Which of the following integrates scope, cost, and schedule and should be updated to reflect changes to a project?
C Risk register
Hint:
Correct Answer: B
Explanation:
The performance measurement baseline (PMB) is a component of the project management plan that integrates scope,
schedule, and cost baselines and is used for comparison to manage, measure, and control project execution. In order for the
project manager and the team to be able to use the PMB as a measure of the project's performance, the PMB must be
updated to reflect the current state of the project, which includes all the approved changes. If the PMB is not updated, it will
give an inaccurate representation of the performance and will not be useful when compared to the results of the earned value
analysis.
C Risk register
Incorrect. The risk register is a repository in which the outputs of the risk management processes are recorded. While
the risk register can be updated with the new risks that may arise as the result of the changes, the risk register is not an
integrated scope, cost, and schedule baseline implied by the question.
Reference:
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc.,
2017, Page(s) 88, 169