Title INNER TANK SUSPENDED DECK KEY PLAN

Document No. ELT-05-ET-DWG-0009


Revision No. 1
Page No. 1 of 3

INNER TANK SUSPENDED DECK KEY PLAN

Project Title : Andres LNG Terminal Expansion Project


Location : Punta Caucedo, Boca Chica, Dominican Republic
Owner : ENERGÍA NATURAL DOMINICANA ENADOM, S. R. L.
Contractor : POSCO Engineering & Construction Co., Ltd.
Discipline : LNG Tank

1 09 Jul 2021 Issue For Construction Y.S Choi J.K Lee H.S Yoo J.M Oh

0 25 May 2021 Issue For Construction Y.S Choi J.K Lee H.S Yoo J.M Oh

A 05 Apr 2021 Issue For Review Y.S Choi J.K Lee H.S Yoo J.M Oh

Rev. No. Issue Date Revision Text Prepared Checked Reviewed Approved

The contents of this document are the sole property of POSCO E&C. Any rights not expressly granted herein are
reserved. Reproduction, transfer or distribution of part or all of the contents in any form without the prior written
permission of POSCO E&C is prohibited.
Title INNER TANK SUSPENDED DECK KEY PLAN
Document No. ELT-05-ET-DWG-0009
Revision No. 1
Page No. 2 of 3

CONTENTS

Rev.
No. DWG. No. Drawing Title
No
1 ELT-05-ET-DWG-0009 1 Inner Tank Suspended Deck Key Plan

= The End =