As a project manager, you just completed planning a corporate restructuring project. Before project execution can begin, the
project sponsor notifies you that the project is being terminated immediately. You are told that the organization has just
announced a merger which renders the project obsolete.
With the project canceled before the execution stage, what should you do next?
D Place the project on hold until it can be reauthorized after the merger is finalized
Hint:
What process still needs to be completed when a project is terminated regardless of where the project is in the lifecycle?
Correct Answer: A
Explanation:
The question states that the project has been terminated. Even though at this stage of the project, only the project
management plan and project documents exist, there are still activities associated with the Close Project or Phase process
that must be performed. Therefore, the next action is to obtain financial and administrative closure of the project.
D Place the project on hold until it can be reauthorized after the merger is finalized
Incorrect. The question states that the project sponsor has terminated the project. Thus, the project is canceled, and
the activities associated with the Close Project or Phase process should be performed. If the project sponsor wishes at
some future point to restart the project, then it should be treated as a new project.
Reference:
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc.,