BILL OF QUANTITIES

PROJECT: CONSTRUCTION OF POWER SUB-STATION


LOCATION: CALBAYOG CITY
OWNER: GTEC

WORK COMPONENT: SECLUSSION FENCE AND GATE


MATERIALS LABOR
ITEM MATERIALS/DESCRIPTION QTY. UNIT UNIT COST TOTAL COST ITEM DESIGNATION Req'd No. DURATION RATE TOTAL COST
1.0 TRENCH
MATERIALS 1.0 Admin/Doc-Control 1.00 20.00 -
Portland cement 50.00 bags 270.00 13,500.00 2.0 Supervisor (Electrical) 1.00 20.00 -
Sand 5.00 cu.m. 1,200.00 6,000.00 3.0 Supervisor (Civil) 1.00 20.00 -
Gravel (3/4) 9.00 cu.m. 1,600.00 14,400.00 4.0 Foreman (Civil) 1.00 20.00 700.00 14,000.00
Ø12mm x 6.0m Re-bars 140.00 pcs. 260.00 36,400.00 6.0 Steelman 2.00 20.00 500.00 20,000.00
#16 GI Wire 20.00 kgms. 100.00 2,000.00 7.0 Carpenter 2.00 20.00 500.00 20,000.00
FORMWORKS & SCAFFOLDS 8.0 Mason 2.00 20.00 500.00 20,000.00
Coco lumber, 2" X 3" X 16' 50.00 pcs. 140.00 7,000.00 9.0 Labor/Helper 6.00 20.00 300.00 36,000.00
6mm thk. Ordinary plywood 30.00 pcs. 520.00 15,600.00 10.0 Service Driver 1.00 20.00 -
C.W. Nails (Assorted) 10.00 kgms. 90.00 900.00 11.0 Electrician 2.00 10.00 500.00 10,000.00
TRENCH COVER
Checkered steel plate, 5mm thick 6.00 sheets 13,510.00 81,060.00
Round bar 10mm x 6m 3.00 kgms. 196.00 588.00 Total = PHP 120,000.00
Angle bar 25mm x 25mm x 3mm THK 12.00 pcs. 497.00 5,964.00
PAINT

Page 1 of 1