Professional Documents
Culture Documents
Final Fire Fighting
Final Fire Fighting
June, 2020
2 Fe - 500 / Fe - 500 D 41500.00
5 MS Flats 43000.00
D Allowances
1 Add for MA @ 20% 0.20
2 Overheads & Contractors Profit @13.615% 0.13615
Water charges
Type of Habitation 2 1 for Rural
2 for Urban
NAME OF WORK :- CONSTRUCTION OF PROPOSED NEW MEDICAL COLLEGE AT VIZIANAGARAM IN VIZANAGARM DISTRICT .
LEAD CHART (COMMON SoR 2019-2020) (Cement - February, 2020 & Steel - June, 2020 rates)
Initial
Reference Convey MA
S.No./ Cost Unloadi
Sl. Source of to SSR Lead in -ance
Description Item Unit excluding ng Total
No. Materials page KM Charge
Code No. seigniorage charges 20%
number s
charges
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
Ordinary Portland Cement 43 / 53
1 1 MT 4600.00 4600.00
grade
2 Reinforcement steel Fe- 500 1 MT 41500.00 41500.00
3 Mild steel bars 1 MT 39000.00 39000.00
4 Structural steel 1 MT 41500.00 41500.00
5 MS flats 1 MT 43000.00 43000.00
6 Sand (un-screened) Denkada 12 27(a) 1 Cum 15.00 510.00 160.00 670.00
7 Sand (unscreened) for filling Denkada 12 27(b) 1 Cum 15.00 375.00 160.00 535.00
8 Sand (screened for plastering items) Denkada 12 28 1 Cum 15.00 590.00 160.00 750.00
Common burnt clay bricks
9 Maddi 10 BMT-A.01 1000 Nos 20.00 6000.00 350.70 54.80 54.80 10.96 6471.26
(23x11x7cm)
(Part II)
17 Rough Stone (OTG) 0 Roads & 1 1 Cum 0.00 171.45 0.00 171.45
Bridges
(Part II)
18 Rough Stone (HBG) Ambativalsa Roads & 12 1 Cum 7.00 250.00 67.80 317.80
Bridges
19 Gravel / Quarry spall Ambativalsa 26 M - 008 1 Cum 7.00 113.00 69.60 182.60
Polished Shahabad / Tandur stone
20 0 11 BMT-B-05 10 Sqm 0.00 1610.00 0.00 6.58 3.29 0.66 1620.53
slabs 15mm to 18mm thick
Polished black Kadapa slabs
21 minimum of 15mm thick (0.457m x 0 11 BMT-B-06 10 Sqm 0.00 1343.00 0.00 5.99 2.99 0.60 1352.58
0.457m)
1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the quarries.
4) Certified that for non SSR items lowest market rates are adopted
5) Certified that 25% extra on labour towards Municipal area allowance is allowed .
D A T A ( SoR 2019-20)
DATA
Sl. No. Description Quantity Rate (Rs.)
1 Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable mate
lead as directed by Executive Engineer duly taking actual premeasurements before dismantling including all la
overheads & contractor profit etc., complete
a) Brick masonry
(BLD-CSTN-14-9/299)
Mazdoor(unskilled) 0.409 Nos. 420.00
Add for MA @ 20% 0.20 171.78
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615 206.14
Rate per 1 cum
l) Clean removal of lime plaster from walls and raking out joints 20mm deep or from
terraced roof
Rate as per and raking out joints 100 mm deep 10.00 sqm
SSR 44.00
Add for MA @ 20% 0.20 44.00
Rate per 10 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 5.28
Rate per 1 sqm
m) Clean removal of cement plaster from walls and raking out joint 200 mm deep
Rate as per SSR 10.00 sqm 54.00
Add for MA @ 20% 0.20 54.00
Rate per 10 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 6.48
Rate per 1 sqm
2 Dismantling doors , windows and clear storey windows, Ventilators etc., ( wood or steel ) shutters includi
architraves,hold fasts and other attachments etc., and stacking them within 100m lead including labour ch
overheads & contractors profit complete for finished item of work
(BLD-CSTN-14-11)
a) Not exceeding 3 sqm in area :
Details of cost per each :
2nd class mason 0.10 Nos. 460.00
Mazdoor(Male) 0.20 Nos. 420.00
2nd class Blacksmith 0.05 Nos. 460.00
Add for MA @ 20% 0.20 153.00
3 Dismantling of existing dilapidated buildings including items like un-reinforced concrete, reinforced concrete,
stone masonry etc., using Dozer (D 50) including all hire, operational, incidental, labour charges and overhead
profit etc. complete finished item of work
4 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wa
soils and depositing on bank with an initial lead of 10m and depth up to 3m including all operational,in
charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finish
excluding dewatering charges etc., as per SS 20 B(APSS 308)
(BLD-CSTN-2-1)
Ordinary Soil - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 3.64 Nos. 420.00
Add for MA @ 20% 0.20 1528.80
b&c)
Overheads & Contractors Profit @13.615% 0.13615 1834.56
Cost for 10 cum ( a+b+c)
Rate per cum (a+b+c) / 10
Rate per 1 cum
1 Conveyance of un-useful excavated earth to a distance of 5 KM for disposal including hire charges o
charges etc., and overheads & contractors profit complete for finished item of work.
2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositing
lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental, labour charges s
sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work exclud
charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 420.00
Add for MA @ 20% 0.20 3494.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2493.40
Crew charges 6.00 hours 267.80
Add MA on crew charges 0.20 1606.80
c&d)
Overheads & Contractors Profit @13.615% 0.13615 21081.84
Cost for 240 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 240
3 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositing
lifts and with an initial lead of 10m and 3m to 6m depth including all operational,incidental, labour charges s
sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work exclud
charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-3)
Ordinary Soil - Mechanical Means up to 3m to 6m depth
Unit : 1 cum
Taking output : 210.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 420.00
Add for MA @ 20% 0.20 3494.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2493.40
Crew charges 6.00 hours 267.80
Add MA on crew charges 0.20 1606.80
c&d)
Overheads & Contractors Profit @13.615% 0.13615 21081.84
Cost for 210 cum ( a+b+c+d) 0.00
Rate per 1 cum (a+b+c+d) / 210
Rate per 1 cum
4 Earth work excavation for foundations (Manual Means) of buildings in ordinary rock ( not requiring
depositing on bank with an initial lead of 10m and depth up to 3m including all operational,incidental, labour c
shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of
dewatering charges etc., as per SS 20 B(APSS 308)
(BLD-CSTN-2-4)
Ordinary rock(not requiring blasting) - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 420.00
Add for MA @ 20% 0.20 2184.00
b&c)
Overheads & Contractors Profit @13.615% 0.13615 2620.80
Cost for 10 cum ( a+b+c)
Rate per 1 cum (a+b+c) / 10
Rate per 1 cum
4 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary rock (not requiring
depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational,in
charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finish
excluding dewatering charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-5)
Ordinary rock(not requiring blasting)- Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 180.00 cum
a) Labour
Mazdoor ( Unskilled) 6.24 Nos. 420.00
Add for MA @ 20% 0.20 2620.80
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2493.40
Crew charges 6.00 hours 267.80
Add MA on crew charges 0.20 1606.80
c&d)
Overheads & Contractors Profit @13.615% 0.13615 20033.52
Cost for 180 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 180
Rate per 1 cum
5 Earth work excavation for foundations for buildings in hard rock (requiring blasting) and depositing on ban
with an initial lead of 10m and up to 3m depth including all operational,incidental, labour charges such as sh
planking, strutting etc., and overheads & contractors profit complete for finished item of work excluding dewaterin
as per SS 20 B(APSS 308)
(BLKD-CSTN-2-6)
Hard rock (requiring blasting)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Driller 0.50 Nos. 510.00
Blaster 0.25 Nos. 570.00
Mazdoor ( Unskilled) 8.35 Nos. 420.00
Add for MA @ 20% 0.20 3904.50
b) Machinery
Air compressor 7cmm (diesel) 1.00 hour 1080.00
Jack hammer/Pneumatic braker 2.00 hours 16.50
Crew charges
Air compressor 1.00 Hours 242.10
Jack hammer/Pneumatic braker 2.00 Hours 378.30
Add MA on crew charges 0.20 998.70
c)Material
Gelatin 80% 3.50 Kgs 59.00
Detonator electric 14 Nos. 9.00
c&d)
Overheads & Contractors Profit @13.615% 0.13615 7329.34
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum
5 Earth work excavation for foundations for buildings in hard rock (blasting prohibited) and depositing on
and with an initial lead of 10m and up to 3m depth including all operational,incidental, labour charges su
sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work exclud
charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-7)
Hard rock (blasting prohibited)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 420.00
Add for MA @ 20% 0.20 2184.00
b) Machinery
Air compressor 6.00 Hours 1080.00
Jack hammer/Pneumatic braker 12.00 Hours 16.50
Crew charges
Air compressor 6.00 Hours 242.10
Jack hammer/Pneumatic braker 12.00 Hours 378.30
Add MA on crew charges 0.20 5992.20
c&d)
Overheads & Contractors Profit @13.615% 0.13615 16489.44
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum
1 Forming embankment with Side earth by mechanical means including pre-watering of soil, removal of top soi
soils, depositing the soils on the embankment, spreading soils, breaking clods, sectioning and consolidation with
Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charge
seigniorage charges, complete for finished item of work as per MoRT&H specification 305 (4th revision) incl
conveyance of all materials , labour charges , overheads and contractors profit etc., complete for finished item of
will be made based on level for finished item of work).
RBR-EECD-4 - 4 - iii
Unit = cum
Taking output = 100 cum 100.00 Cum
a) Labour
Mate - day
Mazdoor (Unskilled) 0.520 day 420.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity
@ 60 cum per hour 1.670 hr 2761.20
Motor grader for grading @ 200 cum per hour
1.00 hour 3020.40
Water tanker 6 kl capacity 4.00 hour 655.20
Vibratory Roller 80 - 100 kN 1.00 hour 2688.50
C) Water 24.000 Kl 107.00
Total
e) Overheads & Contractors Profit 0.13615 23792.80
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Rate per cum
2 Pre construction Anti termite treatment is a process in which chemical toxic to subterrean tremites is apply
during early stage of building Construction 2. Treatement of soil Beneath the building and around the foundatio
chemical use as per BIS - IS 6313 (Part -2) 2013 code specification & CIB RC registered termiticide which create
chemical barrier beneath the building which kills or repels terminates & impervious to tremite entry 3. Imidaclopri
63131) dissolve 2.1 Ml/1 liter of water and apply emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal,
surface of the colums, plinth beams (Back filling) walls and floor junction, external perimeters, along reatin
Liters/Sqm of the horizontal surface of basement top surface of the basement filling below flooring bed (Plinth)
Line meter at expansion joints. The substructure of a depth of 500mm around coulmns & 300mm deep aroun
basements & floor filling area including excavation channel along the wall & rodding etc. cost & Conveyance of
the site, cost of labour for sparying, rodding, overheads and contractor profit etc. complete for furnished item of
approval of the Engineer-in-charge
Unit : 1 sqm
Rate as per SoR 1 sqm 150.00
Overheads & Contractors Profit @13.615% 0.13615 150.00
Rate per 1 sqm
3 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not e
thick,watering and ramming including cost and conveyance of water to work site and all peraitonal,incidental, labo
charges of T&P etc., and overheads & contractors profit complete for fnished item of work(APSS NO.309&310)
4 Filling with carted coarse sand in trenches, sides of foundations and basement with initial lead in layers not e
thick,watering and ramming including cost and conveyance of water to work site and all peraitonal,incidental ,labo
charges of T&P etc., and overheads & contractors profit complete for fnished item of work(APSS NO.309&310)
3 Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides of f
basement with initial lead in layers not exceeding 15cm thick, watering and ramming including cost and conveya
work site and all operaitonal, incidental, labour charges, hire charges of T&P etc., and overheads & contractors
for fnished item of work (APSS NO.309&310)
(BLD-CSTN-2-9) & & Addendum dt.14.05.2019 of the Chief Engineer (R&B) Buildings
Unit : 1 cum
Taking output : 6.00 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 420.00
Add for MA @ 20% 0.20 130.20
4 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations using coarse a
size hard , machine crushed granite from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacit
and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site including all charges for
and hire charges of concrete mixer, laying concrete in foundations and under flooring bed, ramming in 15 cm lay
surface to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (AP
(BLD-CSTN-3-5)
Unit : 1 cum
A.MATERIALS :
Cement 162.00 Kgs 4600.00
Coarse aggregate 40mm 0.90 Cum 897.80
Fine aggregate ( Sand ) 0.45 Cum 670.00
Water (including curing) 1.20 kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
C.LABOUR :
1st class mason 0.10 Nos. 500.00
Mazdoor (unskilled) 1.39 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615 3188.52
Rate per 1 cum
5 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under floo
coarse aggregate 40mm size hard , machine crushed granite from approved quarry using concrete Mixer 10 /
cum) capacity including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to s
charges for machine mixing and hire charges of concrete mixer, laying concrete in foundations and under floorin
in 15 cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit comp
item of work. (APSS No. 402)
(BLD-CSTN-3-7)
Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 4600.00
Coarse aggregate 40mm 0.90 Cum 897.80
Fine aggregate ( Sand ) 0.45 Cum 670.00
Water (including curing) 1.20 kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity 1.00 hour 142.20
Crew charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
C.LABOUR :
1st class mason 0.10 Nos. 500.00
Mazdoor (unskilled) 1.39 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615 3039.48
Rate per 1 cum
6 Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard other than granite stone
approved quarry including cost and conveyance of all materials like cement, screened sand, water, stones etc.,
quarry, to site, including labour for cutting stones to required size and shape, mixing, of cement, mortar, cons
etc.,and overheads & contractors profit complete for finished item of work in foundation and basement. (APSS
( BLD-CSTN-6-13 )
Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 4600.00
Rough stone (OTG) 1.10 Cum 171.45
Fine aggregate(sand) 0.33 Cum 750.00
B) LABOUR
1st class mason 1.20 Nos. 500.00
Mazdoor (unskilled) 2.00 Nos. 420.00
Add for MA @ 20% 0.20 1440.00
( BLD-CSTN-6-13 )
Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 4600.00
Rough stone (HBG) 1.10 Cum 317.80
Fine aggregate(sand) 0.33 Cum 750.00
B) LABOUR
1st class mason 1.20 Nos. 500.00
Mazdoor (unskilled) 2.00 Nos. 420.00
Add for MA @ 20% 0.20 1440.00
8 Vibrated Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite metal an
machine crushed hard granite metal (coarse aggregate) in (2:1) ratio from approved quarry using concrete Mixer
0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate (sand), coarse a
etc. to site, all charges for mixing and hire charges of concrete mixer, laying concrete in position, vibrating, c
charges, overheads & contractors profit etc.,for finished item of work for footings and basement .
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.133 Nos 500.00
2nd class Mason 0.267 Nos 460.00
Mazdoor (both men&women) 4.60 Nos 420.00
Add for MA @ 20% 0.20 2121.32
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 222.90
Crew charges 1.333 hours 387.40
Needle vibrator 40mm ( petrol ) 1.333 hours 27.60
Crew charges 1.333 hours 181.50
Add MA on crew charges 0.20 758.34
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a Footings
Rate for Design mix M 30 1.00 Cum 7021.35
Hire charges of centering and scaffolding 1.00 Cum 288.00
Labour charges 1.00 Cum 631.00
Add for MA @ 20% 0.20 631.00
b Column pedestals
Rate for Design mix M 30 1.00 Cum 7021.35
Hire charges of centering and scaffolding 1.00 Cum 328.00
Labour charges 1.00 Cum 1004.00
Add for MA @ 20% 0.20 1004.00
c Plinth Beams
Rate for Design mix M 30 1.00 Cum 7021.35
Hire charges of centering and scaffolding 1.00 Cum 695.00
Labour charges 1.00 Cum 760.50
Add for MA @ 20% 0.20 760.50
a Footings
Rate for Design mix M 30 1.00 Cum 7021.35
Labour charges 1.00 Cum 631.00
Add for MA @ 20% 0.20 631.00
10 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granit
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and co
materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using casurina bal
wooden reapers, runners, wood posts, wall plates etc., including all operational, incidental and labour charges
batching, machine mixing, lifting of concrete manually, laying concrete, vibrating, curing , overheads & contrac
complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.167 Nos 500.00
2nd class Mason 0.167 Nos 460.00
Mazdoor (both men&women) 5.60 Nos 420.00
Add for MA @ 20% 0.20 2512.32
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 222.90
Crew charges 1.333 hours 387.40
Needle vibrator 40mm ( petrol ) 1.333 hours 27.60
Crew charges 1.333 hours 181.50
Add MA on crew charges 0.20 758.34
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 7490.55 7490.55 7490.55
Hire charges of centering and scaffolding 238.00 238.00 238.00
Labour charges 1757.00 1933.00 2108.00
Add for MA @ 20% 351.40 386.60 421.60
Lift charges of materials(Manual) 0.00 251.23 502.46
Add for MA @ 20% 0.00 50.25 100.49
Rate per 1 cum 9836.95 10349.63 10861.11
Overheads & Contractors Profit @13.615% 1339.30 1409.10 1478.74
Rate per 1 cum 11176.25 11758.73 12339.85
Say 11176 11759 12340
b) LINTELS :
Rate for other Floors FF SF TF
Rate as above 7490.55 7490.55 7490.55
Hire charges of centering and scaffolding 790.00 790.00 790.00
Labour charges 1251.00 1376.00 1501.00
Add for MA @ 20% 250.20 275.20 300.20
Lift charges of materials(Manual) 0.00 251.23 502.46
Add for MA @ 20% 0.00 50.25 100.49
Rate per 1 cum 9781.75 10233.23 10684.71
Overheads & Contractors Profit @13.615% 1331.79 1393.25 1454.72
Rate per 1 cum 11113.54 11626.48 12139.43
Say 11114 11626 12139
C) SIDE WALLS
i) 100mm thick side walls
Cost of M 30 design mix 0.10 cum 7490.55
11 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per 1 cum
a) COLUMNS : of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granit
un supported height up to 4.27 m
Rate for other Floors Cellar SF TF
Rate as above 7490.55 7490.55 7490.55
Hire charges of centering and scaffolding 355.00 355.00 355.00
Extra staging (Hire) 59.16 59.16 59.16
Labour charges 2268.00 2495.00 2722.00
Extra staging (Labour) 377.98 415.82 453.65
Add for MA @ 20% 75.60 83.16 90.73
Lift charges of materials(Manual) 0.00 251.23 502.46
Add for MA @ 20% 0.00 50.25 100.49
Rate per 1 cum 10626.29 11200.18 11774.05
Overheads & Contractors Profit @13.615% 1446.77 1524.90 1603.04
Rate per 1 cum 12073.06 12725.08 13377.09
Say 12073 12725 13377
11 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granit
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.067 Nos 500.00
2nd class Mason 0.133 Nos 460.00
Mazdoor (both men&women) 3.077 Nos 420.00
Add for MA @ 20% 0.20 1387.02
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 222.90
Crew charges 0.308 hours 387.40
Needle vibrator 40mm ( petrol ) 0.308 hours 27.60
Crew charges 0.308 hours 181.50
Add MA on crew charges 0.20 175.22
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 5183.68 5183.68 5183.68
Hire charges of centering and scaffolding 1395.00 1395.00 1395.00
Labour , lift charges for scaffolding 1473.00 1620.00 1768.00
Add for MA @ 20% 294.60 324.00 353.60
Lift charges of materials(Manual) 0.00 138.70 277.40
Add for MA @ 20% 0.00 27.74 55.48
Rate for 1 cum 8346.28 8689.13 9033.17
Overheads & Contractors Profit @13.615% 1136.35 1183.02 1229.87
Rate per 1 cum 9482.63 9872.15 10263.04
Say 9483 9872 10263
B) RCC SLABS :
a) Roof Slabs 115mm thick :
un supported height up to 3.66 m
Rate for Design mix M 30 0.115 Cum 5183.68
1 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per :1 cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granit
A) BEAMS
un supported height up to 4.27 m
Rate for other Floors Cellar SF TF
Rate as above 5183.68 5183.68 5183.68
Hire charges of centering and scaffolding 2085.00 2085.00 2085.00
Extra staging (Hire) 347.49 347.49 347.49
Labour , lift charges for scaffolding 1903.00 2093.00 2284.00
Extra staging (Labour) 317.15 348.82 380.65
Add for MA @ 20% 63.43 69.76 76.13
Lift charges of materials(Manual) 0.00 138.70 277.40
Add for MA @ 20% 0.00 27.74 55.48
Rate for 1 cum 9899.75 10294.20 10689.84
Overheads & Contractors Profit @13.615% 1347.85 1401.56 1455.42
Rate per 1 cum 11247.60 11695.76 12145.26
Say 11248 11696 12145
1 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granit
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.067 Nos 500.00
2nd class Mason 0.133 Nos 460.00
Mazdoor (both men&women) 3.077 Nos 420.00
Add for MA @ 20% 0.20 1387.02
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 222.90
Crew charges 0.308 hours 387.40
Add MA on crew charges 0.20 119.32
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
6 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content o
cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size graded m
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarr
and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, center
scaffolding pipes , jack props , wallers , foot plates , brackets , steel centering plates etc., including
incidental and labour charges, transporting concrete using transit mixer, lifting concrete mechnically, laying
concrete pump, vibrating, curing etc., and overheads & contractors profit complete but excluding cost of steel an
charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.056 Nos 500.00
2nd class Mason 0.056 Nos 460.00
Mazdoor (both men&women) 0.917 Nos 420.00
Add for MA @ 20% 0.20 438.90
C.MACHINERY :
Batching plant 15cum per hour capacity 0.222 hours 719.70
Crew charges 0.222 hours 387.40
Transit mixer 0.222 hours 1705.20
Crew charges 0.222 hours 321.40
Concrete pump 0.222 hours 1345.10
Crew charges 0.222 hours 189.20
Needle vibrator 40mm ( petrol ) 0.222 hours 27.60
Crew charges 0.222 hours 181.50
Add MA on crew charges 0.20 239.65
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a Footings
Rate for Design mix M 25 1.00 Cum 4797.17
Hire charges of centering and scaffolding 1.00 Cum 288.00
Labour charges 1.00 Cum 631.00
Add for MA @ 20% 0.20 631.00
b Column pedestals
Rate for Design mix M 25 1.00 Cum 4797.17
Hire charges of centering and scaffolding 1.00 Cum 328.00
Labour charges 1.00 Cum 1004.00
Add for MA @ 20% 0.20 1004.00
a Haunh Concrete
Rate for Design mix M 30 1.00 Cum 4797.17
Overheads & Contractors Profit @13.615% 0.13615 4797.17
Rate per 1 cum
1 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with cement content o
cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size graded m
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarr
and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, center
scaffolding pipes , jack props , wallers , foot plates , brackets , steel centering plates etc., including
incidental and labour charges, transporting concrete using transit mixer, lifting concrete mechnically, laying
concrete pump, vibrating, curing etc., and overheads & contractors profit complete but excluding cost of steel an
charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.056 Nos 500.00
2nd class Mason 0.056 Nos 460.00
Mazdoor (both men&women) 0.917 Nos 420.00
Add for MA @ 20% 0.20 438.90
C.MACHINERY :
Batching plant 15cum per hour capacity 0.222 hours 719.70
Crew charges 0.222 hours 387.40
Transit mixer 0.222 hours 1705.20
Crew charges 0.222 hours 321.40
Concrete pump 0.222 hours 1345.10
Crew charges 0.222 hours 189.20
Needle vibrator 40mm ( petrol ) 0.222 hours 27.60
Crew charges 0.222 hours 181.50
Add MA on crew charges 0.20 467.50
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a Footings
Rate for Design mix M 30 1.00 Cum 4934.74
Hire charges of centering and scaffolding 1.00 Cum 288.00
Labour charges 1.00 Cum 631.00
Add for MA @ 20% 0.20 631.00
b Column pedestals
Rate for Design mix M 30 1.00 Cum 4934.74
Hire charges of centering and scaffolding 1.00 Cum 328.00
Labour charges 1.00 Cum 1004.00
Add for MA @ 20% 0.20 1004.00
a Haunh Concrete
Rate for Design mix M 30 1.00 Cum 4934.74
Labour charges 1.00 Cum 631.00
Add for MA @ 20% 0.20 631.00
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.111 Nos 500.00
2nd class Mason 0.222 Nos 460.00
Mazdoor (both men&women) 1.56 Nos 420.00
Add for MA @ 20% 0.20 811.14
C.MACHINERY :
Batching plant 15cum per hour capacity 0.444 hours 719.70
Crew charges 0.444 hours 387.40
Transit mixer 0.444 hours 1705.20
Crew charges 0.444 hours 321.40
Concrete pump 0.444 hours 1345.10
Crew charges 0.444 hours 189.20
Needle vibrator 40mm ( petrol ) 0.444 hours 27.60
Crew charges 0.444 hours 181.50
Add MA on crew charges 0.20 479.30
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 6374.50 6374.50 6374.50
Hire charges of centering and scaffolding 238.00 238.00 238.00
Labour charges 1757.00 1933.00 2108.00
Add for MA @ 20% 351.40 386.60 421.60
Rate per 1 cum 8720.90 8932.10 9142.10
Overheads & Contractors Profit @13.615% 1187.35 1216.11 1244.70
Rate per 1 cum 9908.25 10148.21 10386.80
Say 9908 10148 10387
Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content o
cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granite metal (coa
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and conveyance of a
cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using casurina ballies, bam
reapers, runners, wood posts, wall plates etc., including all operational, incidental and labour charges
batching, machine mixing, lifting of concrete mechanically, laying concrete, vibrating, curing , overheads & contrac
complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-18)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.167 Nos 500.00
2nd class Mason 0.167 Nos 460.00
Mazdoor (both men&women) 5.60 Nos 420.00
Add for MA @ 20% 0.20 2512.32
C.MACHINERY :
Batching plant 0.50cum 1.333 hours 222.90
Crew charges 1.333 hours 387.40
Needle vibrator 40mm ( petrol ) 1.333 hours 27.60
Crew charges 1.333 hours 181.50
Add MA on crew charges 0.20 758.34
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
b) LINTELS :
Rate for other Floors FF SF TF
Rate as above 7398.55 7398.55 7398.55
Hire charges of centering and scaffolding 790.00 790.00 790.00
Labour charges 1251.00 1376.00 1501.00
Add for MA @ 20% 250.20 275.20 300.20
Lift charges of materials(Winch 35HP- Electric)
0.00 421.09 463.20
Crew charges 0.00 403.37 443.70
Add for MA @ 20% 0.00 80.67 88.74
Rate per 1 cum 9689.75 10744.88 10985.40
Overheads & Contractors Profit @13.615% 1319.26 1462.92 1495.66
Rate per 1 cum 11009.01 12207.80 12481.06
Say 11009 12208 12481
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.111 Nos 500.00
2nd class Mason 0.222 Nos 460.00
Mazdoor (both men&women) 1.56 Nos 420.00
Add for MA @ 20% 0.20 811.14
C.MACHINERY :
Batching plant 15cum per hour capacity 0.444 hours 719.70
Crew charges 0.444 hours 387.40
Transit mixer 0.444 hours 1705.20
Crew charges 0.444 hours 321.40
Concrete pump 0.444 hours 1345.10
Crew charges 0.444 hours 189.20
Needle vibrator 40mm ( petrol ) 0.444 hours 27.60
Crew charges 0.444 hours 181.50
Add MA on crew charges 0.20 214.19
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors SBF/FF
Rate as above 6413.48
Hire charges of centering and scaffolding 238.00
Labour charges 1757.00
Add for MA @ 20% 351.40
Lift charges of materials(Winch 35HP- Electric)
0.00
Crew charges 0.00
Add for MA @ 20% 0.00
Rate per 1 cum 8759.88
Overheads & Contractors Profit @13.615% 1192.66
Rate per 1 cum 9952.54
Say 9953
C) SIDE WALLS
i) 150mm thick side walls
Cost of M 30 design mix 0.10 cum 6413.48
8 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content o
cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size graded m
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarr
and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, center
scaffolding pipes , jack props , wallers , foot plates , brackets , steel centering plates etc., including
incidental and labour charges ,transporting concrete using transit mixer, lifting concrete mechnically, laying
concrete pump, vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel an
charges for finished item of work (APSS No. 402)
a) COLUMNS :
un supported height up to 4.27 m
Rate for other Floors FF SF TF
Rate as above 6374.50 6374.50 6374.50
Hire charges of centering and scaffolding 355.00 355.00 355.00
Extra staging (Hire) 59.16 59.16 59.16
Labour charges 2268.00 2495.00 2722.00
Extra staging (Labour) 377.98 415.82 453.65
Add for MA @ 20% 529.20 582.16 635.13
Rate per 1 cum 9963.84 10281.64 10599.44
Overheads & Contractors Profit @13.615% 1356.58 1399.85 1443.11
Rate per 1 cum 11320.42 11681.49 12042.55
Say 11320 11681 12043
9 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
kgs per 1 cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size g
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from a
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to
using casurina ballies, bamboos, wooden reapers, runners, wood posts, wall plates etc., including
incidental and labour charges ,transporting concrete using transit mixer, lifting concrete mechnically, laying
concrete pump, vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel an
charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.033 Nos 500.00
2nd class Mason 0.067 Nos 460.00
Mazdoor (both men&women) 0.433 Nos 420.00
Add for MA @ 20% 0.20 229.18
C.MACHINERY :
Batching plant 15cum per hour capacity 0.1333 hours 719.70
Crew charges 0.1333 hours 387.40
Transit mixer 0.1333 hours 1705.20
Crew charges 0.1333 hours 321.40
Concrete pump 0.1333 hours 1345.10
Crew charges 0.1333 hours 189.20
Needle vibrator 40mm ( petrol ) 0.1333 hours 27.60
Crew charges 0.1333 hours 181.50
Add MA on crew charges 0.20 143.90
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 4093.75 4093.75 4093.75
Hire charges of centering and scaffolding 1395.00 1395.00 1395.00
Labour , lift charges for scaffolding 1473.00 1620.00 1768.00
Add for MA @ 20% 294.60 324.00 353.60
Rate for 1 cum 7256.35 7432.75 7610.35
Overheads & Contractors Profit @13.615% 987.95 1011.97 1036.15
Rate per 1 cum 8244.30 8444.72 8646.50
Say 8244 8445 8647
B) RCC SLABS :
a) Roof Slabs 125mm thick :
un supported height up to 3.66 m
Rate for Design mix M 25 0.125 Cum 4093.75
1 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with minimum cement
kgs per 1 cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size g
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from a
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to
using casurina ballies, bamboos, wooden reapers, runners, wood posts, wall plates etc., including
incidental and labour charges ,transporting concrete using transit mixer, lifting concrete mechnically, laying
concrete pump, vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel an
charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 400.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.033 Nos 500.00
2nd class Mason 0.067 Nos 460.00
Mazdoor (both men&women) 0.433 Nos 420.00
Add for MA @ 20% 0.20 229.18
C.MACHINERY :
Batching plant 15cum per hour capacity 0.133 hours 719.70
Crew charges 0.133 hours 387.40
Transit mixer 0.133 hours 1705.20
Crew charges 0.133 hours 321.40
Concrete pump 0.133 hours 1345.10
Crew charges 0.133 hours 189.20
Needle vibrator 40mm ( petrol ) 0.133 hours 27.60
Crew charges 0.133 hours 181.50
Add MA on crew charges 0.20 99.01
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF
Rate as above 4176.78
Hire charges of centering and scaffolding 1395.00
Labour , lift charges for scaffolding 1473.00
0 294.60
Lift charges of materials(Winch 35HP- Electric)
0.00
Crew charges
Add for MA @ 20% 0.00
Rate for 1 cum 7339.38
Overheads & Contractors Profit @13.615% 999.26
Rate per 1 cum 8338.64
Say 8339
a) Roof Slabs 125mm thick :
un supported height up to 3.66 m
Rate for Design mix M 25 0.125 Cum 4176.78
10 Supply and placing of the Design Mix Concrete M 30 grade corresponding to IS 456 with cement content o
cum of concrete using batching and mixing plant of 15 cum per hour capacity with 20mm size graded m
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarr
and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, cc
casurina ballies, bamboos, wooden reapers, runners, wood posts, wall plates etc.,,including all operationa
labour charges ,transporting concrete using transit mixer, lifting concrete mechnically, laying concrete using c
vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel and its fabrication char
item of work (APSS No. 402)
I BEAMS :
A) un supported height up to 4.27 m
Rate for other Floors FF SF TF
Rate as above 4093.75 4093.75 4093.75
Hire charges of centering and scaffolding 1395.00 1395.00 1395.00
Extra staging (Hire) 232.49 232.49 232.49
Labour , lift charges for scaffolding 1473.00 1620.00 1768.00
Extra staging (Labour) 245.49 269.99 294.65
Add for MA @ 20% 343.70 378.00 412.53
Rate for 1 cum 7783.43 7989.23 8196.42
Overheads & Contractors Profit @13.615% 1059.71 1087.73 1115.94
Rate per 1 cum 8843.14 9076.96 9312.36
Say 8843 9077 9312
un supported height up to 4.88 m
Rate for other Floors FF SF TF
Rate as above 4093.75 4093.75 4093.75
Hire charges of centering and scaffolding 2085.00 2085.00 2085.00
Extra staging (Hire) 694.97 694.97 694.97
Labour , lift charges for scaffolding 1903.00 2093.00 2284.00
Extra staging (Labour) 634.31 697.64 761.30
Add for MA @ 20% 507.46 558.13 609.06
Rate for 1 cum 9918.49 10222.49 10528.08
Overheads & Contractors Profit @13.615% 1350.4 1391.79 1433.4
Rate per 1 cum 11268.89 11614.28 11961.48
Say 11269 11614 11961
C) BEAMS :
un supported height up to 7.32 m
Rate for other Floors FF
Rate as above 4093.75
Hire charges of centering and scaffolding 2085.00
Extra staging (Hire) 2084.92
Labour , lift charges for scaffolding 1903.00
Extra staging (Labour) 1902.92
Add for MA @ 20% 761.18
Rate for 1 cum 12830.78
Overheads & Contractors Profit @13.615% 1746.91
Rate per 1 cum 14577.69
Say 14578
II Roof Slabs :
A) Roof Slabs 150mm thick :
un supported height up to 4.27 m
Rate for Design mix M 25 0.125 Cum 4093.75
11 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content of
cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granite metal (co
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and conveyance of a
cement, fine aggregate (sand), coarse aggregate, water etc., to site, centering using casurina ballies , bam
reapers , runners , wood posts , wall plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5c
end with an average thickness of 6.25cm including all operational, incidental and labour charges such as w
machine mixing, lifting of concrete manually, laying concrete, curing, overheads & contractors profit complete etc
cost of steel and its fabrication charges for finished item of work (APSS No. 402, 403 & 903)
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.067 Nos 500.00
2nd class Mason 0.133 Nos 460.00
Mazdoor (both men&women) 3.077 Nos 420.00
Add for MA @ 20% 0.20 1387.02
C.MACHINERY :
Batching plant 0.50cum 0.308 hours 222.90
Crew charges 0.308 hours 387.40
Add MA on crew charges 0.20 119.32
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 4600.00
Common burnt clay bricks 23x11x7cms 512 Nos 6471.26
Fine aggregate ( Sand ) 0.20 cu.m. 750.00
B.LABOUR :
1st class mason 0.24 Nos. 500.00
2nd class mason 0.56 Nos. 460.00
Mazdoor (Unskilled) 1.89 Nos. 420.00
Add for MA @ 20% 0.20 1171.40
water charges @ 1% 0.01 5034.57
Rate per 1 cum
a Up to basement
Rate as worked out above 1.00 Cum 5084.91
Overheads & Contractors Profit @13.615% 0.13615 5084.91
Rate per 1 cum
b) Superstructure :
Rate for other Floors FF SF
Rate as worked out above 5084.91 5084.91
Hire charges for Access Scaffolding 30.35 30.35
Labour charges for scaffolding 233.71 334.65
Add for MA @ 20% 46.74 66.93
Lift charges ( Page 131 of Std. Data ) 0.00 117.14
Add for MA @ 20% 0.00 23.43
Rate per 1 cum 5395.72 5657.41
Overheads & Contractors Profit @13.615% 734.63 770.26
Rate per 1 cum 6130.35 6427.67
Say 6130 6428
12 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Sand) using common burn
class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x 11 x 7 cms from approved source h
crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement, screened sand, br
to site, labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
overheads & contractors profit complete for finished item of work. (APSS No. 501 & 504).
(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 4600.00
Common burnt clay bricks 23x11x7cms 512 Nos 6471.26
Fine aggregate ( Sand ) 0.20 cu.m. 750.00
B.LABOUR :
1st class mason 0.24 Nos. 500.00
2nd class mason 0.56 Nos. 460.00
Mazdoor (Unskilled) 1.89 Nos. 420.00
Add for MA @ 20% 0.20 1171.40
water charges @ 1% 0.01 5034.57
Rate per 1 cum
a Up to basement
Rate as worked out above 1.00 Cum 5084.91
Overheads & Contractors Profit @13.615% 0.13615 5084.91
Rate per 1 cum
b) Superstructure :
Rate for other Floors FF SF TF
Rate as worked out above 5084.91 5084.91 5084.91
Hire charges for Access Scaffolding 44.87 44.87 44.87
Labour charges for scaffolding 345.48 494.70 643.87
Add for MA @ 20% 69.10 98.94 128.77
Lift charges ( Page 131 of Std. Data ) 0.00 117.14 234.28
Add for MA @ 20% 0.00 23.43 46.86
Rate per 1 cum 5544.36 5863.99 6183.56
Overheads & Contractors Profit @13.615% 754.86 798.38 841.89
Rate per 1 cum 6299.22 6662.37 7025.45
Say 6299 6662 7025
13 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement : Sand) using
bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size
(BLD-CSTN-5-12) 23 x 11 x 7 cms
Unit - 10sqm
A.MATERIALS :
Common burnt clay bricks 23x11x7cms 565 Nos. 6471.26
Cement 79.20 Kgs 4600.00
Fine aggregate ( Sand ) 0.22 cu.m. 750.00
B.LABOUR :
1st class mason 0.60 Nos. 500.00
2nd class mason 0.60 Nos. 460.00
Mazdoor (Unskilled) 2.75 Nos. 420.00
Add for MA @ 20% 0.20 1731.00
water charges @ 1% 0.01 6262.78
Rate per 10 sqm
Rate per 1 sqm
(BLD-CSTN-5-17)
Unit = 1 Cum
A.MATERIALS
No of blocks required for
1 Cum of Masonry 110 Nos 24621.86
Cement 24.00 Kgs 4600.00
Fine aggregate ( Sand ) 0.10 cu.m. 750.00
B .LABOUR
1st class mason 0.24 Nos. 500.00
2nd class mason 0.56 Nos. 460.00
Mazdoor (Unskilled) 1.89 Nos. 420.00
Add for MA @ 20% 0.20 1171.40
water charges @ 1% 0.01 4299.48
Rate per 1 cum
b) Superstructure :
Rate for other Floors FF SF TF
Rate as worked out above 4342.48 4342.48 4342.48
Hire charges for Access Scaffolding 45.87 45.87 45.87
Labour charges for scaffolding 353.16 505.69 658.18
Add for MA @ 20% 70.63 101.14 131.64
Lift charges ( Page 131 of Std. Data ) 0.00 117.14 234.28
Add for MA @ 20% 0.00 23.43 46.86
4812.14 5135.74 5459.30
Overheads & Contractors Profit @13.615% 655.17 699.23 743.28
Rate per 1 cum 5467.31 5834.97 6202.58
Say 5467 5835 6203
(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
Flyash lime solid blocks 247 Nos. 11276.38
Cement 36.00 Kgs 4600.00
Fine aggregate ( Sand ) 0.10 cu.m. 750.00
B.LABOUR :
1st class mason 0.60 Nos. 500.00
2nd class mason 0.60 Nos. 460.00
Mazdoor (Unskilled) 2.75 Nos. 420.00
Add for MA @ 20% 0.20 1731.00
water charges @ 1% 0.01 5103.07
Rate per 10 sqm
Rate per 1 sqm
Internal walls :
Rate for other Floors FF SF TF
Rate as worked out above 515.41 515.41 515.41
Hire charges for Access Scaffolding 10.32 10.32 10.32
Labour charges for scaffolding 79.46 113.78 148.09
Add for MA @ 20% 15.89 22.76 29.62
Lift charges ( Page 131 of Std. Data ) 0.00 17.31 34.62
Add for MA @ 20% 0.00 3.46 6.92
Rate per 1 sqm 621.08 683.04 744.98
Overheads & Contractors Profit @13.615% 84.56 93.00 101.43
Rate per 1 sqm 705.64 776.04 846.41
Say 706 776 846
Internal walls :
Rate for other Floors FF SF TF
Rate as worked out above 234.10 234.10 234.10
Hire charges for Access Scaffolding 10.32 10.32 10.32
Labour charges for scaffolding 79.46 113.78 148.09
Add for MA @ 20% 15.89 22.76 29.62
Lift charges ( Page 131 of Std. Data ) 0.00 17.31 34.62
Add for MA @ 20% 0.00 3.46 6.92
Rate per 1 sqm 339.77 401.73 463.67
Overheads & Contractors Profit @13.615% 46.26 54.70 63.13
Rate per 1 sqm 386.03 456.43 526.80
Say 386 456 527
14 Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed hard granite metal (coa
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.
including cost and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water etc.
all charges for machine mixing, hire charges of concrete mixer, laying concrete in position, curing etc., & lift
overheads & contractors profit for bed blocks & hold fasts for finished item of work. (APSS No. 402)
15 Plain Cement Concrete (1:2:4) using 20mm size graded machine crushed hard granite metal (coarse aggregate
- 1970 and IS 2386 Part 1 to Part 8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacit
and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water etc. to site including
machine mixing, hire charges of concrete mixer, laying concrete in position, curing etc., & lift charges , an
contractors profit for septic tank bed, in sunken slabs for finished item of work. (APSS No. 402)
(BLD-CSTN-3-11)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1244.30
Sand 0.45 Cum 670.00
Cement 330.00 Kgs 4600.00
Water ( including for curing ) 1.20 Kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
C.LABOUR :
1st class mason 0.10 Nos. 500.00
Mazdoor (Unskilled) 1.39 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615 4273.17
Rate per 1 cum
16 Plain Cement Concrete M 20 nominal mix using 20mm size graded machine crushed hard granite metal (coa
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.
including cost and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water etc.
all charges centering, labour charges such as weigh batching, machine mixing, hire charges of concrete mixer, la
position, curing etc., & lift charges , and overheads & contractors profit for Kerb stone & Saucer Drain for finish
(APSS No. 402)
(BLD-CSTN-3-11)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1244.30
Sand 0.45 Cum 670.00
Cement 330.00 Kgs 4600.00
Water ( including for curing ) 1.20 Kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
Needle vibrator 40mm ( petrol ) 1.00 hours 27.60
Crew charges 1.00 hours 181.50
Add MA on crew charges 0.20 181.50
C.LABOUR :
1st class mason 0.100 Nos. 500.00
Mazdoor (Unskilled) 1.390 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
Hire charges of centering and scaffolding 1.00 Cum 64.00
Lift charges for scaffolding 1.00 Cum 341.00
Add for MA @ 20% 0.20 341.00
15 Plain Cement Concrete M 20 nominal mix using 20mm size graded machine crushed hard granite metal (coa
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.
including cost and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water etc.
all charges centering, labour charges such as weigh batching, machine mixing, hire charges of concrete mixer, la
position, curing etc., & lift charges , and overheads & contractors profit for steps for finished item of work. (APSS
(BLD-CSTN-3-11)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1244.30
Sand 0.45 Cum 670.00
Cement 330.00 Kgs 4600.00
Water ( including for curing ) 1.20 Kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
Needle vibrator 40mm ( petrol ) 1.00 hours 27.60
Crew charges 1.00 hours 181.50
Add MA on crew charges 0.20 181.50
C.LABOUR :
1st class mason 0.100 Nos. 500.00
Mazdoor (Unskilled) 1.390 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
16 Reinforced Cement Concrete M 20 nominal mix using 12mm size hard granite machine crushed graded
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum quantit
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and con
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering, sh
charges such as weigh batching, machine mixing, hire charges of concrete mixer, laying concrete, lift charges,
overheads & contractors profit complete for finished item of work (APSS No. 402 & 403) for sill slabs.
(BLD-CSTN-3-13 - A)
A.MATERIALS :
Cement 330.00 Kgs 4600.00
12mm HBG graded metal 0.90 Cum 1044.80
Sand 0.45 Cum 670.00
B.LABOUR :
1st class Mason 0.133 Nos 500.00
2nd class Mason 0.267 Nos 460.00
Mazdoor (both Men & Women) 3.60 Nos 420.00
Add for MA @ 20% 0.20 1701.32
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
Water(including for curing) 1.20 kl 107.00
Basic cost per 1 cum
19 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters including labo
straightening,
(BLD-CSTN-4.2) cutting, bending to in
& Amendment required sizes and
SoR 2011-12 shapes,
page placing in position with cover blocks of approved ma
No. 392
Unit - 1 MT
a) Material
Mild steel bars including 5% for overlaps and
wastage 1.05 MT 39000.00
Binding wire 6.00 Kgs 55.00
b) Labour for cutting, bending, shifting to site,
tying and placing in position
1st class Blacksmith / Barbender 3.00 Nos. 625.00
2nd class Blacksmith / Barbender 7.00 Nos. 495.00
Mazdoor(Unskilled) 10.00 Nos. 420.00
Add for MA @ 20% 0.20 9540.00
2 Fabrication,supplying,erecting and fixing in position tubular steel trusses and roof frame work with
structural steel tubes confirming to IS 1161-1979 consisting of principal rafters, ties, purlins,cleats, holding d
plates and gusset plates(the member sizes as per the approved drawing ) complete painted with one coat of
primer, including cost and conveyance of all materials to work site and all operational, incidental,labour charge
welding of joints at site and painting one coat of primer complete and as directed by the Engineer-in-charge for
work IS 1161-1979 & IS 806
21 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top coat
CM (1:4) with dubara sponge finishing including cost and conveyance of all materials like cement, sand, water etc
operational, incidental charges on materials and including cost of all labour charges for mixing mortar, finishing
charges, curing, including cutting grooves as directed by Engineer - in - charge etc., and overheads & contractors
for finished item of work. (SS 901,903 & 904)
( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 4600.00
Fine aggregate (Sand) 0.11 Cum 750.00
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 4600.00
Fine aggregate (Sand) 0.04 Cum 750.00
B.LABOUR :
1st Class Mason 0.63 Nos. 500.00
2nd Class Mason 1.47 Nos. 460.00
Mazdoor (Unskilled) 3.90 Nos. 420.00
Add for MA @ 20% 0.20 2629.20
water charges @ 1% 0.01 3455.22
Rate per 10 sqm
Rate per 1 sqm
Walls in superstructure :
Rate for other Floors FF SF TF
Rate as worked out above 348.98 348.98 348.98
Hire charges for Access Scaffolding 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.81
Add for MA @ 20% 1.59 2.28 2.96
Lift charges ( Page 131 of Std. Data ) 0.00 26.29 52.58
Add for MA @ 20% 0.00 5.26 10.52
Rate per 1 sqm 359.55 395.22 430.88
Overheads & Contractors Profit @13.615% 48.95 53.81 58.66
Rate per 1 sqm 408.50 449.03 489.54
Say 409 449 490
22 Plastering 12mm thick single coat in CM(1:5) using screened sand including cost and conveyance of all materi
sand, water etc., to site and all operational, incidental charges on materials and including cost of all labour cha
mortar, finishing, curing as directed by Engineer-in-charge etc., and overheads & contractors profit complete for
work.(SS 901,903 & 904)
a) for basement :
Rate per 1 sqm 1.00 sqm 259.77
Overheads & Contractors Profit @13.615% 0.13615 259.77
Rate per 1 sqm
b) Walls in superstructure :
Rate for other Floors FF SF TF
Rate as worked out above 259.77 259.77 259.77
Hire charges for Access Scaffolding 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.81
Add for MA @ 20% 1.59 2.28 2.96
Lift charges ( Page 131 of Std. Data ) 0.00 18.84 37.68
Add for MA @ 20% 0.00 3.77 7.54
Rate per 1 sqm 270.34 297.06 323.79
Overheads & Contractors Profit @13.615% 36.81 40.45 44.08
Rate per 1 sqm 307.15 337.51 367.87
Say 307 338 368
23 Plastering 20mm thick in two coats using screened sand with base coat of 16mm thick in CM(1:6) and top co
in CM(1:4) with dubara sponge finishing including cost and conveyance of all materials like cement, sand, water
(BLD-CSTN-8-9)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 16mm thick
Cement 43.20 Kgs 4600.00
Fine aggregate (Sand) 0.18 Cum 750.00
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 4600.00
Fine aggregate (Sand) 0.04 Cum 750.00
B.LABOUR :
1st Class Mason 0.63 Nos. 500.00
2nd Class Mason 1.47 Nos. 460.00
Mazdoor (Unskilled) 3.90 Nos. 420.00
Add for MA @ 20% 0.20 2629.20
water charges @ 1% 0.01 3585.00
Rate per 10 sqm
Rate per 1 sqm
Walls in superstructure :
Rate for other Floors Cellar/FF SF TF
Rate as worked out above 362.09 362.09 362.09
Hire charges for Access Scaffolding 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.81
Add for MA @ 20% 1.59 2.28 2.96
Lift charges ( Page 131 of Std. Data ) 0.00 26.29 52.58
Add for MA @ 20% 0.00 5.26 10.52
Rate per 1 sqm 372.66 408.33 443.99
Overheads & Contractors Profit @13.615% 50.74 55.59 60.45
Rate per 1 sqm 423.40 463.92 504.44
Say 423 464 504
b) Walls in superstructure :
Rate for other Floors FF SF TF
Rate as worked out above 272.35 272.35 272.35
Hire charges for Access Scaffolding 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.81
Add for MA @ 20% 1.59 2.28 2.96
Lift charges ( Page 131 of Std. Data ) 0.00 18.84 37.68
Add for MA @ 20% 0.00 3.77 7.54
282.92 309.65 336.37
Overheads & Contractors Profit @13.615% 38.52 42.16 45.80
Rate per 1 sqm 321.44 351.81 382.17
Say 321 352 382
24 Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3) prop. using
20mm thick (average) mixed with integral cement water proofing liquid confirming to IS: 2645-2003 manufactu
manufacturers as approved by Engineer-in-charge at 200ml per one bag of cement, laid over roof slab when it is
smooth with a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost and
all materials like cement, sand, water proofing compound, water etc., to site, operational, incidental, and lab
mixing mortar, laying, lift charges, rendering smooth and thread lining, curing including rounding off junctions o
etc., and overheads & contractors profit complete for finished item of work. (APSS No. 901 & 903).
(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cement 100.80 Kgs 4600.00
Fine aggregate (Sand) 0.21 Cum 750.00
Integral cement waterproofing liquid 0.40 Ltrs 190.00
B.LABOUR :
1st Class Mason 0.66 Nos. 500.00
2nd Class Mason 1.54 Nos. 460.00
Mazdoor (Unskilled) 3.70 Nos. 420.00
Add for MA @ 20% 0.20 2592.40
water charges @ 1% 0.01 3808.06
Rate per 10 sqm
26 Providing specialized high performance acrylic polymer modified elastomeric cementitious waterproof
bottom and sides of sunken slabs of toilets duly cleaning of the surface from dirt, dust and other contamina
and application of two coats of high performance Acrylic polymer modified Elastomeric cementitious waterproof c
Mtr. / Kg /Each Coat ) including cost and conveyance of all materials to site, operationals & incidental charges, l
and overheads & contractors profit complete for finished item of work
(BLD-CSTN-8-11)
Unit : 10 sqm
A)MATERIALS
Rabbit wire mesh 13.30 sqm 17.00
Cement for base coat and plastering 240.00 Kgs 4600.00
Cement for lumps 50.00 Kgs 4600.00
Fine aggregate (Sand) 0.50 cu.m. 750.00
Excluding TMT steel/mild steel & binding wire
B) LABOUR CHARGES
1st Class Mason 8.00 Nos. 500.00
Operator concrete mixer 1.00 Nos. 510.00
Mazdoor (Unskilled) 10.00 Nos. 420.00
Add for MA @ 20% 0.20 8710.00
C)Machinery :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 2.00 hours 142.20
Crew charges 2.00 hours 252.20
Add MA on crew charges 0.20 252.20
water charges @ 1% 0.01 13276.78
Rate per 10 sqm
Rate per 1 sqm
28 Flooring with polished shahabad / Tandur stone slabs of 15 mm to 18 mm thick set over a base coat of C
thick using screened sand over already laid CC bed / RCC roof slab including neat cement slurry of honey l
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished shahabad stone 15 to 18mm thick 11.00 sqm 1620.53
Cement for CM (1:8) proportion for base coat
21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
Cement for pointing 20.00 Kgs 4600.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 3.10 Nos 500.00
Mason 2nd class 1.10 Nos 460.00
Mazdoor(un skilled) 0.86 Nos 420.00
Add for MA @ 20% 0.20 2417.20
Add water charges 1% 0.01 5116.38
Rate for 10 sqm
29 Flooring with Polished black Kadapa slabs minimum of 15 mm thick of size 0.457m x 0.457m
(1:8) , 12mm thick using screened sand over already laid CC bed / RCC roof slab including neat cement slur
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished black Kadapa slabs minimum of
15mm thick 11.00 sqm 1352.58
Cement for CM (1:8) proportion for base coat
21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
Cement for pointing 20.00 Kgs 4600.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 3.10 Nos 500.00
Mason 2nd class 1.10 Nos 460.00
Mazdoor(un skilled) 0.86 Nos 420.00
Add for MA @ 20% 0.20 2417.20
Add water charges 1% 0.01 4821.64
Rate for 10 sqm
(BLD-CSTN-9-6)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles 7 to 8mm thick (300mm x
300mm) 10.50 sqm 370.00
Cement for CM(1:8) proportion for base coat 21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White Cement 2.00 Kgs 27.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 0.96 Nos 500.00
Mason 2nd class 2.24 Nos 460.00
Mazdoor(un skilled) 3.30 Nos 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 7755.84
Rate for 10 sqm
30 Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm
between 8-10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finis
(BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Vitrified tiles 8 to 10mm thick of size 600mm x
600mm 10.50 sqm 418.00
Cement for CM(1:8)proportion for base coat 21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White Cement 6.00 Kgs 27.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 0.96 Nos 500.00
Mason 2nd class 2.24 Nos 460.00
Mazdoor(un skilled) 3.30 Nos 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 8367.84
Rate for 10 sqm
29 Flooring with non-skid Double charged / multi charged stain free full body porcelain vitrified tiles with
pigment of Size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712,
(BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Vitrified tiles 8 to 10mm thick of size 600mm x
600mm 10.50 sqm 612.00
Cement for CM(1:8)proportion for base coat 21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White Cement 6.00 Kgs 27.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 0.96 Nos 500.00
Mason 2nd class 2.24 Nos 460.00
Mazdoor(un skilled) 3.30 Nos 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 10404.84
Rate for 10 sqm
(BLD-CSTN-9-9)
Unit = 10 sqm.
A. MATERIALS:
Granite stone tiles 8mm thick (mirror polished
of all shades) 10.50 sqm 1005.00
Cement for CM(1:8) for base coat 21.60 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White Cement 6.00 Kgs 27.00
Sand for CM(1:8) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 0.96 Nos 500.00
Mason 2nd class 2.24 Nos 460.00
Mazdoor(un skilled) 3.30 Nos 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 14531.34
Rate for 10 sqm
30 Flooring with 16 mm to 18 mm thick high polished granite stone slabs other than black and regular
shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and design as per the patte
the Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thick
sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey like consistency sp
per sqm and jointed neatly with white cement paste mixed with pigment of matching shade to full depth inc
conveyance of all materials like cement , sand , water , granite slabs etc., to work site and all operational, incide
charges, polishing charges, cost of base coat and overheads & contractors profit complete for finished item of w
special)
(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other than black 16
to 18mm thick 10.50 sqm 2342.00
Cement for CM(1:8) for base coat 36.00 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing 6.00 Kgs 27.00
Sand for CM(1:8) 0.20 Cum 750.00
B .LABOUR
Mason 1st class 3.00 Nos 500.00
Mason 2nd class 1.00 Nos 460.00
Mazdoor(un skilled) 8.00 Nos 420.00
Add for MA @ 20% 0.20 5320.00
Add water charges 1% 0.01 31604.40
Rate for 10 sqm
32 Providing window sills with 16 mm to 18 mm thick high polished granite stone slabs black colour as a
Engineer-in-Charge set over base coat of cement mortar (1:8) , 20mm thick using screened sand over CC b
including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with whit
mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement
granite slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the edge , po
cost of base coat and overheads & contractors profit complete for finished item of work (S.S.701 & special)
(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs black 16 to 18mm
thick 10.50 sqm 1991.00
Cement for CM(1:8) for base coat 36.00 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing 6.00 Kgs 27.00
Sand for CM(1:8) 0.20 Cum 750.00
B .LABOUR
Mason 1st class 3.00 Nos 500.00
Mason 2nd class 1.00 Nos 460.00
Mazdoor(un skilled) 8.00 Nos 420.00
Add for MA @ 20% 0.20 5320.00
Machine cutting charges 43.48 RM 17.00
Half rounding the edges 43.48 RM 318.00
Add for MA @ 20% 0.20 5826.32
Add water charges 1% 0.01 43649.96
Rate for 10 sqm
(BLD-CSTN-9-13)
Unit : 10sqm
A.MATERIALS :
6mm to 12mm HBG Metal 0.17 Cum 1044.80
Cement 120.00 Kgs 4600.00
Sand 0.085 Cum 670.00
Add for glass strips 10.00 sqm 10.00
B. LABOUR
Mason 1st class 1.25 Nos. 500.00
Mason 2nd class 0.06 Nos. 460.00
Mazdoor (unskiled) 3.00 Nos. 420.00
Add for MA @ 20% 0.20 1912.60
Add water charges 1% 0.01 3181.69
Rate per 10 sqm
(BLD-CSTN-9-4)
Unit : 10sqm
A.MATERIALS :
Chequred tiles 25mm thick 10.50 sqm 269.00
Cement for CM(1:6) proportion for base coat 28.80 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 6.00 Kgs 27.00
Sand for CM(1:6) proportion 0.12 Cum 750.00
B. LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor (unskiled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 6836.46
Rate per 10 sqm
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
Cement 400.00 Kgs 4600.00
Water ( including for curing ) 1.20 Kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
Needle vibrator 40mm ( petrol ) 1.00 hours 27.60
Crew charges 1.00 hours 181.50
Add MA on crew charges 0.20 181.50
C.LABOUR :
1st class mason 0.100 Nos. 500.00
Mazdoor (Unskilled) 1.390 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
69 Supply of precast concrete blocks for paving of M-40 grade and thickness not less than 80 mm for Mediu
conforming to IS 15658:2006 in all shapes and designs as per the manufacturer's specification including cost and
all materials and all labour charges etc.
34 Supply and application of epoxy flooring of light green or light blue colour in Operation Theatres and labou
Epoxy seamless joint free finish with 3mm thickness and anti slip & water washable chemical resistance durable a
shedding with attractive finishing including cost and conveyance of all materials and all labour charges,
contractor profit etc., complete for finished item of work.
Supplying and fixing of teak wood flooring using mill run grate / certified better grade teak wood as per drawin
wood runners of size 65mmx40mm placed at 275mm C/C over the polythene sheet acting as vapour barrior and f
reapers of 19mm thick including cost of teak wood reapers, runners, polythene sheet, fitting with steel pins and r
etc., complete including labour charges for laying strips, frizes for parquest flooring continuously shaped, to
rebratred, chamfered, rejointed, beeded moulded, rounded along of any its edges, ends or facer, etc.,
conveyance, tax, duties etc., complete for finished item of work.
+0.007
= 0.164 0.164 87017.00
No. of wooden reapers 75mm x19 mm
@ 75 C/C 4/0.075 = 5.33 or Say 54 Nos.
54 No . 54X4X0.0
Add 5% wastage 75X0.019
= 0.3078
+0.015
=0.323
0.323 142391.00
Rubber shoker @ 200 C/C
No. of shokers 4/0.20 = 20 15X20 =
Total No. 15X20 300
300 20.00
Polythene sheets of 125 microns 4 x 4 4X4 = 16 16 18.00
Screw 75 mm for fixing the RCC to floor 100
no. 10 Sqm 16X10 = 1 160.00 4.00
Labour
1st class carpenter 3.12 Nos. 520.00
2nd class carpenter 7.28 Nos. 460.00
Man Mazdoor 8.64 Nos. 420.00
Add for MA @ 20% 0.20 8600.00
Rate per 16 Sqm
Rate per 1 Sqm
Overheads & Contractors Profit @13.615% 0.13615 4845.05
approved brand PU including cost & labour charges for laying strips, frizes for parquest flooring continuously s
grooved, rebratred, chamfered, rejointed, beeded moulded, rounded along of any its edges, ends or facer, etc.,
cost of thinner & PU of approved brands such as Jenson & Nichosln, Asian paints, Berger paints or equivalen
cost, conveyance etc., complete for finished item of work.
Rate as per DSR 2019 - item code 11.34 1.00 sqm 9971.20
Rate for 1 Sqm
36 Providing Polished black Kadapa slabs minimum of 15 mm thick in single piece as specified set over a b
a) (1:5)
Treads, 12mm thickwide
of 0.30m using
: screened sand over already laid CC bed / RCC roof slab including neat cement slur
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished black Kadapa slabs minimum of
15mm thick 11.00 sqm 2028.87
Cement for CM (1:5) proportion for base coat
34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
Cement for jointing 20.00 Kgs 4600.00
Sand for CM(1:5) 0.12 Cum 750.00
B .LABOUR
Mason 1st class 3.10 Nos 500.00
Mason 2nd class 1.10 Nos 460.00
Mazdoor(un skilled) 0.86 Nos 420.00
Add for MA @ 20% 0.20 2417.20
Flat nosing the edges 33.33 RM 50.00
Add for MA @ 20% 0.20 666.60
Add water charges 1% 0.01 7424.99
Rate for 10 sqm
34 Providing 16 mm to 18 mm thick high polished leather finish granite stone slabs (steel grey or pearl blac
and design as per the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base
mortar (1:5) , 12mm thick using screened sand over CC bed already laid or RCC roof slab including neat grey c
honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigm
shade to full depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc., t
all operational, incidental labour & lift charges, full rounding the edges of treads , providing 3 grooves of size 2mm
full length of treads , polishing charges, cost of base coat and overheads & contractors profit complete for finish
for treads and risers (S.S.701 & special)
36 Providing skirting to internal walls to 10 cm height with Polished Kadapa stone slabs
equal to flooring stones set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurr
(BLD-CSTN-9-22)
Unit = 10 sqm
A.MATERIALS :
Cost of Kdapa stone slabs 10.50 sqm 1352.58
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
B.LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor(unskilled) 3.10 Nos. 420.00
Add for MA @ 20% 0.20 2812.40
Add water charges 1% 0.01 5195.87
Rate for 10 sqm
37 Providing skirting to internal walls to 10 cm height with non-skid red or white full body ceramic floor til
between 7-8 mm 1st quality of any colour and finish in all shades and designs as approved by Engineer-in-charg
(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of full body ceramic tiles 8 mm thick 10.50 sqm 374.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 6.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.77 Nos. 500.00
Mazdoor(unskilled) 0.80 Nos. 420.00
Add for MA @ 20% 0.20 721.00
Add water charges 1% 0.01 5354.98
Rate per 10 sqm
38 Providing skirting to internal walls to 10 cm height with Soluble salt porcelain vitrified tiles screen printed
of 8 to 10mm thick of any colour and finish in all shades and designs, length equal to flooring tiles, set over base
(BLD-CSTN-9-20)
Unit = 10 sqm
Cost of vitrified tiles 8-10mm thick 10.50 sqm 418.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 2.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor(unskilled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 8319.46
Rate for 10 sqm
(BLD-CSTN-9-20)
Unit = 10 sqm
Cost of vitrified tiles 8-10mm thick 10.50 sqm 612.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 2.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor(unskilled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 10356.46
Rate for 10 sqm
37 Supply and application of epoxy coving with SIKA brand with 50mmx50mm width at the corners of the all wall
Theatres, labour rooms including cost and conveyance of all materials and labour charges, overheads and c
etc., complete for finished item of work .
38 Cladding to internal walls with 8 mm thick mirror polished granite tiles length equal to flooring tiles, set ov
CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.
(BLD-CSTN-9-21)
Unit = 10 sqm
A.MATERIALS :
Cost of granite tiles 8mm thick 10.50 sqm 1005.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 5.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor(unskilled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 14563.96
Rate for 10 sqm
Rate for other Floors FF SF TF
Rate as worked out above 14709.60 14709.60 14709.60
Lift charges ( Page 131 of Std. Data ) 0.00 289.64 579.28
Add for MA @ 20% 0.00 57.93 115.86
14709.60 15057.16 15404.73
Overheads & Contractors Profit @13.615% 2002.71 2050.03 2097.35
Rate per 10 sqm 16712.31 17107.19 17502.08
Rate per 1 sqm 1671.23 1710.72 1750.21
Say 1671 1711 1750
36 Providing skirting to internal walls 10 cm height with High Polished Granite 16 mm to 18 mm thick
other than black and regular colours, length equal to flooring slabs set over base coat of CM(1:5) 12 mm thick
(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2342.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 5.00 Kgs 27.00
Machine cutting charges 66.67 RM 17.00
Add for MA @ 20% 0.20 453.36
B.LABOUR
Mason 1st class 2.10 Nos. 500.00
Man Mazdoor(Beldar) 4.90 Nos. 420.00
Add for MA @ 20% 0.20 3108.00
Add water charges 1% 0.01 30080.44
Rate for 10 sqm
37 Providing cladding to walls with High Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) other
regular colours, length equal to flooring slabs set over base coat of CM(1:5) 12 mm thick using screened sand wit
of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed
matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., and overhead
profit complete for finished item of work.
(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2342.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 5.00 Kgs 27.00
Machine cutting charges 66.67 RM 17.00
Add for MA @ 20% 0.20 453.36
B.LABOUR
Mason 1st class 2.10 Nos. 500.00
Man Mazdoor(Beldar) 4.90 Nos. 420.00
Add for MA @ 20% 0.20 3108.00
Add water charges 1% 0.01 30080.44
Rate for 10 sqm
38 Providing dadooing with glazed red or white full body ceramic wall tiles of size 300 x 450 mm / 320 mm
thickness 6 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in
designs with borders as approved by Engineer-in-Charge flushed to wall surface set over base coat of CM(1
using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and joi
cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cem
water etc., and overheads & contractors profit complete for finished item of work.
(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of glazed coloured tiles 10.50 sqm 396.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 6.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.77 Nos. 500.00
Mazdoor(unskilled) 0.80 Nos. 420.00
Add for MA @ 20% 0.20 721.00
Add water charges 1% 0.01 5585.98
Rate for 10 sqm
(BLD-CSTN-9-20)
Unit = 10 sqm
A.MATERIALS :
Cost of porcelain wall tiles 10.50 sqm 554.00
Sand for CM(1:5) base coat 0.12 cum 750.00
Cement for CM(1:5) base coat 34.56 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 2.00 Kgs 27.00
B.LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor(unskilled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 9747.46
Rate for 10 sqm
40 Flooring with plain Cement Concrete general purpose tiles conforming to IS: 13801 using aggregates, ceme
size 300 x 300 mm and thickness 20 mm of any shade set over base coat of cement mortar (1:6), 12 mm thick
sand over CC bed already laid of any shades as approved by Engineer - In - Charge including neat cement slur
consistency spread @ 3.3 kgs per sqm and jointed with neat white cement to full depth mixed with pigment of m
including cost and conveyance of all materials like cement, sand, water and tiles etc.,and overheads & co
complete for finished item of work.
(BLD-CSTN-9-4)
Unit : 10sqm
A.MATERIALS :
Plain cement concrete tiles 300mm x 300mm
BMT-D.04 10.50 sqm 241.00
Cement for CM(1:6) proportion for base coat 28.80 Kgs 4600.00
Cement for slurry 33.00 Kgs 4600.00
White cement for jointing & pointing 6.00 Kgs 27.00
Sand for CM(1:6) proportion 0.12 Cum 750.00
B. LABOUR
Mason 1st class 0.96 Nos. 500.00
Mason 2nd class 2.24 Nos. 460.00
Mazdoor (unskiled) 3.30 Nos. 420.00
Add for MA @ 20% 0.20 2896.40
Add water charges 1% 0.01 6542.46
Rate per 10 sqm
Rate per 1 sqm
41 Providing plinth protection using plain Cement Concrete general purpose tiles conforming to IS: 13801 us
cement, pigments of size 300 x 300 mm and thickness 20 mm of any shade for a width of 1200mm set ov
cement mortar (1:6), 12 mm thick using screened sand over PCC(1:5:10) bed 100mm thick along with drain c
225 mm thick walls using fly ash cement / lime solid blocks of size 290mm x 225mm x 140mm from approved
minimum crushing strength of 50 Kg/Sqcm. and plastering 2mm thick two coats with base coat of 8mm thick in C
coat of 4mm thick in CM (1:4) for brick masonry drain, laying of tiles in between basement of the building and br
directed by the Engineer - in - charge including cost and conveyance of all materials to site, all labour charge
cement concrete, laying, curing, overheads & contractor profit etc., complete for finished item of work.
40 Filling with light weight concrete in Cement Concrete (1:5:10) proportion using brick jelly for low roofs inc
conveyance of all materials like cement, sand, brick bats etc., to site including cost of all labour charges for
ramming, curing , overheads & contractors profit etc., complete for finished item of work. (APSS. No. 402)
(BLD-CSTN-3-7)
Unit: 1 Cum
2
Cement 129.60 Kgs 4600.00
Cost of brick jelly 20mm size(1/3rd rate) 460 Nos. 6471.26
Fine aggregate ( Sand ) 0.45 Cum 670.00
Water (including curing) 1.20 kl 103.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
C.LABOUR :
1st class mason 0.10 Nos. 500.00
Mazdoor (unskilled) 1.39 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate for other Floors FF SF TF
Rate as above 3218.92 3218.92 3218.92
Lift charges ( Page 131 of Std. Data ) 0.00 63.38 126.76
Add for MA @ 20% 0.00 12.68 25.35
Rate per 1 cum 3218.92 3294.98 3371.03
Overheads & Contractors Profit @13.615% 438.26 448.61 458.97
Rate per 1 cum 3657.18 3743.59 3830.00
Say 3657 3744 3830
40 Filling with well burnt cinder aggregate as per IS:2686-1977 in sunken slabs including cost and convey
labour charges for filling, ramming, overheads and contractor profit etc., complete for finished item of work
Unit : 1 cum
Taking output 6.00 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 420.00
Add for MA @ 20% 0.20 130.20
b)Material :
Cost of well burnt cinder aggregate 6.00 cum 614.00
Rate per 6 cum
(BLDS-CSTN-3-13)
Unit: 1 Cum
A.MATERIALS :
Cement 129.60 Kgs 4600.00
40mm HBG metal 0.90 Cum 897.80
Sand 0.45 Cum 670.00
B.LABOUR :
1st class Mason 0.167 Nos 500.00
2nd class Mason 0.167 Nos 460.00
Mazdoor (unskilled) 4.70 Nos 420.00
Add for MA @ 20% 0.20 2134.32
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew charges 1.00 hour 252.20
Needle vibrator 40mm ( petrol ) 1.00 hour 27.60
Crew charges 1.00 hour 181.50
Add MA on crew charges 0.20 433.70
Water(including for curing) 1.20 kl 107.00
Basic cost per 1 cum
Rate per 1 RM
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 2833.07
43 Supplying and fixing of stainless steel (grade 304) railing for ramp as per approved drawing with top rail of
and 2mm thick medium class fixed in to wall with 25mm dia pipe of 0.30m length @ 1m centre to centre and w
polishing all members of the railing thouroughly , lacquer finishing to present seamless finish including cost and
all materials, electrodes, welding charges, cost of all consumables, labour charges , overheads & contrac
complete for finished item of work.
Rate per 10 RM
Overheads & Contractors Profit @13.615% 0.13615 1257.09
44 Supplying and fixing of stainless steel (grade 304) grab bars 200mm length grab bars in toilets as per ap
with 25mm dia pipe with base plates 2 Nos., buffing, polishing thouroughly , lacquer finishing to present
including cost and conveyance of all materials, labour charges , overheads & contractors profit etc., complete for
work.
45 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressur
including cost of necessary PVC Bends, shoes, iron / PVC clamps and all other accessories and fixing in positio
and conveyance of all materials, operational & incidental charges including all labour charges for fixing a
overheads & contractors profit complete for finished item of work. (APSS No. 1328)
PVC pipe 110mm dia 6.00 RM 162.00
MS Clamps 3 Nos. 15.00
Labour charges for fixing pipes 6.00 RM 70.00
Rate per 6 RM
46 Supply and fixing jallies ( cement concrete ) of 50mm thick as per the design approved by the Engineer-in-Ch
cost and conveyance of materials to site and labour charges etc., overheads & contractors profit complete for
work.
(BLD-CSTN-11-5)
Unit : 10 sqm
A.MATERIALS :
White cement 2.00 kgs 27.00
B.LABOUR :
Painter 1st class 0.063 Nos. 580.00
Painter 2nd class 0.147 Nos. 460.00
Mazdoor(unskilled) 0.32 Nos. 420.00
Add for MA @ 20% 0.20 238.56
Sundries including brushes , ladders etc., @
1% 1% 340.27
Rate per 10 sqm
Overheads & Contractors Profit @13.615% 0.13615 343.67
Rate per 10 sqm
Rate per 1 sqm
48 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2 mm
plastered surface to prepare the surface even and smooth after thoroughly brushing the surface to remove all dirt
loose powdered materials, applying emery paper, Sand the surface, clean & wipe off loose dust, applying knifin
putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparatio
and conveyance of all materials to work site and all operational, incidental, labour charges, over heads and c
etc., complete for finished item of work in all floors for internal walls
49 Providing and applying exterior texture of average 2 to 3 mm thickness over plastered surface to prepare th
and smooth after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials,
paper, Sand the surface, clean & wipe off loose dust, applying putty/ texture paint filler by putty knife / muslin pad
- 3 hrs for the surface preparation including cost and conveyance of all materials to work site and all operatio
labour charges, scaffolding charges, overheads and contractors profit etc., complete for finished item of work
external walls
(BLD-CSTN-12-1)
Unit = 10 sqm
Cost of white cement 0.50 Kg 27.00
Painter 1st class 0.08 Nos. 580.00
Painter 2nd class 0.19 Nos. 460.00
Cost of washable oil bound distemper 1.70 Ltrs 81.00
Painter 1st class 0.36 Nos. 580.00
Painter 2nd class 0.84 Nos. 460.00
Add for MA @ 20% 0.20 729.00
Sundries including brushes , ladders etc., @
1% 0.01 1026.00
51 Painting to old walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC conten
grams/litre as approved by Engineer-In-Charge, to give an even shade after thourughly brushing the old surfac
(BLD-CSTN-11-10)
Unit = 10 sqm
Cost of washable oil bound distemper 1.70 Ltrs 81.00
Painter 1st class 0.36 Nos. 580.00
Painter 2nd class 0.84 Nos. 460.00
Add for MA @ 20% 0.20 595.20
Sundries including brushes , ladders etc., @
1% 0.01 851.94
52 Painting to new walls with 2 coats of water proof cement paint of shade as approved by the Engineer-In
base coat of aproved
(BLD-CSTN-12-1 white cement base coat making 3 coats in all to give an even shade after thourughly brush
& 12-5)
Cost of white cement for base coat 1.00 Kgs 27.00
Painter 1st class 0.08 Nos. 580.00
Painter 2nd class 0.19 Nos. 460.00
Water proof cement paint 2.00 Kgs 1009.00
Painter 1st class 0.15 Nos. 580.00
Painter 2nd class 0.35 Nos. 460.00
Mazdoor(unskilled) 1.50 Nos. 420.00
Add for MA @ 20% 0.20 1011.80
Sundries including brushes , ladders etc., @
1% 0.01 1321.88
53 Painting to old walls with 2 coats of water proof cement paint of shade as approved by the Engineer-In-Ch
even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, inc
(BLD-CSTN-12-4)
Water proof cement paint 2.00 Kgs 1009.00
Painter 1st class 0.15 Nos. 580.00
Painter 2nd class 0.35 Nos. 460.00
Mazdoor(unskilled) 1.50 Nos. 420.00
Add for MA @ 20% 0.20 878.00
Sundries including brushes , ladders etc., @
1% 0.01 1134.32
54 Supply & application of one coat water based cement primer of interior grade I and two coats of acrylic
having VOC (VolatileAmendment
(BLD-CSTN-12-2& Organic Compound) content less than 50 grams/litre for internal walls
in SoR 2011-12)
Unit 10 sqm.
A. Materials:-
Cost of cement primer interior grade I 1.00 Kg 141.00
Painter 1st class 0.21 Nos. 580.00
Painter 2nd class 0.49 Nos. 460.00
Acrylic emulsion paint 0.80 Ltrs 168.00
Painter 1st class 0.36 Nos. 580.00
Painter 2nd class 0.84 Nos. 460.00
Add for MA @ 20% 0.20 942.40
Sundries including brushes , ladders etc., @
1% 0.01 1406.28
50 Supply & application of one coat water based cement primer of interior grade I and two coats of syn
luxury plastic emulsion paint of superior grade having VOC (Volatile Organic Compound) content less than 50
internal walls including cost and conveyance of all materials to site, incidental, operational and all labour ch
overheads & contractors profit complete for finished item of work in all floors.
51 Supply & application of one coat water based cement primer of exterior grade II and two coats of a
emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for exterior walls inc
conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc.,an
contractors profit complete for finished item of work in all floors.
51 Supply & application of one coat water based cement primer of exterior grade II and two coats of syn
luxury plastic emulsion paint of superior grade having VOC (Volatile Organic Compound) content less than 50
exterior walls including cost and conveyance of all materials to site, incidental, operational and all labour ch
overheads & contractors profit complete for finished item of work in all floors.
52 Providing and applying water proof wall putty of white cement or polymer or cement based of average 1 to
over plastered surface to prepare the surface even and smooth after thoroughly brushing the surface to rem
remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off loose dust,
paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surfa
applying one coat of cement primer of interior grade-1 and two coats of poy-urethane paint (MRF) of ligh
blue colour with 1mm thickness with anti fungal and anti bacterial chemical resistance durable and non pa
including cost and conveyance of all materials to work site and all operational, incidental, labour charges, o
contractors profit etc., complete for finished item of work in all floors for internal walls and ceiling of Operatio
labour rooms.
b) primer coat
Cost of cement primer interior grade I 1.00 Kg 141.00
Painter 1st class 0.21 Nos. 580.00
Painter 2nd class 0.49 Nos. 460.00
Add for MA @ 20% 0.20 347.20
Sundries including brushes , ladders etc., @
1% 0.01 557.64
Total (a+b+c)
Overheads&Contractors Profit @13.615% 0.13615 3615.45
Rate per 10 sqm
Rate per 1 sqm
53 Painting to new wood work and flush shutters with lappam finish , over a primary coat and painting
synthetic enamel paint Grade-I VOC (Volatile Organic Compound) content less than 50 grams/litre of approved
cost and conveyance of all materials to site cost of primer coat and all labour charges etc. complete including
paper on lappam coats for neat finish and overheads & contractors profit complete in all floors (APSS No.1200, 1
1.70mts 1.80mts
54 Painting to old wood work and flush shutters with two coats of synthetic enamel paint Grade-II
Compound) content less than 50 grams/litre of approved brand and shade including cost and conveyance of all
(BLD-CSTN-12-12-196)
Cost of Synthetic Enamel Paint 1.10 Ltr 248.00
1st Class Painter 0.36 Nos. 580.00
2nd Class Painter 0.84 Nos. 460.00
Add for MA @ 20% 0.20 595.20
Sundries including brushes , ladders etc., @
1% 0.01 987.04
55 Painting primer coat on new wood work using red oxide Iron primer paint grade - 1 of approved brand inc
conveyance of all materials to site , all labour charges etc., and overheads & contractors profit complete in all flo
(BLD-CSTN-12-7)
Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 121.00
B.LABOUR :
1st Class Painter 0.21 Nos. 580.00
2nd Class Painter 0.49 Nos. 460.00
Add for MA @ 20% 0.20 347.20
Sundries including brushes , ladders etc., @
1% 0.01 501.34
56 Painting two coats with synthetic enamel paint Grade-I VOC (Volatile Organic Compound) content
grams/litre to new iron work including cost and conveyance of all materials to site, incidental, operational
charges etc., and overheads & contractors profit complete for finished item of work in all floors. (SS No. 1201, 121
(BLD-CSTN-12-12-197)
Unit : 10 sqm
A.MATERIALS :
Cost of Synthetic Enamel Paint 1.10 Ltr 248.00
B.LABOUR :
1st Class Painter 0.33 Nos. 580.00
2nd Class Painter 0.77 Nos. 460.00
Add for MA @ 20% 0.20 545.60
Sundries including brushes , ladders etc., @
1% 0.01 927.52
52 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content
grams/litre over primer coat of red oxide to new iron work including cost and conveyance of all materials to
operational and all labour charges etc., and overheads & contractors profit complete for finished item of work i
No. 1201, 1212 & 1207).
53 Painting two coats with synthetic enamel paint Gr-I having VOC (Volatile Organic Compound) conten
grams/litre to old iron work including cost and conveyance of all materials to site, incidental, operational and all
(BLD-CSTN-12-12-198)
Unit : 10 sqm
A.MATERIALS :
Cost of Synthetic Enamel Paint 0.90 Ltr 248.00
B.LABOUR :
1st Class Painter 0.33 Nos. 580.00
2nd Class Painter 0.77 Nos. 460.00
Add for MA @ 20% 0.20 545.60
Sundries including brushes , ladders etc., @
1% 0.01 877.92
53 Supply & applying Melamine Polish Glossy/ Matt finish to the wood works duly cleaning the surface and
paper, sand the wood with 180 No., emery paper and then with 320 No., emery paper, clean & wipe off loose
suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No
apply two component wood sealer, air dry for 24 hrs, sand with 320 No emery paper, applying one coat of app
thinner (for spraying)/ applying one coat of approved brushing thinner or general purpose thinner (for brushing) a
with spray or brush) two coats of approved brand melamine including cost & labour charges, emery papers, c
melamine polish, over heads and contractors profit etc., complete for finished item of work
54 Supply & applying Poly-Urethane Water Proof Polish Glossy/ Matt finish to the wood works duly cleaning
applying emery paper, sand the wood with 180 No., emery paper and then with 320 No., emery paper, clean &
dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 18
emery paper, applying two component wood sealer, after the surface preparation applying one coat of approv
thinner (for spraying) / applying one coat of approved brushing PU thinner or general purpose thinner (for brus
one coat of PU by brush or spray, air-dry overnight, sand again with 180 No. emery paper and removing dust, a
coat of PU, air drying for 4 - 6 Hrs, sand with 320 No emery paper, and applying (either with spray or brus
approved brand PU including cost & labour charges, emery papers, cost of thinner & Poly-Urethane Water Pro
heads and contracors profit etc., complete for finished item of work
54 Supply & fixing of Rolling shutter made of 80 x 1.25 mm machine rolled CRCA laths, interlocked together thro
length and jointed together at the ends by end-locks, mounted on specially designed pipe shaft of 50mm dia nom
class pipe with brackets, plates, guide channels, stoppers, bottom locking plates and arrangements for inside &
with push-pull operations including cost of hood cover and springs complete, painted with one coat of approve
locks, ball bearings, all accessories etc., overheads & contractors profit complete for finished item of work as p
1108
55 Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 mm centre, B
iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and side vertical frames of the collap
65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat for the pulleys to guide
necessary hold fasts, bolts, nuts, rivets, locking arrangements, stoppers, handles, all accessories all fixtures a
one coat of approved steel primer etc., overheads & contractors profit complete for finished item of work as per sp
56 Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25 mm thic
and conveyance of all materials to site, all incidental, operational, labour charges etc.overheads & contractors pro
finished item of work as per approved drawing for all floors
1.70mts 1.80mts
57 Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm fixed to wa
one edge and resting over the other block walls/columns concealing expansion joint with slotted holes for free edg
sheet to facilitate free movement of aluminium sheet over the finished surface of expansion joint and wall face us
screws with nylon receiver complete including cost and conveyance of all materials to site, all incidental, ope
charges , overheads & contractors profit etc., complete for finished item of work as per approved drawing (for all f
joints and bottom of slab)
58 Supplying and fixing aluminium composite cladding 4mm thick of approved make
aluminium
Rate as persheet
SSR cover material natural polyethylene1.00
aluminium
sqm cladding panel 2387.00
fixed with extruded aluminiu
Overheads & Contractors Profit @13.615% 0.13615 2387.00
Rate per 1 sqm
59 Supplying and fixing aluminium composite cladding 4mm thick of approved make
aluminium
Rate as persheet
SSR cover material natural polyethylene1.00
aluminium
sqm cladding panel 2678.00
fixed with extruded aluminiu
Overheads & Contractors Profit @13.615% 0.13615 2678.00
Rate per 1 sqm
58 Providing and Fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel / P
(Base steel as per IS 513 of ‘D’ quality, galvanized as per IS 277 with Zinc of 120 Gm/sqm) with total coat
0.72mm. The glass holding section made of 304 grade stainless steel of 0.6mm thick as per the design
calculations as given in IS: 875. Primer coat with epoxy primer of 5 – 7 microns thick, finish painted with a polye
16 microns thick and back coated with Alkyd backer of 5-7 microns or powder coated with pure polyester pow
microns thick. The vertical section should be of 50mm x100mm x 0.72mm, 33mm x 58mm x 0.72mm for frame ho
stiffener section should be 48mm x 98mm x 1mm, cover profiles sections should be of 20mm x 58mm x 0.58mm
section should be of 37mm x 37mm & 37mm x 18mm. Including 5mm thick Ocean Blue reflective glass. Brackets
powder coated/Electroplated should be used to connect vertical to horizontal, vertical to slab, to fix verticals at t
per site requirement.
Gasket made of Ethyl Propylene Diamine Monomer. Natural cure, with Good U.V. Resistance Silicon to be use
sections to concrete/masonry wall should be with self-expanding cap & screws. The rate is inclusive of cost and
all materials to site, all labour charges, incidental charges, cost of all consumables etc. and scaffolding charg
overheads & contractors profit etc., complete for finished item of work in all floors.
59 Providing and Fixing Top Hung shutters in Structural Glazing fabricated from Roll formed sections made
Steel / Powder
incidental coated
charges, (Base
cost of steel as per etc.
all consumables IS 513
andofscaffolding
‘D’ quality,charges,
galvanized
formaswork,
per IS 277 with&Zinc
overheads of 120 prof
contractor Gm
for
Ratefinished
as peritem
SSRof work in all floors. 1.00 sqm 5355.00
Overheads & Contractors Profit @13.615% 0.13615 5355.00
Rate per 1 sqm
60 Supply and fixing of curtain Glazing made of pre painted steel (base steel as per IS 513 of 0.6 mm th
galvanized
a) Fixed as per
Glazing ISx277
2'-0" 2'-0"with Zinc of 120 GSM)
(609.6x609.6mm) andPrimer
2'-0" xcoated with epoxy primergrid
3'-0" (609.6x914.4mm) of 5-7 microns
outer thick,
frames finish
section
mm
Rate as per SSR 1.00 sqm 5466.00
Overheads & Contractors Profit @13.615% 0.13615 5466.00
Rate per 1 sqm
b) Fixed Glazing 3'-0" x 3'-0" (914.4x914.4mm), 3'-0" x 4'-0" (914.4x1219.2mm) grid outer frames section s
mm
Rate as per SSR 1.00 sqm 4295.00
Overheads & Contractors Profit @13.615% 0.14 4295.00
Rate per 1 sqm
61 Providing and fixing in true horizontal level 13 mm - Mineral Fiber Ceiling tile of 595 x 595 (Square ed
model) using hot dipped Galvanized Steel section exposed surface with pre-coated capping, main Tee of size
every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c and sub-cros
mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid
every 1200 mm c/c in both directions using 2.0 mm thick pre-straightened GI Wire including cost and conveyance
and labour charges such as cutting , fixing of standing of frame work exposing roof making, overheads & contr
complete for finished item of work in all floor in all floors.
62 Providing and fixing in true horizontal level 15 mm - Mineral Fiber Ceiling tile of 595 x 595 (Square ed
model) using hot dipped Galvanized Steel section exposed surface with pre-coated capping, main Tee of size
every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c and sub-cros
mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid
every 1200 mm c/c in both directions using 2.0 mm thick pre-straightened GI Wire including cost and conveyance
and labour charges such as cutting , fixing of standing of frame work exposing roof making, overheads & contr
complete for finished item of work in all floor in all floors.
63 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1) using 12.5
Board conforming to&IS
(BLD-CSTN-10-31 2095
vide - 1993
Page No. fixing
389 oftoSoR
Gyp 2011-12)
steel GI perimeter channels of size 20 mm x 27 mm x 30 mm(w
Unit - 1 sqm
A) Material requirement as per India Gypsum
12.5mm Gypboard
1219mm x 1829mm size Boards 1.03 sqm 210.00
GI Ceiling Angle - 25mm x 10mm x 0.5mm 0.64 RM 63.00
GI Ceiling section - 51.5mm x 26mm x 10.5mm
x 0.55mm thick 0.84 RM 72.00
Intermediate channel - 45mm x 15mm x 15mm
x 0.9mm 0.84 RM 71.00
Perimeter channel - 20mm x 27mm x 30mm
(web) of 0.55mm thick 0.40 RM 63.00
Connecting Clips 1.84 Nos. 3.00
Rawl Plug 0.64 Nos. 2.00
Soffit Cleats 0.64 Nos. 3.00
Drywall screws - 25mm 18.00 Nos. 2.00
Jointing Compound 0.55 Kgs. 25.00
Jointing Paper tape 1.46 RM 4.00
Drywall top coat 0.15 Ltrs 120.00
B) Labour Charges
1st Class Carpenter 0.12 Nos. 580.00
2nd Class Carpenter 0.12 Nos. 460.00
1st Class Painter 0.024 Nos. 580.00
2nd Class Painter 0.024 Nos. 460.00
Power Saw cutter - Hand Operated - Operator
0.012 Nos. 580.00
Power Drill - Hand Operated - Operator 0.024 Nos. 580.00
Unskilled Mazdoor 0.072 Nos. 420.00
Add for MA @ 20% 0.20 200.88
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 102.00
Power Drill - Hand Operated - Hire Charges 0.64 Hours 95.00
60 Supplying and fixing Gyp board Fine line Grid false ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Board sh
595mm x 595mm conforming to IS 2095 - 1992 fixing to Gyp steel precoated GI wall angle of size 25mm x 25mm
along the perimeter of ceiling screw fixed to brick work / partition at 610mm center to center and suspending
using precoated GI Tee section (24mm x 38mm x 0.7mm) from soffit at 1220mm center to center fixed with GI S
plugs and steel expansion fasteners & connecting clip to the GI Tee section with 4mm dia GI rod with galvanis
level clip of PVC unversal holding clips system at 1200mm center to center and fixing the 12.5mm Gypboard sh
595mm x 595mm and finishing two coats of drywall top coat, overheads and contractor profit complete for finish
in all floors.
61 Providing and fixing Thermocole False ceiling in true horizontal level 600mm x 600mm using 12mm thick The
anodized Aluminium& Tee
(BLD-CSTN-10-34 videsections
Page No.of 392
sizeof24.50mm x 24.0mm x 2.4mm in grid with cross tee of size 24mm x 2
SoR 2011-12)
Unit 1 sqm
A) Material requirement
12mm Thermocole sheet 1.00 sqm 24.00
Aluminium angle - 24mmx 24mm 0.40 RM 24.00
Anodised Aluminium T section - 24mm x
24.5mm x 2.4mm 3.20 RM 29.00
GI rod-prestraightened 2.0mm dia. -
Connecting rod 1.28 Nos. 8.00
Rawl plugs 1.28 Nos. 2.00
B) Labour charges
1st Class Carpenter 0.11 Nos. 580.00
2nd Class Carpenter 0.11 Nos. 460.00
Power Saw cutter - Hand Operated - Operator
0.02 Nos. 580.00
Power Drill - Hand Operated - Operator 0.04 Nos. 580.00
Unskilled Mazdoor 0.20 Nos. 420.00
Add for MA @ 20% 0.20 231.12
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.16 Hours 102.00
Power Drill - Hand Operated - Hire Charges 0.32 Hours 95.00
64 Suplying and fabricating, erecting and fixing in position tabular trusses of approved design with M.S tube c
specifications including roof frame work consisting of rafters,ties struts and purlins including cost of foundation
bearings plates,etc.,complete as per the approved drawing including cost and conveyance of all materials, lab
fabrication and fixing, hire charges of all tools and plants, all incidental charges, overheads and contractor profi
for finished item of work in all floors as directed by the Engineer-in-Charge
61 Supplying and fixing 50mm dia nominal bore Medium Grade properties & weight as per IS 1239 ISI mark MS
of GI Sheet including cost and conveyance of all materials to work site and all operational, incidental, labou
complete for finished item of work in all floors.
62 Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & G.I
filled with white lead & including a coat of approved steel primer and two coats of approved paint on over la
Unit : 10 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets 103.09 Kgs 62.00
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
47.91 Nos. 5.00
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos. with washers or srews, if wooden
battens used. 43.90 Nos. 9.00
Limpet washers (for scam & ‘J’ bolts) 884 +
810 = 1694 91.82 Nos. 2.00
Bitumen washers 91.82 Nos. 2.00
Zinc cromate yellow paint 0.14 Ltrs 175.00
Ready mixed paint 0.20 Ltrs 248.00
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 460.00
Man mazdoor (beldar) 0.91 Nos. 420.00
For primer painting one coat
Painter 1st class 0.018 Nos. 580.00
Painter 1st class 0.042 Nos. 460.00
Mazdoor (coolie) 0.06 Nos. 420.00
For two coats of painting to over laps
Painter 1st class 0.042 Nos. 580.00
Painter 1st class 0.098 Nos. 460.00
Mazdor (coolie) 0.14 Nos. 420.00
Add for MA @ 20% 0.20 951.80
Rate per 10 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 860.98
Rate per 1 sqm
63 Supplying and fixing of Pre-painted Galvalume Trapezoidal Profile Roofing sheets with 0.50mm thicknes
Zinc coating AZ150 GSM. Tensile Strength: 550 MPA. Paint coating: Regular Modified Polyester painting. Pai
(Top): 18 to 20 Microns, (Bottom): 5 to 7 Microns. Sheet Width: 1.020, Length: Maximum 12 Meters with Regular
fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white lead & including a co
steel primer and two coats of approved paint on over lapping of sheets complete (up to a pitch of 600) etc., com
the cost of purlins, rafters, trusses including cost and conveyance of all materials , labour charges , overheads
profit etc., complete for finished item of work in all floors.
Unit : 10 sqm
A. MATERIALS:
Galvalume sheet 0.50mm thick 10.50 sqm 386.00
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
47.91 Nos. 5.00
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos. with washers or srews, if wooden
battens used. 43.90 Nos. 9.00
Limpet washers (for scam & ‘J’ bolts) 91.82 Nos. 2.00
Bitumen washers 91.82 Nos. 2.00
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 460.00
Man mazdoor (beldar) 0.91 Nos. 420.00
Add for MA @ 20% 0.20 768.60
Rate per 10 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 597.73
Rate per 1 sqm
62 Roofing with UV resistant multi-wall polycarbonate sheets of any colour 6mm thick fixed with Alumin
glazing set 40mm wide and as per drawing etc., complete excluding the cost of purlins,rafters,trusses,alum
glazing set 40mm wide including cost and conveyance of all materials, labour charges, overheads and contra
complete for finished item of work
Unit : 10 sqm
A. MATERIALS:
Cost of multi-wall polycarbonate sheets 6mm
thick Rate as per BMT-E.21 10.50 sqm 1147.00
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
47.91 Nos. 5.00
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos. with washers or srews, if wooden
battens used. 43.90 Nos. 9.00
Limpet washers (for scam & ‘J’ bolts) 91.82 Nos. 2.00
Bitumen washers 91.82 Nos. 2.00
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 460.00
Man mazdoor (beldar) 0.91 Nos. 420.00
Add for MA @ 20% 0.20 768.60
Rate per 10 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 1396.78
Rate per 1 sqm
63 Supplying and fixing Aluminium Universal glazing set 40mm wide for jointing and fixing Polycarb
including cost and conveyance of all materials, labour charges, overheads and contractors profit etc., complete f
of work
Unit : 10 sqm
A. MATERIALS:
Cost of Aluminium Universal glazing set 40mm
wideRate as per BMT-E.22 1.00 RM 109.00
Labour charges 5% of material cost 0.05 109.00
Rate per 1RM
Overheads & Contractors Profit @13.615% 0.13615 114.45
Rate per 1 RM
65 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement con
per 1 cum of concrete using weigh batcher / mixer with 20mm size graded machine crushed hard granite
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 380.00 Kgs 4600.00
20mm HBG graded metal 0.80 Cum 1244.30
Sand 0.40 Cum 670.00
B.LABOUR :
1st class Mason 0.07 Nos 500.00
2nd class Mason 0.13 Nos 460.00
Mazdoor (both men&women) 3.08 Nos 420.00
Add for MA @0% 0.00 1387.02
C.MACHINERY :
Batching plant 0.50 cum 0.31 hours 222.90
Crew charges 0.31 hours 387.40
Needle vibrator 40mm ( petrol ) 0.31 hours 27.60
Crew charges 0.31 hours 181.50
Add MA on crew charges 0.00 175.22
Water(including for curing) 1.20 kl 107.00
Rate per 1 cum
65 Supply and delivery and fixing of encapsulated plastic steps for man holes manufactured as per comp
specification including cost of materials packing as per companiess standards, loading, transportation, unloading
site of work including labour charges for fixing, overheads and contractor profit etc., complete for finished item of
66 Supply and placing in postion water stopper 8 - 10 mm thick 310 mm wide including cost and conveyance of all
and sales and other taxes on all materials to site etc., complete for finished item of work
66 Supplying & fixing 602 x 602 mm CI man hole frame and cover (light weight) 30 Kgs including cost and c
labour charges for fixing, overheads and contractor profit etc., complete for finished item of work
67 Supplying and fixing of MS Gate, doors, grill to windows / in open court yards using MS angles, flat, squar
cost and conveyance of all materials, cutting, bending, welding, all operational charges, labour charges,
contractor profit etc., complete for finished item of work.
Rate per 1 Kg
67 Reinforced Cement Concrete M 20 nominal mix using 20mm size hard granite machine crushed graded
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum quantit
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and con
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering, sh
charges such as weigh batching, machine mixing, hire charges of concrete mixer, laying concrete, lift charges,
overheads & contractors profit complete for finished item of work (APSS No. 402 & 403) for precast slabs over
(BLD-CSTN-3-13 - A)
A.MATERIALS :
Cement 330.00 Kgs 4600.00
20mm HBG graded metal 0.90 Cum 1244.30
Sand 0.45 Cum 670.00
B.LABOUR :
1st class Mason 0.067 Nos 500.00
2nd class Mason 0.133 Nos 460.00
Mazdoor (both Men & Women) 2.500 Nos 420.00
Add for MA @ 20% 0.20 1144.68
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew Charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
Water(including for curing) 1.20 kl 107.00
Basic cost per 1 cum
70 Plain Cement Concrete (1:3:6) (cement: fine aggregate: Coarse aggregate) for foundations using coarse a
size hard , machine crushed granite from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacit
and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site including all charges for
and hire charges of concrete mixer, laying concrete in foundations and under flooring bed, ramming in 15 cm lay
surface to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (AP
(BLD-CSTN-3-5)
Unit : 1 cum
A.MATERIALS :
Cement 220.00 Kgs 4600.00
Coarse aggregate 40mm 0.90 Cum 897.80
Fine aggregate ( Sand ) 0.45 Cum 670.00
Water (including curing) 1.20 kl 107.00
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 142.20
Crew charges 1.00 hour 252.20
Add MA on crew charges 0.20 252.20
C.LABOUR :
1st class mason 0.10 Nos. 500.00
Mazdoor (unskilled) 1.39 Nos. 420.00
Add for MA @ 20% 0.20 633.80
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615 3455.32
Rate per 1 cum
71 Providing, laying Reinforced cement concrete Hume pipes of 300mm dia. NP-3 class for cross ducts inc
conveyance of Pipes etc., complete and Labour charges for laying, jointing of 300mm dia. R.C.C Hume pip
including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 290
revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work
(B) MATERIAL :
Cost of 300mm Dia., pipes 12.50 RM 844.00
Lead charges 15 KM 12.50 RM 63.05
Rate for 12.50 RM
Rate for 1 RM
Overheads & Contractors Profit @13.615% 0.13615 1033.45
Rate for 1 RM
ROAD WORKS
70 Construction of Granular sub-base by providing HBG material confirming to Grading - III of MORT &
including cost and conveyance of all material to work site and spreading in uniform layers with motor grader
RBR-SBBS-2/2(A)
means, on prepared surface mixing by mix place method with Rotavator/ approved means, at OMC and c
vibratory roller to achieve the desired density etc., complete for finished item of work as per MoRT& H specifi
revision) and as directed by the Engineer- in - charge (Payment will be made based on levels for finished item of w
Unit : 1 cum
Taking output : 300 cum
a) Labour
Mate day
Mazdoor skilled 2.40 day 420.00
Mazdoor unskilled 8.00 day 420.00
Add for MA @ 20% 0.20 4368.00
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour 6.00 hr 3020.40
Vibratory roller 8T 6.00 hr 2688.50
Water tanker 6 KL 3.00 hr 655.20
c) Material Grading III
Coarse graded Granular sub-base Material 9.5
mm to 4.75 mm @ 66% 255.00 cum 632.80
Coarse graded Granular sub-base Material
2.36 mm & below @ 34%
129.00 cum 487.80
Water 18.00 Kl 107.00
with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous ope
provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, do
approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 1
compound (where specified) and water finishing to lines and grade as per drawing and Technical Specificatio
MORD.
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate day -
Mason 1st Class 5.00 day 500.00
Mason (2nd class) 5.00 day 460.00
Mazdoor (Unskilled) 150.00 day 420.00
Mazdoor (Skilled) 6.00 day 420.00
Mazdoor ( semi skilled) 6.00 day 420.00
Blacksmith for cutting of dowel bars including
removal of burrs, fabrications & fixing of dowel
bars. 1.00 day 495.00
Add for MA @ 20% 0.20 73335.00
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6
mixers) with weigh batcher and suitable
capacity calibrated water tank 36.00 hour 142.20
crew charges 36.00 hour 252.20
Add for M25% on crew charges 0.20 9079.20
Needle vibrator hire charges 9.00 hour 27.60
crew charges 9.00 hour 181.50
Add for M25% on crew charges 0.20 1633.50
Screed vibrator 9.00 hour 50.00
Plate vibrator 9.00 hour 48.00
Concrete joint cutting machine for initial & final
cuts 4.00 hour 100.00
Water tanker 6 kl capacity) 5.00 hour 655.20
Air Compressor 2 hour 1322.10
c) Material
Crushed stone coarse aggregates, grading will
be as per Clause 1501.2.4.1 (Table 1500.1) of
specifications @ 0.90 cum/cum of concrete (25
mm & 12.5 mm blending) 67.50 cum 1144.55
Sand as per IS:383 and conforming to Clause
1500.2.4.2 @ 0.45 cum/cum of concrete
33.75 cum 670.00
Cement 26.25 MT 4600.00
Polythene sheet 125 micron 412.50 sqm 18.00
Mild steel dowel bar 25 mm dia of grade S 240.
500 mm long 20 Nos. at culvert/bridge slab and
at construction joint including 5 per cent
wastage.
(4 x 20 x 0.500) + 5 per cent wastage = 42 m
@ 2.80 kg per m = 117.6 kg. 0.12 MT 39000.00
Bituminous sealant 800 ml per joint for 23
joints ( BMT-H.93)(SoR 2014-15) 19.00 litre 96.00
Jute rope 12 mm dia including 5 per cent
wastage 90.00 RM 5.00
Polythene sheathing, covering 2/3rd dowel
bars (20x23) and tight fit including 5 per cent
wastage 483.00 Nos. 0.60
Plasticizer 0.5 per cent by weight of
cement(BMT-H.63)(SoR 2014 - 15) 122.00 litre 107.00
Water for curing 18.00 kl 107.00
Joint filler board 20 mm thick as per IS:1838
BMT-U.02 3.00 sqm 902.00
72 Providing, Laying, Spreading and compacting graded HBG/HBG crushed stone aggregate to Wet
specification including cost of all materials and including premixing the material with water at OMC in Mecha
carriage of mixed material by tipper to site , laying in uniform layers with paver in base courses on well prepar
compacting with Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-Charge and a
specification.406 (5th revision) for finished item of work. (Payment based on levels for finished item of work)
B) Machinery
Wet mix plant of 60 tonne hr. capacity 6.60 hours 167.70
Electric generator 125 KVA 6.00 hours 1543.10
Front end loader 1 cum capacity 6.00 hours 1594.70
Mechanical Paver finisher 6.00 hours 2290.60
Vibratory roller 8 - 10 tonne 3.90 hours 2688.50
Water tanker 6 KL capacity 3.00 hours 937.00
C)Material
45 to 22.40mm IRC&MoRT&H HBG M/C
metal@ 30% 89.10 cum
(Av. Of 40-45, 25-27, 19-22mm )
22.4 to 2.36mm IRC&MoRT&H HBG M/C
metal@40% 118.80 cum 978.80
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-
7mm, 2.36 - 5mm )
2.36mm to 75 micron @ 30% (2.36mm &
below) 89.10 cum 487.80
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 202664.64
73 Supply & Fabication and fixing of Structural steel for fencing post with 65 x 65 x6 mm size equal angles a
8mm rods for anchoring concrete at bottom of the fencing post, drilling 5 Nos holes at equal intervals to MS an
wide MS flats of 6mm thick together and fitted with bolts and nuts after placing of chain linked mesh in position in
with synthetic enamel paint two coats over a primary coat of red oxide including cost and conveynace of all mat
charges overheads and contractor profit etc., complete for finished item of work
Unit: 2 RM
65 x 65 x 6mm size angle
(2 RM x 5.80Kg/RM) 2.00 5.80 11.60
Rate per 2 RM
Rate per 1 RM
Overheads & Contractors Profit @13.615% 0.13615 681.12
74 Supply & Fixing of Hot dipped Galvanised Iron Chain link mesh 8 gauge - (4.0 mm) as per IS: 2721-1979:
50 mm) - 8 Gauge including cost and conveynace of materials, labour charges cutting & fixing charges an
contractor profit etc., for complete finished item of work.
Unit = 1SQM
Cost of 2"x2" Chain link mesh (BMT-F.20) 1.00 Sqm 404.00
Labour charges for fixing, cost of binding wire
@10%
Rate per 1 Sqm
Overheads & Contractors Profit @13.615% 0.13615 444.40
75 Manufacturing, supply and erection of 600 mm width MS ladders with 50mm x 50mm x 6 mm MS angles
and horizontals fixed at 25 cm c/c as per approved drawing including cost of all materials,, fabrication, all othe
operational charges, welding, transportation to site, fixing in position duly embedding in concrete, overheads
profit etc., complete for finished item of work in all floors.
Rate per 1 Kg
VIZIANAGARAM IN VIZANAGARM DISTRICT .
Amount
Per Unit
(Rs.)
nd disposal of unserviceable materials with 100m
before dismantling including all labour charges ,
1 Each 171.78
34.36
206.14
28.07
234.20
say 234
1 Each 1024.80
204.96
1229.76
167.43
1397.19
say 1397
1 Each 2049.60
409.92
2459.52
334.86
2794.38
say 2794
1 Each 1814.40
362.88
2177.28
296.44
2473.72
say 2474
10 sqm 66.00
13.20
79.20
7.92
1.08
9.00
say 9
1 cum 390.00
78.00
468.00
63.72
531.72
say 532
10 sqm 120.00
24.00
144.00
14.40
1.96
16.36
say 16
10 sqm 143.00
28.60
171.60
17.16
2.34
19.50
say 19
1 cum 206.00
41.20
247.20
33.66
280.86
say 281
10 sqm 44.00
8.80
52.80
5.28
0.72
6.00
say 6
10 sqm 55.00
11.00
66.00
6.60
0.90
7.50
say 7
10 sqm 44.00
8.80
52.80
5.28
0.72
6.00
say 6
eep
10 sqm 54.00
10.80
64.80
6.48
0.88
7.36
say 7
1 No. 46.00
1 No. 84.00
1 No. 23.00
30.60
183.60
25.00
208.60
Say 209
1 No. 59.80
1 No. 113.40
1 No. 32.20
41.08
246.48
33.56
280.04
Say 280
1 Hour 1546.80
210.60
1757.40
say 1757
1 No. 1528.80
305.76
1834.56
249.78
2084.34
208.43
Say 208
1 cum 75.30
10.25
85.55
Say 86
1 No. 3494.40
698.88
1 Hour 14960.40
1 Hour 1606.80
321.36
21081.84
2870.29
23952.13
99.80
Say 100
1 No. 3494.40
698.88
1 Hour 14960.40
1 Hour 1606.80
321.36
21081.84
2870.29
23952.13
114.06
Say 114
1 No. 2184.00
436.80
2620.80
356.82
2977.62
297.76
Say 298
in ordinary rock (not requiring blasting) and
depth including all operational,incidental, labour
ntractors profit complete for finished item of work
1 No. 2620.80
524.16
1 Hour 14960.40
1 Hour 1606.80
321.36
20033.52
2727.56
22761.08
126.45
Say 126
1 No. 255.00
1 No. 142.50
1 No. 3507.00
780.90
1 Hour 1080.00
1 Hour 33.00
1 Hour 242.10
1 Hour 756.60
199.74
1 Kg 206.50
1 No. 126.00
7329.34
997.89
8327.23
832.72
Say 833
g prohibited) and depositing on bank for all lifts
onal,incidental, labour charges such as shoring,
for finished item of work excluding dewatering
1 No. 2184.00
436.80
1 Hour 6480.00
1 Hour 198.00
1 Hour 1452.60
1 Hour 4539.60
1198.44
16489.44
2245.04
18734.48
1873.45
Say 1873
1 hr 4611.20
1 hr 3020.40
1 hr 2620.80
1 hr 10754.00
1 Kl 2568.00
23792.80
3239.39
27032.19
270.32
Say 270.00
c to subterrean tremites is apply/ inject into soil
uilding and around the foundations conduct and
registered termiticide which creates a continuous
ous to tremite entry 3. Imidacloprid 30.5% SC (IS
/Square meter (Sqm) of internal, external vertical
external perimeters, along reatining wall @ 5.0
filling below flooring bed (Plinth) & @ 2.0 Litres/
d coulmns & 300mm deep around plinth beams,
dding etc. cost & Conveyance of all materials to
c. complete for furnished item of work as per the
1 sqm 150.00
20.42
170.42
170
1 No. 130.20
26.04
1 cum 182.60
1 Kl 12.84
351.68
47.88
399.56
Say 400
1 No. 130.20
26.04
1 cum 3210.00
3366.24
33.66
3399.90
462.90
3862.80
643.80
Say 644
1 No. 130.20
26.04
156.24
1.56
157.80
21.48
179.29
29.88
Say 30
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
3188.52
434.12
3622.64
Say 3623
for foundations and under flooring bed using
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8
coarse aggregate, water etc. to site including all
e in foundations and under flooring bed, ramming
heads & contractors profit complete for finished
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
3039.48
413.83
3453.31
Say 3453
1 Each 600.00
1 Each 840.00
288.00
2437.34
24.37
2461.71
335.16
2796.87
Say 2797
d granite stones carted from approved quarry
water, stones etc., from approved quarry, to site
cement, mortar, construction, curing etc.,and
and basement. (APSS No. 601 & 615)
1 Each 600.00
1 Each 840.00
288.00
2598.32
25.98
2624.30
357.30
2981.60
Say 2982
1 Cum 538.68
1 Cum 373.29
1 Cum 301.50
1 MT 1012.00
1 Kl 128.40
1 hour 142.20
1 hour 252.20
50.44
1 hour 27.60
1 hour 181.50
36.30
1 Each 50.00
1 Each 583.80
126.76
1 Cum 64.00
1 Cum 341.00
68.20
4277.87
582.43
4860.30
Say 4860
o IS 456 with minimum cement content of 380
ded machine crushed hard granite metal (coarse
ed quarry including cost and conveyance of all
site, centering using steel scaffolding pipes ,
including all operational, incidental and labour
ly, laying concrete, vibrating, curing etc., and
rication charges for finished item of work (APSS
1 Each 66.50
1 Each 122.82
1 Each 1932.00
424.26
1 hour 297.13
1 hour 516.40
1 hour 36.79
1 hour 241.94
151.67
1 kl 128.40
7021.35
1 Cum 7021.35
1 Cum 288.00
1 Cum 631.00
126.20
8066.55
1098.26
9164.81
Say 9165
1 Cum 7021.35
1 Cum 328.00
1 Cum 1004.00
200.80
8554.15
1164.65
9718.80
Say 9719
1 Cum 7021.35
1 Cum 695.00
1 Cum 760.50
152.10
8628.95
1174.83
9803.78
Say 9804
1 Cum 7021.35
1 Cum 64.00
1 Cum 341.00
68.20
7494.55
1020.38
8514.94
Say 8515
1 Cum 7021.35
1 Cum 631.00
126.20
7778.55
1059.05
8837.60
Say 8838
1 Each 83.50
1 Each 76.82
1 Each 2352.00
502.46
1 hour 297.13
1 hour 516.40
1 hour 36.79
1 hour 241.94
151.67
1 kl 128.40
7490.55
4F 5F 6F
7490.55 7490.55 7490.55
238.00 238.00 238.00
2284.00 2460.00 2636.00
456.80 492.00 527.20
753.70 1004.93 1256.16
150.74 200.99 251.23
11373.79 11886.47 12399.14
1548.54 1618.34 1688.14
12922.33 13504.81 14087.28
12922 13505 14087
4F 5F 6F
7490.55 7490.55 7490.55
790.00 790.00 790.00
1626.00 1751.00 1877.00
325.20 350.20 375.40
753.70 1004.93 1256.16
150.74 200.99 251.23
11136.19 11587.67 12040.34
1516.19 1577.66 1639.29
12652.38 13165.33 13679.63
12652 13165 13680
4F 5F 6F
1123.58 1123.58 1123.58
1000.00 1000.00 1000.00
2149.00 2314.00 2480.00
429.80 462.80 496.00
113.05 150.74 188.42
22.61 30.15 37.68
4838.05 5081.27 5325.69
658.7 691.82 725.09
5496.75 5773.09 6050.78
5497 5773 6051
4F 5F 6F
1498.11 1498.11 1498.11
1000.00 1000.00 1000.00
2149.00 2314.00 2480.00
429.80 462.80 496.00
150.74 200.99 251.23
30.15 40.20 50.25
5257.80 5516.10 5775.59
715.85 751.02 786.35
5973.65 6267.12 6561.94
5974 6267 6562
4F 5F 6F
7490.55 7490.55 7490.55
355.00 355.00 355.00
59.16 59.16 59.16
2948.00 3175.00 3175.00
491.31 529.15 529.15
98.26 105.83 105.83
753.70 1004.93 1256.16
150.74 200.99 251.23
12346.72 12920.61 13222.08
1681.01 1759.14 1800.19
14027.73 14679.75 15022.27
14028 14680 15022
1 Each 33.50
1 Each 61.18
1 Each 1292.34
277.40
1 hour 68.65
1 hour 119.32
1 hour 8.50
1 hour 55.90
35.04
1 kl 128.40
5183.68
4F 5F 6F
5183.68 5183.68 5183.68
1395.00 1395.00 1395.00
1915.00 2062.00 2210.00
383.00 412.40 442.00
416.11 554.81 693.51
83.22 110.96 138.70
9376.01 9718.85 10062.90
1276.54 1323.22 1370.06
10652.55 11042.07 11432.96
10653 11042 11433
1 Cum 596.12
1 Cum 647.96
4F 5F 6F
647.96 647.96 647.96
158.00 158.00 158.00
217.00 234.00 251.00
43.40 46.80 50.20
52.01 69.35 86.69
10.40 13.87 17.34
1128.78 1169.98 1211.19
153.68 159.29 164.9
1282.46 1329.27 1376.09
1282 1329 1376
1 Cum 777.55
4F 5F 6F
777.55 777.55 777.55
158.00 158.00 158.00
217.00 234.00 251.00
43.40 46.80 50.20
62.42 83.22 104.03
12.48 16.64 20.81
1270.85 1316.22 1361.58
173.03 179.2 185.38
1443.88 1495.42 1546.96
1444 1495 1547
1 Cum 907.14
4F 5F 6F
907.14 907.14 907.14
163.00 163.00 163.00
224.00 241.00 258.00
44.80 48.20 51.60
72.82 97.09 121.36
14.56 19.42 24.27
1426.33 1475.85 1525.38
194.19 200.94 207.68
1620.52 1676.79 1733.06
1621 1677 1733
1 Cum 1036.74
4F 5F 6F
1036.74 1036.74 1036.74
163.00 163.00 163.00
224.00 241.00 258.00
44.80 48.20 51.60
83.22 110.96 138.70
16.64 22.19 27.74
1568.40 1622.09 1675.78
213.54 220.85 228.16
1781.94 1842.94 1903.94
1782 1843 1904
4F 5F 6F
5183.68 5183.68 5183.68
2085.00 2085.00 2085.00
347.49 347.49 347.49
2474.00 2664.00 2664.00
412.32 443.98 443.98
82.46 88.80 88.80
416.11 554.81 693.51
83.22 110.96 138.70
11084.28 11478.72 11645.16
1509.13 1562.83 1585.49
12593.41 13041.55 13230.65
12593 13042 13231
1 Cum 647.96
4F 5F 6F
647.96 647.96 647.96
236.00 236.00 236.00
39.33 39.33 39.33
280.00 301.00 301.00
46.66 50.16 50.16
9.33 10.03 10.03
52.01 69.35 86.69
10.40 13.87 17.34
1321.70 1367.70 1388.51
179.95 186.21 189.05
1501.65 1553.91 1577.56
1502 1554 1578
1 Cum 777.55
4F 5F
777.55 777.55
236.00 236.00
39.33 39.33
280.00 301.00
46.66 50.16
9.33 10.03
62.42 83.22
12.48 16.64
1463.77 1513.94
199.29 206.12
1663.06 1720.06
1663 1720
1 Cum 907.14
4F 5F
907.14 907.14
243.00 243.00
40.5 40.5
289.00 311.00
48.16 51.83
9.63 10.37
72.82 97.09
14.56 19.42
1624.82 1680.35
221.22 228.78
1846.04 1909.13
1846 1909
1 Each 33.50
1 Each 61.18
1 Each 1292.34
277.40
1 hour 68.65
1 hour 119.32
23.86
1 kl 128.40
5108.10
1 cum 191.55
4F 4F 5F
191.55 191.55 191.55
93.60 93.60 93.60
150.00 161.40 172.80
30.00 32.28 34.56
15.60 20.81 26.01
3.12 4.16 5.20
483.88 503.80 523.72
65.88 68.59 71.3
549.76 572.39 595.02
550 572 595
1 Each 28.00
1 Each 25.76
1 Each 385.14
87.78
1 hour 159.77
1 hour 86.00
1 hour 378.55
1 hour 71.35
1 hour 298.61
1 hour 42.00
1 hour 6.13
1 hour 40.29
47.93
1 kl 128.40
4797.17
1 Cum 4797.17
1 Cum 288.00
1 Cum 631.00
126.20
5842.37
795.44
6637.80
Say 6638
1 Cum 4797.17
1 Cum 328.00
1 Cum 1004.00
200.80
6329.97
861.82
7191.79
Say 7192
1 Cum 4797.17
1 Cum 695.00
1 Cum 760.50
152.10
6404.77
872.01
7276.77
Say 7277
1 Cum 4797.17
1 Cum 64.00
1 Cum 341.00
68.20
5270.37
717.56
5987.93
Say 5988
1 Cum 4797.17
653.13
5450.30
Say 5450
1 Each 28.00
1 Each 25.76
1 Each 385.14
87.78
1 hour 159.77
1 hour 86.00
1 hour 378.55
1 hour 71.35
1 hour 298.61
1 hour 42.00
1 hour 6.13
1 hour 40.29
93.50
1 kl 128.40
4934.74
1 Cum 4934.74
1 Cum 288.00
1 Cum 631.00
126.20
5979.94
814.17
6794.10
Say 6794
1 Cum 4934.74
1 Cum 328.00
1 Cum 1004.00
200.80
6467.54
880.55
7348.09
Say 7348
1 Cum 4934.74
1 Cum 695.00
1 Cum 760.50
152.10
6542.34
890.74
7433.07
Say 7433
1 Cum 4934.74
1 Cum 64.00
1 Cum 341.00
68.20
5407.94
736.29
6144.23
Say 6144
1 Cum 4934.74
1 Cum 631.00
126.20
5691.94
774.96
6466.89
Say 6467
o IS 456 with cement content of 380 kgs per 1
pacity with 20mm size graded machine crushed
1 to Part 8) from approved quarry including cost
aggregate, water etc., to site, centering using
ates etc., including all operational, incidental and
chnically, laying concrete using concrete pump,
ost of steel and its fabrication charges for finished
1 Each 55.50
1 Each 102.12
1 Each 653.52
162.23
1 hour 319.55
1 hour 172.01
1 hour 757.11
1 hour 142.70
1 hour 597.22
1 hour 84.00
1 hour 12.25
1 hour 80.59
95.86
1 kl 128.40
6374.50
4F 5F 6F
6374.50 6374.50 6374.50
238.00 238.00 238.00
2284.00 2460.00 2636.00
456.80 492.00 527.20
9353.30 9564.50 9775.70
1273.45 1302.21 1330.96
10626.75 10866.71 11106.66
10627 10867 11107
1.00 cum 637.45
4F 5F 6F
956.18 956.18 956.18
1000.00 1000.00 1000.00
1956.18 1956.18 1956.18
266.33 266.33 266.33
2222.51 2222.51 2222.51
2223 2223 2223
4F 5F 6F
1466.14 1466.14 1466.14
1000.00 1000.00 1000.00
2466.14 2466.14 2466.14
335.76 335.76 335.76
2801.90 2801.90 2801.90
2802 2802 2802
1 Each 83.50
1 Each 76.82
1 Each 2352.00
502.46
1 hour 297.13
1 hour 516.40
1 hour 36.79
1 hour 241.94
151.67
1 kl 128.40
7398.55
4F 5F 6F
7398.55 7398.55 7398.55
790.00 790.00 790.00
1626.00 1751.00 1877.00
325.20 350.20 375.40
1 Each 55.50
1 Each 102.12
1 Each 653.52
162.23
1 hour 319.55
1 hour 172.01
1 hour 757.11
1 hour 142.70
1 hour 597.22
1 hour 84.00
1 hour 12.25
1 hour 80.59
42.84
1 kl 128.40
6413.48
4F 5F 6F
6374.50 6374.50 6374.50
355.00 355.00 355.00
59.16 59.16 59.16
2948.00 3175.00 3402.00
491.31 529.15 566.98
687.86 740.83 793.80
10915.83 11233.64 11551.44
1486.19 1529.46 1572.73
12402.02 12763.10 13124.17
12402 12763 13124
4F 5F 6F
6374.50 6374.50 6374.50
355.00 355.00 355.00
118.33 118.33 118.33
2948.00 3175.00 3402.00
982.63 1058.29 1133.95
196.53 211.66 226.79
10974.99 11292.78 11610.57
1494.24 1537.51 1580.78
12469.23 12830.29 13191.35
12469 12830 13191
4F 5F 6F
6374.50 6374.50 6374.50
355.00 355.00 355.00
177.49 177.49 177.49
2948.00 3175.00 3402.00
1473.94 1587.44 1700.93
294.79 317.49 340.19
11623.72 11986.92 12350.11
1582.57 1632.02 1681.47
13206.29 13618.94 14031.58
13206 13619 14032
1 Each 16.50
1 Each 30.82
1 Each 181.86
45.84
1 hour 95.94
1 hour 51.64
1 hour 227.30
1 hour 42.84
1 hour 179.30
1 hour 25.22
1 hour 3.68
1 hour 24.19
28.78
1 kl 128.40
4093.75
4F 5F 6F
4093.75 4093.75 4093.75
1395.00 1395.00 1395.00
1915.00 2062.00 2210.00
383.00 412.40 442.00
7786.75 7963.15 8140.75
1060.17 1084.18 1108.36
8846.92 9047.33 9249.11
8847 9047 9249
1 Cum 511.72
4F 5F 6F
511.72 511.72 511.72
158.00 158.00 158.00
217.00 234.00 251.00
43.40 46.80 50.20
930.12 950.52 970.92
126.64 129.41 132.19
1056.76 1079.93 1103.11
1057 1080 1103
1 Cum 614.06
4F 5F 6F
614.06 614.06 614.06
158.00 158.00 158.00
217.00 234.00 251.00
43.40 46.80 50.20
1032.46 1052.86 1073.26
140.57 143.35 146.12
1173.03 1196.21 1219.38
1173 1196 1219
1 Cum 716.41
4F 5F 6F
716.41 716.41 716.41
163.00 163.00 163.00
224.00 241.00 258.00
44.80 48.20 51.60
1148.21 1168.61 1189.01
156.33 159.11 161.88
1304.54 1327.72 1350.89
1305 1328 1351
1 Cum 736.88
1 Cum 818.75
4F 5F 6F
818.75 818.75 818.75
163.00 163.00 163.00
224.00 241.00 258.00
44.80 48.20 51.60
1250.55 1270.95 1291.35
170.26 173.04 175.82
1420.81 1443.99 1467.17
1421 1444 1467
1 Cum 1023.44
1 Each 16.50
1 Each 30.82
1 Each 181.86
45.84
1 hour 95.94
1 hour 51.64
1 hour 227.30
1 hour 42.84
1 hour 179.30
1 hour 25.22
1 hour 3.68
1 hour 24.19
19.80
1 kl 128.40
4176.78
1 Cum 522.10
1 Cum 626.52
1 Cum 730.94
4F 5F 6F
4093.75 4093.75 4093.75
1395.00 1395.00 1395.00
232.49 232.49 232.49
1915.00 2062.00 2210.00
319.15 343.65 368.32
446.83 481.13 515.66
8402.22 8608.02 8815.23
1143.96 1171.98 1200.19
9546.18 9780.00 10015.42
9546 9780 10015
4F 5F 6F
4093.75 4093.75 4093.75
2085.00 2085.00 2085.00
694.97 694.97 694.97
2474.00 2664.00 2855.00
824.63 887.96 951.63
659.73 710.39 761.33
10832.08 11136.07 11441.68
1474.79 1516.18 1557.78
12306.87 12652.25 12999.46
12307 12652 12999
4F 5F 6F
4093.75 4093.75 4093.75
2085.00 2085.00 2085.00
1042.46 1042.46 1042.46
2474.00 2664.00 2855.00
1236.95 1331.95 1427.44
742.19 799.19 856.49
11674.35 12016.35 12360.14
1589.46 1636.03 1682.83
13263.81 13652.38 14042.97
13264 13652 14043
1 Cum 511.72
4F 5F 6F
511.72 511.72 511.72
236.00 236.00 236.00
39.33 39.33 39.33
280.00 301.00 323.00
46.66 50.16 53.83
65.33 70.23 75.37
1179.04 1208.44 1239.25
160.53 164.53 168.72
1339.57 1372.97 1407.97
1340 1373 1408
1 Cum 511.72
4F 5F 6F
511.72 511.72 511.72
236.00 236.00 236.00
78.66 78.66 78.66
280.00 301.00 323.00
93.33 100.33 107.66
74.67 80.27 86.13
1274.38 1307.98 1343.17
173.51 178.08 182.87
1447.89 1486.06 1526.04
1448 1486 1526
1 Cum 511.72
4F 5F 6F
511.72 511.72 511.72
236.00 236.00 236.00
118 118 118
280.00 301.00 323.00
139.99 150.49 161.49
84.00 90.30 96.90
1 Cum 511.72
1 Cum 614.06
4F 5F
614.06 614.06
236.00 236.00
39.33 39.33
280.00 301.00
46.66 50.16
65.33 70.23
1281.38 1310.78
174.46 178.46
1455.84 1489.24
1456 1489
1 Cum 614.06
4F 5F 6F
614.06 614.06 614.06
236.00 236.00 236.00
78.66 78.66 78.66
280.00 301.00 323.00
93.33 100.33 107.66
74.67 80.27 86.13
1376.72 1410.32 1445.51
187.44 192.01 196.81
1564.16 1602.33 1642.32
1564 1602 1642
1 Cum 614.06
4F 5F 6F
614.06 614.06 614.06
236.00 236.00 236.00
118 118 118
280.00 301.00 323.00
139.99 150.49 161.49
84.00 90.30 96.90
1472.05 1509.85 1549.45
200.42 205.57 210.96
1672.47 1715.42 1760.41
1672 1715 1760
1 Cum 614.06
1 Cum 614.06
1 Cum 716.41
4F 5F 6F
716.41 716.41 716.41
243.00 243.00 243.00
40.5 40.5 40.5
289.00 311.00 333.00
48.16 51.83 55.5
67.43 72.57 77.70
1404.50 1435.30 1466.11
191.22 195.42 199.61
1595.72 1630.72 1665.72
1596 1631 1666
1 Cum 716.41
4F 5F 6F
716.41 716.41 716.41
243.00 243.00 243.00
81.00 81.00 81.00
289.00 311.00 333.00
96.33 103.66 111
77.07 82.93 88.80
1502.80 1538.00 1573.21
204.61 209.4 214.19
1707.41 1747.40 1787.40
1707 1747 1787
1 Cum 716.41
4F 5F 6F
716.41 716.41 716.41
243.00 243.00 243.00
121.50 121.50 121.50
289.00 311.00 333.00
96.33 103.66 111.00
77.07 82.93 88.80
1543.30 1578.50 1613.71
210.12 214.91 219.71
1753.42 1793.41 1833.42
1753 1793 1833
1 Cum 716.41
1 Cum 818.75
4F 5F 6F
818.75 818.75 818.75
243.00 243.00 243.00
121.50 121.50 121.50
289.00 311.00 333.00
144.49 155.49 166.49
86.70 93.30 99.90
1703.44 1743.04 1782.64
231.92 237.31 242.71
1935.36 1980.35 2025.35
1935 1980 2025
1 hour 68.65
1 hour 119.32
23.86
1 kl 128.40
5016.10
1 cum 188.10
4F 5F 6F
188.10 188.10 188.10
93.60 93.60 93.60
150.00 161.40 172.80
30.00 32.28 34.56
1 Cum 5084.91
692.31
5777.22
Say 5777
1 Each 120.00
1 Each 257.60
1 Each 793.80
234.28
50.35
5084.91
1 Cum 5084.91
692.31
5777.22
Say 5777
4F 5F 6F
5084.91 5084.91 5084.91
44.87 44.87 44.87
793.09 942.26 1091.43
158.62 188.45 218.29
351.42 468.56 585.70
70.28 93.71 117.14
6503.19 6822.76 7142.34
885.41 928.92 972.43
7388.60 7751.68 8114.77
7389 7752 8115
1 Each 300.00
1 Each 276.00
1 Each 1155.00
346.20
62.63
6325.41
632.54
4F 5F 6F
632.54 632.54 632.54
10.32 10.32 10.32
182.41 216.72 251.03
36.48 43.34 50.21
51.93 69.24 86.55
10.39 13.85 17.31
924.07 986.01 1047.96
125.81 134.25 142.68
1049.88 1120.26 1190.64
1050 1120 1191
h cement / lime solid blocks of size 290mm x
0 Kg/Sqcm. including cost and conveyance of all
ke mixing cement mortar, scaffolding charges,
omplete for finished item of work. (APSS No. 501
1 Each 120.00
1 Each 257.60
1 Each 793.80
234.28
42.99
4342.48
1 cum 4342.48
591.23
4933.71
say 4934
4F 5F 6F
4342.48 4342.48 4342.48
45.87 45.87 45.87
810.71 963.20 1115.69
162.14 192.64 223.14
351.42 468.56 585.70
70.28 93.71 117.14
5782.90 6106.46 6430.01
787.34 831.39 875.45
6570.24 6937.85 7305.46
6570 6938 7305
ement : Sand) using fly ash cement / lime solid
ngth of 50 Kg/Sq.cmand placing 2 Nos. of 6mm
ed into mortar joints of main brick walls where
sand, bricks, water etc., to site, all operational,
ing charges, constructing masonry, lift charges,
its fabrication charges complete for finished item
1 Each 300.00
1 Each 276.00
1 Each 1155.00
346.20
51.03
5154.10
515.41
4F 5F 6F
515.41 515.41 515.41
10.32 10.32 10.32
182.41 216.72 251.03
36.48 43.34 50.21
51.93 69.24 86.55
10.39 13.85 17.31
806.94 868.88 930.83
109.86 118.30 126.73
916.80 987.18 1057.56
917 987 1058
1 Each 300.00
1 Each 276.00
1 Each 1155.00
346.20
23.18
2340.98
234.10
4F 5F 6F
234.10 234.10 234.10
10.32 10.32 10.32
182.41 216.72 251.03
36.48 43.34 50.21
51.93 69.24 86.55
10.39 13.85 17.31
525.63 587.57 649.52
71.56 80.00 88.43
597.19 667.57 737.95
597 668 738
1 Cum 1119.87
1 Cum 301.50
1 MT 1012.00
1 Kl 128.40
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
3767.17
4F 5F 6F
3767.17 3767.17 3767.17
64.00 64.00 64.00
443.30 477.40 511.50
88.66 95.48 102.30
190.14 253.52 316.90
38.03 50.70 63.38
4591.30 4708.27 4825.25
625.11 641.03 656.96
5216.41 5349.30 5482.21
5216 5349 5482
1 Cum 1119.87
1 Cum 301.50
1 MT 1518.00
1 Kl 128.40
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
4273.17
581.79
4854.96
say 4855
1 Cum 1119.87
1 Cum 301.50
1000 Kgs 1518.00
1 Kl 128.40
1 hour 142.20
1 hour 252.20
50.44
1 hour 27.60
1 hour 181.50
36.30
1 Each 50.00
1 Each 583.80
126.76
4518.57
1.00 Cum 64.00
1.00 Cum 341.00
68.20
4991.77
679.63
5671.40
Say 5671
1 Cum 1119.87
1 Cum 301.50
1000 Kgs 1518.00
1 Kl 128.40
1 hour 142.20
1 hour 252.20
50.44
1 hour 27.60
1 hour 181.50
36.30
1 Each 50.00
1 Each 583.80
126.76
4518.57
4F 5F 6F
4518.57 4518.57 4518.57
64.00 64.00 64.00
443.30 477.40 511.50
88.66 95.48 102.30
190.14 253.52 316.90
38.03 50.70 63.38
5342.70 5459.67 5576.65
727.41 743.33 759.26
6070.11 6203.01 6335.91
6070 6203 6336
1 Each 66.50
1 Each 122.82
1 Each 1512.00
340.26
1 hour 142.20
1 hour 252.20
50.44
1 kl 128.40
5374.64
4F 5F 6F
5374.64 5374.64 5374.64
64.00 64.00 64.00
443.30 477.40 511.50
88.66 95.48 102.30
510.40 680.53 850.66
102.08 136.11 170.13
6583.08 6828.16 7073.24
896.29 929.65 963.02
7479.37 7757.81 8036.26
7479 7758 8036
1 Each 33.50
1 Each 61.18
1 Each 1050.00
228.94
1 hour 142.20
1 hour 252.20
50.44
1 kl 128.40
4706.68
1 cum 235.33
235.33
4F 5F 6F
235.33 235.33 235.33
1 cum 117.67
117.67
4F 5F 6F
117.67 117.67 117.67
1 MT 43575.00
1 Kgs 330.00
1 Each 1875.00
1 Each 3465.00
1 Each 4200.00
1908.00
55353.00
4F 5F 6F
55353.00 55353.00 55353.00
2862.00 3816.00 4770.00
572.40 763.20 954.00
58787.40 59932.20 61077.00
8003.90 8159.77 8315.63
66791.30 68091.97 69392.63
66791 68092 69393
1 MT 40950.00
1 Kgs 330.00
1 Each 1875.00
1 Each 3465.00
1 Each 4200.00
1908.00
52728.00
4F 5F 6F
52728.00 52728.00 52728.00
2862.00 3816.00 4770.00
572.40 763.20 954.00
56162.40 57307.20 58452.00
7646.51 7802.38 7958.24
63808.91 65109.58 66410.24
63809 65110 66410
1 MT 41500.00
1 MT 27000.00
Kgs 5000.00
3160.00
76660.00
10437.26
87097.26
Say 87097
1 MT 60000.00
1 MT 24000.00
Kgs 21000.00
6120.00
111120.00
15128.99
126248.99
Say 126249
eened sand including cost and conveyance of all
rges on materials and including cost of all labour
tc., and overheads & contractors profit complete
1 Each 225.00
1 Each 483.00
1 Each 1176.00
376.80
25.72
2597.74
259.77
4F 5F 6F
259.77 259.77 259.77
2.46 2.46 2.46
35.90 42.56 49.22
7.18 8.51 9.84
56.52 75.36 94.20
11.30 15.07 18.84
373.13 403.73 434.33
50.80 54.97 59.13
423.93 458.70 493.46
424 459 493
1 Each 315.00
1 Each 676.20
1 Each 1638.00
525.84
34.55
3489.77
348.98
4F 5F 6F
348.98 348.98 348.98
1.03 1.03 1.03
18.24 21.67 25.10
3.65 4.33 5.02
78.88 105.17 131.46
15.78 21.03 26.29
466.56 502.21 537.88
63.52 68.38 73.23
530.08 570.59 611.11
530 571 611
1 Each 225.00
1 Each 483.00
1 Each 1176.00
376.80
25.72
2597.74
259.77
1 sqm 259.77
35.37
295.14
Say 295
4F 5F 6F
259.77 259.77 259.77
1.03 1.03 1.03
18.24 21.67 25.10
3.65 4.33 5.02
56.52 75.36 94.20
11.30 15.07 18.84
350.51 377.24 403.96
47.72 51.36 55.00
398.23 428.60 458.96
398 429 459
1 Each 315.00
1 Each 676.20
1 Each 1638.00
525.84
35.85
3620.85
362.09
4F 5F 6F
362.09 362.09 362.09
1.03 1.03 1.03
18.24 21.67 25.10
3.65 4.33 5.02
78.88 105.17 131.46
15.78 21.03 26.29
479.67 515.32 550.99
65.31 70.16 75.02
544.98 585.48 626.01
545 585 626
1 Each 225.00
1 Each 483.00
1 Each 1176.00
376.80
26.97
2723.47
272.35
37.08
309.43
Say 309
4F 5F 6F
272.35 272.35 272.35
1.03 1.03 1.03
18.24 21.67 25.10
3.65 4.33 5.02
56.52 75.36 94.20
11.30 15.07 18.84
363.09 389.81 416.54
49.44 53.07 56.71
412.53 442.88 473.25
413 443 473
slopes with CM (1:3) prop. using screened sand
ming to IS: 2645-2003 manufactured by reputed
ment, laid over roof slab when it is green, finished
of 45cmx45cm including cost and conveyance of
operational, incidental, and labour charges for
including rounding off junctions of wall and slab
SS No. 901 & 903).
1 Each 330.00
1 Each 708.40
1 Each 1554.00
518.48
38.08
3846.14
4F 5F 6F
3846.14 3846.14 3846.14
777.72 1036.96 1296.20
155.54 207.39 259.24
4779.40 5090.49 5401.58
650.72 693.07 735.43
5430.12 5783.56 6137.01
543.01 578.36 613.70
543 578 614
sump side wall,sump bottom slab,in side of
g screened sand 12mm thick mixed with integral
uted manufacturers as approved by Engineer-in-
ished smooth with a floating coat of neat cement
luding cost and conveyance of all materials like
tal, and labour charges for mixing mortar, laying,
unctions of wall and slab etc., and overheads &
1 Each 225.00
1 Each 483.00
1 Each 1176.00
376.80
27.60
2787.20
4F 5F 6F
2787.20 2787.20 2787.20
565.20 753.60 942.00
113.04 150.72 188.40
3465.44 3691.52 3917.60
471.82 502.60 533.38
3937.26 4194.12 4450.98
393.73 419.41 445.10
394 419 445
1 Sqm 650.00
88.50
738.50
say 738
th rabbit wire mesh & nomianl reinforcement as
cost and conveyance of all materials to site,
work site, centering, scaffolding and form work,lift
ork but excluding cost of steel and its fabrication
1 sqm 226.10
1000 Kgs 1104.00
1000 Kgs 230.00
1 cu.m. 375.00
1 Each 4000.00
1 Each 510.00
1 Each 4200.00
1742.00
1 hours 284.40
1 hours 504.40
100.88
132.77
13409.55
1340.95
4F 5F 6F
1340.95 1340.95 1340.95
4.12 5.15 6.18
18.24 21.67 25.10
3.65 4.33 5.02
261.30 348.40 435.50
52.26 69.68 87.10
1680.52 1790.18 1899.85
228.80 243.73 258.66
1909.32 2033.91 2158.51
1909 2034 2159
1 Each 1550.00
1 Each 506.00
1 Each 361.20
483.44
51.16
5167.55
4F 5F 6F
5167.55 5167.55 5167.55
725.16 966.88 1208.60
145.03 193.38 241.72
6037.74 6327.80 6617.87
822.04 861.53 901.02
6859.78 7189.33 7518.89
685.98 718.93 751.89
686 719 752
10 sqm 1487.84
1 Each 1550.00
1 Each 506.00
1 Each 361.20
483.44
48.22
4869.85
4F 5F
4869.85 4869.85
725.16 966.88
145.03 193.38
5740.05 6030.11
781.51 821.00
6521.56 6851.11
652.16 685.11
652 685
0 mm x 300 mm and thickness between 7-8 mm
colour and finish in all shades and designs as
12mm thick using screened sand over CC bed
ency spread @ 3.3 Kgs per sqm & jointed neatly
luding cost of all materials like cement, screened
hed item of work. (APSS No.701 & 707)
1 sqm 3885.00
1000 Kgs 99.36
1000 Kgs 151.80
1 Kg 54.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
77.56
7833.40
4F 5F 6F
7833.40 7833.40 7833.40
868.92 1158.56 1448.20
173.78 231.71 289.64
8876.10 9223.67 9571.24
1208.48 1255.80 1303.12
10084.58 10479.47 10874.36
1008.46 1047.95 1087.44
1008 1048 1087
1 sqm 3927.00
1000 Kgs 99.36
1000 Kgs 151.80
1 Kg 54.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
77.98
7875.82
4F 5F
7875.82 7875.82
868.92 1158.56
173.78 231.71
8918.52 9266.09
1214.26 1261.58
10132.78 10527.67
1013.28 1052.77
1013 1053
1 sqm 4389.00
1000 Kgs 99.36
1000 Kgs 151.80
1 Kg 162.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
83.68
8451.52
4F 5F 6F
8451.52 8451.52 8451.52
868.92 1158.56 1448.20
173.78 231.71 289.64
9494.22 9841.79 10189.36
1292.64 1339.96 1387.28
10786.86 11181.75 11576.64
1078.69 1118.18 1157.66
1079 1118 1158
1 sqm 6426.00
1000 Kgs 99.36
1000 Kgs 151.80
1 Kg 162.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
104.05
10508.89
4F 5F 6F
10508.89 10508.89 10508.89
868.92 1158.56 1448.20
173.78 231.71 289.64
11551.59 11899.16 12246.73
1572.75 1620.07 1667.39
13124.34 13519.23 13914.12
1312.43 1351.92 1391.41
1312 1352 1391
1 sqm 10552.50
1000 Kgs 99.36
1000 Kg 151.80
1 Kg 162.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
145.31
14676.65
4F 5F
14676.65 14676.65
868.92 1158.56
173.78 231.71
15719.36 16066.93
2140.19 2187.51
17859.55 18254.44
1785.95 1825.44
1786 1825
1 sqm 24591.00
1000 Kgs 165.60
1000 Kgs 151.80
1 Kg 162.00
1 Cum 150.00
1 Each 1500.00
1 Each 460.00
1 Each 3360.00
1064.00
316.04
31920.44
4F 5F 6F
31920.44 31920.44 31920.44
1596.00 2128.00 2660.00
319.20 425.60 532.00
33835.64 34474.04 35112.44
4606.72 4693.64 4780.56
38442.36 39167.68 39893.00
3844.24 3916.77 3989.30
3844 3917 3989
1 sqm 20905.50
1000 Kgs 165.60
1000 Kgs 151.80
1 Kg 162.00
1 Cum 150.00
1 Each 1500.00
1 Each 460.00
1 Each 3360.00
1064.00
1 RM 283.39
1 RM 5301.06
446.76
339.50
34289.61
4F 5F 6F
34289.61 34289.61 34289.61
1596.00 2128.00 2660.00
319.20 425.60 532.00
36204.81 36843.21 37481.61
4929.28 5016.20 5103.12
41134.09 41859.41 42584.73
4113.41 4185.94 4258.47
4113 4186 4258
1 sqm 20905.50
1000 Kgs 165.60
1000 Kgs 151.80
1 Kg 162.00
1 Cum 150.00
1 Each 1500.00
1 Each 460.00
1 Each 3360.00
1064.00
1 RM 739.16
1 RM 13826.64
1165.26
436.50
44086.46
4F 5F 6F
44086.46 44086.46 44086.46
1596.00 2128.00 2660.00
319.20 425.60 532.00
46001.66 46640.06 47278.46
6263.13 6350.04 6436.96
52264.79 52990.10 53715.42
5226.48 5299.01 5371.54
5226 5299 5372
1 Cum 177.62
1000 Kgs 552.00
1 Cum 56.95
1 sqm 100.00
1 Each 625.00
1 Each 27.60
1 Each 1260.00
382.52
31.82
3213.50
4F 5F
3213.50 3213.50
573.78 765.04
114.76 153.01
3902.04 4131.55
531.26 562.51
4433.30 4694.06
443.33 469.41
443 469
S: 13801 using aggregates, cement, pigments of
by Engineer - In - Charge set over base coat of
or RCC roof slab including neat cement slurry of
ite cement to full depth mixed with pigment of
t, sand, water and tiles etc.,and overheads &
1 sqm 2824.50
1000 Kgs 132.48
1000 Kgs 151.80
1.00 Kgs 162.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
68.36
6904.82
4F 5F 6F
6904.82 6904.82 6904.82
868.92 1158.56 1448.20
173.78 231.71 289.64
7947.53 8295.10 8642.66
1082.06 1129.38 1176.70
9029.59 9424.48 9819.36
902.96 942.45 981.94
903 942 982
1 hour 142.20
1 hour 252.20
50.44
1 hour 27.60
1 hour 181.50
36.30
1 Each 50.00
1 Each 583.80
126.76
4682.64
1 cum 2341.32
1 cum 32.00
1 cum 170.50
34.10
1 sqm 300.00
1 sqm 350.00
1 RM 520.00
1 RM 455.00
4202.92
572.23
4775.15
477.51
Say 478
1 SQM 443.00
1 SQM 178.00
35.60
656.60
89.40
746.00
Say 746
Operation Theatres and labour rooms - SIKA
able chemical resistance durable and non particle
terials and all labour charges, overheads and
1 sqm 1940.00
ess of 2 mm with a wearing surface impregnated
ents with wearing resistance and Fire Resistance
es for fixing, all labour charges, overheads &
1 sqm 720.00
216.00
936.00
127.44
1063.44
Say 1063
1 Cum 14253.38
1 Cum 46019.35
1 No 6000.00
1 Sqm 288.00
Nos 640.00
1 Each 1622.40
1 Each 3348.80
1 Each 3628.80
1720.00
77520.73
4845.05
659.65
5504.70
Say 5505
er grade teak wood as per drawing over the teak
eet acting as vapour barrior and fixing teak wood
runners, polythene sheet, fitting with steel pins
roof polish glossy/matt finish to the wooden
with 180 no, emery paper and then with 320 no.,
wood filler by putty knife/ muslin pad, air dry for 2-
sealer, after the surface preparation applying one
pproved brushing PU thinner or general purpose
night, sand again with 180 Nos emery paper and
with 180 nos. emery paper and removing dust,
er, and applying (either with spray or brush) two
1 sqm 5505.00
1 sqm 1037.00
6542
ic concrete flooring 20 mm thick leveling layer of
umen penetration 80/25 (blown type) @ 2.45 kg
pe) up to half depth, planed, levelled smooth and
1 sqm 9971.20
9971.20
Say 9971
10 sqm 1782.58
1 Each 1550.00
1 Each 506.00
1 Each 361.20
483.44
1 RM 1666.50
133.32
69.76
7045.58
4F 5F
7045.58 7045.58
725.16 966.88
145.03 193.38
7915.77 8205.83
1077.73 1117.22
8993.50 9323.05
899.35 932.31
899 932
10 sqm 1782.58
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Each 480.00
1 Each 1030.40
1 Each 1302.00
562.48
55.58
5613.82
4F 5F
5613.82 5613.82
843.72 1124.96
168.74 224.99
6626.29 6963.77
902.17 948.12
7528.46 7911.89
752.85 791.19
753 791
10 sqm 2231.76
1 Each 1550.00
1 Each 506.00
1 Each 361.20
483.44
1 RM 1666.50
133.32
74.25
7499.24
4F 5F
7499.24 7499.24
725.16 966.88
145.03 193.38
8369.43 8659.50
1139.50 1178.99
9508.93 9838.49
950.89 983.85
951 984
10 sqm 2231.76
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Each 480.00
1 Each 1030.40
1 Each 1302.00
562.48
60.07
6067.49
4F 5F
6067.49 6067.49
843.72 1124.96
168.74 224.99
7079.95 7417.44
963.94 1009.88
8043.89 8427.32
804.39 842.73
804 843
1 sqm 24591.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 162.00
1 Cum 90.00
1 Each 1500.00
1 Each 460.00
1 Each 3360.00
1064.00
1 RM 566.61
1 RM 13731.96
1143.89
469.80
47450.03
4F 5F 6F
47450.03 47450.03 47450.03
1596.00 2128.00 2660.00
319.20 425.60 532.00
49365.23 50003.63 50642.03
6721.08 6807.99 6894.91
56086.31 56811.62 57536.94
5608.63 5681.16 5753.69
5609 5681 5754
1 sqm 24591.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 135.00
1 RM 1133.39
90.67
1 Each 1050.00
1 Each 2058.00
621.60
300.80
30381.24
4F 5F 6F
30381.24 30381.24 30381.24
932.40 1243.20 1554.00
186.48 248.64 310.80
31500.12 31873.08 32246.04
4288.74 4339.52 4390.30
35788.86 36212.60 36636.34
3578.89 3621.26 3663.63
3579 3621 3664
bad/Tandur stone slabs 15mm to 18mm thick,
g screened sand with cement slurry of honey like
10 sqm 1782.58
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Each 480.00
1 Each 1030.40
1 Each 1302.00
562.48
55.58
5613.82
4F 5F 6F
5613.82 5613.82 5613.82
843.72 1124.96 1406.20
168.74 224.99 281.24
6626.29 6963.77 7301.26
902.17 948.12 994.07
7528.46 7911.89 8295.33
75.28 79.12 82.95
75 79 83
10 sqm 1420.21
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Each 480.00
1 Each 1030.40
1 Each 1302.00
562.48
51.96
5247.82
4F 5F
5247.82 5247.82
843.72 1124.96
168.74 224.99
6260.29 6597.78
852.34 898.29
7112.63 7496.07
71.13 74.96
71 75
1 Each 385.00
1 Each 336.00
144.20
53.55
5408.53
4F 5F
5408.53 5408.53
216.30 288.40
43.26 57.68
5668.09 5754.61
771.71 783.49
6439.80 6538.10
64.40 65.38
64 65
1 sqm 4389.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 54.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
83.19
8402.65
4F 5F 6F
8402.65 8402.65 8402.65
868.92 1158.56 1448.20
173.78 231.71 289.64
9445.35 9792.92 10140.49
1285.99 1333.31 1380.63
10731.34 11126.23 11521.12
107.31 111.26 115.21
107 111 115
in free full body porcelain vitrified tiles with
mm of any colour and finish in all shades and
se coat of CM(1:5) 12 mm thick using screened
gs per sqm and jointing with white cement paste
rials like tiles, cement, sand and water etc.,and
&707)
1 sqm 6426.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 54.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
103.56
10460.02
4F 5F 6F
10460.02 10460.02 10460.02
868.92 1158.56 1448.20
173.78 231.71 289.64
11502.72 11850.29 12197.86
1566.10 1613.42 1660.74
13068.82 13463.71 13858.60
130.69 134.64 138.59
131 135 139
1 sqm 10552.50
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 135.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
145.64
14709.60
4F 5F
14709.60 14709.60
868.92 1158.56
173.78 231.71
15752.30 16099.87
2144.68 2192.00
17896.98 18291.87
178.97 182.92
179 183
1 RM 536.00
1 sqm 10552.50
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 135.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
145.64
14709.60
4F 5F
14709.60 14709.60
868.92 1158.56
173.78 231.71
15752.30 16099.87
2144.68 2192.00
17896.98 18291.87
1789.70 1829.19
1790 1829
1 sqm 24591.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 135.00
1 RM 1133.39
90.67
1 Each 1050.00
1 Each 2058.00
621.60
300.80
30381.24
4F 5F 6F
30381.24 30381.24 30381.24
932.40 1243.20 1554.00
186.48 248.64 310.80
31500.12 31873.08 32246.04
4288.74 4339.52 4390.30
35788.86 36212.60 36636.34
357.89 362.13 366.36
358 362 366
1 sqm 24591.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 135.00
1 RM 1133.39
90.67
1 Each 1050.00
1 Each 2058.00
621.60
300.80
30381.24
4F 5F 6F
30381.24 30381.24 30381.24
932.40 1243.20 1554.00
186.48 248.64 310.80
31500.12 31873.08 32246.04
4288.74 4339.52 4390.30
35788.86 36212.60 36636.34
3578.89 3621.26 3663.63
3579 3621 3664
1 sqm 4158.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 162.00
1 Each 385.00
1 Each 336.00
144.20
55.86
5641.84
4F 5F 6F
5641.84 5641.84 5641.84
216.30 288.40 360.50
43.26 57.68 72.10
5901.40 5987.92 6074.44
803.48 815.25 827.03
6704.88 6803.17 6901.47
670.49 680.32 690.15
670 680 690
0mm x 600 mm with any type of design texture
free and thickness between 6-8 mm 1st quality
nish in all shades and designs with borders and
d to wall surface set over base coat of CM(1:5)
cy spread at the rate of 3.30 kgs per sqm and
l depth, including cost of all materials like tiles,
ished item of work.
1 sqm 5817.00
1 cum 90.00
1000 Kgs 158.98
1000 Kgs 151.80
1 Kg 54.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
97.47
9844.93
4F 5F 6F
9844.93 9844.93 9844.93
868.92 1158.56 1448.20
173.78 231.71 289.64
10887.63 11235.20 11582.77
1482.35 1529.67 1576.99
12369.98 12764.87 13159.76
1237.00 1276.49 1315.98
1237 1276 1316
1 sqm 2530.50
1000 Kgs 132.48
1000 Kgs 151.80
1.00 Kgs 162.00
1 Cum 90.00
1 Each 480.00
1 Each 1030.40
1 Each 1386.00
579.28
65.42
6607.88
660.79
1 Cum 127.32
1 Cum 40.12
1 Cum 999.08
1 Sqm 575.82
1 Cum 792.95
2535.29
2112.74
Say 2113
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
3218.92
4F 5F
3218.92 3218.92
190.14 253.52
38.03 50.70
3447.09 3523.14
469.32 479.68
3916.41 4002.82
3916 4003
ngs
1 No. 130.20
26.04
1 cum 3684.00
3840.24
4F 5F 6F
3840.24 3840.24 3840.24
39.06 52.08 65.10
7.81 10.42 13.02
3887.11 3902.74 3918.36
529.23 531.36 533.48
4416.34 4434.10 4451.84
736.06 739.02 741.97
736 739 742
1 Each 83.50
1 Each 76.82
1 Each 1974.00
426.86
1 hour 142.20
1 hour 252.20
1 hour 27.60
1 hour 181.50
86.74
1 kl 128.40
5085.50
5F 6F 7F
5085.50 5085.50 5085.50
238.00 238.00 238.00
2460.00 2636.00 2811.00
492.00 527.20 562.20
853.73 1067.16 1280.59
170.75 213.43 256.12
9299.98 9767.29 10233.41
1266.19 1329.82 1393.28
10566.17 11097.11 11626.69
10566 11097 11627
1 Kg 7083.40
1 Kg 2803.40
1 RM 217.10
1 Each 1040.00
1 No 390.00
1 No 195.00
11728.90
2549.76
2833.07
385.72
3218.79
say 3219
1 Kg 8705.30
1 Kg 3445.30
1 RM 150.30
1 Each 270.00
12570.90
1257.09
171.15
1428.24
say 1428
1 Kg 158.88
1 Kg 62.88
1 RM 33.40
1 Each 160.00
1 No 60.00
1 No 30.00
505.16
68.78
573.94
say 574
1 sqm 340.00
1 Each 30.00
1 Each 27.60
1 Each 115.50
34.62
547.72
4F 5F 6F
547.72 547.72 547.72
10.32 10.32 10.32
182.41 216.72 251.03
36.48 43.34 50.21
51.93 69.24 86.55
10.39 13.85 17.31
839.25 901.19 963.14
114.26 122.7 131.13
953.51 1023.89 1094.27
954 1024 1094
1 kgs 54.00
1 Each 36.54
1 Each 67.62
1 Each 134.40
47.71
3.40
343.67
46.79
390.47
39.05
Say 39
20 Kg 632.50
1 Each 158.34
1 Each 293.02
1 Each 382.20
166.71
16.33
1649.10
224.52
1873.62
187.36
Say 187
25 Kg 1128.84
1 Each 158.34
1 Each 293.02
1 Each 382.20
166.71
21.29
1 sqm 10.30
1 sqm 79.50
15.90
2256.10
307.17
2563.27
256.33
Say 256
1 Kg 13.50
1 Each 46.40
1 Each 87.40
1 Ltr 137.70
1 Each 208.80
1 Each 386.40
145.80
10.26
1036.26
141.09
1177.35
117.73
Say 118
1 Ltr 137.70
1 Each 208.80
1 Each 386.40
119.04
8.52
860.46
117.15
977.61
97.76
Say 98
13.22
1335.10
181.77
1516.87
151.69
Say 152
11.34
1145.66
155.98
1301.65
130.16
Say 130
1 Kg 141.00
1 Each 121.80
1 Each 225.40
1 Ltrs 134.40
1 Each 208.80
1 Each 386.40
188.48
14.06
1420.34
193.38
1613.72
161.37
Say 161
1 Kg 141.00
1 Each 121.80
1 Each 225.40
1
Ltrs
323.20
1 Each 208.80
1 Each 386.40
188.48
15.95
1611.03
219.34
1830.37
183.04
Say 183
1 Kg 180.00
1 Each 121.80
1 Each 225.40
1 Ltrs 155.20
1 Each 121.80
1 Each 225.40
1 Each 630.00
264.88
19.24
1943.72
264.64
2208.36
220.84
Say 221
1 Kg 180.00
1 Each 121.80
1 Each 225.40
1
Ltrs
323.20
1 Each 121.80
1 Each 225.40
1 Each 630.00
264.88
20.92
2113.40
287.74
2401.14
240.11
Say 240
20 Kg 632.50
1 Each 158.34
1 Each 293.02
1 Each 382.20
166.71
16.33
1649.10
1 Kg 141.00
1 Each 121.80
1 Each 225.40
69.44
5.58
563.22
1 Ltr 675.00
1 Each 208.80
1 Each 386.40
119.04
13.89
1403.13
3615.45
492.24
4107.69
410.77
Say 411
1 Ltr 91.00
1 Each 121.80
1 Each 225.40
1 Ltr 297.60
1 Each 208.80
1 Each 386.40
188.48
16.49
1665.97
226.82
1892.80
189.28
Say 189
9.87
996.91
135.73
1132.64
113.26
Say 113
1 Ltr 84.70
1 Each 121.80
1 Each 225.40
69.44
5.01
506.35
68.94
575.29
57.53
Say 58
1 Each 191.40
1 Each 354.20
109.12
9.28
936.80
127.54
1064.34
106.43
Say 106
1 Ltr 84.70
1 Ltr 272.80
1 Each 121.80
1 Each 225.40
1 Each 191.40
1 Each 354.20
178.56
14.29
1443.15
196.48
1639.63
163.96
Say 164
1 Ltr 223.20
1 Each 191.40
1 Each 354.20
109.12
8.78
886.70
120.72
1007.42
100.74
Say 101
ved brand for new wood work to teak wood frame
nd conveyance of all materials to site, all labour
1 Ltrs 40.81
1 Ltrs 156.48
1 Nos. 556.80
1 Nos. 1030.40
317.44
21.02
2122.95
289.04
2411.99
241.20
Say 241
1 Ltrs 20.41
1 Ltrs 4.32
1 Nos. 139.20
1 Nos. 257.60
1 Nos. 336.00
146.56
9.04
913.13
124.32
1037.46
Say 1037
1 Nos. 139.20
1 Nos. 257.60
1 Nos. 336.00
146.56
9.25
934.34
127.21
1061.55
Say 1062
1 sqm 3198.00
435.41
3633.41
Say 3633
1 sqm 2798.00
380.95
3178.95
Say 3179
joints on terrace (Size : 25mm x 12mm):
lymer based bonding agent– ROOFBOND SBR
ZORIBOND SBR (PMCC)/ SIKA LATEX (Sika)
7E or equivalent mixing with cement as per
einstatement concrete/mortar admixture with -
RD ARM (EBT) / WATERSHIELD AR / Fosroc to
ng of masking tape on top of the joint both sides.
ave the depth of 12mm on the joint. f]. Providing
mer on inner edge on joints. g]. Providing and
pth with - ROOFSEAL PS (Armstrong ) / POWER
SIKA POLYSULPHIDE (Sika) / WATERSHIELD
h]. Removing of masking tape and providing and
OFSEAL PS (Armstrong ) / POWER n SEAL PS
PHIDE (Sika) / WATERSHIELD PS including cost
etc., complete for finished item of work
1 RM 650.00
88.50
738.50
Say 738
1 sqm 329.00
44.79
373.79
Say 374
1 sqm 256.00
1 RM 165.00
421.00
64.00
8.71
72.71
Say 73
1 sqm 6625.00
901.99
7526.99
Say 7527
1 sqm 321.00
1 RM 13.60
1 RM 64.00
1 RM 62.40
1 RM 10.24
1 No. 2.56
1 No. 69.60
1 No. 55.20
1 No. 13.92
1 No. 11.04
1 No. 6.96
1 No. 6.96
1 No. 30.24
38.78
1 No. 32.64
1 No. 30.40
769.54
7.70
777.24
105.82
883.06
Say 883
1 sqm 416.00
1 RM 13.60
1 RM 64.00
1 RM 62.40
1 RM 10.24
1 No. 2.56
1 No. 69.60
1 No. 55.20
1 No. 13.92
1 No. 11.04
1 No. 6.96
1 No. 6.96
1 No. 30.24
38.78
1 No. 32.64
1 No. 30.40
864.54
8.65
873.19
118.88
992.07
Say 992
1 sqm 216.30
1 RM 40.32
1 RM 60.48
1 RM 59.64
1 RM 25.20
1 No. 5.52
1 No. 1.28
1 No. 1.92
1 No. 36.00
1 Kg. 13.75
1 RM 5.84
1 Ltr 18.00
1 No. 69.60
1 No. 55.20
1 No. 13.92
1 No. 11.04
1 No. 6.96
1 No. 13.92
1 No. 30.24
40.18
1 Hour 32.64
1 Hour 60.80
818.75
8.19
826.93
112.59
939.52
Say 940
1 sqm 238.00
1 RM 14.00
1 RM 147.20
1 RM 14.08
1 No. 2.56
1 No. 3.84
1 No. 16.08
1 Ltr 18.00
1 No. 69.60
1 No. 55.20
1 No. 13.92
1 No. 11.04
1 No. 6.96
1 No. 6.96
1 No. 30.24
38.78
1 Hour 32.64
1 Hour 30.40
749.50
7.50
757.00
103.07
860.06
Say 860
1 sqm 24.00
1 RM 9.60
1 RM 92.80
1 No. 10.24
1 No. 2.56
1 No. 62.64
1 No. 49.68
1 No. 11.60
1 No. 23.20
1 No. 84.00
46.22
1 No. 16.32
1 No. 30.40
463.26
4.63
467.90
63.70
531.60
Say 532
1 Kgs 306.00
1 Kgs 137.70
Kgs 25.50
16.12
485.32
66.08
551.39
Say 551
1 Kg 6391.58
1 No. 239.55
1 No. 395.10
1 No. 183.64
1 No. 183.64
1 Ltr 24.50
1 Ltr 49.60
1 No. 386.40
1 No. 382.20
1 No. 10.44
1 No. 19.32
1 No. 25.20
1 No. 24.36
1 No. 45.08
1 No. 58.80
190.36
8609.77
860.98
117.22
978.20
Say 978
1 sqm 4053.00
1 No. 239.55
1 No. 395.10
1 No. 183.64
1 No. 183.64
1 No. 386.40
1 No. 382.20
153.72
5977.25
597.73
81.38
679.11
Say 679
1 No. 239.55
1 No. 395.10
1 No. 183.64
1 No. 183.64
1.00 RM 109.00
5.45
114.45
15.58
130.03
say 130
1 Each 166.00
16.60
182.60
24.86
207.46
Say 207
1 Each 415.00
415.00
56.50
471.50
Say 472
1 Each 2564.00
349.09
2913.09
Say 2913
1 hour 142.20
1 hour 252.20
50.44
1 Each 50.00
1 Each 583.80
126.76
3455.32
470.44
3925.76
Say 3926
NP-3 class for cross ducts including cost and
of 300mm dia. R.C.C Hume pipes in position
MoRT&H Specification 2900, 2905 and 2906 (5th
Charge for finished item of work
MoRT&H SDB
1 Each 70.00
1 Each 250.00
1 Each 1260.00
0.00
1 RM 10550.00
1 RM 788.13
12918.13
1033.45
140.70
1174.15
1174
1 day 0.00
1.00 day 1008.00
1.00 day 3360.00
873.60
1 hr 18122.40
1 hr 16131.00
1 hr 1965.60
1 cum 161364.00
1 cum 62926.20
1 Kl 1926.00
267676.80
892.26
121.48
Total 1013.74
Say 1014.00
n joint only, plain cement concrete pavement,
or any other type as per Clause 1501.2.2 M30
crete mixer of not less than 0.2 cum capacity and
ide formwork (steel channel, laying and fixing of
rmwork as per drawing), spreading the concrete
and finished in continuous operation including
ding strips, primer, sealant, dowel bars, near
d, curing of concrete slabs for 14- days, curing
awing and Technical Specification Clause 1501
1 day 2500.00
1 day 2300.00
1 day 63000.00
1 day 2520.00
1 day 2520.00
1 day 495.00
14667.00
1 hour 5119.20
1 hour 9079.20
1815.84
1 hour 248.40
1 hour 1633.50
326.70
1 hour 450.00
1 hour 432.00
1 hour 400.00
1 hour 3276.00
1 hour 2644.20
1 cum 77257.13
1 cum 22612.50
1 MT 120750.00
1 sqm 7425.00
1 MT 4586.40
1 litre 1824.00
1 RM 450.00
1 No. 289.80
1 litre 13054.00
1 kl 1926.00
1 sqm 2706.00
Total 366307.87
10989.24
377297.11
51369.00
428666.11
5715.55
Say 5716
1 No. 240.00
1 No. 920.00
1 No. 4200.00
1072.00
Total 6432.00
1 Hour 1106.82
1 Hour 9258.60
1 Hour 9568.20
1 Hour 13743.60
1 Hour 0.00
1 Hour 2811.00
Total 36488.22
10133.23
212797.87
42559.57
255357.45
1134.92
Say 1135
Kgs
1 Kg 481.40
1 Kg 9.24
1 Kg 202.10
1 Kgs 446.50
1 Kgs 82.69
1 Kg 123.00
1 Sqm 17.32
1362.24
681.12
92.73
773.86
Say 774.00
1 Sqm 404.00
40.40
444.40
60.51
504.91
Say 505
mm x 50mm x 6 mm MS angles 2 Nos. verticals
all materials,, fabrication, all other incidental and
bedding in concrete, overheads and contractors
1000 kg 41.50
1 Kg 27.00
1 Kg 5.00
3.16
76.66
10.44
87.10
87
JOINERY DATA
COMMON SoR 2019-20
b) Labour charges for aluminium doors ( S.No.11 of Page No. 396 of SoR 2011-12 )
1st class carpenter 0.099 Nos. 580.00 Each
2nd class carpenter 0.198 Nos. 460.00 Each
Power Saw Cutter -Hand Operated -Operator 0.099 Nos. 580.00 Each
Power Drill -Hand Operated -Operator 0.099 Nos. 580.00 Each
Mazdoor(Unskilled) 0.297 Nos. 420.00 Each
Non-technical work inspector 0.099 Nos. 520.00 Each
Add for MA @ 20% 0.20 439.56
Machinery
Power Saw Cutter -Hand Operated -Hire
charges 0.793 Hrs 102.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.793 Hrs 95.00 1 Hour
c) Labour charges for aluminium sliding windows ( S.No.10 of Page No. 395 of SoR 2011-12 )
1st class carpenter 0.096 Nos. 580.00 Each
2nd class carpenter 0.289 Nos. 460.00 Each
Power Saw Cutter -Hand Operated -Operator 0.096 Nos. 580.00 Each
Power Drill -Hand Operated -Operator 0.096 Nos. 580.00 Each
Mazdoor(Unskilled) 0.289 Nos. 420.00 Each
Non-technical work inspector 0.096 Nos. 520.00 Each
Add for MA @ 20% 0.20 471.28
C.Machinery
Power Saw Cutter -Hand Operated -Hire
charges 0.771 Hrs 102.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.771 Hrs 95.00 1 Hour
d) Labour charges for aluminium partitions partly glazed ( S.No.8 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.434 Nos. 580.00 Each
2nd class carpenter 0.434 Nos. 460.00 Each
Power Saw Cutter -Hand Operated -Operator 0.043 Nos. 580.00 Each
Power Drill -Hand Operated -Operator 0.058 Nos. 580.00 Each
Mazdoor(Unskilled) 0.145 Nos. 420.00 Each
Non-technical work inspector 0.072 Nos. 520.00 Each
Add for MA @ 20% 0.20 608.28
C.Machinery
Power Saw Cutter -Hand Operated -Hire
charges 0.347 Hrs 102.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.463 Hrs 95.00 1 Hour
Power charges for Motors 1% 0.01 809.32
Labour charges per 1 sqm
e) Labour charges for aluminium casement windows ( S.No.9 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.100 Nos. 580.00 Each
2nd class carpenter 0.300 Nos. 460.00 Each
Power Saw Cutter -Hand Operated -Operator 0.100 Nos. 580.00 Each
Power Drill -Hand Operated -Operator 0.100 Nos. 580.00 Each
Mazdoor(Unskilled) 0.300 Nos. 420.00 Each
Non-technical work inspector 0.100 Nos. 520.00 Each
Add for MA @ 20% 0.20 490.00
C.Machinery
Power Saw Cutter -Hand Operated -Hire
charges 0.800 Hrs 102.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.800 Hrs 95.00 1 Hour
1 Supply and fixing of two shutter main door cum fixed window as per approved drawing with best teak
wood frame of section 150mm x 100 mm with fixed fan light of 500mm at top and fixed panels of 600mm
width at sides fixed with 12mm thick Tinted - Bronze/Green glass using 12mm x 12mm teak wood beading
and fixing ornamental grill made of 25mm x 5mm MS flats as per the approved drawing in fan light portion
and fixed panels and 1st class teak wood top and middle rails & styles of section 120mm x 35mm, bottom
rail of size 150mm x 35mm and 12mm thick plain float glass for shutter with ornamental etching including
cost and
conveyance to site of teak wood frame, shutters, glass including supply and fixing 6 Nos MS Zhold fasts
of size 300 mm x 40 mm x 5mm including cost of ISI marked brass fixtures of 8 Nos butt hinges(IS:205)
250mm long , 1 No. aldrop (IS:2681) 450mm long, 3 Nos tower bolts- 10mm (IS:204) of 200 mm long , 2
Nos 450 mm long fancy handles, 2 Nos door stoppers, 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing
the frame in position, fixing the shutters to the frame, fixing glass in fan light portion etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth of not less than 40 mm) (3000mm x 2600mm)
Cost analysis
Cost of best TW frame 2 m to 3m length 0.1680 Cum 130525.0 1 Cum
Cost of best TW frame up to 2 m length 0.1724 Cum 122614.0 1 Cum
Cost of 12mm thick tinted glass 6.12 Sqm 1375.00 1 Sqm
Cost of 12mm thick plain float glass 3.78 Sqm 996.00 1 Sqm
Cost of teak wood beading 44.80 RM 26.00 1 RM
Cost of 250mm long brass butt hinges 8 Nos 500.00 Each
Cost of 450mm long brass fancy handles 2 Nos 1454.00 Each
2 Supply and fixing of ornamental grill made of 25mm x 5mm MS flats for fixing in fan light portion and
side fixed panels for door cum window as per the approved drawing including cutting the flat to required
length, welding, painting with red oxide single coat including cost and conveyance of all materials, labour
charges etc., complete for finished otem of work.
for grill of size 535mm x 435mm 0.2327
MS flats: 4(0.535+0.435)+4x0.1+2x0.38 5.04 RM 1 Kg/RM 5.04
Cost of MS flats 5.04 Kgs 43000.00 1000 Kgs
Labour charges for fabrication 5.04 Kgs 27.00 1 Kg
labour charges for fixing in position 5.04 Kgs 5.00 1 Kg
Add for MA @ 20% 0.20 79.63
Painting with red oxide 0.2327 Sqm 506.35 10 Sqm
Rate per 0.2327 Sqm
Rate per 1 Sqm
Cost analysis
Cost of best TW frame 2 m to 3m length 0.0630 Cum 130525.0 1 Cum
Cost of best TW frame up to 2 m length 0.0926 Cum 122614.0 1 Cum
Cost of 12mm thick plain float glass 4.20 Sqm 996.00 1 Sqm
Cost of teak wood beading 12.40 RM 26.00 1 RM
Cost of 250mm long brass butt hinges 8 Nos 500.00 Each
Cost of 450mm long brass fancy handles 2 Nos 1454.00 Each
1 Supply and fixing of two shutter main door as per approved drawing with best teak wood frame of
section 150mm x 100 mm and 1st class teak wood top and middle rails & styles of section 120mm x
35mm, bottom rail of size 150mm x 35mm and 12mm thick plain float glass for shutter including cost and
conveyance to site of teak wood frame, shutters, glass including supply and fixing 6 Nos MS Z hold fasts
of size 300 mm x 40 mm x 5mm including cost of ISI marked brass fixtures of 8 Nos butt hinges(IS:205)
250mm long , 1 No. aldrop (IS:2681) 450mm long, 3 Nos tower bolts- 10mm (IS:204) of 200 mm long , 2
Nos 450 mm long fancy handles, 2 Nos door stoppers, 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing
the frame in position, fixing the shutters to the frame etc., including overheads & contractors profit complete
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 40 mm) (1800mm x 2100mm)
Cost analysis
Cost of best TW frame 2 m to 3m length 0.0630 Cum 130525.0 1 Cum
Cost of best TW frame up to 2 m length 0.0869 Cum 122614.0 1 Cum
Cost of 12mm thick plain float glass 3.78 Sqm 996.00 1 Sqm
Cost of teak wood beading 12.00 RM 26.00 1 RM
Cost of 250mm long brass butt hinges 8 Nos 500.00 Each
Cost of 450mm long brass fancy handles 2 Nos 1454.00 Each
1 Supply and fixing of two shutter main door as per approved drawing with best teak wood frame of
section 150mm
conveyance x 100
to site mm wood
of teak and frame,
1st class teak wood
shutters top supply
including and middle rails &6 styles
and fixing Nos MS of Zhold
section 120mm
fasts of sizex
35mm,
300 mmbottom
x 40
Quantity analysis rail
mm of
x size
5mm 150mm x
including 35mm
cost and
of ISI 20mm
marked
Size : thick teak
brass wood
fixtures
1.80m x 2.10m panel
of 8 for
Nos shutter
butt including
hinges(IS:205)
3.78 cost and
250mm
long , 1 No. aldrop (IS:2681) 450mm
Best teak wood frame above 2m long for long, 3 Nos tower bolts- 10mm (IS:204) of 200 mm long , 2 Nos 450
mm long
outer framefancy handles, 2 Nos door stoppers, 2 Nos.
2x2.10 Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame
= 4.20 RM x 0.15 x 0.10 0.0630 Cum
in position, fixing the shutters to the frame etc., including overheads & contractors profit complete for
Shutter styles
finished item of work as per APSS 1001 & 1002 2 x (The
2 x 2.10
vertical frame of door shall be embedded in flooring
for a depth of not less than 40 mm) (1800mm =x 8.40 RM x 0.12 x 0.035
2100mm) 0.0353 Cum
0.0983 Cum
Best teak wood frame up to 2m long for outer
frame 1x1.80
= 1.80 RM x 0.15 x 0.10 0.0270 Cum
Shutter
Top and middle rail 2 x 2 x 0.90
= 3.60 RM x 0.12 x 0.035 0.0151 Cum
Bottom rail 2 x 0.9
= 1.80 RM x 0.15 x 0.035 0.0095 Cum
Cost analysis
Cost of best TW frame 2 m to 3m length 0.0983 Cum 130525.0 1 Cum
Cost of best TW frame up to 2 m length 0.1272 Cum 122614.0 1 Cum
Cost of teak wood beading 12.00 RM 26.00 1 RM
Cost of 250mm long brass butt hinges 8 Nos 500.00 Each
Cost of 450mm long brass fancy handles 2 Nos 1454.00 Each
Cost analysis
Cost of best TW frame 2 m to 3m length 0.03393 cum 130525.00 1 cum
Cost of best TW frame up to 2 m length 0.02925 cum 122614.00 1 cum
Cost of 4 mm thick pin headed glass 1.00 sqm 280.00 1 sqm
Cost of TW beading 6.00 RM 26.00 1 RM
Cost of 35 mm thick flush shutter 3.895 sqm 1396.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of brass tower bolt 200mm long 2 Nos. 317.00 Each
Cost of brass tower bolt 150mm long 1 No. 231.00 Each
Cost of brass Butt hinges 150mm long 6 Nos. 324.00 Each
Cost of brass aldrop 300mm long 1 No. 1087.00 Each
Cost of brass fancy handle 150mm long 2 Nos. 299.00 Each
Cost of brass door stopper 2 Nos. 168.00 Each
Cost of Rubber / Nylon door stop bushes 2 Nos. 9.00 Each
Cost of 10mm MS square bars 3.14 Kgs 41500.00 1000 Kgs
Labour charges for frame work 0.06318 cum 12475.20 1 cum
Add for MA @ 20% 0.20 788.18
4 Supply and fixing of doors as per approved drawings with best teak wood frame of section 100mm x 65
mm with fixed fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm
Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 35mm
thick double shutters with bond wood solid block board type core having cross bands and face veneers,
hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS
2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides, fixing 1mm thick mat
finish laminated sheet to full width and height of the flush shutter both sides
including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply
and fixing 6 nos MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked brass
(BLD-CSTN-13-16)
Size : 2.00m x 2.60 m 5.20
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 2.00 + 0.50
= 4.50 x 0.10 x 0.065 0.02925
0.06318
Cost analysis
Cost of best TW frame 2 m to 3m length 0.03393 cum 130525.00 1 cum
Cost of best TW frame up to 2 m length 0.02925 cum 122614.00 1 cum
Cost of 4 mm thick pin headed glass 1.00 sqm 280.00 1 sqm
Cost of TW beading 6.00 RM 26.00 1 RM
Cost of 35 mm thick flush shutter 3.895 sqm 1396.00 1 sqm
Cost of 1mm thick mat finish laminated sheet 7.79 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of brass tower bolt 200mm long 2 Nos. 317.00 Each
Cost of brass tower bolt 150mm long 1 No. 231.00 Each
Cost of brass Butt hinges 150mm long 6 Nos. 324.00 Each
Cost of brass aldrop 300mm long 1 No. 1087.00 Each
Cost of brass fancy handle 150mm long 2 Nos. 299.00 Each
Cost of brass door stopper 2 Nos. 168.00 Each
Cost of Rubber / Nylon door stop bushes 2 Nos. 9.00 Each
Cost of 10mm MS square bars 3.14 Kgs 41500.00 1000 Kgs
Labour charges for frame work 0.06318 cum 12475.20 1 cum
Add for MA @ 20% 0.20 788.18
5 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65 mm with fixed fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x
12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of
30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made
conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides
including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos.
MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos.
butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts - 10mm (IS:204)
of 200 mm long at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber /
Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan
light portion etc., including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(1800mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.80m x 2.60m 4.68
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.80 + 0.50
= 4.10 x 0.10 x 0.065 0.02665
0.06058
including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts
- 10mm (IS:204) of 200 mm long at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2
Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing
glass in fan light portion etc., including overheads & contractors profit complete for finished item of work as
per APSS 1001 & 1002 The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1800mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.80m x 2.60m 4.68
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.80 + 0.50
= 4.10 x 0.10 x 0.065 0.02665
0.06058
Cost of 1mm thick mat finish laminated sheet 6.970 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Alumimium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2
Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing
glass in fan light portion etc., including overheads & contractors profit complete for finished item of work as
per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1500mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.50m x 2.60m 3.90
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.50 + 0.50
= 3.50 x 0.10 x 0.065 0.02275
0.05668
Cost analysis
Cost of medium TW frame 2 m to 3m length
0.03393 cum 79106.00 1 cum
Cost of 1mm thick mat finish laminated sheet 5.74 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
2 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65 mm with
including cost split type fan light
and conveyance to of
site500mm
of teakatwood
the top fixed
frame, withshutter
flush 4mm thick pin headed
including supplyglass using 612mm
and fixing Nos.
MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos.
(BLD-CSTN-13-16)
Size : 1.20m x 2.60m 3.12
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.20 + 0.50
= 2.90 x 0.10 x 0.065 0.01885
0.05278
Cost analysis
2 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65 mm with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm
x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of
30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made
conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides
including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2
Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing
glass in fan light portion etc, including overheads & contractors profit complete for finished item of work as
per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1200mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.20m x 2.60m 3.12
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.20 + 0.50
= 2.90 x 0.10 x 0.065 0.01885
0.05278
Cost analysis
Cost of 1mm thick mat finish laminated sheet 4.51 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
3 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65
6 mm
Nos. with
MS splitfasts
Z hold typeoffan light
size 300ofmm500mm at the
x 40 mm top fixed
x 5mm with 4mm
including cost thick
of ISIpin headed
marked glass using
Aluminium 12mm
fixtures of
3 Nos. butt hinges
(BLD-CSTN-13-16) (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
Size : 1.00m x 2.60m 2.60
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.00
= 2.00 x 0.10 x 0.065 0.01300
0.04693
Cost analysis
3 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65 mm with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm
x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of
30mm thick single shutter with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made
conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides fixing 1mm
thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing
6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of
3 Nos. butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 1 No. door stopper and 1 No. Rubber /
Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan
light portion etc, including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(1000mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.00m x 2.60m 2.60
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.00
= 2.00 x 0.10 x 0.065 0.01300
0.04693
Cost analysis
Cost of 1mm thick mat finish laminated sheet 3.69 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
4 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x 65
6 mm
Nos. with
MS splitfasts
Z hold typeoffan light
size 300ofmm
500mm at the
x 40 mm top fixed
x 5mm with 4mm
including cost thick
of ISIpin headed
marked glass using
Aluminium 12mm
fixtures of
3 Nos. butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
(BLD-CSTN-13-16)
Size : 0.90m x 2.60m 2.34
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 0.90
= 1.80 x 0.10 x 0.065 0.01170
0.04563
Cost analysis
5 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm
x6 65 mm
Nos. MSwith splitfasts
Z hold typeoffan light
size 300ofmm
500mm at the
x 40 mm top fixed
x 5mm with 4mm
including cost thick
of ISIpin headed
marked glass using
Aluminium 12mm
fixtures of
3 Nos. butt hinges
(BLD-CSTN-13-16) (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
Size : 0.90m x 2.60m 2.34
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 0.90
= 1.80 x 0.10 x 0.065 0.01170
0.04563
Cost analysis
Cost of 1mm thick mat finish laminated sheet 3.28 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
6 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
supply and flush
fixing door shutters
6 Nos. MS Z of 30 fasts
hold mm thick double
of size 300 mmshutters withx bond
x 40 mm 5mm wood solidcost
including block
of board type
ISI marked
Aluminium fixtures
(BLD-CSTN-13-16) of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
Size : 2.00m x 2.10m 4.20
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 2.00
= 2.00 x 0.10 x 0.065 0.01300
0.04043
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked
Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter
to the frame etc, including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(2000mm x 2100mm)
(BLD-CSTN-13-16)
Size : 2.00m x 2.10m 4.20
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 2.00
= 2.00 x 0.10 x 0.065 0.01300
0.04043
Cost of 1mm thick mat finish laminated sheet 7.79 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
9 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
supply and flush
fixing door shutters
6 Nos. MS Z of 30 fasts
hold mm thick double
of size 300 mmshutters withx bond
x 40 mm 5mm wood solidcost
including block
of board type
ISI marked
Aluminium fixtures of 6 Nos. butt hinges (IS:205)150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
(BLD-CSTN-13-16)
Size : 1.80m x 2.10m 3.78
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.80
= 1.80 x 0.10 x 0.065 0.01170
0.03913
Cost of 1mm thick mat finish laminated sheet 6.97 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
10 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
supply and flush
fixing door shutters
6 Nos. MS Z of 30 fasts
hold mm thick double
of size 300 mmshutters withx bond
x 40 mm 5mm wood solidcost
including block
of board type
ISI marked
Aluminium fixtures
(BLD-CSTN-13-16) of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
Size : 1.50m x 2.10m 3.15
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.50
= 1.50 x 0.10 x 0.065 0.00975
0.03718
11 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate
sheet including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked
Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter
to the frame etc., including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(1500mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.50m x 2.10m 3.15
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.50
= 1.50 x 0.10 x 0.065 0.00975
0.03718
Cost of 1mm thick mat finish laminated sheet 5.74 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
Cost of Aluminium butt hinges 150mm long 6 Nos. 120.00 Each
Cost of Aluminium aldrop 300mm long 1 No. 308.00 Each
Cost of Aluminium handle 150mm long 2 Nos. 103.00 Each
Cost of Aluminium door stopper 2 Nos. 53.00 Each
Cost of Rubber / Nylon door stop bushes 2 Nos. 9.00 Each
Labour charges for frame work 0.03718 cum 12475.20 1 cum
Add for MA @ 20% 0.20 463.83
12 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
supply and flush
fixing door shutters
6 Nos. MS Z of 30fasts
hold mm thick
of sizedouble
300 mm shutters
x 40 mmwithx bond
5mm wood solidcost
including block
of board type
ISI marked
Alumium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780
0.03523
13 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate
sheet including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked
Alumium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos.
tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter
to the frame etc., including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(1200mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780
0.03523
Cost of 1mm thick mat finish laminated sheet 4.51 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 2 Nos. 103.00 Each
Cost of Aluminium butt hinges 150mm long 6 Nos. 120.00 Each
Cost of Aluminium aldrop 300mm long 1 No. 308.00 Each
Cost of Aluminium handle 150mm long 2 Nos. 103.00 Each
Cost of Aluminium door stopper 2 Nos. 53.00 Each
Cost of Rubber / Nylon door stop bushes 2 Nos. 9.00 Each
Labour charges for frame work 0.035 cum 12475.20 1 cum
Add for MA @ 20% 0.20 439.50
14 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
fixing 6 Nos.flush
MS Zdoor
holdshutters
fasts ofofsize
30 300
mm mm
thickx single
40 mmshutter
x 5mm with bond cost
including woodofsolid block board
ISI marked type
Aluminium
fixtures of 3 Nos.
(BLD-CSTN-13-16) butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
Size : 1.00m x 2.10m 2.10
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650
0.03393
30 mm thick flush shutter 0.90 x 2.05 1.845
Cost analysis
3 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminated
sheet including supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
(IS:204) of 200 mm x 10 mm dia at top , 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc.,
including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (1000mm x
2100mm)
(BLD-CSTN-13-16)
Size : 1.00m x 2.10m 2.10
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650
0.03393
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 79106.00 1 cum
Cost of 1mm thick mat finish laminated sheet 3.69 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
1 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked
fixing 6 Nos.flush
MS Zdoor
holdshutters
fasts ofofsize
30 300
mm mm
thickx single
40 mmshutter
x 5mm with bond cost
including woodofsolid block board
ISI marked type
Aluminium
fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
(BLD-CSTN-13-16)
Size : 1.05m x 2.10m 2.21
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.05
= 1.05 x 0.10 x 0.065 0.00683
0.03426
Cost analysis
Cost of 1mm thick mat finish laminated sheet 3.90 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc,
including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (900mm x
2100mm)
(BLD-CSTN-13-16)
Size : 0.90m x 2.10m 1.89
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.90
= 0.90 x 0.10 x 0.065 0.00585
0.03328
Cost analysis
4 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate
sheet including supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc,
including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (900mm x
2100mm)
(BLD-CSTN-13-16)
Size : 0.90m x 2.10m 1.89
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.90
= 0.90 x 0.10 x 0.065 0.00585
0.03328
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 79106.00 1 cum
Cost of medium TW frame up to 2 m length 0.00585 cum 71195.00 1 cum
Cost of 30 mm thick flush shutter 1.64 sqm 1232.00 1 sqm
Cost of 1mm thick mat finish laminated sheet 3.28 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
Cost of Aluminium butt hinges 150mm long 3 Nos. 120.00 Each
Cost of Aluminium aldrop 300mm long 1 No. 308.00 Each
Cost of Aluminium handle 150mm long 2 Nos. 103.00 Each
Cost of Aluminium door stopper 1 No. 53.00 Each
Cost of Rubber / Nylon door stop bushes 1 No. 9.00 Each
Labour charges for frame work 0.03328 cum 12475.20 1 cum
Add for MA @ 20% 0.20 415.17
Labour charges for fixing flush door shutter
to the frame , fixing the fixtures to the shutter 1.64 sqm 383.00 1 sqm
Add for MA @ 20% 0.20 628.12
Add for nails & screws etc.
Rate for 1.89 sqm
Overheads & Contractors Profit @13.615% 0.13615 8407.83
5 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and
ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate
sheet including supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc,
including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (800mm x
2100mm)
(BLD-CSTN-13-16)
Size : 0.80m x 2.10m 1.68
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.80
= 0.80 x 0.10 x 0.065 0.00520
0.03263
Cost analysis
Cost of 1mm thick mat finish laminated sheet 2.87 sqm 370.00 1 sqm
Labour charges for fixing laminated sheet
Cost of MS Z hold fasts 6 Nos. 32.00 Each
Cost of Aluminium tower bolt 200mm long 1 No. 103.00 Each
5 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and
ISINo.
1 marked
towerflush
bolt door shutter
(IS:204) of 30mm
of 150 mm x thick
10mmsingle
dia, 2shutter with bond
Nos. 125mm longwood solid(IS:208),1
handles block board
No.type Core/
Rubber
Nylon door stop bushes including PVC door cladding 1.50mm thick to the flush doors shutters pasted with
(BLD-CSTN-13-16)
Quantity analysis Size : 0.80m x 2.10m 1.68
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.80
= 0.80 x 0.10 x 0.065 0.00520
0.03263
Cost analysis
6 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and
ISINo.
1 marked
towerflush
bolt door shutter
(IS:204) of 30mm
of 150 mm x thick
10mmsingle
dia, 2shutter with bond
Nos. 125mm longwood solid(IS:208),1
handles block board
No.type Core/
Rubber
Nylon door stop bushes including PVC door cladding 1.50mm thick to the flush doors shutters pasted with
(BLD-CSTN-13-16)
Quantity analysis Size : 0.75m x 2.10m 1.575
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.75
= 0.75 x 0.10 x 0.065 0.00488
0.03231
Cost analysis
5 Supplying and fixing single side prelam solid panel PVC door frame (Choukhat): Providing and fixing
factory made Pac single side Prelam door frame of the size 50x7 mm with a wall thickness of 5mm, made
out of extruded 5mm rigid Pac single side prelam sheet, meter cut at two corners and joined with 2 Nos. of
150mm long brackets of 15 x 15mm MS Square tube. The two vertical door profiles are to be reinforced
with 19 x 19mm MS. square tube of 19 guage. The door frame shall be fixed to the wall using 65/100mm
long MS. Screws through the frame by using Pac fasteners. a minimum of 4 Nos. of screws to be provided
for each vertical member and minimum 2nos. for horizontal member etc. complete as per manufacture
specification and direction of Engineer-incharge including conveyance of all materials, labour charges for
fixing, overheads & contractors profit complete for finished item of work.
1 Supply & Fixing of Stainless steel Fire Rated doors, frames & shutters made of Stainless steel of 304
grade hairline finish, frame with 1.2mm thick Stainless steel of 304 grade hairline finish sheet formed to
double rebate profile of ize 143 mm X 58 mm with maximum bending radius of 1.4 mm and filled with in-fill
Polyurethane foam, the Door Shutters are with 0.80 mm thick Stainless steel of 304 grade hairline finish
Sheet formed to provide a 46 mm thick fully flush, double skin door shell with Lock Seam joints at stile
edges, fitted with in-fill of Honeycomb Kraft Paper and coated with polyester powders of Pure polyester/
epoxy polyester or polyurethane powder for powder coating of thickness 60 – 65 microns and are coated
with Zinc Phosphate Primer to receive any paint on site or finished with Thermosetting Polyurethane paint
of Aliphatic Grade providing high levels of scratch resistance and durability, the Shutter provided with 6 MM
clear float vision glass in Circular, Square or Rectangular shapes, Stainless Steel Ball Bearing Butt Hinges
3 mm thick fixed flush to the frame and shutter (Profile 102x76x3mm thick).Mortise Sash Lock with Lever
Handles, Mortise Dead Bolt, etc for 60 minutes Fire Rated door conforming to IS:3614 (Part2) 1992 etc.,
complete including conveyance of all materials, labour charges for fixing, overheads & contractors profit
complete for finished item of work in all floors.
7 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing
with fixed fan light of 500mm height at top door using aluminium sections of 101.60 mmm x 44.45mm ,
3.18 mm thick for frame and door shutter made of styles , top and middle rail of 47.62mm x 44.45mm ,
3.18 mm thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium
sections 25mm microns thick, 5 mm thick plain float glass fitted with suitable aluminium glazing clips and
rubber beading in fan light portion, double shutters fitted with 5mm thick frosted / ground glass in the
top half and MDF Board: interior-Both Side Laminated -12 mm thick in the bottom half fitted with
suitable aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor
spring of approved brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost
of cutting floors as required , embedding in floors
and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete
(Weight Capacity up to 130 Kgs) as approved by Engineer-in-Charge including supply and fixing ISI
marked powder coated aluminium fixtures of 3 Nos. of butt hinges (IS:205) of 150mm long(for each
shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208) 150mm
dia and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing the
door with required No. of screws etc., including overheads & contractors profit complete for finished item
of work. (The Aluminium section used shall be standard make confirming to IS 1948 – 1961) and as
approved by the Engineer) (2000mm x 2600mm)
(BLD-CSTN-13-31)
Quantity analysis Size : 2.00m x 2.60m 5.20
8 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing
with fixed
and fan lightplates
SS cover of 500mm
with height
brass atpivot
top door
and using
sigle aluminium
piece MS sections
Sheet of 101.60
outer boxmmm
with x slide
44.45mm
plate,
etc.complete( Weight Capacity up to 130 Kgs ) as approved by Engineer-in-Charge including supply and
(BLD-CSTN-13-31)
Quantity analysis Size : 1.80m x 2.60m 4.68
9 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing
with fixed fan light of 500mm height at top door using aluminium sections of 101.60 mmm x 44.45mm ,
3.18 mm thick for frame and door shutter made of styles , top and middle rail of 47.62mm x 44.45mm ,
3.18 mm thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium
sections 25mm microns thick, 5 mm thick plain float glass fitted with suitable aluminium glazing clips and
rubber beading in fan light portion, double shutters fitted with 5mm thick frosted / ground glass in the
top half and MDF Board: interior-Both Side Laminated -12 mm thick in the bottom half fitted with
suitable aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor
spring of approved brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost
of cutting floors as required , embedding in floors
and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate
etc.complete( Weight Capacity up to 130 Kgs ) as approved by Engineer-in-Charge including supply and
fixing ISI marked powder coated aluminium fixtures of 3 Nos. of butt hinges (IS:205) of 150mm long(for
each shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208)
150mm dia and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door ,
fixing the door with required No. of screws etc., including overheads & contractors profit complete for
finished item of work. (The Aluminium section used shall be standard make confirming to IS 1948 – 1961)
and as approved by the Engineer) (1500mm x 2600mm)
(BLD-CSTN-13-31)
Quantity analysis Size : 1.50m x 2.60m 3.90
of Aliphatic Grade providing high levels of scratch resistance and durability, the Shutter provided with 6 MM
clear float vision glass in Circular, Square or Rectangular shapes, Stainless Steel Ball Bearing Butt Hinges
3 mm thick fixed flush to the frame and shutter (Profile 102x76x3mm thick).Mortise Sash Lock with Lever
Handles, Mortise Dead Bolt, etc including cost and conveyance of all materials, labour charges for fixing,
overheads & contractors profit complete for finished item of work in all floors for industrial, commercial,
residential, cleanroom applications
1 Providing and fixing of factory made of High Density High Moisture Resistant Wood Fibre (HDHMR)
single shutter Duradoor made up of FRAME: Door frame manufactured with High Density High Moisture
Resistant Wood Fibre (HDHMR) of 36mm width x 100mm depth , laminated with 0.2mm thick PVC Foil
using hot press and PUR adhesive, fitted with Gasket for energy efficiency and noise protection,affixed to
the wall using high strength expandable PU Foam/ self-expandable wall fixing screws.Max dimensions in
MM of 280 (depth) x 2440 (height) SHUTTER: Factory made 41mm thick shutter sandwiched with High
Density High Moisture Resistant Wood Fibre (HDHMR) of 5.5mm thick skinson both sides and HDHMR of
30mm thickness as skeleton,core of high density Honey Comb and Laminated Veneer Lumber (LVL) for
holding the lock body and hardware, laminated with 0.2mm thick PVC Foil and edge-banded with 1mm
thick PVC edge-band using hot press and PUR adhesives. Max dimensions in MM of 1200 (width) x
41(thickness) x 2400 (height), ARCHITRAVE: Factory made Architrave of size 80mm x 12mm
fitted to pre-made grooves within the frame for added aesthetics. Four design variants available, made with
Density High Moisture Resistant Wood Fibre(HDHMR) of different thicknesses depending on the design
variant, laminated with 0.2mm thick PVC Foil using hot press and PUR adhesive, fitted to the wall using
strong quick acting adhesives. Hardware & accessories: Imported hardware including door handle – 1 No,
cylindrical magnetic lock -1 No., SS hinges – 3 Nos. including cost and conveyance of all materials,
hardware and accessories, transportation, labour charges for fixing, overheads & contractors profit
complete for finished item of work in all floors
(1200mm x 2100mm) & (1000mm x 2100mm) for Recreation Hall, Indoor games , Dining and
Kitchen
Rate as per SoR BMT-N.86 1.00 sqm 11249.00 1 sqm
Overheads & Contractors Profit @13.615% 0.13615 11249.00
Rate per 1 sqm
Say
1 Providing of Factory made prelaminated FPVC (Foamed Polyvinyl Chloride) Door frame of the size
105x40mm
high densitywith a wall
craft thickness
paper honey of 10mm
comb madesandwiched
board, out of extruded rigid FPVC
on both profileprelaminated
sides with mitre joined with
ABS 6sheet
Nos.
thickness of 1.5mm . PVC
Rate as per SoR BMT-N.67 edge banding of size 0.45mm on the vertical
1.00 Each 14189.00 sides. Hardware
1 Each made out of steel
3 Providing & Fixing of Scientific Doors with metal door frames and door shutters made of galvanize
steel (base steel as per IS 513 of 0.58 mm thick D quality, galvanized as per IS 277 with Zinc of 120
GSM)coated with Zinc Phosphate Primer to receive any paint on site or finished with Thermosetting
Polyurethane paint of Aliphatic Grade providing high levels of scratch resistance and durability/Epoxy
polyester powder for powder coating paint thickness 50-60 microns (Dry film thickness) outer frame section
of 100 x 58 mm x 1.2 mm thick, shutter section of 0.80 mm thick galvanized steel sheet pressed (roll
formed) for 46mm thick fully flush, double skin door shell seam joints at stile edges, in-fill of honeycomb
Kraft paper used to give the required rigidity and effective acoustic insulation with 6” Tower bolt – 1 No., 6”
D handles – 2 Nos., 10” Aldrops – 1 No., Butt Hinges – 3 Nos, Mortise Lock of approved quality – 1 No,
frames fixed to the concrete/masonry wall by means of self expanding screws including overheads and
contractor profit etc.,complete for finished item of work for Single leaf Door
3 Providing and fixing factory made uPVC white colour sliding glazed door comprising of uPVC multi-
chambered frame with in-built roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2 mm
thick galvanized mild steel section made from roll forming process of required length (shape & size
according to uPVC profile), appropriate dimension uPVC extruded glazing beads, uPVC extruded interlock
and uPVC extruded Inline sash adaptor (if required), EPDM gasket, wool pile, zinc alloy(white powder
coated) handle with key on one side of extreme panels along with zinc plated mild steel multi point locking
having transmission gear with keeps, zinc alloy (white powder coated) cresent lock (ifrequired), stainless
steel (SS 304 grade) body with adjustable double nylon rollers (weight bearing capacity to be 120 kg), G.I
fasteners 100 x 8 mm size for fixing frame to finished wall and necessary stainless steel screws etc. Profile
of frame & sash shall be mitred cut and fusion welded at all corners, including drilling of holes for fixing
hardware's and drainage of water etc. After fixing frame the gap between frame and adjacent finished wall
shall be filled with weather proof silicon sealent over backer rod of required size and of approved quality, all
complete as per approved drawing & direction of Engineer-in-Charge inclusive of cost of Single / double
glass panes, wire mesh and silicon sealent including overheads and contractor profit etc., complete for
finished item of work Note: For uPVC frame and sash extruded profiles minus 5% tolerancein dimension
i.e. in depth & width of profile shall be acceptable. Variationin profile dimension in higher side shall be
accepted but no extra payment on this account shall be made.
Two track two panels sliding door made of (big series) frame 67 x 50 mm & sash 46 x 82 mm both having
wall thickness of 2.3 ± 0.2 mm and single glazing bead / double glazing bead of appropriate dimension.
(Area of door above 2.00 sqm upto 5.00 sqm)
Rate as per SoR BMT-N.85.A 1.00 sqm 5404.00 1 sqm
3 Providing & Fixing of Openable Windows with Fly-mesh made of pre-painted steel (Base Steel as per
a IS 513 of
Centre 0.58both
fixed mm side
thickopenable
galvanizedshutter
as perwindow
IS 277 with zinc of x1800mm
: 1800mm 150 GSM) primer coated with
3.24epoxy primer
Window portion 2.34 sqm 5797.00 1 sqm
Fan light portion 0.90 sqm 4295.00 1 sqm
Rate per 3.24 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
b Centre fixed both side openable shutter window : 1500mm x1800mm 2.70
Window portion 1.95 sqm 6625.00 1 sqm
Fan light portion 0.75 sqm 4295.00 1 sqm
Rate per 2.70 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
c Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.16
Window portion 1.56 sqm 7288.00 1 sqm
Fan light portion 0.60 sqm 4295.00 1 sqm
Rate per 2.16 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62
Window portion 1.17 sqm 7288.00 1 sqm
Fan light portion 0.45 sqm 4295.00 1 sqm
Rate per 1.62 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
A) WINDOWS
a Centre fixed both side openable shutter window 1800mm x 1800mm with fixed 3.24
fan lightportion
Window of 500mm at top : 2.34 sqm 5411.00 1 sqm
Fan light portion 0.90 sqm 4295.00 1 sqm
Rate per 3.24 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
b Centre fixed both side openable shutter window 1500x1800 with fixed fan light 2.70
of 500mm at
Window portion top : 1.95 sqm 5411.00 1 sqm
Fan light portion 0.75 sqm 4295.00 1 sqm
Rate per 2.70 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
c Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.16
Window portion 1.56 sqm 6074.00 1 sqm
Fan light portion 0.60 sqm 4295.00 1 sqm
Rate per 2.16 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62
Window portion 1.17 sqm 6074.00 1 sqm
Fan light portion 0.45 sqm 4295.00 1 sqm
Rate per 1.62 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 sqm 474.00 1 sqm
add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
B) VENTILATORS :
a Top Hung of any size 1.00 sqm 6295.00 1 sqm
8 Providing and fixing factory made uPVC white colour sliding glazed window comprising of uPVC
multi-chambered frame with in-built roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2
mm thick galvanized mild steel section made from roll forming process of required length (shape & size
according to uPVC profile), appropriate dimension of uPVC extruded glazing beads and uPVC extruded
interlocks, EPDM gasket, wool pile, zinc alloy (white powder coated) touch locks with hook, zinc alloy body
with single nylon rollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8 mm size for fixing
frame to finished wall and necessary stainless steel screws etc. Profile of frame & sash shall be mitred cut
and fusion
welded at all corners, including drilling of holes for fixing hardware's and drainage of water etc. After fixing
frame the gap between frame and adjacent finished wall shall be filled with weather proof silicon sealent
over backer rod of required size and of approved quality, all complete as per approved drawing & direction
of Engineer-in-Charge inclusive of cost of Single / double glass panes of 4mm thick pin headed glass, wire
mesh and silicon sealent . Note: For uPVC frame and sash extruded profiles minus 5% tolerancein
dimension i.e. in depth & width of profile shall be acceptable.Variation in profile dimension in higher side
shall be accepted. But no extra payment on this account shall be made.
a) Two track two panels sliding window made of frame 67 x 50 mm & sash 46 x 62 mm both having wall
thickness of 2.3 ± 0.2 mm and single glazing bead / double glazing bead of appropriate dimension .
Rate as per SoR 1.00 sqm 6038.00 1.00 sqm
Deduct cost of 5mm thick plain float glass 1.00 sqm 474.00 1 sqm
Add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
b) Three track three panels sliding window with fly proof SS wire mesh (Two nos. glazed & one no.
wire mesh panels) made of frame 92 x 44 mm & sash 32 x 60 mmboth having wall thickness of 1.9 ± 0.2
mm and single glazing bead of appropriate dimension
9 Providing and fixing factory made uPVC white colour casement/casement cum fixed glazed
windows comprising
Profile of frame of shall
& sash uPVCbemulti-chambered frame,sash
mitred cutand fusion weldedand mullion
at all (where
corners, ever(ifrequired)
mullion required) extruded
shall be
also fusionwelded
Casement windowincluding drilling of
double panels holes
with for fixing
top fixed with hardware's
S.S.friction and drainage
hinges (350 xofwater
19 x 1.9etc.
mm)After
madefixing
of
(small
Rate asseries) frame 47 x 50mm, sash 47 x 68 mm & 1.00
per SoR mullion
sqm47 x 686283.00
mm all having
1.00wall
sqmthickness of 1.9 ±
10 Providing and fixing factory made uPVC white colour casement/casement cum fixed glazed
windows comprising of uPVC multi-chambered frame,sash and mullion (where ever required) extruded
Profile of frame & sash shall be mitred cutand fusion welded at all corners, mullion (if required) shall be
also fusionwelded
Casement including
cum fixed drilling ofhaving
panel window holes both
for fixing hardware's
end single and drainage
casement ofwaterfixed
panel, middle etc. panels
After fixing
at top completely
Rate as per SoR fixed ventilator with S.S friction hinges (350
1.00 sqm x 19 x 1.9)
6517.00made of (big
1.00 sqm series) frame 67 x
9 Providing and fixing factory made uPVC white colour fixed glazed windows / Ventilators comprising
of uPVC multi chambered frame and mullion (where ever required) extruded profiles duly reinforced with
1.60± 0.2 mm thick galvanized mild steel section made from roll forming process of required length (shape
& size according to uPVC profile), uPVC extruded glazing beads of appropriate dimension, EPDM
gasket,G.I fasteners 100 x 8 mm size for fixing frame to finished wall, plastic packers, plastic caps and
necessary stainless steel screws etc. Profileof frame shall be mitred cut and fusion welded at all corners,
mullion (if required) shall be also fusion welded including drilling of holes for fixing hardware and drainage
of water etc.
After fixing frame the gap between frame and adjacent finished wall shall be filled with weather proof silicon
sealant over backer rod of required size and of approved quality, all complete as per approved drawing &
direction of Engineer-in-Charge inclusive of cost of Single / double glass panes and silicon sealant. Note:
For uPVC frame, sash and mullion extruded profiles minus 5%tolerance in dimension i.e. in depth & width
of profile shall be acceptable.Variation in profile dimension in higher side shall be accepted. But, no extra
payment on this account shall be made.
Fixed windows / Ventilators made of (small series) frame 47 x 50mm & mullion 47 x 68 mm both having
wall thickness of 1.9 ±0.2 mm and single glazing bead of appropriate dimension.
Rate as per SoR 1.00 sqm 5830.00 1.00 sqm
10 Supplying and fixing of 7.5mm thick Aluminium Grill (as approved by the department) 3.58 Kg/Sqm
including cost
Rate as per SoRand conveyance of all materials, accessories,
1.00 sqmlabour charges
941.00 for1.00
transportation,
sqm erection at
11 Supplying and fixing of MS Grill to windows / in open court yards using 25mm x 6mm MS flat alround
and 10mm MS square bars horizontally at 125mm centre to centre and vertically at 300mm centre to
centre including fixing with 4 Nos of MS Z holdfasts (2 on each side) duly making cutting brick masonry,
fixing and making to original surface neatly including cost and conveyance of all materials, cutting,
bending, welding, operational charges, labour charges, overheads and contractor profit etc., complete for
finished item of work.
10 Supplying and fixing of MS doors, grill to windows, ventilators / in open court yards using MS
angles, flat, square bars including cost and conveyance of all materials, cutting, bending, welding, all
operational charges, labour charges, overheads and contractor profit etc., complete for finished item of
work.
Cost of steel 1.05 Kgs 41500.00 1000 Kgs
Labour charges for fabrication of steel 1.00 Kgs 27.00 1 Kg
Labour charges for fixing 1.00 5.00
Add for MA @ 20% 0.20 15.80
11 Providing and fixing Pre painted Steel sliding Window /Door fabricated from roll formed sections made
of Galvanized
The steeltocolour
Window/Door coated with
be panelled /powder
4mmcoated (Base
thick pin Steelglass.
headed as perThe
IS 513 „D‟ quality
gaskets are to galvanized
be made ofasEthyl
per
Propylene
Rate as perDiamine
SoR Manomer [EPDM]. Corner Brackets forsqm
1.00 internal and external 1.00
6166.00 frame to be made of glass
sqm
Deduct cost of 5mm thick plain float glass 1.00 sqm 474.00 1 sqm
Add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
12 Providing and fixing 3 Track 3 Shutter Pre painted Steel sliding Window fabricated from roll formed
sections made of Galvanized steel colour coated /powder coated (Base Steel as per IS 513 „D‟ quality
galvanized as per IS 277 with Zinc of 120 Gms./ Sq.mtr) with total coated thickness of 0.58mm. Primer
Coat with epoxy primer of 5-7 microns thick, finished paint with a polyester paint of 12-16 microns thick and
back coated with Alkyd backer of 5-7 microns or powder coated with pure polyester powder up to 50-60
microns thick. The External Section for Three Track Three Sliding Shutter should be of 44 x 107mm with a
provision for bottom track insert profile of 10x9 mm made of aluminium. Section for Window glass shutter
should be of 35x49mm , Section for Window Euro groove should be of 25x24mm made of plastic to
accommodate standard accessories, and section for window lap strip should be of 21x4mm made of
plastic. Section for Mesh Shutter should be of 35x49mm. The Window to be panelled with 4mm thick pin
headed glass. The gaskets are to be made of Ethyl Propylene Diamine Manomer [EPDM]. Corner Brackets
for internal and external frame to be made of glass filled nylon. Touch lock to be provided for Window
Shutter. Sections are to be cut to length,
joined and assembled by means of corner brackets. The above frame to be fixed to Brick/Concrete
masonry by using Nylon self expanding caps and driving MS electroplated 80mm screws into the caps
through frames. The Grill for safety for windows to be made of 10mm thick square rod bars with 152mm
pitch for complete item of work including cost and conveyance of all materials, accessories, labour charges
for transportation, erection at site complete for finished item of work. (The rate includes overheads and
contractors profit and in all floors)
Rate as per SoR 1.00 sqm 6818.00 1.00 sqm
Deduct cost of 5mm thick plain float glass 1.00 sqm 474.00 1 sqm
Add cost of 4mm thick pin headed glass 1.00 sqm 280.00 1 sqm
13 Supply and fixing powder coated alimunium fully glazed 2 shutter windows with fixed panel in
between openable shutters as per approved drawings using anodized aluminium sections of 38.50mm x
33mm , 3mm thick for outer frame, 59mm(3mm) x 33mm(2.5mm) x 30mm(3mm) for mullions and 38.5mm
x 33mm , 3mm thick for shutter frame , powder coating of alluminium sections 25mm microns thick and
fixing 5 mm thick plain glass fitted with suitable aluminium galzing clips and rubber beading including
supplying and fixing powder coated aluminium adjustable frictional stay hinges (2 Nos. per shutter), handle
with lock (1 No. per shutter) including cost and conveyance to site of powder coated aluminium sections,
glass, rubber beading, fixtures etc., including labour charges for manufacturing window, fixing in position
using wooden blocks and sheet metal screws, etc., complete for finished item of work in all floors. (The
aluminium sections used shall be standard make confirming to IS 1948-1961 and as approved by the
Engineer and fixtures shall be of ISI marked) (1800mm x 1300mm).
14 Supply and fixing powder coated alimunium fully glazed top hung ventilators fixed with 5mm thick
plain glass
Quantity using suitable alluminium glazingSize
analysis clips: and rubber
0.90mxbeading
0.50m as per approved drawings using
0.45
1) Outer frame ( 38.50mm x 33mm, 3mm
thick ) 2 ( 0.90 + 0.50 )
= 2.80 RM @ 0.775 Kgs / RM 2.17 Kgs.
2) Shutters Z Section (38.50mm x 33mm x,
3mm thick 2x2(0.45+0.50)
= 3.80 RM @ 0.663 Kgs / RM 2.52 Kgs.
3) Glazing clips 2x2(0.45+0.50)
= 3.80 RM @ 0.101 Kgs /RM. 0.38 Kgs.
5.07 Kgs.
Cost analysis
Cost of powder coated Al. sections 5.07 Kgs. 306.00 1 Kgs.
Cost of 5mm thick plain glass 0.45 sqm 474.00 1 sqm
Cost of rubber beading 3.80 RM 2.00 1 RM
Labour charges 0.45 sqm 753.06 1 sqm
Add for Screws, Nails, Nuts, Bolts LS
15 Supplying and fixing powder coated aluminium three track sliding window as per the approved
drawing
Quantitywith all required accessories such as
analysis stoppers,
Size : bolts, weather
1.20m x 1.20m stripping etc with
1.44top and sides
Window frame
bottom : 1.20m 1.26 Kgs/RM 1.512
sides : (10015) 2 x 1.20m 1.099 Kgs/RM 2.638
top : (10015) 1.20m 1.099 Kgs/RM 1.319
Window shutters
bottom : (13005) 2 x 0.60m 0.546 Kgs/RM 0.66
3 x1.20+
plain sides & top : (13005) 2x 0.60) 0.546 Kgs/RM 2.621
sides inter locking : (12004) 3 x 1.20m 0.615 Kgs/RM 2.214
Glazing clips 2x2x(0.60+1.20)
= 7.20 RM @ 0.101 Kgs /RM 7.20 0.727
11.686
Cost analysis
A.Material :
Cost of powder coated Al. sections 11.686 Kgs. 306.00 1 Kgs.
Cost of 4mm thick pin headed glass 1.44 sqm. 280.00 1 sqm.
Cost of rubber beading 3.60 RM 2.00 1 RM
Cost of aluminium handles 100mm long 3 Nos 68.00 1 Each
Cost of SS mesh(BMT-F.19) 0.78 sqm. 446.00 1 sqm.
B.Labour charges 1.44 sqm 724.60 1 sqm
Add for screws, nails, nuts, bolts, nylon
rollers etc., LS
Rate per 1.44 Sqm:
Overheads&Contractors Profit @13.615% 0.13615 5590.95
16 Supplying and fixing powder coated aluminium three track sliding window with fixed fan light of
500mm
Quantityatanalysis
top as per the approved drawing with
Sizeall: required accessories
1.50m x 1.70m such as stoppers,
2.55bolts, weather
Window frame
bottom : 1.50m 1.26 Kgs/RM 1.890
sides : (10015) 2 x 1.20m 1.099 Kgs/RM 2.638
top : (10015) 1.50m 1.099 Kgs/RM 1.649
fan light sides & top (4687) 2 x 0.50+1.5 0.942 Kgs/RM 2.748
Window shutters
bottom : (13005) 3 x 0.50m 0.546 Kgs/RM 0.82
3 x1.20+
plain sides & top : (13005) 1.50) 0.546 Kgs/RM 2.785
sides inter locking : (12004) 3 x 1.20m 0.615 Kgs/RM 2.214
Glazing clips 3x2x(0.50+0.50)+3x2x(0.50+1.20)
= 16.20 RM @ 0.101 Kgs /RM 16.20 1.636
16.379
Cost analysis
A.Material :
Cost of powder coated Al. sections 16.379 Kgs. 306.00 1 Kgs.
Cost of 4mm thick pin headed glass 2.55 sqm. 280.00 1 sqm.
Cost of rubber beading 8.10 RM 2.00 1 RM
Cost of aluminium handles 100mm long 3 Nos 68.00 1 Each
Cost of SS mesh(BMT-F.19) 0.72 sqm. 446.00 1 sqm.
B.Labour charges 2.55 sqm 724.60 1 sqm
Add for screws, nails, nuts, bolts, nylon
rollers etc., LS
Rate per 2.55 Sqm:
Overheads&Contractors Profit @13.615% 0.13615 8124.00
17 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approved
drawings with
alluminium all required
glazing clips andaccessories such as
rubber beading stoppers,bolts,weather
including stripping
cost and conveyance etc. offorpowder
to site all sizes and
coated
aluminium sections,& S.No.10
(BLD-CSTN-13-30 glass, rubber
of SoRbeading, fixtures etc., including labour charges for manufacturing
, page 395)
Size 1.80m x 1.80m 3.24
Quantity analysis
Window frame
bottom : (8932) 1.80m 0.909 Kgs/RM 1.636 Kgs.
sides : (8931) 2 x 1.30m 0.784 Kgs/RM 2.038 Kgs.
top : (8992) 1.80m 1.005 Kgs/RM 1.809 Kgs.
fan light sides&top(4687) 1.80+2x 0.5 0.942 Kgs/RM 2.638 Kgs.
Window shutters
bottom : (8603) 3 x 0.60m 0.641 Kgs/RM 1.15 Kgs.
plain sides & top : (8604) 3 (1.30+0.600.522 Kgs/RM 2.975 Kgs.
sides inter locking : (8602) 3 x 1.30m 0.663 Kgs/RM 2.586 Kgs.
Glazing clips 3x2(0.60+0.50)+3x2x(0.60+1.30)
= 18.00 RM @ 0.101 Kgs /RM 1.818 Kgs.
16.654 Kgs.
Cost analysis
A.Material :
Cost of powder coated Al. sections 16.654 Kgs. 306.00 1 Kgs.
Cost of 5mm thick plain glass 3.24 sqm 474.00 1 sqm
Cost of rubber beading 9.00 RM 2.00 1 RM
B.Labour charges 3.24 sqm 724.60 1 sqm
Add for Screws, Nails, Nuts, Bolts etc., LS
Rate per 3.24 sqm
18 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approved
drawings
rubber with all
beading required
, fixtures accessories
etc., such as
including labour stoppers,bolts,weather
charges for manufacturing stripping etc. for
window, fixing all sizesusing
in position and
wooden
Quantityblocks and sheet metal screws, overheads
analysis Size : & contractors
1.20m x profit
1.80metc., complete for finished item of
2.16
Quantity analysis
Window frame
bottom : (8932) 1.20m 0.909 Kgs/RM 1.091 Kgs.
sides : (8931) 2 x 1.30m 0.784 Kgs/RM 2.038 Kgs.
top : (8992) 1.20m 1.005 Kgs/RM 1.206 Kgs.
fan light sides&top(4687) 1.20+2x 0.5 0.942 Kgs/RM 2.072 Kgs.
Window shutters
bottom : (8603) 2 x 0.60m 0.641 Kgs/RM 0.77 Kgs.
plain sides & top : (8604) 2 (1.30+0.600.522 Kgs/RM 1.984 Kgs.
sides inter locking : (8602) 2 x 1.30m 0.663 Kgs/RM 1.724 Kgs.
Glazing clips 2x2(0.60+0.50)+2x2x(0.60+1.30)
= 12.00 RM @ 0.101 Kgs /RM 1.212 Kgs.
12.096 Kgs.
Cost analysis
A.Material :
Cost of powder coated Al. sections 12.10 Kgs. 306.00 1 Kgs.
Cost of 5mm thick plain glass 2.16 sqm 474.00 1 sqm
Cost of rubber beading 6.00 RM 2.00 1 RM
B.Labour charges 2.16 sqm 724.60 1 sqm
Add for Screws, Nails, Nuts, Bolts etc., LS
Rate per 2.16 sqm
19 Supply and fixing of cement bonded pre-laminated particle boards aluminum glazed partitions using
10mm cement bonded pre-laminated particle boards and 5.00 mm thick plain glass to full height. Using
with LAM to a height of 0.91 meter at bottom panel and remaining height with glass and aluminum sections
anodized to 12 to 15 microns and of sections of size 37mm x 62mm and 1.5mm thickness with one meter
centre to centre duly fixed with clip beading on both sides including fixing the frame to pillars by M.S. flats,
bolts and nuts including cost and conveyance of all materials etc., complete as directed during execution
and overheads & contractors profit etc., complete for finished item of work
12 Supply & Fixing of Hot dipped Galvanised Iron Chain link mesh 8 gauge - (4.0 mm) as per IS: 2721-1979:
2"x2"
Unit = (50 mm x 50 mm) - 8 Gauge including cost and conveynace of materials, labour charges cutting &
1SQM
Cost of 2"x2" Chain link mesh (BMT-F.20)
1.000 Sqm 404.0 1.00 Sqm
Labour charges 1.000 53.8
13 Supply & Fabication and fixing of Structural steel for fencing post with 65 x 65 x6 mm size equal
angles and welded with 8mm rods for anchoring concrete at bottom of the fencing post, drilling 5 Nos
Unit: 2 RM
65 x 65 x 6mm size angle
(2 RM x 5.80Kg/RM) 2.00 5.80 11.6 Kgs
Rate per 2 RM
Rate per 1 RM
Say
14 Supply and fixing of doors as per approved drawings with 1st Grade Burma teak wood frame of section
250mmand
Supply x 150 mmofof84Nos.
fixing verticals of 2.85m
MS hold height
fasts of with mm
size (450 one xhorizontal
100 mm xat8mm)
the top
flatof
of 6.10m of length
2 nos welded with a
together
to fix with the help of anchor fasteners of 4 nos (Two on either side) including cost of ISI marked Brass
(BLD-CSTN-13-16)
(this item is already approved in medical
college @ TPT) Size : 6.10m x 2.85m 17.39
Quantity analysis
Outer frame - Vertical 4 x 2.85
=4 x 2.85 x 0.25 x 0.15 0.4275
Outer frame - Horizontal 1 x 6.1
= 6.10 x 0.25 x 0.15 0.22875
1 X 2 X 1.55
= 2 x 1.55 x 0.25 x 0.15 0.11625
0.7725
All round beading 12mm x 12mm =2 x 0.012x0.012x13.40
0.00386 0.00386
=2 x 0.012x0.012x14.40
0.00415 0.00415
0.00801
0.21066
50 mm thick teak wood shutter 0.21066
Cost analysis
Cost of 1st grade burma teak wood upto 2m 0.11625 cum 168485.00 1 cum
Cost of 1st grade burma teak wood upto 2m -
3m 0.4275 cum 173298.00 1 cum
Cost of 1st grade burma teak wood above
3m 0.22875 182272.00 1 cum
Cost of 50mm thick 1st grade burma teak
wood flanks 0.211 Cum 197369.00 1 cum
Cost 12mm thick plain glass 4.560 Sqm 996.00 1 Sqm
Cost 12mm thick plain glass 5.760 Sqm 996.00 1 Sqm
Cost of MS Flat for Hold Fast including
anchor bolts holes 110.00 Kgs 50.00 1 Kg
Cost of Anchor bolts 16.00 Nos. 30.00 1 No
Cost of Brass atique model tower bolt of
450mm long 6 Nos. 1400.00 1 Each
Cost of Brass atique model butt hinges of
250mm long 16 Nos. 1500.00 1 Each
Cost of Brass atique Ornamental Aldrop of
450mm long 1 No. 2982.00 1 Each
Cost of Brass atique Ornamental handles
450mm long 4 Nos. 2800.00 1 Each
Cost of Brass atique Ornamental handles
300mm long 4 Nos. 2000.00 1 Each
Cost of Brass atique model door stoppers 4 Nos. 700.00 1 Each
19 Supply and fixing of front Elevation as per approved drawings with 1st Grade Bhalasha teak wood frame of
section
Supply and150mm x 150
fixing of 8mm
Nos.ofMS
4 verticals of 2.85m
hold fasts of size height
(450 mmandx three horizontals
100 mm of 6.10m
x 8mm) flat of length
of 2 nos weldedeach with
together
to fix with the help of anchor fasteners of 4 nos (Two on either side), including cost and conveyance of teak
(BLD-CSTN-13-16)
(this item is already approved in medical
college @ TPT) Size : 6.10m x 2.85m 17.39
Quantity analysis
Outer frame - Vertical 4 x 2.85
=4 x 2.85 x 0.15 x 0.15 0.2565
Outer frame - Horizontal 3 x 6.10
=3 x 6.10 x 0.15 x 0.15 0.41175
0.66825
All round beading 20mm x 20mm 55.00
=56 56
Cost analysis
Cost of 1st grade burma teak wood above
3m 0.41175 cum 182272.00 1 cum
Cost of 1st grade burma teak wood upto 2m -
3m 0.2565 cum 173298.00 1 cum
Cost of TW beading 56.00 RM 26.00 1 rm
Cost of MS Flat for Hold Fast including
anchor bolts holes 110.00 Kgs 50.00 1 Kg
Cost of Anchor bolts 16.00 Nos. 30.00 1 No
20 Supply and fixing of doors as per approved drawings with 1st Grade Bhalasha teak wood frame of section
250mm
Supply andx 150 mmofof84Nos.
fixing verticals of 2.85m
MS hold height
fasts of with mm
size (450 one xhorizontal
100 mm xat8mm)
the top
flatof
of 6.10m of length
2 nos welded with a
together
to fix with the
(BLD-CSTN-13-16) help of anchor fasteners of 4 nos (Two on either side) including cost of ISI marked Brass
(this item is already approved in medical
college @ TPT) Size : 6.40m x 2.85m 18.24
Quantity analysis
Outer frame - Vertical 4 x 2.85
=4 x 2.85 x 0.25 x 0.15 0.4275
0.20989
50 mm thick teak wood shutter 0.20989
Cost analysis
Cost of 1st grade bhalasha teak wood upto
2m 0.1575 cum 229840.00 1 cum
Cost of 1st grade bhalasha teak wood upto
2m -3m 0.4275 cum 229840.00 1 cum
Cost of 1st grade bhalasha teak wood above
3m 0.2475 254520.00 1 cum
Cost of 50mm thick 1st grade bhlasha teak
wood flanks 0.210 Cum 247030.00 1 cum
Cost 12mm thick plain glass 7.200 Sqm 1177.00 1 Sqm
Cost 12mm thick plain glass 4.320 Sqm 1177.00 1 Sqm
Cost of MS Flat for Hold Fast including
anchor bolts holes 110.00 Kgs 50.00 1 Kg
Cost of Anchor bolts 16.00 Nos. 30.00 1 No
Cost of Brass atique model tower bolt of
450mm long 6 Nos. 1400.00 1 Each
Cost of Brass atique model butt hinges of
250mm long 16 Nos. 1500.00 1 Each
Cost of Brass atique Ornamental Aldrop of
450mm long 1 No. 3200.00 1 Each
Cost of Brass atique Ornamental handles
450mm long 4 Nos. 2800.00 1 Each
Cost of Brass atique Ornamental handles
300mm long 4 Nos. 2000.00 1 Each
Cost of Brass atique model door stoppers 4 Nos. 700.00 1 Each
21 Supply & fixing of synthetic Venetian blinds Vertical blinds 100 mm wide with all accessories including cost
and conveyance of all materials, cost of all consumables, labour charges , overheads & contractors profit
etc., complete for finished item of work in all floors.
2)
57.42
91.08
57.42
57.42
124.74
51.48
87.91
80.89
75.34
683.69
6.84
690.53
SoR 2011-12 )
55.68
132.94
55.68
55.68
121.38
49.92
94.26
78.64
73.25
717.42
7.17
724.60
94 of SoR 2011-12 )
251.72
199.64
24.94
33.64
60.90
37.44
121.66
35.39
43.99
809.32
8.09
817.41
f SoR 2011-12 )
58.00
138.00
58.00
58.00
126.00
52.00
98.00
81.60
76.00
745.60
7.46
753.06
sqm
21928.20
21138.65
8415.00
3764.88
1164.80
4000.00
2908.00
2982.00
951.00
336.00
192.00
18.00
10669.02
4246.56
849.31
2831.40
566.28
3609.90
721.98
2.34
91295.33
11704.53
1593.57
13298.10
13298
Sqm
Kgs
216.72
136.08
25.20
15.93
11.78
405.71
1743.30
84.70
121.80
225.40
69.44
5.01
506.35
est teak wood frame of
les of section 120mm x
utter including cost and
g 6 Nos MS Z hold fasts
Nos butt hinges(IS:205)
204) of 200 mm long , 2
r stop bushes including
labour charges for fixing
ontractors profit complete
r shall be embedded in
sqm
8223.08
11354.06
4183.20
322.40
4000.00
2908.00
2982.00
951.00
336.00
192.00
18.00
1941.14
388.23
1201.20
240.24
2.34
39242.88
9343.54
1272.12
10615.67
10616
sqm
8223.08
10655.16
3764.88
312.00
4000.00
2908.00
2982.00
951.00
336.00
192.00
18.00
1870.03
374.01
1081.08
216.22
4.00
37887.45
10023.13
1364.65
11387.78
11388
12830.61
15596.50
312.00
4000.00
2908.00
2982.00
951.00
336.00
192.00
18.00
2813.16
562.63
1.16
43503.06
11508.75
1566.92
13075.66
13076
e of section 100mm x 65
sssupply
using and
12mm x 12mm
fixing 6 nos
ass fixtures of 6 Nos butt
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
4428.71
3586.46
280.00
156.00
5437.42
192.00
634.00
231.00
1944.00
1087.00
598.00
336.00
18.00
130.31
788.18
157.64
1491.79
298.36
286.00
57.20
2.81
22140.87
3014.48
25155.35
4837.57
4838
e of section 100mm x 65
ss using 12mm x 12mm
h door shutter of 35mm
bands and face veneers,
y made conforming to IS
fixing 1mm thick mat
cum
cum
cum
sqm
RM
sqm
Kgs
4428.71
3586.46
280.00
156.00
5437.42
2882.30
100.00
192.00
634.00
231.00
1944.00
1087.00
598.00
336.00
18.00
130.31
788.18
157.64
1491.79
298.36
286.00
57.20
2.81
25123.17
3420.52
28543.69
5489.17
5489
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
1897.35
252.00
145.60
4293.52
192.00
206.00
720.00
308.00
206.00
106.00
18.00
117.28
755.75
151.15
1334.76
266.95
257.40
51.48
1.51
13964.81
1901.31
15866.11
3390.20
3390
frame of section 100mm
ded glass using 12mm x
ed flush door shutter of
g cross bands and face
etic resin factory made
ping on all sides, fixing
utter both sides
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
1897.35
252.00
145.60
4293.52
2578.90
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
117.28
755.75
151.15
1334.76
266.95
257.40
51.48
2.47
16644.67
2266.17
18910.84
4040.78
4041
frame of section 100mm
eaded glass using 12mm
ked flush door shutter of
g cross bands and face
etic resin factory made
ping on all sides, fixing
utter both sides
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
1619.69
252.00
218.40
3535.84
2123.80
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
97.73
707.09
141.42
1099.21
219.84
257.40
51.48
3.73
14867.70
2024.24
16891.94
4331.27
4331
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
1342.03
201.60
187.20
2778.16
192.00
206.00
720.00
308.00
206.00
106.00
18.00
78.19
658.44
131.69
863.67
172.73
205.92
41.18
4.75
11105.62
1512.03
12617.65
4044.12
4044
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
1342.03
201.60
187.20
2778.16
1668.70
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
78.19
658.44
131.69
863.67
172.73
205.92
41.18
3.74
12873.31
1752.70
14626.01
4687.82
4688
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
925.54
168.00
83.20
2273.04
192.00
103.00
360.00
308.00
206.00
53.00
9.00
65.16
585.46
117.09
706.64
141.33
171.60
34.32
4.22
9190.65
1251.31
10441.96
4016.14
4016
ed Aluminium fixtures of
No. tower bolt (IS:204) of
pper and 1 No. Rubber /
of screws, bolt and nuts
rame, fixing glass in fan
em of work as per APSS
of not less than 10 mm)
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
925.54
168.00
83.20
2273.04
1365.30
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
65.16
585.46
117.09
706.64
141.33
171.60
34.32
4.01
10655.74
1450.78
12106.52
4656.35
4656
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
832.98
151.20
78.00
2020.48
192.00
103.00
360.00
308.00
206.00
53.00
9.00
58.64
569.24
113.85
628.12
125.62
154.44
30.89
4.47
8683.00
1182.19
9865.19
4215.89
4216
cum
cum
cum
sqm
RM
sqm
Kgs
2684.07
832.98
151.20
78.00
2020.48
1213.60
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
58.64
569.24
113.85
628.12
125.62
154.44
30.89
4.47
9996.60
1361.04
11357.64
4853.69
4854
on 100mm x 65 mm and
d solidcost
uding block
of board type
ISI marked
81) 300mm long, 2 Nos.
Sqm
cum
cum
cum
sqm
2169.88
925.54
4798.64
192.00
206.00
720.00
308.00
206.00
106.00
18.00
504.37
100.87
1491.79
298.36
3.44
12048.88
2868.78
390.58
3259.37
3259
on 100mm x 65 mm and
d solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
, flush shutter, laminate
Sqm
cum
cum
cum
sqm
2169.88
925.54
4798.64
2882.30
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
504.37
100.87
1491.79
298.36
3.44
15031.18
3578.85
487.26
4066.11
4066
on 100mm x 65 mm and
d solidcost
uding block
of board type
ISI marked
81) 300mm long, 2 Nos.
sqm
cum
cum
cum
sqm
2169.88
832.98
4293.52
192.00
206.00
720.00
308.00
206.00
106.00
18.00
488.15
97.63
1334.76
266.95
1.96
11241.83
2974.03
404.91
3378.94
3379
on 100mm x 65 mm and
d solidcost
uding block
of board type
ISI marked
81) 300mm long, 2 Nos.
sqm
cum
cum
cum
sqm
2169.88
832.98
4293.52
2578.90
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
488.15
97.63
1334.76
266.95
1.96
13920.73
3682.73
501.40
4184.14
4184
on 100mm x 65 mm and
d solidcost
uding block
of board type
ISI marked
81) 300mm long, 2 Nos.
sqm
cum
cum
cum
sqm
2169.88
694.15
3535.84
192.00
206.00
720.00
308.00
206.00
106.00
18.00
463.83
92.77
1099.21
219.84
4.75
10036.26
3186.12
433.79
3619.91
3620
on 100mm x 65 mm and
d solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
, flush shutter, laminate
sqm
cum
cum
cum
sqm
2169.88
694.15
3535.84
2123.80
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
463.83
92.77
1099.21
219.84
1.53
12256.84
3891.06
529.77
4420.83
4421
on 100mm x 65 mm and
d solidcost
uding block
of board type
ISI marked
81) 300mm long, 2 Nos.
sqm
cum
cum
cum
sqm
2169.88
555.32
2778.16
192.00
206.00
720.00
308.00
206.00
106.00
18.00
439.50
87.90
863.67
172.73
2.54
8825.70
3502.26
476.83
3979.09
3979
on 100mm x 65 mm and
d solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
, flush shutter, laminate
uding cost of ISI marked
81) 300mm long, 2 Nos.
es (IS:208), 2 Nos. door
res to door with required
osition, fixing the shutter
em of work as per APSS
of not less than 10 mm)
sqm
cum
cum
cum
sqm
2169.88
555.32
2778.16
1668.70
100.00
192.00
206.00
720.00
308.00
206.00
106.00
18.00
439.50
87.90
863.67
172.73
2.98
10594.84
4204.30
572.42
4776.72
4777
on 100mm x 65 mm and
ofsolid block board
ISI marked type
Aluminium
m long, 1 No. tower bolt
sqm
cum
cum
cum
sqm
2169.88
462.77
2273.04
192.00
103.00
360.00
308.00
206.00
53.00
9.00
423.28
84.66
706.64
141.33
3.60
7496.19
1020.61
8516.79
4055.62
4056
on 100mm x 65 mm and
solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
flush shutter, laminated
sqm
cum
cum
cum
sqm
2169.88
462.77
2273.04
1365.30
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
423.28
84.66
706.64
141.33
5.62
8963.51
1220.38
10183.89
4849.47
4849
on 100mm x 65 mm and
ofsolid block board
ISI marked type
Aluminium
m long, 1 No. tower bolt
sqm
cum
cum
cum
sqm
2169.88
486.26
2399.94
1441.52
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
427.40
85.48
746.08
149.22
3.60
9240.38
1258.08
10498.45
4761.20
4761
on 100mm x 65 mm and
solid block board type
of phenol formaldehyde
mmercial ply with internal
flush shutter including
sqm
cum
cum
cum
sqm
2169.88
416.49
2020.48
192.00
103.00
360.00
308.00
206.00
53.00
9.00
415.17
83.03
628.12
125.62
0.33
7090.13
965.32
8055.45
4262.14
4262
on 100mm x 65 mm and
solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
, flush shutter, laminate
sqm
cum
cum
cum
sqm
2169.88
416.49
2020.48
1213.60
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
415.17
83.03
628.12
125.62
4.43
8407.83
1144.73
9552.56
5054.26
5054
on 100mm x 65 mm and
solid block board type
of phenol formaldehyde
mmercial ply with internal
and height of the flush
, flush shutter, laminate
sqm
cum
cum
cum
sqm
2169.88
370.21
1767.92
1061.90
100.00
192.00
103.00
360.00
308.00
206.00
53.00
9.00
407.07
81.41
549.61
109.92
3.25
7852.17
1069.07
8921.24
5310.26
5310
cum
cum
cum
sqm
2169.88
370.21
1767.92
192.00
84.00
360.00
284.00
92.00
9.00
407.07
81.41
549.61
109.92
538.13
4.25
7019.39
955.69
7975.08
4747.07
4747
cum
cum
sqm
2169.88
347.43
1642.26
192.00
84.00
360.00
284.00
92.00
9.00
403.07
80.61
510.54
102.11
499.88
3.44
6780.22
923.13
7703.34
4891.01
4891
330.00
44.93
374.93
375
free consisting of frame
op and bottom rails. MS.
m thick high density EPS
nd fire resistant moulded
ours after routing to the
de of the EPS. The edge
ing 2 rigid foam sheet of
k and 30mm width Pac
of size 150mmX100mm
irection of Engineer – in-
xtures 3 Nos. butt hinges
204) of 150 mm x 10mm
including labour charges
plete for finished item of
3250.28
84.00
360.00
284.00
92.00
9.00
549.61
109.92
3.72
4742.52
645.69
5388.22
3754.85
3755
16186.00
2203.72
18389.72
18390
m roll formed sections
per IS 513 „D‟ quality
ness of 0.58mm. Primer
12-16 microns thick and
ster powder up to 50-60
x 59mm with a provision
glass shutter should be
plastic to accommodate
ade ofplastic. Section for
mm made of plastic to
The Window/Door to be
thyl Propylene Diamine
glass filled nylon. Touch
nd assembled by means
ng Nylon self-expanding
. The Grill for safety for
e item of work . For Door
ories, labour charges for
d item of work.
6166.00
839.50
7005.50
7006
per IS 513 of 0.58 mm
with
e. epoxycaps
Mullion primer of 5-7
made of
y wall by means of
d be of 46x70mm, fixed self
4477.00
609.54
5086.54
5087
should be of 46x70mm,
and section for middle
5105.00&
695.05
5800.05
5800
sqm
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
15834.89
474.00
1516.80
1260.00
29.60
7074.00
720.00
576.00
400.00
616.00
3590.76
2.53
32094.57
4369.68
36464.25
7012.36
7012
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
15120.68
426.60
1365.12
1134.00
28.00
7074.00
720.00
576.00
400.00
616.00
3231.68
4.87
30696.95
4179.39
34876.34
7452.21
7452
sqm
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
sqm.
sqm.
sqm.
RM
14049.68
355.50
1137.60
945.00
25.60
7074.00
720.00
576.00
400.00
616.00
2693.07
0.98
28593.43
3893.00
32486.43
8329.85
8330
of Skin pass galvanized
per IS 277 with Hot Zinc
frame with 1.2mm thick
8 mm and filled with in-fill
ed Iron Sheet formed to
stile edges, fitted with in-
ster/ epoxy polyester or
ted with Zinc Phosphate
nt
9902.00
1348.16
11250.16
11250
1931.83
16120.83
16121
ters made of galvanize
IS 277 with Zinc of 120
hed with Thermosetting
ce and durability/Epoxy
ess) outer frame section
steel sheet pressed (roll
ges, in-fill of honeycomb
6” Tower bolt – 2 Nos.,
approved quality – 1 No,
ncluding overheads and
9971.00
1357.55
11328.55
11329
9348.00
1272.73
10620.73
10621
46 x 82 mm both having
f appropriate dimension.
5404.00
735.75
6139.75
6140
706.04
5891.82
5892
sqm
12918.75
3221.25
16140.00
5977.78
-474.00
280.00
5783.78
787.46
6571.24
6571
sqm
11369.28
2577.00
13946.28
6456.61
-474.00
280.00
6262.61
852.65
7115.27
7115
sqm
8526.96
1932.75
10459.71
6456.61
-474.00
280.00
6262.61
852.65
7115.27
7115
sqm
13564.98
5797.00
-474.00
280.00
5603.00
762.85
6365.85
6366
sqm
12918.75
6625.00
-474.00
280.00
6431.00
875.58
7306.58
7307
sqm
11369.28
7288.00
-474.00
280.00
7094.00
965.85
8059.85
8060
sqm
8526.96
7288.00
-474.00
280.00
7094.00
965.85
8059.85
8060
ed ventilators made of
nized as per IS 277 with
ed with a polyester paint
n for outer frame of 46 x
and section for beading
section and the windows
ors with Ethyl propylene
th corner brocket centre
owder coated and nylon
ade of glass filled nylon,
ncluding 10 mm square
r finished item of work in
sqm
12661.74
3865.50
16527.24
5101.00
-474.00
280.00
4907.00
668.09
5575.09
5575
sqm
10551.45
3221.25
13772.70
5101.00
-474.00
280.00
4907.00
668.09
5575.09
5575
sqm
9475.44
2577.00
12052.44
5579.83
-474.00
280.00
5385.83
733.28
6119.11
6119
sqm
7106.58
1932.75
9039.33
5579.83
-474.00
280.00
5385.83
733.28
6119.11
6119
5411.00
-474.00
280.00
5217.00
710.29
5927.29
5927
5411.00
-474.00
280.00
5217.00
710.29
5927.29
5927
6074.00
-474.00
280.00
5880.00
800.56
6680.56
6681
6074.00
-474.00
280.00
5880.00
800.56
6680.56
6681
6295.00
857.06
7152.06
7152
4306.00
586.26
4892.26
4892
ow comprising of uPVC
einforced with 1.60 ± 0.2
ed length (shape & size
ads and uPVC extruded
with hook, zinc alloy body
0 x 8 mm size for fixing
sash shall be mitred cut
795.66
6639.66
6640
8058.00
-474.00
280.00
7864.00
1070.68
8934.68
8935
855.43
7138.43
7138
887.29
7404.29
7404
/ Ventilators comprising
files duly reinforced with
of required length (shape
riate dimension, EPDM
ackers, plastic caps and
on welded at all corners,
g hardware and drainage
47 x 68 mm both having
5830.00
793.75
6623.75
6624
128.12
1069.12
1069
Kgs
Kgs
Kgs
1094.60
361.20
128.00
938.95
173.88
109.89
2806.53
917.17
124.87
1042.04
1042
43.58
27.00
5.00
3.16
78.74
10.72
89.45
89
813.09
6785.09
6785
fixed to Brick/Concrete
m screws into the caps
re rod bars with 152mm
essories, labour charges
includes overheads and
6818.00
-474.00
280.00
6624.00
901.86
7525.86
7526
sqm
5030.64
1109.16
22.80
364.00
150.00
1762.15
6.95
8445.70
1149.88
9595.58
4100.68
4101
288.37
2406.42
5347.59
5348
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
sqm
RM
3575.92
403.20
7.20
204.00
347.88
1043.42
9.33
5590.95
761.21
6352.15
4411.22
4411
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
sqm
RM
5011.97
714.00
16.20
204.00
321.12
1847.72
8.98
8124.00
1106.08
9230.08
3619.64
3620
5096.12
1535.76
18.00
2347.70
7.19
9004.77
1226.00
10230.77
3157.64
3158
3701.38
1023.84
12.00
1565.13
2.60
6304.95
858.42
7163.36
3316.37
3316
2908.00
395.92
3303.92
3304
eak wood frames of size
or shutters with 18mm x
MS fixtures 3 Nos. butt
0mm, 2 Nos of handles
nveyance of all materials
item of work.
sqm
1281.51
1730.16
120.00
48.00
50.00
244.80
100.00
179.64
1995.84
435.10
1.18
6186.23
842.26
7028.48
3253.93
3254
404.00
53.82
457.82
62.33
520.15
520.00
x 65 x6 mm size equal
cing post, drilling 5 Nos
481.40
9.84
202.10
446.50
82.69
123.00
196.80
1542.32
771.16
772.00
sqm
cum
cum
cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
19586.38
74084.90
41694.72
41577.04
4541.76
5736.96
5500.00
480.00
8400.00
24000.00
2982.00
11200.00
8000.00
2800.00
55856.06
11171.21
4276.80
855.36
3015.32
603.06
1500.00
327861.58
44638.35
372499.93
21426.51
21427
sqm
cum
cum
RM
75050.50
44450.94
1456.00
5500.00
480.00
53443.50
17655.00
21600.00
20010.00
31062.26
1500.00
272208.20
38109.15
310317.35
17849.72
17850
sqm
cum
cum
cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
36199.80
98256.60
62993.70
51850.21
8474.40
5084.64
5500.00
480.00
8400.00
24000.00
3200.00
11200.00
8000.00
2800.00
59221.55
14805.39
4276.80
1069.20
3015.32
753.83
1500.00
411081.44
57551.40
468632.85
25692.59
25693
1290.00
387.00
1677.00
52.69
1729.69
1730
NAME OF WORK :-
FIRE DATA
INTERNAL HYDRANT SYSTEM
1 Supply,installation,testing and commissioning of single headed EACH 7475.00 7475.00
Internal / External hydrant valve with instantaneous Gun metal
couplings of 63mm dia with Cast iron wheel ISI marked
conforming to IS 5290 (Type -A) with blank Gun Metal cap and
chain as required.
Makes: Newage/ Winco/ Padmini / Safex/Minimax
( SSR 21-22, Item NO: 9.5.31 )
8492.72
SAY 8493.00
2 Supplying and fixing of hose cabinet of size 750mm X 600mm x EACH 3335.00 3335.00
250mm made of No 16 gauge SWG CRCA sheet with 6mm thick
glazed glass door including necessary locking arrangement
suitable to accommodate 2 Nos 15 mtr long Hose pipe, 1 No
branch pipe, mounted on wall OR raised brick platform and duly
painted with Post office red externally and white internally with
synthetic enamel paint complete in all respect, for external hydrant
as required.
MAKE: Approved makes
( SSR 21-22, Item NO: ELEC-9.5.40)
3423.09
SAY 3424.00
3 Supplying and fixing 63mm dia, 15 mtr long RRL hose pipe with EACH 5520.00 5520.00
63mm dia Male and Female Gun metal / SS couplings duly binded
with GI wire, rivets etc conforming to IS 636 (Type -A) as required.
Makes: Newage/ Winco/ Padmini / Safex / Minimax
( ELEC-9.5.37 )
6271.55
SAY 6272.00
4 Supply and fixing 63mm dia Gun metal branch pipe with 20mm EACH 2530.00 2530.00
(Nominal internal diameter) size Gun metal / SS nozzle
conforming to IS 903, suitable for instantaneous connection to
interconnect hose pipe coupling as required.
Makes: Newage/ Winco/ Padmini / Safex / Minimax/NewTech
( ELEC-9.5.41 )
2874.46
SAY 2875.00
5 Supplying and fixing First -Aid Hose Reel with MS construction EACH 7705.00 7705.00
spray painted in Post office Red, Conforming to Is 884 with upto
date amendments, complete with the following as required.
a) 36.6 Mtr Long 20mm (Nominal internal) dia water hose
Thermoplastic / Textile reinforced / Rubber braided /
Polypropylene Type - 2 as per IS:12585
Makes: Eversafe/ Reliance/ Newage/ SRI / Safex.
b) 20mm (Nominal internal) dia gun metal globe valve and nozzle.
Makes: Reliance/ Newage/ Safex/NewTech/Winco/Minimax
c) Drum and brackets for fixing the equipments on wall.
d) Connections from riser with 25mm dia stop valve (gun metal) &
MS pipe.
( ELEC-9.5.39 )
8754.04
SAY 8755.00
3067.61
SAY 3068.00
B 100mm dia ONE RM 1400.00 1400.00
1590.61
SAY 1591.00
1267.94
SAY 1268.00
381.75
SAY 382.00
5356.95
SAY 5357.00
4116.27
SAY 4117.00
8 Supply, installation, testing and commissioning of 25 / 20mm dia EACH 1265.00 1265.00
Air Release Valve
( ELEC-9.5.53 )
1437.23
SAY 1438.00
9 Supply and fixing air vessel made of 250 mm dia, 8 mm thick MS EACH 16445.00 16445.00
sheet, 1200mm in height with air release valve on top and flanged
connection to riser, drain arrangement with 25mm dia Gun metal
wheel valve, with required accessories, pressure gauge and
painting with synthetic enamel paint of approved shade as
required.
( ELEC-9.5.44 )
18683.99
SAY 18684.00
10 Supply, fabricating , installing structural steel supports for fixing all EACH Kg 72.00 72.00
sizes of MS pipes from ceiling / wall with MS Channels, Angles,
Flats, Rods, as required at site with anchor fasteners, Clamps,
threaded rods, nuts, bolts,washers etc complete with painting.
( ELEC-9.5.59 )
81.79
SAY 82.00
SPRINKLER SYSTEM
11 Providing , laying, testing & Commissioning of following classe " C
" Class MS pipes conforming to IS 3589 and 1239 including
fittings like elbows, tees, flanges, tapers, nuts, bolts, gaskets etc.,
complete.
Makes: Jindal / Hissar / Tata pipes/Prakash Surya
3067.20
SAY 3068.00
1908.48
SAY 1909.00
1267.78
SAY 1268.00
954.24
SAY 955.00
763.39
SAY 764.00
647.52
SAY 648.00
511.20
SAY 512.00
H 25 mm dia ( ELEC-9.5.30 ) ONE RM 336.00 336.00
381.70
SAY 382.00
574.82
SAY 575.00
574.82
SAY 575.00
13 Supply, fabricating , installing structural steel supports for fixing all KG 72.00 72.00
sizes of MS pipes from ceiling / wall with MS Channels, Angles,
Flats, Rods, as required at site with anchor fasteners, Clamps,
threaded rods, nuts, bolts,washers etc complete with painting.
( ELEC-9.5.59 )
81.79
SAY 82.00
14 Supply, installation, testing & commissioning of sprinkler flexible NO 1208.00 1208.00
pipe (UL Listed) of stainless steel complete with 15 NPT on
reducer thread with maximum working pressure of 175 PSI test
pressure of 875 PSI (Burst) with branch line (Inlet) 25mm NPT
male thread to sprinkler head (Outlet) 15mm NPT female thread
with reducer, nipple, 2 side brackets, center bracket, stockbar of
following sizes complete as required Makes :
Tyko/Newage/HDELEC-(9.5.54)
1372.29
SAY 1373.00
15 Supplying, fixing, testing and commissioning of butterfly valve PN EACH 4715.00 4715.00
1.6, with Bronze / Gun metal seat duly ISI marked complete with
Nuts, Bolts, Washers, gaskets, conforming to IS 13095 of
following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/ Zolotto
/SANT/NEUG/
Honeywell For 150 mm Dia (ELEC-9.5.32)
5356
SAY 5357.00
16 Providing and fixing Flow Switches in 150 mm dia MS pipe. EACH 7705.00 7705.00
Makes : System Sensor / Switzer /Honeywell (ELEC-9.5.49)
8753
SAY 8753.00
17 Providing , laying, testing & Commissioning of following classe " C
" Class MS pipes conforming to IS 3589 and 1239 including
fittings like elbows, tees, flanges, tapers, nuts, bolts, gaskets etc.,
complete.
Makes: Jindal / Hissar / Tata pipes/Prakash Surya (ELEC-9.5.30)
763.39
SAY 764.00
AUTO DETECTION SYSTEM
18 Supply and installation of plug -in type photo electric smoke EACH 1610.00 1610.00
detectors including the cost of base plate. 75mm dia MS outlet
box for fixing of the detector base. Mounting accessories etc
complete and as per specifications and as required.
Makes : As per list of recommended
brands.
( ELEC-9.3.7 ).
1828.96
SAY 1829.00
19 Supply and installation of plug -in type photo electric smoke EACH 1610.00 1610.00
detectors including the cost of base plate. 75mm dia MS outlet
box for fixing of the detector base. Mounting accessories etc
complete and as per specifications and as required.
Makes : As per list of recommended
brands.
( ELEC-9.3.7 ).
1828.96
SAY 1829.00
20 Supply and installation of response indicators for above false EACH 173.00 173.00
ceiling detectors.
( ELEC-9.3.5 ).
196.53
SAY 197.00
21 Supply and installation of intelligent analogue addressable rate of EACH 1495.00 1495.00
rise cum fixed temparature heat detectors including the cost of
base plate. 75mm dia MS outlet box for fixing of the detector
base, mounting accessories etc., complete as per specifications
and as required.
ELEC-ELEC-9.3.8
1698.32
SAY 1699.00
22 Supply, Installation, testing and commissioning of conventional EACH 16675.00 16675.00
Micro
processor based Fire Alarm panel with ……., 12V SMF batteries
etc.,
complete with all standard accessories.
Makes : As per list of recommended brands.
18942.80
SAY 18943.00
23 Supply of 2 Core x 1.5Sqmm FRLS armoured copper cable as per RM 85.00 85.00
IS. 7098 / Part-I / 1988 including all taxes etc., complete.
Makes: Universal / CCI / Unicab / Polycab / Finolex / KEI /
Havells. ( 2 CORE 1.50 SQMM)
96.56
SAY 97.00
### Supply and Installation of Intelligent analogue addressable fault NO 3000.00 3000.00
isolator modules ncluding the cost of mounting accessories
complete as per specifications
and complete as required.
Makes: Siemens / Morley / Honeywell/ Ravel/Seaara.
Overheads&Contractors Profit @13.615% 0.136 3000.00 408.00
3408.00
SAY 3408.00
15676.80
SAY 15677.00
980.37
SAY 981.00
### Supply and installation of dust and vermin proof manual call point EACH 690.00 690.00
to initiate audio visual alarm including the cost of mounting
accessories complete as per specifications and as required.
(ELEC-9.3.4)
783.84
SAY 784.00
### Supply of 2 Core x 1.5Sqmm FRLS armoured copper cable as per ONE RM 85.00 85.00
IS. 7098 / Part-I / 1988 including all taxes etc., complete.
Makes: Universal / CCI / Unicab / Polycab / Finolex / KEI /
Havells.
Overheads&Contractors Profit @13.615% 0.136 85.00 11.56
96.56
SAY 97.00
FIRE EXTINGUISHERS
### Supply and fixing of Co2 type Fire Extinguishers 4.5 Kg capacity EACH 10235.00 10235.00
confirming to IS 2878 made from ISI marked steam less cylinder
confirming to IS:7285 & CE certified and fitted with ISI marked
controlled valve confirming to IS:3224, high pressure 1 Mtr
discharge hose & horn complete with initial gas charged with
carrying handle with wheels and wall mounting bracket. Squeeze
lever discharge, used un-used indicator, Aphoxy coated paint
(Red) with 93% gloss with 2 years warranty Including
transportation, all taxes and all labour charges etc complete.
Makes : As per list of recommended
brands as category I.
11626.96
SAY 11627.00
### Supply and fixing of ISI mark (IS:15683) Mono ammonium EACH 4600.00 4600.00
phosphate powder 90 (MAP) 2 Kg Fire extinguisher, stored
pressure type, pressure gauge, gross wt. 3.6 kg, empty wt.1.6 kg,
Discharge time minimum 8 sec, controllable discharge
mechanism, range min. 2 mts applicable on classes A,B, C &
electrically started fire, A rating -2 A, B rating -21 B, can
construction: Deep drawn and Co2 mig welding, Valve
construction: Forging & Machining, internal coating of can: Epoxy
powder coating, External coating of Can:Epoxy polyster powder
coating, sheet metal thickness:1.60mm, Helium leak detection
tested with 5 years warranty Including transportation, all taxes and
all
labour charges etc complete..
Makes : As per list of recommended
brands as category I.
5225.60
SAY 5226.00
### Supply and fixing of ABC stored pressure squeeze grip type fire EACH 9315.00 9315.00
extinguishers, 9 kg capacity, IS:15683 : 2006, filled with ABC
Mono Ammonium Phosphate base powder-90 complete with
discharge hose and wall mounting bracket, 2mm Mild Steel,
EPDM Rubbers, Pressure Guage, which work effectively on all
class of fires (A, B, C & Electrical fires) with 5 years warranty
Including transportation, all taxes and all labour charges etc
complete.Makes : Makes : As per list of recommended
brands as category I.
Overheads&Contractors Profit @13.615% 0.136 9315.00 1266.84
10581.84
SAY 10582.00
### Supply and fixing of ISI mark (IS:15683) Clean Agent HCFC 123, EACH 22425.00 22425.00
4 Kg Fire exitinguisher , Stored pressure type, pressure guage,
gross weight 6.9Kg , empty weight 2.9 Kg, discharge time
minimum 8 secs, controllable discharge mechanism, range
minimum 2 meters, applicable on class A,B,C and electrically
started Fire, A rating- 1A, B rating-21B, can construction: Deep
drawn & CO2 mig welded, Valve construction: Forging &
Machining, Internal coating of Can: Epoxy powder coating,
External coating of can: Epoxy polyster powder coating, sheet
metal thickness: 1.60 mm, Helium leak detection tested, 5 Years
Makes : As per list of recommended
brands as category I.
25474.80
SAY 25475.00
### Supply and fixing of Cease fire or its equivalent Escape gear Mild EACH 15525.00 15525.00
Steel box size
425mmx360mmx140mm Epoxy powder coated to protect it from
Weathering , smoke hood tested to Eupropean Standard EN 403
1993-S known to reduce Carbon Monoxide, propend(acrloein),
hydrogen chloride, hydrogen Cyanide and Solid and liquid toxic
particles to manageable level for atleast 15 minutes shall with
stand tempeartures upto 80 degrees single use only Fire Blanket
size 1.2m x1.8m used to cover
any vessel containing used to Extinguish a clothing fire
wrap blanket around the victim.(ELEC-9.4.16)
17636.40
SAY 17637.00
121495.20
SAY 121496.00
### Providing 'Fire Retardant Paint 1 hr Fire Resistance can be used 1 No 2185.00 2185.00
to 'flame retard only 100 % cotton fabric, is normally used 'to treat
coarse fabric e.g. tents etc. and gives
coverage of 'approx. 120 to 130 sq.ft. to a fabric of 275-325 gsm.
'Can be applied 'Meant only for 100% cotton and coarse fabric like
canvas '/ tents, natural wood etc.
Makes: SEAARA/AGS/SALAMANDRA(ELEC-9.4.27)
2482.16
SAY 2483.00
### Providing 'Flame retard any kind of fabric, be it 100% polyester or 1 No 2990.00 2990.00
'100% cotton. It is normally used to flame 'retard upholstery,
curtains, carpets etc., gives a coverage
'of approx. 120 to 130 sq.ft. to a fabric of 275-325 gsm.(ELEC-
9.4.28)
Overheads&Contractors Profit @13.615% 0.136 2990.00 406.64
3396.64
SAY 3397.00
### Providing 'Fire Retardant coat towards passive protection to 1 No 4830.00 4830.00
sustain 'up to 1000 Deg.C. for 1 hour. This product can be used
for 'all the materials such as cable, steel, wood, cloth
& 'concrete surface etc.(ELEC-9.4.29)
5486.88
SAY 5487.00
SIGNAGE BOARDS
### Supply and fixing of Escape signage boards in Rigid Photo Each 1380.00 1380.00
luminecent based glow in Dark rigid sheet with high intensity
luminous properties with specificaiton.
Makes: Cease Fire or its equivalent make Model-1ES01
( ELEC-9.4.15)
1567.68
SAY 1568.00
FIRE DOORS
### Supply & Fixing of Stainless steel Fire Rated doors, frames & ONE 17650.00 17650.00
shutters made of Stainless steel of 304 grade hairline finish,frame SQM
with 1.2mm thick Stainless steel of 304 grade hairline finish sheet
formed to double rebate profile of ize 143 mm X58 mm with
maximum bending radius of 1.4 mm and filled with in-fill
Polyurethane foam, the Door Shutters are with 0.80 mm thick
Stainless steel of 304 grade hairline finish Sheet formed to
provide a 46 mm thick fully flush, double skin door shell with Lock
Seam joints at stile edges, fitted with in-fill of Honeycomb Kraft
Paper and coated with polyester powders
of Pure polyester/ epoxy polyester or polyurethane powder for
powder coating of thickness 60 – 65 microns and arecoated with
Zinc Phosphate Primer to receive any paint on site or finished with
Thermosetting Polyurethane paint ofAliphatic Grade providing
high levels of scratch resistance and durability, the Shutter
provided with 6 MM clear floatvision glass in Circular, Square or
Rectangular shapes, Stainless Steel Ball Bearing Butt Hinges 3
mm thick fixedflush to the frame and shutter (Profile 102x76x3mm
thick).Mortise Sash Lock with Lever Handles, Mortise DeadBolt,
etc for 60 minutes Fire Rated door conforming toIS:3614 (Part2)
1992
BMT-N.60) (BMT-N.60)
20050.40
SAY 20051.00
TERRACE FLOOR
### Providing , laying, testing & Commissioning of following classe " C
" Class MS pipes conforming to IS 3589 and 1239 including
fittings like elbows, tees, flanges, tapers, nuts, bolts, gaskets etc.,
complete.
Makes: Jindal / Hissar / Tata pipes
1908.48
SAY 1909.00
B 150mm dia ( ELEC-9.5.30 ) ONE RM 2700.00 2700.00
3067.20
SAY 3068.00
C 100 mm dia Two Way Fire Brigade risers ONE RM 1680.00 1680.00
1908.48
SAY 1909.00
4115.73
SAY 4116.00
4572.40
SAY 4573.00
### Supply, installation, testing and commissioning of stainless steel Y EACH 9200.00 9200.00
– Stainer
fabricated outof 1.6 mm thick SS 304 with following sizes
confirming to IS
specifications complete with rubber gasket, GI bolts , nuts,
washers etc as required
Makes: Leader / Zolotto/SANT/Honeywell.
( ELEC-9.5.38)
150 MM dia
10451.20
SAY 10452.00
### Supplying , installation , testing and commissioning of electric EACH 50025.00 50025.00
driven Terrace / Booster pump suitable for automatic operation
and consisting of following :
complete in all respect as required.a) Horizontal type, multistage,
centrifugal pump of cast iron body & bronze impeller
with stainless steel shaft, mechanical seal and flow of 900 lpm at
45 Mtr head
conforming to IS 1520b) Suitable HP SQ cage induction motor
TEFC type suitable for operation on
415Volts, 3 phase 50 Hz. AC with IP 55 class of protection for
enclosure,
horizontal foot mounted type with Class-'F' insulation, conforming
to IS-325c) M.S. Fabricated common base plate, coupling,
coupling guard, foundation bolts
etc as required.d) Suitable cement concrete foundation duly
plastered with anti vibration pads.
Makes of Pumps : Kirloskar / Mather&Platt.
Makes of Motors : Siemens / ABB / Kirloskar
56828.40
SAY 56829.00
PUMP ROOM
### Supplying, fixing, testing and commissioning of butterfly valve PN
1.6, with Bronze / Gun metal seat duly ISI marked complete with
Nuts, Bolts, Washers, gaskets, conforming to IS 13095 of
following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / SANT/NEU-G
5356.24
SAY 5357.00
### Supplying and wrapping the anticorrosive material for buried pipes
with coating of Primer and wrapping with 4 mm thick polymer
corrosion resistant tape as per IS : 10221 with 15 mm overlap as
per specificatios.
A 150mm dia (ELEC-9.5.58 ) ONE RM 345.00 345.00
391.92
SAY 392.00
353.30
SAY 354.00
8622.24
SAY 8623.00
### Supply, installation, testing and commissioning of cast iron Y – EACH 9200.00 9200.00
Stainer flanged end with SS mesh of following sizes confirming to
IS specifications complete with rubber gasket, GI bolts , nuts,
washers etc as required
Makes: Audco / Kirloskar / NVR / Leader / Zolotto.
( ELEC-9.5.38)
150 MM dia
SAY 10452.00
### Supplying, installation, testing and commissioning of electric EACH 165600.00 165600.00
driven main fire pump suitable for automatic operation and
consisting of following complete in all respect as required
a) Horizontal type, multistage, centrifugal, split casing pump of
cast iron body &
bronze impeller with stainless steel shaft, mechanical seal to
ensure a minimum pressure of 3.5 Kg / sq.cm. at highest and
farthest outlet at specified flow of 1620 lpm at 56 Mtr. head
conforming to IS 1520
b) Suitable HP SQ cage induction motor, TEFC, synchronous
speed 1500 RPM, suitable for operation on 415Volts, 3 phase 50
Hz. AC with IP 55 protection for enclosure, horizontal foot
mounted type with Class-'F' insulation, conforming to IS- c) M.S.
Fabricated common base plate, coupling, coupling guard,
foundation bolts
d) Suitable cement concrete foundation duly plastered with anti
vibration pads.
ELEC 9.5.13
188121.60
SAY 188122.00
### Supplying , installation, Testing and commissioning of diesel EACH 478400.00 478400.00
engine driven main fire pump suitable for automatic operation and
consisting of following :
a) Horizontal type, multistage, centrifugal pump of cast iron body
& bronze impeller
with stainless steel shaft, mechanical seal to ensure a minimum
pressure of 3.5 Kg
b) Suitable HP, 1500 RPM water cooled with radiator, diesel
engine conforming to
relevant BS & IS standard complete with auto starting mechanism,
12 Volts / 24
Volts electric starting equipment, Diesel Tank, exhaust pipe
extended upto 1 m.
outside pump house duly insulated with 50mm thick glass wool
with 1.0mm thick
alluminium sheet cladding, residential silencer, instruments and
protection as per
specification, stop solenoid for auto stop in the event of fault with
audio indications,
painted with post office red colour etc as required.
c) M.S. Fabricated common base plate, coupling, coupling guard,
foundation bolts
etc as required.
d) Suitable cement concrete foundation duly plastered with anti
vibration pads.
ELEC-9.5.6
543462.40
SAY 543463.00
### Fabrication, supply,Transportation, EACH 247250.00 247250.00
Insallation testing & commissioning of
Electrical control panel of cubical
construction, floor mounted type,
fabricated out of 2mm thick CRCA
sheet, compartmentalised with hinged
lockable doors, dust and vermin proof,
powder coated of approved shade
after 7 tank treatment process, cable
alley, interconnection with suitable
size copper conductor cable/solid
copper strip, having switchgears and
accessories, mountings and internal
wiring, earth terminals, numbering etc.
complete in all respect, suitable for
main fire pump, pressurisation pump
& diesel pump set complete with
following in coming and Outgoings,
suitable for operation on 415V, 3
phase, 50Hz Ac Supply.
Makes : As per list of recommended
brands.INCOMING :250A, 50kA 4 Pole MCCB, Ics=100%
Icu ratingDigital Voltmeter 0-500V with selector
switchDigital Ammeter (0-250 A) with selector swtich & CTs
etc.LED type RYB phase indicating lamps, ON, OFF, trip
indicating lampsSet of Copper Bus Bar 300AOUTGOING :
( Note : All outgoing feeders for pumps should have digital
Ammeter with
selector switches, and LED type ON, OFF, trip indicating
lamps)MAIN FIRE PUMP125 A, 50kA TPN MCCB, Ics=100% Icu,
with fully automatic Star/Delta
starter suitable for 60 HP pump with overload protection, current
sensing
type single phase preventor complete with all acceessories and
internal
wiring required for automatic operation selector switch for
local/remote,
auto/manual/OFF operation.
280876.00
SAY 280876.00
### Providing and fixing of Pressure Switch in the MS pipe Line EACH 2588.00 2588.00
including connection etc as required.
Makes : Danfoss / Indfoss /Systemsensor/Honeywell ELEC-9.5.47
2939.97
SAY 2940.00
### Supply, installation, testing and commissioning of Bourden type, EACH 690.00 690.00
stainless steel dial type pressure gauge with isolation valve and
pipe having calibration of 0-16 kg/cm2.
MAKES: HGURU / FIEBIG and Approved makes
( ELEC-9.5.50 )
783.84
SAY 784.00
### Supply, installation, testing and commissioning of 25mm dia Ball EACH 667.00 667.00
valve
Makes : Zoloto / Leader / SANT/NEU-G
( ELEC-9.5.52 )
757.71
SAY 758.00
### Providing and fixing Flow Switches in 150 mm dia MS pipe. EACH 7705.00 7705.00
Makes : System Sensor / Switzer /Honeywell
8752.88
SAY 8753.00
### Supply, installation, testing and commissioning of Bourden type, EACH 690.00 690.00
stainless steel dial type pressure gauge with isolation valve and
pipe having calibration of 0-16
kg/cm2.
MAKES: HGURU / FIEBIG
783.84
SAY 784.00
### Supply and fixing air vessel made of 250 mm dia, 8 mm thick MS EACH 16445.00 16445.00
sheet, 1200mm in height with air release valve on top and flanged
connection to riser, drain arrangement with 25mm dia Gun metal
wheel valve, with required accessories, pressure gauge and
painting with synthetic enamel paint of approved shade as
required.
( ELEC-9.5.44 )
18681.52
SAY 18682.00
3067.20
SAY 3068.00
U.G CABLES
### Supply and Transportation of XLPE/PVC insulated & PVC
sheathed armoured cables of 1.1 KV grade with copper conductor
as per IS 7098 Part-I -1988 etc complete Make:
Torrent / Universal / Unicab / Havells / KEI
/Polycab/Gloster/Orbit/Avocab
Make: Raychem /M
A seal/ Denson/
4C x 70 sq.mmMulty/ Transeal- Hongshang. ONE RM 3500.00 3500.00
3976.00
SAY 3976.00
852.00
SAY 852.00
511.20
SAY 512.00
### Supply and fixing 4 way fire brigade connection of cast iron body Each 9200.00 9200.00
with 4 Nos Gun metal Male instantaneous inlet couplings
complete with cap and chain as required for 150mm dia MS pipe
connection, conforming to IS 904 as required.
Makes: Newage/
Winco/ Padmini / Safex / Minimax/NewTech/Honeywell
( ELEC-9.5.42 )
10451.20
SAY 10452.00
### Supply and fixing 2 way fire brigade connection of cast iron body Each 6900.00 6900.00
with 4 Nos Gun metal Male instantaneous inlet couplings
complete with cap and chain as required for 150mm dia MS pipe
connection, conforming to IS 904 as required.
Makes: Newage/
Winco/ Padmini / Safex / Minimax/NewTech/Honeywell
( ELEC-9.5.42 )
7838.40
SAY 7839.00
### Supply and installation testing and commissioning of 15 Watt Each 2107.00 2107.00
column speaker (Makes: Philips/eqvt) including cost all taxes etc
complete for finished item of work as directed by the engineer-in-
charge.(Market Rate )
2393.55
SAY 2394.00
### Supply and laying of shielded twin twisted pair 1.0 sqmm cable in Each 38.00 38.00
existing conduit.(Market Rate )
43.17
SAY 44.00
### Supply, installation, testing and commissioning of 120W amplifiers Each 9465.00 9465.00
for public addressing system suitable for operation on 230V, 50
Hz single phase Ac supply including all labour charges etc.,
complete., (Market Rate)
10752.24
SAY 10753.00
### Supply and Fixing of Focus Wall Speaker - 30 watts including Each 3435.00 3435.00
labour charges etc., complete.
Make: Ahuja - WB - 330T/PHILIPS /Mega. (Market Rate )
3902.16
SAY 3903.00
### Testing and commissioning of the Public Address system (Market Each Job 2000.00 2000.00
Rate )
2272.00
SAY 2272.00
EXTERNAL YARD HYDRANT
a) 80 mm dia pipe fiited with single headed 63mm dia landing 7475.00
valve as per design (Rs 7300/-)
15927.00
18093.07
SAY 18094.00
### Providing , laying, testing & Commissioning of following classe " C
" Class MS pipes conforming to IS 3589 and 1239 including
fittings like elbows, tees, flanges, tapers, nuts, bolts, gaskets etc.,
complete.
Makes: Jindal / Hissar / Tata pipes
3067.20
SAY 3068.00
1590.40
SAY 1591.00
### Supply, installation, testing and commissioning of stainless steel Y EACH 9200.00 9200.00
– Stainer
fabricated outof 1.6 mm thick SS 304 with following sizes
confirming to IS
specifications complete with rubber gasket, GI bolts , nuts,
washers etc as required
Makes: Leader / Zolotto/SANT/Honeywell.
( ELEC-9.5.38)
100 MM dia
10451.20
SAY 10452.00
5356.24
SAY 5357.00
JOCKEY PUMPS
Supplying , installation , testing and commissioning of electric EACH 49000 49000.00
driven pressurisation / Jockey pump suitable
for automatic operation and consisting of following : complete in
all respect as required a) Horizontal type, multistage, centrifugal
pump of cast iron body & bronze impeller
with stainless steel shaft, mechanical seal and flow of 180 lpm at
56 Mtr head
conforming to IS 1520 .b) Suitable HP SQ cage induction motor
TEFC type suitable for operation on
415Volts, 3 phase 50 Hz. AC with IP 55 class of protection for
enclosure,
horizontal foot mounted type with Class-'F' insulation, conforming
to IS-325c) M.S. Fabricated common base plate, coupling,
coupling guard, foundation bolts
etc as required.d) Suitable cement concrete
Overheads&Contractors foundation duly
Profit @13.615% 0.136 49000.00 6664.00
plastered with anti vibration pads.
Makes of Pumps : Kirloskar / Mather&Platt. 55664.00
Makes of Motors : Siemens/ ABB/ KirloskarELEC-9.5.17
SAY 55664.00
EACH 56350 56350.00
64013.60
SAY 64014.00
HOSPITAL BUILDING AT PRODDTUR
HOSPITAL BUILDING
GROUND + TWO FLOORS
S.
Quantity Description of Work Unit
NO.
2 18.0 Nos Supplying and fixing of hose cabinet of size 750mm X 600mm x 250mm made of No EACH
16 gauge SWG CRCA sheet with 6mm thick glazed glass door including necessary
locking arrangement suitable to accommodate 2 Nos 15 mtr long Hose pipe, 1 No
branch pipe, mounted on wall OR raised brick platform and duly painted with Post
office red externally and white internally with synthetic enamel paint complete in all
respect, for external hydrant as required.
MAKE: Approved makes
3 36.0 Nos Supplying and fixing 63mm dia, 15 mtr long RRL hose pipe with 63mm dia Male and EACH
Female Gun metal / SS couplings duly binded with GI wire, rivets etc conforming to
IS 636 (Type -A) as required. Maks: Newage/ Winco/ Padmini / Safex / Minimax
4 18.0 Nos Supply and fixing 63mm dia Gun metal branch pipe with 20mm (Nominal internal EACH
diameter) size Gun metal / SS nozzle conforming to IS 903, suitable for
instantaneous connection to interconnect hose pipe coupling as required.
Makes: Newage/ Winco/ Padmini / Safex / Minimax/NewTech
5 18.0 Nos Supplying and fixing First -Aid Hose Reel with MS construction spray painted in EACH
Post office Red, Conforming to Is 884 with upto date amendments, complete with
the following as required.
a) 36.6 Mtr Long 20mm (Nominal internal) dia water hose Thermoplastic / Textile
reinforced / Rubber braided / Polypropylene Type - 2 as per IS:12585
Makes: Eversafe/ Reliance/ Newage/ SRI / Safex.
b) 20mm (Nominal internal) dia gun metal globe valve and nozzle.
Makes: Reliance/ Newage/ Safex/NewTech/Winco/Minimax
c) Drum and brackets for fixing the equipments on wall.
d) Connections from riser with 25mm dia stop valve (gun metal) & MS pipe.
6 Providing , laying, testing & Commissioning of following classe "C" Class MS pipes
conforming to IS 3589 and 1239 including fittings like elbows, tees, flanges, tapers,
nuts, bolts, gaskets etc., complete.
Makes: Jindal / Hissar / Tata pipes/Prakash Surya
7 Supplying, fixing, testing and commissioning of butterfly valve PN 1.6, with Bronze /
Gun metal seat duly ISI marked complete with Nuts, Bolts, Washers, gaskets,
conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/ Zolotto /SANT/NEUG/
Honeywell
8 18.0 Nos Supply, installation, testing and commissioning of 25 / 20mm dia Air Release Valve EACH
( ELEC-9.5.53 )
9 6.0 Nos Supply and fixing air vessel made of 250 mm dia, 8 mm thick MS sheet, 1200mm in EACH
height with air release valve on top and flanged connection to riser, drain
arrangement with 25mm dia Gun metal wheel valve, with required accessories,
pressure gauge and painting with synthetic enamel paint of approved shade as
required.
( ELEC-9.5.44 )
10 250.0 Kg Supply, fabricating , installing structural steel supports for fixing all sizes of MS EACH
pipes from ceiling / wall with MS Channels, Angles, Flats, Rods, as required at site Kg
with anchor fasteners, Clamps, threaded rods, nuts, bolts,washers etc complete
with painting.
( ELEC-9.5.59 )
B SPRINKLER SYSTEM
11 Providing , laying, testing & Commissioning of following classe " C " Class MS
pipes conforming to IS 3589 and 1239 including fittings like elbows, tees, flanges,
tapers, nuts, bolts, gaskets etc., complete.
Makes: Jindal / Hissar / Tata pipes/Prakash Surya
12 Providing fixing, testing and commissioning of 15mm size quartzoid bulb type
sprinklers of rating 68º C. pendent / side wall with required accessories.
Makes: HD / TYCO / VIKING / NEWAGE/ SHARP /
SAFEX
( ELEC-9.5.45 )
14 40.0 NO Supply, installation, testing & commissioning of sprinkler flexible pipe (UL Listed) of NO
stainless steel complete with 15 NPT on reducer thread with maximum working
pressure of 175 PSI test pressure of 875 PSI (Burst) with branch line (Inlet) 25mm
NPT male thread to sprinkler head (Outlet) 15mm NPT female thread with reducer,
nipple, 2 side brackets, center bracket, stockbar of following sizes complete as
required Makes : Tyko/Newage/HD
15 12.0 NO Supplying, fixing, testing and commissioning of butterfly valve PN 1.6, with Bronze / EACH
Gun metal seat duly ISI marked complete with Nuts, Bolts, Washers, gaskets,
conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/ Zolotto /SANT/NEUG/
Honeywell For 150 mm Dia
16 12.0 NO Providing and fixing Flow Switches in 150 mm dia MS pipe. EACH
Makes : System Sensor / Switzer /Honeywell
17 Providing , laying, testing & Commissioning of following classe " C " Class MS
pipes conforming to IS 3589 and 1239 including fittings like elbows, tees, flanges,
tapers, nuts, bolts, gaskets etc., complete.
Makes: Jindal / Hissar / Tata pipes/Prakash Surya
14 100.0 Nos Supply and installation of plug -in type photo electric smoke detectors including the EACH
cost of base plate. 75mm dia MS outlet box for fixing of the detector base. Mounting
accessories etc complete and as per specifications and as required.
Makes : As per list of recommended
brands.( Below False Ceiling )
( ELEC-9.2.10 ).
15 100.0 Nos Supply and installation of response indicators for above false ceiling detectors. EACH
( ELEC-9.3.5 ).
16 10.0 Nos Supply and installation of intelligent analogue addressable rate of rise cum fixed EACH
temparature heat detectors including the cost of base plate. 75mm dia MS outlet
box for fixing of the detector base, mounting accessories etc., complete as per
specifications and as required.
ELEC-ELEC-9.3.8)
17 15.0 Nos Supply, Installation, testing and commissioning of conventional Micro EACH
processor based Fire Alarm panel with ……., 12V SMF batteries etc.,
complete with all standard accessories.
Makes : As per list of recommended brands.
18 5700.0 Nos Supply of 2 Core x 1.5Sqmm FRLS armoured copper cable as per IS. 7098 / Part-I / RM
1988 including all taxes etc., complete.
Makes: Universal / CCI / Unicab / Polycab / Finolex / KEI / Havells. ( 2 CORE 1.50
SQMM
### 19.0 NO Supply and Installation of Intelligent analogue addressable fault isolator modules NO
ncluding the cost of mounting accessories complete as per specifications
and complete as required.
Makes: Siemens / Morley / Honeywell/ Ravel/Seaara.
### 1.0 NO Supply, Installation, testing and commissioning of intellegent analogue addressable NO
epeater panel including the cost of mounting accessories complete
as per specification as required.
Makes: Siemens / Morley / Honeywell/ Ravel/Seaara (ELEC-9.2.4)
18 24.0 Nos Supply and installation of duel tone electronic hooter of 85dB including the cost of EACH
mounting accessories complete as per specifications and as required.
( ELEC-9.3.3 )
19 24.0 Nos Supply and installation of dust and vermin proof manual call point to initiate audio EACH
visual alarm including the cost of mounting accessories complete as per
specifications and as required.(ELEC-9.3.4)
20 672.0 RM Supply of 2 Core x 1.5Sqmm FRLS armoured copper cable as per IS. 7098 / Part-I / ONE
1988 including all taxes etc., complete. RM
Makes: Universal / CCI / Unicab / Polycab / Finolex / KEI / Havells.
E FIRE EXTINGUISHERS
21 129.0 Nos Supply and fixing of Co2 type Fire Extinguishers 4.5 Kg capacity confirming to IS EACH
2878 made from ISI marked steam less cylinder confirming to IS:7285 & CE
certified and fitted with ISI marked controlled valve confirming to IS:3224, high
pressure 1 Mtr discharge hose & horn complete with initial gas charged with
carrying handle with wheels and wall mounting bracket. Squeeze lever discharge,
used un-used indicator, Aphoxy coated paint (Red) with 93% gloss with 2 years
warranty Including transportation, all taxes and all labour charges etc complete.
Makes: Makes : Safex / Kenex / Bharat / Reliance/NewTech
( ELEC-9.4.14 ).
22 129.0 Nos Supply and fixing of ISI mark (IS:15683) Mono ammonium phosphate powder 90 EACH
(MAP) 2 Kg Fire extinguisher, stored pressure type, pressure gauge, gross wt. 3.6
kg, empty wt.1.6 kg, Discharge time minimum 8 sec, controllable discharge
mechanism, range min. 2 mts applicable on classes A,B, C & electrically started
fire, A rating -2 A, B rating -21 B, can construction: Deep drawn and Co2 mig
welding, Valve construction: Forging & Machining, internal coating of can: Epoxy
powder coating, External coating of Can:Epoxy polyster powder coating, sheet
metal thickness:1.60mm, Helium leak detection tested with 5 years warranty
Including transportation, all taxes and all
labour charges etc complete..
Makes: Safex / Kenex / Bharat / Reliance/NewTech
(ELEC-9.4.4 ).
23 129.0 Nos Supply and fixing of ABC stored pressure squeeze grip type fire extinguishers, 9 kg EACH
capacity, IS:15683 : 2006, filled with ABC Mono Ammonium Phosphate base
powder-90 complete with discharge hose and wall mounting bracket, 2mm Mild
Steel, EPDM Rubbers, Pressure Guage, which work effectively on all class of fires
(A, B, C & Electrical fires) with 5 years warranty Including transportation, all taxes
and all labour charges etc complete.Makes : Safex / Kenex / Bharat /
Reliance/NewTech
24 10.0 Nos Supply and fixing of ISI mark (IS:15683) Clean Agent HCFC 123, 4 Kg Fire EACH
exitinguisher , Stored pressure type, pressure guage, gross weight 6.9Kg , empty
weight 2.9 Kg, discharge time minimum 8 secs, controllable discharge mechanism,
range minimum 2 meters, applicable on class A,B,C and electrically started Fire, A
rating- 1A, B rating-21B, can construction: Deep drawn & CO2 mig welded, Valve
construction: Forging & Machining, Internal coating of Can: Epoxy powder coating,
External coating of can: Epoxy polyster powder coating, sheet metal thickness: 1.60
mm, Helium leak detection tested, 5 Years warranty.Makes : Safex / Kenex / Bharat
/ Reliance/NewTech
25 6.0 Nos Supply and fixing of Cease fire or its equivalent Escape gear Mild Steel box size EACH
425mmx360mmx140mm Epoxy powder coated to protect it from Weathering ,
smoke hood tested to Eupropean Standard EN 403 1993-S known to reduce
Carbon Monoxide, propend(acrloein), hydrogen chloride, hydrogen Cyanide and
Solid and liquid toxic
particles to manageable level for atleast 15 minutes shall with stand tempeartures
upto 80 degrees single use only Fire Blanket size 1.2m x1.8m used to cover
any vessel containing used to Extinguish a clothing fire
wrap blanket around the victim.
26 1.0 Nos Supply,Installationand commissioning of Auto Detection and Aerosol Suppression EACH
System using Non Pressurised Aerosol Generator System with detection of
thermocord and Inbuilt Aerosol Sprinkler flexibility of adjusting it for a temperature of
57/68/93/141 degree centigrade as per the site environment to make the system
standalone. It can be used for all classes of fire, The product Min. Life shall be 15
years and no Maintenance. The Discharge time should
be 80 sec. The Generator has a net weight of 8 kg. Active Substance of 4 kg. The
Generator has a capacity to cover 80 m³.
Makes: SEAARA/AGS/SALAMANDRA
27 6.0 Nos Providing 'Fire Retardant Paint 1 hr Fire Resistance can be used to 'flame retard 1 No
only 100 % cotton fabric, is normally used 'to treat coarse fabric e.g. tents etc. and
gives
coverage of 'approx. 120 to 130 sq.ft. to a fabric of 275-325 gsm. 'Can be applied
'Meant only for 100% cotton and coarse fabric like canvas '/ tents, natural wood etc.
Makes: SEAARA/AGS/SALAMANDRA
28 6.0 Nos Providing 'Flame retard any kind of fabric, be it 100% polyester or '100% cotton. It is 1 No
normally used to flame 'retard upholstery, curtains, carpets etc., gives a coverage
'of approx. 120 to 130 sq.ft. to a fabric of 275-325 gsm.
29 6.0 Nos Providing 'Fire Retardant coat towards passive protection to sustain 'up to 1000 1 No
Deg.C. for 1 hour. This product can be used for 'all the materials such as cable,
steel, wood, cloth
& 'concrete surface etc.
F SIGNAGE BOARDS
30 24.0 Nos Supply and fixing of Escape signage boards in Rigid Photo luminecent based glow Each
in Dark rigid sheet with high intensity luminous properties with specificaiton.
Makes: Cease Fire or its equivalent make Model-1ES01
( ELEC-9.4.15)
G FIRE DOORS
31 50.4 SQM Supply & Fixing of Stainless steel Fire Rated doors, frames & shutters made of ONE
Stainless steel of 304 grade hairline finish,frame with 1.2mm thick Stainless steel of SQM
304 grade hairline finish sheet formed to double rebate profile of ize 143 mm X58
mm with maximum bending radius of 1.4 mm and filled with in-fill Polyurethane
foam, the Door Shutters are with 0.80 mm thick Stainless steel of 304 grade hairline
finish Sheet formed to provide a 46 mm thick fully flush, double skin door shell with
Lock Seam joints at stile edges, fitted with in-fill of Honeycomb Kraft Paper and
coated with polyester powders
of Pure polyester/ epoxy polyester or polyurethane powder for powder coating of
thickness 60 – 65 microns and arecoated with Zinc Phosphate Primer to receive
any paint on site or finished with Thermosetting Polyurethane paint ofAliphatic
Grade providing high levels of scratch resistance and durability, the Shutter
provided with 6 MM clear floatvision glass in Circular, Square or Rectangular
shapes, Stainless Steel Ball Bearing Butt Hinges 3 mm thick fixedflush to the frame
and shutter (Profile 102x76x3mm thick).Mortise Sash Lock with Lever Handles,
Mortise DeadBolt, etc for 60 minutes Fire Rated door conforming toIS:3614 (Part2)
1992
BMT-N.60)
32 37.8 SQM Supply & Fixing of Stainless steel Fire Rated doors, frames & shutters made of ONE
Stainless steel of 304 grade hairline finish,frame with 1.2mm thick Stainless steel of SQM
304 grade hairline finish sheet formed to double rebate profile of ize 143 mm X58
mm with maximum bending radius of 1.4 mm and filled with in-fill Polyurethane
foam, the Door Shutters are with 0.80 mm thick Stainless steel of 304 grade hairline
finish Sheet formed to provide a 46 mm thick fully flush, double skin door shell with
Lock Seam joints at stile edges, fitted with in-fill of Honeycomb Kraft Paper and
coated with polyester powders of Pure polyester/ epoxy polyester or polyurethane
powder for powder coating of thickness 60 – 65 microns and arecoated with Zinc
Phosphate Primer to receive any paint on site or finished with Thermosetting
Polyurethane paint ofAliphatic Grade providing high levels of scratch resistance and
durability, the Shutter provided with 6 MM clear floatvision glass in Circular, Square
or Rectangular shapes, Stainless Steel Ball Bearing Butt Hinges 3 mm thick
fixedflush to the frame and shutter (Profile 102x76x3mm thick).Mortise Sash Lock
with Lever Handles, Mortise DeadBolt, etc for 60 minutes Fire Rated door
conforming toIS:3614 (Part2) 1992
BMT-N.60)
H TERRACE FLOOR
32 Providing , laying, testing & Commissioning of following classe " C " Class MS
pipes conforming to IS 3589 and 1239 including fittings like elbows, tees, flanges,
tapers, nuts, bolts, gaskets etc., complete.
Makes: Jindal / Hissar / Tata pipes
33 Supplying, fixing, testing and commissioning of butterfly valve PN 1.6, with Bronze /
Gun metal seat duly ISI marked complete with Nuts, Bolts, Washers, gaskets,
conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / SANT/NEU-G
34 Providing, installation, testing and commissioning of dual Plate non - return valve of
following sizes confirming to IS: 5312 complete with rubber gasket, GI bolts, nuts,
washers etc as required
Makes: BDK / NEU-G / Leader/ Zolotto / SANT/Honeywell
35 1.0 Nos Supply, installation, testing and commissioning of stainless steel Y – Stainer EACH
fabricated outof 1.6 mm thick SS 304 with following sizes confirming to IS
specifications complete with rubber gasket, GI bolts , nuts, washers etc as required
Makes: Leader / Zolotto/SANT/Honeywell.
( ELEC-9.5.38)
150 MM dia
36 1.0 Nos Supplying , installation , testing and commissioning of electric driven Terrace / EACH
Booster pump suitable for automatic operation and consisting of following :
complete in all respect as required.a) Horizontal type, multistage, centrifugal pump
of cast iron body & bronze impeller
with stainless steel shaft, mechanical seal and flow of 900 lpm at 45 Mtr head
conforming to IS 1520b) Suitable HP SQ cage induction motor TEFC type suitable
for operation on
415Volts, 3 phase 50 Hz. AC with IP 55 class of protection for enclosure,
horizontal foot mounted type with Class-'F' insulation, conforming to IS-325c) M.S.
Fabricated common base plate, coupling, coupling guard, foundation bolts
etc as required.d) Suitable cement concrete foundation duly plastered with anti
vibration pads.
Makes of Pumps : Kirloskar / Mather&Platt.
Makes of Motors : Siemens / ABB / Kirloskar
PUMP ROOM
37 Supplying, fixing, testing and commissioning of butterfly valve PN 1.6, with Bronze /
Gun metal seat duly ISI marked complete with Nuts, Bolts, Washers, gaskets,
conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / SANT/NEU-G
39 Providing, installation, testing and commissioning of dual plate non - return valve of
following sizes confirming to IS: 5312 complete with rubber gasket, GI bolts, nuts,
washers etc as required
Makes: BDK / NEU-G / Leader/ Zolotto / SANT/Honeywell
( ELEC-9.5.33 )
40 3.0 Nos Supply, installation, testing and commissioning of cast iron Y – Stainer flanged end EACH
with SS mesh of following sizes confirming to IS specifications complete with rubber
gasket, GI bolts , nuts, washers etc as required
Makes: Audco / Kirloskar / NVR / Leader / Zolotto.
( ELEC-9.5.38)
150 MM dia
37 1.0 Nos Supplying, installation, testing and commissioning of electric driven main fire pump EACH
suitable for automatic operation and consisting of following complete in all respect
as required
a) Horizontal type, multistage, centrifugal, split casing pump of cast iron body &
bronze impeller with stainless steel shaft, mechanical seal to ensure a minimum
pressure of 3.5 Kg / sq.cm. at highest and farthest outlet at specified flow of 1620
lpm at 56 Mtr. head conforming to IS 1520
b) Suitable HP SQ cage induction motor, TEFC, synchronous speed 1500 RPM,
suitable for operation on 415Volts, 3 phase 50 Hz. AC with IP 55 protection for
enclosure, horizontal foot mounted type with Class-'F' insulation, conforming to IS-
c) M.S. Fabricated common base plate, coupling, coupling guard, foundation bolts
d) Suitable cement concrete foundation duly plastered with anti vibration pads.
ELEC 9.5.13.
38 1.0 Nos Supplying , installation, Testing and commissioning of diesel engine driven main fire EACH
pump suitable for automatic operation and consisting of following :
a) Horizontal type, multistage, centrifugal pump of cast iron body & bronze impeller
with stainless steel shaft, mechanical seal to ensure a minimum pressure of 3.5 Kg
b) Suitable HP, 1500 RPM water cooled with radiator, diesel engine conforming to
relevant BS & IS standard complete with auto starting mechanism, 12 Volts / 24
Volts electric starting equipment, Diesel Tank, exhaust pipe extended upto 1 m.
outside pump house duly insulated with 50mm thick glass wool with 1.0mm thick
alluminium sheet cladding, residential silencer, instruments and protection as per
specification, stop solenoid for auto stop in the event of fault with audio indications,
painted with post office red colour etc as required.
c) M.S. Fabricated common base plate, coupling, coupling guard, foundation bolts
etc as required.
d) Suitable cement concrete foundation duly plastered with anti vibration pads.
ELEC-9.5.6
39 1.0 Nos Fabrication, supply,Transportation, EACH
Insallation testing & commissioning of
Electrical control panel of cubical
construction, floor mounted type,
fabricated out of 2mm thick CRCA
sheet, compartmentalised with hinged
lockable doors, dust and vermin proof,
powder coated of approved shade
after 7 tank treatment process, cable
alley, interconnection with suitable
size copper conductor cable/solid
copper strip, having switchgears and
accessories, mountings and internal
wiring, earth terminals, numbering etc.
complete in all respect, suitable for
main fire pump, pressurisation pump
& diesel pump set complete with
following in coming and Outgoings,
suitable for operation on 415V, 3
phase, 50Hz Ac Supply.
Makes : As per list of recommended
brands.INCOMING :250A, 50kA 4 Pole MCCB, Ics=100%
Icu ratingDigital Voltmeter 0-500V with selector
switchDigital Ammeter (0-250 A) with selector swtich & CTs
etc.LED type RYB phase indicating lamps, ON, OFF, trip indicating lampsSet of
Copper Bus Bar 300AOUTGOING :
( Note : All outgoing feeders for pumps should have digital Ammeter with
selector switches, and LED type ON, OFF, trip indicating lamps)MAIN FIRE
PUMP125 A, 50kA TPN MCCB, Ics=100% Icu, with fully automatic Star/Delta
starter suitable for 60 HP pump with overload protection, current sensing
type single phase preventor complete with all acceessories and internal
wiring required for automatic operation selector switch for local/remote,
auto/manual/OFF operation.ssories and internal wiring required for
automatic operation selector switch for local/remote, auto/manual/OFF
operation.JOCKEY PUMP
63 A, 50kA TPN MCCB, Ics=100% Icu, with suitable protection, current sensing
type single phase preventor complete with all acceessories and internal wiring
required for automatic operation, selector switch for ocal/remote, auto/manual/OFF
operation.DIESEL ENGINE CONTROL
Control for diesel engine comprising - Automatic/Manual selctor switch & 3
attempts starting device, timers and relays as required, push buttons, start/stop in
manual mode Indicating lamp for high/ Low Lub. Oil pressure, High Water Temp
and Engine on indication Water Temp and Engine on indication. Battery charger
suitbale for 12V/24 V DC with boost and trickle selector switch, 0-30 V DC volt
meter, and 0- 20 A DC Ammeter All standard relays and accessories for automatic
operation of diesel engine System Controller.
40 2.0 Nos Providing and fixing of Pressure Switch in the MS pipe Line including connection etc EACH
as required.
Makes : Danfoss / Indfoss /Systemsensor/Honeywell ELEC-9.5.47
41 3.0 Nos Supply, installation, testing and commissioning of Bourden type, stainless steel dial EACH
type pressure gauge with isolation valve and pipe having calibration of 0-16 kg/cm2.
MAKES: HGURU / FIEBIG and Approved makes
( ELEC-9.5.50 )
42 3.0 Nos Supply, installation, testing and commissioning of 25mm dia Ball valve EACH
Makes : Zoloto / Leader / SANT/NEU-G
( ELEC-9.5.52 )
43 2.0 Nos Providing and fixing Flow Switches in 150 mm dia MS pipe. EACH
Makes : System Sensor / Switzer /Honeywell
### 3.0 Nos Supply and fixing air vessel made of 250 mm dia, 8 mm thick MS EACH
sheet, 1200mm in height with air release valve on top and flanged connection to
riser, drain arrangement with 25mm dia Gun metal wheel valve, with required
accessories, pressure gauge and painting with synthetic enamel paint of approved
shade as required.
( ELEC-9.5.44 )
### Providing , laying, testing & Commissioning of following classe " C " Class MS
pipes conforming to IS 3589 and 1239 including fittings like elbows, tees, flanges,
tapers, nuts, bolts, gaskets etc., complete.
Makes: Jindal / Hissar / Tata pipes
U.G CABLES
45 1.0 Nos Supply and fixing 2 way fire brigade connection of cast iron body with 2 Nos Gun Each
metal Male instantaneous inlet couplings complete with cap and chain as required
for 100mm dia MS pipe connection, conforming to IS 904 as required. Makes:
Newage/
Winco/ Padmini / Safex / Minimax/NewTech/Honeywell
48 25.0 EACH Supply, Installation, Tesing and Commissioning of Yard Hydrants comprising of the Each
following : a) 80 mm dia pipe fitted with single headed 63mm dia landing valve as
per design. b) Providing 2 nos 15 mtrs long 63 mm dia CP hose with SS 304 male
and Female instantaneous coupling. c) 63 mm dia branch pipe with gun metal
hexogonal detachable nozzle made of instantaneous couping.
d) Two keys in recess type compartment for break glass. e) 80 mm dia GI bend. f)
80 mm dia GIDF stand pipe ( 1 mtrs below ground + 1 mtr above ground ). The pipe
portion below ground shall be treated with anti - corrosive wrapping and coating of
Pypkote make as per detailed specification. The quoted rate shall be inclusive of
supply and fixing of hose cabinet with hinged front door and lock made of 16G MS
sheet of suitable size to accommodtae the above in MS cabinet with glass door and
supporting frame.
49 30 EACH Supply and installation testing and commissioning of 15 Watt column speaker EACH
(Makes: Philips/eqvt) including cost all taxes etc complete for finished item of work
as directed by the engineer-in-charge.(Market Rate )
50 500 RM Supply and laying of shielded twin twisted pair 1.0 sqmm cable in existing conduit. RM
(Market Rate )
51 10 EACH Supply, installation, testing and commissioning of 120W amplifiers for public EACH
addressing system suitable for operation on 230V, 50 Hz single phase Ac supply
including all labour charges etc., complete., (Market Rate)
52 10 EACH Supply and Fixing of Focus Wall Speaker - 30 watts including labour charges etc., EACH
complete.
Make: Ahuja - WB - 330T/PHILIPS /Mega. (Market Rate
PITAL BUILDING
8493.00 152874.00
3424.00 61632.00
6272.00 225792.00
2875.00 51750.00
8755.00 157590.00
1591.00 114552.00
1268.00 25360.00
382.00 7640.00
4117.00 74106.00
1438.00 25884.00
18684.00 112104.00
82.00 20500.00
3068.00 147264.00
1909.00 477250.00
1268.00 101440.00
955.00 76400.00
764.00 91680.00
648.00 259200.00
512.00 307200.00
382.00 322790.00
575.00 402500.00
575.00 25875.00
82.00 164000.00
1373.00 54920.00
5357.00 64284.00
8753.00 105036.00
764.00 916800
1829.00 512120.00
1829.00 182900.00
197.00 19700.00
1699.00 16990.00
18943.00 284145.00
97.00 552900.00
3408.00 64752.00
15677.00 15677.00
981.00 23544.00
784.00 18816.00
97.00 65184.00
11627.00 1499883.00
5226.00 674154.00
10582.00 1365078.00
25475.00 254750.00
17637.00 105822.00
121496.00 121496.00
2483.00 14898.00
3397.00 20382.00
5487.00 32922.00
1568.00 37632.00
20051.00 1010570.40
20051.00 757927.80
1909.00 190900.00
3068.00 153400.00
1909.00 28635.00
4116.00 4116
4573.00 9146
10452.00 10452
56829.00 56829
5357.00 10714.00
392.00 17640.00
354.00 12390.00
8623.00 51738.00
10452.00 31356
188122.00 188122
543463.00 543463
244240.00 244240
2940.00 5880.00
784.00 2352
758.00 2274
8753.00 17506
18682.00 56046
3068.00 153400
3976.00 437360
852.00 63900
512.00 40960
10452.00 10452.00
7839.00 7839.00
64014.00 64014.00
3068.00 1840800.00
18094.00 452350.00
2394.00 71820.00
44.00 22000.00
10753.00 107530.00
3903.00 39030.00
2272.00 2272.00
17149592.20
TOTAL 17149593.00