INSPECTION & TEST PLAN

CONSTRUCTION OF PETROLEUM INSTITUTE


RESEARCH CENTERAT SAS AL NAKHL REF. NO. ITP-6012-0101
PROJECT NO. 6012 - AGREEMENT NO. 116012C1 REV. NO. 02
DATE : 04.03.2014
PAGE : 1 OF 1
ACTIVITY: INSTALLATION OF AIR HANDLING UNITS & FRESH AIR HANDLING UNITS
AREA/LOCATION: PI Building Phase 1A
ITP approved by CONTRACTOR's QA/QC: ITP approved by COMPANY:
Signature: Signature:
Date: Date:
INSPECTION LEVEL VERIFICATION
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION/CRITERIA
SUBCON CONT. COMPANY RECORD

1 DOCUMENTATION

Specs. DIV 23, Section 237300, Item 1.5. Submittals. (1.5.1 Product Data: As per Approved
Once (Approval MAR Ref. No. M0056 Rev.02: Sumbit manufacturer's technical product for air handling units
1.1 Material Approval prior to start of showing dimensions, weights, capacities,ratings fan performace with operating pointclearly H H R Approved MAR
activity) indicated, motor electrical characteristics, gages and finishes of materials, and installation
instruction.

Specs. DIV 23, Section 237300, Item 1.5. 1.5.2 Shop Drawing: Submit assembly type shop
1.2 Shop Drawing Approval Each Shop Drawing drawing showing unit dimensions, weight, loadings, required clearances, construction details, and H H R Approved DTF
filed connection details.

Once (Approval
1.3 Method Statement Approval prior to start of All forms (MS, QCP, ITP, Check list & Risk Assesstment) as per Annexure "K" of agreement. H H R Approved DTF
activity)

2 MATERIAL INSPECTION

As Per Specs. Book 3 of 4, DIV 23, Section 237300 Item 2 (Products)/ MAR #. M-0056 Rev.02
2.1 Check the Material as per approved submittal. Each Delivery
(AHU & FAHU): Incorporate comments on the Approved MAR.
H H H MVR Approval

3 INSTALLATION INSPECTION

Area Wise or As As per approved shop drawings.As Per Specs. Book 3 of 4, DIV 23, Clause 237300 Item 3.
Check the installation as per approved drawing. Check the physical ITR, Check List FM -
3.1 Installation of equipment. instructed by (Execution). Clause 3.1. (Installation). Install as shown on the drawings, as detailed, and H H H
6012-0101 Rev 02
Company. according to AHU manufacturer's installation instructions.

LEGEND: H: HOLD W10: WITNESS 10% W100: WITNESS 100% S: SURVEILLANCE R: REVIEW
ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL COMPANY APPROVAL

NAME : NAME :
SIGN : SIGN :
DATE: DATE: