largest decline reached 1.99 percent with
the crisis intensified sharply in September 2008 (Tansey and Spillane, 2014). Until late 2009,
with the efforts of many countries implementing national economic stimulus plans
especially in the construction sector, global economy began to recover, and so global CCIs
did in the second quarter of 2009. The quartile growth rate reached 1.91 percent in 2011.
The overall fluctuation of global CCIs is generally in line with the change of annual global
GDP growth as shown in Figures 4 and 5 which is aligned with previous studies that
emphasize the existence of close linkages between construction sector and macroeconomics
(Wigren, 2011; Ng et al., 2009).
Synchronicity of CCIs
Figure 2 describes potential synchronicity between a sample’s cost indices and global cost
indices. Using Equations (5) and (6), deviation is calculated and the results are listed in Table III.
As shown in Figure 6, 20 samples except the USA and Singapore had significant synergistic
relationships with the reference curve, because the correlation coefficients are all above
0 at the significance level of 1 percent. In total, 18 samples had a relatively strong
correlated relationship (correlation coefficient W0.4) between domestic cost indices and
global CCIs. Moreover, 10 out of 18 samples were subject to extremely strong correlation.
5%
Annual growth rate
4%
3%
Growth Rate (%)
2%
1%
0%
–1%
–2%
05
06
07
08
09
10
11
12
13
14
15
16
20
20
20
20
20
20
20
20
20
20
20
20
Figure 5.
Time (yearly) Annual growth of
global GDP
Source: World Bank
ECAM Significant co-movement of the cost indices is thus acknowledged. Previous studies on
international business cycle and property price have revealed co-movement across countries
( Jara and Romero, 2017; Mink et al., 2015; Hirata et al., 2013). As demonstrated in this study, the
same law applies to construction cost in the global construction industry.
As for the deviation, it is found that those countries and regions (e.g. Uganda, Hong
Kong, Turkey, Singapore and Lithuania) with relatively smaller sizes of construction
markets are likely to undergo much more vibration and inconsistence (τ o0.5 or g W1). The
top 8 nations based on synchronicity coefficients is Austria, Portugal, Denmark, Turkey,
Mauritius, Finland, Uganda and China. This is largely because that these economic entities
are externally oriented with rather smaller gross outputs. Specifically, China is a huge
country, but it was sampled in this study using the city of Shenzhen, which has been the
frontier of implementing the national policy of “reform and opening.” The top 8 for large
deviation with global trend are Hong Kong, Uganda, Turkey, Japan, USA, France, Singapore
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
and the Netherlands, which indicates that changes of CCIs among these economies are much
subject to their own individual factors rather than global ones.
Meanwhile, there is an interesting phenomenon of clustering in Europe, where the
synchronicity coefficients and deviation degrees are very similar to each other. The reason
might be the common features of construction markets through European Union (EU).
America Singapore Japan Lithuania Hong Kong Uganda Turkey Canada Italy Australia France
τ −0.313** 0.216 0.387** 0.395** 0.798** 0.808** 0.865** 0.617** 0.679** 0.749** 0.765**
g 0.81 0.53 0.79 0.45 2.28 1.86 1.07 0.38 0.49 0.36 0.59
The Germany Spain Norway UK China Finland Mauritius Denmark Portugal Austria
Table III. Netherlands
Synchronicity and τ 0.779** 0.798** 0.799** 0.8** 0.8** 0.803** 0.816** 0.822** 0.843** 0.86** 0.889**
deviation of g 0.53 0.5 0.38 0.08 0.41 0.32 0.45 0.34 0.37 0.49 0.3
global CCIs Note: **Coefficient is significant at 1 percent level (two-tailed)
2.5
France HK
0.6
The Netherlands
Portugal Portugal
2.0 Uganda
Finland
0.4 Denmark
Australia UK
Mauritius
China Austria
1.5
0.2
0.70 0.75 0.80 0.85 0.90
Deviation
Turkey
1.0
The USA Japan
Singapore France
Italy Portugal
0.5 CanadaAustralia
Lithuania Denmark
Austria
China Mauritius
–2%
–4%
Growth Rate
–6% Global
Asia
Am-Euro
–8%
–10% Figure 7.
Synchronicity of
global CCIs with time
–12% (percentages)
ECAM Another aspect worth of discussion is the dynamic synchronicity of CCI growth in the
Global Financial Crisis. During this period, CCIs were downturn together with widening
dispersion. One of the main reasons for such higher dispersion goes to different
development stages of construction industries. For instance, the USA and EU have been the
predominant construction markets for decades, while most of construction industries in
Asia are experiencing rapid development as driven by ambitious urbanization (Ye et al.,
2018). Another reason may be different economic situations of these countries/regions. In
effect, advanced economies had stepped into a new era with much more independence on the
construction industry, and the growth of the construction industries is rather steady
(Ng et al., 2009). Furthermore, similarity between the USA and EU in both the development
stages of construction industry and economic competitiveness can be another cause leading
to higher synchronicity. Nevertheless, in line with the general tendency of
CCI synchronicity, the degree of synchronization is assumed to be stable and fluctuates
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Implications
The features of CCIs as presented above offer an overview of global construction cost
trends. Specifically, the identified CCIs synchronicity outlines a common pattern that most
of countries might be encountering in the current age, and the similarity of CCIs
development has been aggregating in the recent years. CCIs have been widely adopted by
cost estimators, investment planners and financial institutions for preparing bids,
estimating and overseeing (Lu, 2012). The diverse applications of CCI suggest that those
contractors who are ready to operate international business may find it beneficial to
understand those countries where CCIs are still unavailable. As Williams (1994) pointed out,
the trends of construction cost should be incorporated into bid preparation and taking
advantage of short-term fluctuations in material prices for material purchases. Therefore,
the results help contractors gain more confidence in struggle for overseas construction
works, manage construction cost uncertainty and improve decision making on bidding
prices. Furthermore, the findings indicate that methods of cost management in
multinational corporations may possibly simplified to general approaches in the future,
which can greatly improve production efficiency and reduce management cost.
The synchronicity degree of different country pairs provides reference to marginal profit
counting and it facilitates contractors to formulate competition strategies overseas. The
construction market is inextricably bound up with housing industries. Hence, CCIs are not
only a key indicator to oversee the construction industry but also play an important role in
the regulation of housing markets (Lovell and Smith, 2010). A better understanding of CCIs
across different countries enables to establish policy framework and attain sustainable
growth in both construction and housing. In addition, the research findings are available for
national governments to compose CCIs of their own particularly in developing countries
where they might have been aware of the complexity of establishing one. Previous studies
have attempted to address cost escalation factors in the area of construction project
management with the focus on the rapidly changing construction materials sector (Hwang
et al., 2012). In this sense, this study provides new insights into CCIs worldwide and gives a
prediction of global CCIs for multiple uses.
Conclusions
Construction cost is a key competitiveness indicator that deserves much attention of
contractors nowadays. However, the difficulty in owning a proper perception
of construction cost is surfacing in the international construction context in which
considerable contractors often fail to accumulate sufficient knowledge. In this study, a
reference curve of CCIs is extracted to reflect the major trend of global CCIs, and the
synchronicity degree of CCIs and the vibration degree of CCIs are calculated. The findings Synchronicity
suggest that a significant synchronicity between global CCIs can be confirmed, the global of global CCIs
CCIs have been rising, and the growth rate has become relatively stable over the past
decades. It is worthwhile to note that subject to common factors, CCIs of different
construction markets at the national level can be linked to each other. However, some
specific factors may cause CCIs to vibrate in an economic entity.
The primary contributions of this study to the body of knowledge is addressing the
co-movement of CCIs all over the world and measuring the changes of synchronicity degree
with time and in different countries pairs. This common pattern facilitates a much
more reliable estimation for preparing bids and project planning when little information is
known about the project. It also provides references for policy makers to establish policy
frameworks to sustain growth in construction and housing markets. The major limitation,
however, is the availability of data: only 22 regions/countries are examined, the distribution
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
References
Anaman, K.A. and Osei‐Amponsah, C. (2007), “Analysis of the causality links between the growth of
the construction industry and the growth of the macro‐economy in Ghana”, Construction
Management and Economics, Vol. 25 No. 9, pp. 951-961.
Ashuri, B. and Lu, J. (2010), “Forecasting ENR construction cost index: a time series analysis
approach”, Construction Research Congress, pp. 1345-1355.
Ashuri, B. and Shahandashti, S.M. (2012), “Quantifying the relationship between construction cost
index (CCI) and macroeconomic factors in the United States”, Proceedings of the 48th ASC
Annual International Conference, Birmingham City University, Birmingham, April 11-14.
Ashuri, B., Seyed, M.S. and Lu, J. (2012), “Empirical tests for identifying leading indicators of ENR
construction cost index”, Construction Management and Economics, Vol. 30 No. 11, pp. 917-927.
Barber, H. and El-Adaway, I. (2014), “US economic indicators and stock prices of construction
equipment manufacturers: a statistical relationship analysis”, Construction Research Congress
2014: Construction in a Global Network, pp. 1063-1072.
Bayo, J. and López-Castellanos, J. (2016), “Principal factor and hierarchical cluster analyses for the
performance assessment of an urban wastewater treatment plant in the southeast of Spain”,
Chemosphere, Vol. 155 No. 1, pp. 152-162.
Bishop, C.M. (2006), Pattern Recognition and Machine Learning, Springer, New York, NY, pp. 561-563.
Chan, K. and Hameed, A. (2006), “Stock price synchronicity and analyst coverage in emerging
markets”, Journal of Financial Economics, Vol. 80 No. 1, pp. 115-147.
Deng, X., Low, S.P., Li, Q. and Zhao, X. (2014), “Developing competitive advantages in political risk
management for international construction enterprises”, Journal of Construction Engineering
and Management, Vol. 140 No. 9.
Edey, M. (2009), “The global financial crisis and its effects”, Economic Papers A Journal of Applied
Economics & Policy, Vol. 28 No. 3, pp. 186-195.
Eurostat (2015), available at: http://ec.europa.eu/eurostat/help/first-visit/database (accessed
January 15, 2015).
Grau, D. and Back, W.E. (2015), “Predictability index: novel metric to assess cost and schedule
performance”, Journal of Construction Engineering and Management, Vol. 141 No. 12.
ECAM Grogan, T. (2011), “As the construction recovery stalls, what is the impact on inflation?”, Engineering
News-Record, Vol. 266 No. 9, p. 30.
Guerrero-de-Lizardi, C. (2013), “A case of ‘no man’s land’ in economics: the theory of index numbers and
its applications”, International Journal of Pluralism and Economics Education, Vol. 5 No. 2,
pp. 144-156.
Hassanein, A.A.G. and Khalil, B.N.L. (2006), “Building Egypt 1 – a general indicator cost index for the
Egyptian construction industry”, Cost Engineering, Vol. 50 No. 5, pp. 18-26.
Hassim, S., Muniandy, R., Alias, A.H., Abdullah, P., Anumba, C. and Shen, G. (2018), “Construction
tender price estimation standardization (TPES) in Malaysia: modeling using fuzzy neural
network”, Engineering Construction & Architectural Management, Vol. 25 No. 3, pp. 443-457.
Hirata, H., Kose, M.A., Otrok, C. and Terrones, M.E. (2013), “Global house price fluctuations:
synchronization and determinants”, Social Science Electronic Publishing, Vol. 9 No. 1, pp. 119-166.
House, R. (1987), The Random House Dictionary of the English Language, Random House, New York, NY.
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Hwang, S. (2011), “Time series models for forecasting construction costs using time series indexes”,
Journal of Construction Engineering and Management, Vol. 137 No. 9, pp. 656-662.
Hwang, S., Park, M., Lee, H.S. and Kim, H. (2012), “Automated time-series cost forecasting system for
construction materials”, Journal of Construction Engineering & Management, Vol. 138 No. 11,
pp. 1259-1269.
James, F. and Daniel, M. (2008), “Organizational professionalism in globalizing law firms”, Work,
Employment & Society, Vol. 22 No. 1, pp. 7-25.
Jara, A. and Romero, N. (2017), “International synchronicity of housing prices”, Social Science Electronic
Publishing, Vol. 31 No. 2, pp. 115-134.
Joukar, A. and Nahmens, I. (2015), “Volatility forecast of construction cost index using general
autoregressive conditional heteroskedastic method”, Journal of Construction Engineering and
Management, Vol. 142 No. 1.
Kaiser, H.F. and Rice, J. (1974), “Little Jiffy, Mark Iv”, Journal of Educational & Psychological
Measurement, Vol. 34 No. 1, pp. 111-117.
Kalemli-Ozcan, S., Papaioannou, E. and Peydró, J.L. (2013), “Financial regulation, financial
globalization and the synchronization of economic activity”, Journal of Finance, Vol. 68 No. 3,
pp. 1179-1228.
Kapelko, M. and Abbott, M. (2016), “Productivity growth and business cycles: case study of the Spanish
construction industry”, Journal of Construction Engineering & Management, Vol. 143 No. 5.
Ke, H., Wu, R.Z. and Luo, G.F. (2013), “Study on compilation and application of engineering cost index
for construction project in China”, Applied Mechanics & Materials, Vol. 357-360, pp. 2233-2237.
Langston, C. (2014), “Construction efficiency: a tale of two developed countries”, Engineering
Construction & Architectural Management, Vol. 21 No. 3, pp. 320-335.
Li, H., Jin, Z., Li, V., Liu, G. and Skitmore, R.M. (2013), “An entry mode decision-making model for the
international expansion of construction enterprises”, Engineering Construction & Architectural
Management, Vol. 20 No. 2, pp. 160-180.
Llukan, P. (2011), Kendall’s Tau, Springer, Berlin and Heidelberg.
Lovell, H. and Smith, S.J. (2010), “Agencement, in housing markets: the case of the UK construction
industry”, Geoforum, Vol. 41 No. 3, pp. 457-468.
Low, S.P. and Jiang, H. (2003), “Internationalization of Chinese construction enterprises”, Journal of
Construction Engineering and Management, Vol. 129 No. 6, pp. 589-598.
Lu, J. (2012), “Empirical tests for identifying leading indicators of ENR construction cost index”,
Construction Management & Economics, Vol. 30 No. 11, pp. 917-927.
Milcheva, S. and Zhu, B. (2016), “Bank integration and co-movements across housing markets”,
Journal of Banking & Finance, Vol. 72, Supplement, pp. S148-S171.
Mink, M., Jacobs, J.P.A.M. and De Haan, J. (2015), “Measuring coherence of output gaps with an Synchronicity
application to the euro area”, Oxford Economic Papers, Vol. 64 No. 2, pp. 217-236. of global CCIs
Molugaram, K. and Rao, G.S. (2017), Statistical Techniques for Transportation Engineering,
Elsevier, Amsterdam.
Moore, D.S. (2010), The Basic Practice of Statistics, Palgrave Macmillan, London.
Mulva, S.P. and Dai, J. (2012), Performance Assessment, Construction Industry Institute, University of
Texas at Austin, Austin, TX.
Ng, S.T., Fan, R.Y.C., Wong, J.M.W., Chan, A.P.C., Chiang, Y.H., Lam, P.T.I. and Kumaraswamy, M.
(2009), “Coping with structural change in construction: experiences gained from advanced
economies”, Construction Management & Economics, Vol. 27 No. 2, pp. 165-180.
Nistorescu, T. and Ploscaru, C. (2010), “Impact of economic and financial crisis in the construction
industry”, Management & Marketing, Vol. 8 No. 1, pp. 25-36.
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Nunes, A., Lopes, J. and Balsa, C. (2011), “Is there a causal relationship between construction activity
and the Portuguese economy? An econometric empirical application”, 10th European Conference
on Research Methodology in Business and Management in Cane, Academic Publishing Limited,
Chandler, AZ, pp. 41-42.
Oluwatayo, A. and Amole, D. (2012), “Characteristics of global architectural firms”, Engineering
Construction & Architectural Management, Vol. 19 No. 4, pp. 393-405.
O’Neill, R. (2015), “Teaching index numbers to economists”, Cogent Economics & Finance, Vol. 3 No. 1,
pp. 1-10.
Ozdemir, E. and Kilic, S. (2011), “2008 Global economic crisis and the construction sector: a field
research from marketing perspective”, Anadolu University Journal of Social Sciences, Vol. 11
No. 5, pp. 43-68.
Patrick, M.C. and Aaron, S. (2011), “Measuring the intermittent synchronicity of macroeconomic
growth in Europe”, International Journal of Bifurcation and Chaos, Vol. 21 No. 4, pp. 1215-1231.
Pukthuanthong, K. and Roll, R. (2009), “Global market integration: an alternative measure and its
application”, Journal of Financial Economics, Vol. 94 No. 2, pp. 214-232.
Puth, M.T., Neuhäuser, M. and Ruxton, G.D. (2015), “Effective use of Spearman’s and Kendall’s
correlation coefficients for association between two measured traits”, Animal Behaviour,
Vol. 102, pp. 77-84.
Raftery, J., Pasadilla, B., Chiang, Y.H., Hui, E.C. and Tang, B.S. (1998), “Globalization and construction
industry development: implications of recent developments in the construction sector in Asia”,
Construction Management & Economics, Vol. 16 No. 6, pp. 729-737.
Rangvid, J., Santa-Clara, P. and Schmeling, M. (2016), “Capital market integration and consumption risk
sharing over the long run”, Journal of International Economics, Vol. 64 No. 10, pp. 13455-13461.
Renata, S. and Marek, P. (2015), “Construction costs analysis and its importance to the economy”,
Procedia. Economics and Finance, Vol. 34 No. 1, pp. 35-42.
Shahandashti, S.M. (2014), “Analysis of construction cost variations using macroeconomic, energy and
construction market variables”, doctoral dissertation, Georgia Institute of Technology, Atlanta, GA.
Shane, J.S., Molenaar, K.R., Anderson, S. and Schexnayder, C. (2009), “Construction project cost
escalation factors”, Journal of Management in Engineering, Vol. 25 No. 4, pp. 221-229.
Skitmore, M. (1987), Construction Prices: The Market Effect. University of Salford Environmental
Resources Unit, Salford.
Smith, P. (2016), “Global professional standards for project cost management”, Procedia-Social and
Behavioral Sciences, Vol. 226 No. 14, pp. 124-131.
Tansey, P. and Spillane, J. (2014), “Government influence on the construction industry during the
economic recession 2007-2013”, Proceedings 30th Annual ARCOM Conference ARCOM,
Portsmouth, pp. 1101-1110.
ECAM Taylor, R.G. and Bowen, P.A. (1987), “Building price-level forecasting: an examination of techniques
and applications”, Construction Management and Economics, Vol. 5 No. 1, pp. 21-44.
Touran, A. and Lopez, R. (2006), “Modeling cost escalation in large infrastructure projects”, Journal of
Construction Engineering and Management, Vol. 132 No. 8, pp. 853-860.
Trefor, P.W. (1994), “Predicting changes in construction cost indexes using neural networks”, Journal
of Construction Engineering and Management, Vol. 120 No. 2, pp. 306-320.
Vitsounis, T.K., Paflioti, P. and Tsamourgelis, I. (2014), “Determinants of container ports throughput
convergence. a business cycle synchronicity analysis”, Rivista Internazionale Di Economia Dei
Transporti, Vol. 41 No. 2, pp. 201-230.
Vol, N. (2006), “Construction costs rapidly increasing”, Ashrae Journal, Vol. 48 No. 9, p. 9.
Volosovych, V. (2011), “Measuring financial market integration over the long run: is there a u-shape?”,
Journal of International Money and Finance, Vol. 30 No. 7, pp. 1535-1561.
Welcome, P. (2005), “Long-term global market correlations”, Journal of Business, Vol. 78 No. 1, pp. 1-38.
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
Wigren, R. (2011), “The robustness of the causal and economic relationship between construction
flows and economic growth: evidence from western Europe”, Applied Economics, Vol. 43 No. 7,
pp. 891-900.
Williams, T.P. (1994), “Predicting changes in construction cost indexes using neural networks”,
Journal of Construction Engineering and Management, Vol. 120 No. 2, pp. 306-320.
Xu, J.W. and Moon, S. (2011), “Stochastic forecast of construction cost index using a cointegrated vector
autoregression model”, Journal of Management in Engineering, Vol. 29 No. 1, pp. 10-18.
Ye, K., Lu, W. and Jiang, W. (2009), “Concentration in the international construction market”,
Construction Management & Economics, Vol. 27 No. 12, pp. 1197-1207.
Ye, K., Shen, L. and Lu, W. (2014), “A discriminant model for measuring competition intensity of
construction market”, Engineering, Construction and Architectural Management, Vol. 21 No. 2,
pp. 152-169.
Ye, M., Lu, W., Flanagan, R. and Ye, K. (2018), “Diversification in the international construction
business”, Construction Management & Economics, Vol. 36 No. 6, pp. 348-361.
Yildiz, A.E., Dikmen, I., Birgonul, M.T., Ercoskun, K. and Alten, S. (2014), “A knowledge-based risk
mapping tool for cost estimation of international construction projects”, Automation in
Construction, Vol. 43 No. 7, pp. 144-155.
Yun, J.M., Kim, S. and Choi, S. (2012), “Hashing with generalized Nystrom approximation”, IEEE 12th
International Conference on Data Mining (ICDM), IEEE Computer Society Press, Brussels,
Washington, DC, December, pp. 1188-1193.
Zhang, MA. and He, R. (2011), “Sluggish growth and growing import restrictions-outlook of US
macro-economy and policies in 2011”, International Economic Review, Vol. 1 No. 1, pp. 57-66.
Further reading
Blair, A.N., Lye, L.M. and Campbell, W.J. (2011), “Forecasting construction cost escalation”, Canadian
Journal of Civil Engineering, Vol. 20 No. 4, pp. 602-612.
Department for Business Innovation & Skills (2013), Results of BIS Consultation on the Uses of
Construction Price and Cost Indices, London Department for Business Innovation and Skills
(issuing body), available at: https://assets.publishing.service.gov.uk/government/uploads/
system/uploads/attachment_data/file/186912/BIS-13-761-construction-price-cost-indices-user-
consultation-results.pdf
Flexner, E.B.B. (1987), The Random House Dictionary of the English Language, Random House,
New York, NY.
Fredricksa, G.A. and Nelsen, R.B. (2007), “On the relationship between Spearman’s rho and Kendall’s
tau for pairs of continuous random variables”, Journal of Statistical Planning & Inference,
Vol. 137 No. 7, pp. 2143-2150.
Hua, G.B. (1996), “Residential construction demand forecasting using economic indicators: a Synchronicity
comparative study of artificial neural networks and multiple regression”, Construction of global CCIs
Management and Economics, Vol. 14 No. 1, pp. 25-34.
Kim, D.Y., Ashuri, B. and Han, S.H. (2012), “Financial valuation of investments in international
construction markets: real-options approach for market-entry decisions”, Journal of
Management in Engineering, Vol. 29 No. 4, pp. 355-368.
Stasiak-Betlejewska, R. and Potkány, M. (2015), “Construction costs analysis and its importance to the
economy”, Procedia Economics and Finance, Vol. 34, pp. 35-42.
Szmidt, E. and Kacprzyk, J. (2011), “The Spearman and Kendall rank correlation coefficients between
intuitionistic fuzzy sets”, Eusflat, doi: 10.2991/eusflat.2011.85.
Corresponding author
Kunhui Ye can be contacted at: Kunhui.YE@Gmail.com
Downloaded by CHONGQING UNIVERSITY At 05:15 01 April 2019 (PT)
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com