DANIEL P.

MESIANO
LICENSED CIVIL ENGINEER, 0147915
62 Gil St. New Banicain Olongapo City

Date : July 06, 2020

Project : PROPOSED TEMPORARY FENCE, GATE AND RAMP


Owner : AJET
Location : LOT OS-F1B, AREA B, SUBIC TECHNO PARK, SBFZ
Subject : COST ESTIMATE

Sir,
We are pleased to submit our Price Proposal of the above subject project in the amount of Two Hundred Forty Two Thousand Nine
Hundred Thirty One Pesos and 32/100 (Php 242,931.32 ). This price proposal includes the cost of labor, materials, mobilization, tools,
equipment and technical supervision necessary for the satisfactory completion of the project. Details are as follows:

ITEM PARTICULARS QTY. UNIT UNIT COST TOTAL COST

I. GENERAL REQUIREMENTS
Supervision 3,000.00
Permits and Licenses 22,000.00
Sub-total 25,000.00

II. SITE WORKS


Mobilization & Demobilization 1 lot 3,000.00 3,000.00
Layout & Staking 1 lot 1,500.00 1,500.00
Clearing & Grubbing 1 lot 3,500.00 3,500.00
Earthworks 4.26 cu.m. 345.00 1,469.01
Sub-total 9,469.01

III. PERIMETER FENCE & SLIDING GATE


Steel Works 1 lot 164,991.50 164,991.50
Concrete Works 0.51 cu.m 6,541.89 3,338.33
Reinforcing Steel Bars 29 kgs 53.53 1,552.35
Sub-total 169,882.18

IV. RAMP AND SLAB


Concreting Works 4.49 cu.m 6,541.89 29,373.08
Reinforcing Steel Bars 172 kgs 53.53 9,207.05
Sub-total 38,580.13

TOTAL PROJECT COST 242,931.32

III. TERMS AND CONDITIONS:


1.0 Seventy Percent (70%) Down Payment, Balance-Payable thru progress billing.
2.0 Duration of Work: Twenty (20) Working Days.
3.0 Warranty - Six (6) months on supplied materials and workmanship.

We hope that the above proposal is satisfactory, should you find that this price proposal is acceptable, kindly signify your intent by
affixing your signature provided below.

Thank you very much, Conforme :_________________________________

Engr. Daniel P. Mesiano Date :


Project-in-charge