Professional Documents
Culture Documents
Full Plant Survey MAY 14, 2014 Minera Cerro Bayo: July 9, 2014
Full Plant Survey MAY 14, 2014 Minera Cerro Bayo: July 9, 2014
Full Plant Survey MAY 14, 2014 Minera Cerro Bayo: July 9, 2014
KM4202
PHASE 2
July 9, 2014
1.0 Acknowledgements
Thank you also to Mr. David Tachoires, for assisting with sampling and being
quite amicable despite my clumsiness in pouring slurry on his head, and to JP for
ensuring stable circuit operation, and providing data for the survey period after
the survey. The contribution of the operating and maintenance teams is also noted
in accepting our interference and presence in the concentrator, and providing
support when required. And to all, for putting up with my limited, though now
somewhat improved, Spanglish.
2
On May 14, 2014, ALS Metallurgy personnel surveyed the Minera Cerro Bayo
concentrator with the assistance of the on-site metallurgical team. Thirteen
process stream samples were collected, as well as a subsequent belt cut sample.
No testing of the belt cut sample was conducted in this program. A summary of
the sample locations and overall metallurgical balance, created using Bilmat*, is
shown in Figure 1. Further details of sample locations, plant conditions at the
time of the survey, sample pulp densities and assays are provided in Appendix I.
Full size distributions for each stream are located in Appendix II.
The objective of the program was to identify potential areas for improvement in
metallurgical response within the Minera Cerro Bayo flowsheet. The
concentrator already operates very well; the metallurgical balance indicated that at
the time of the survey about 90 percent of the silver and 91 percent of the gold
was recovered into a final concentrate, which graded about 1 percent silver and
108 g/tonne gold.
However, there are some obvious nuances in the circuit that could be capitalized
upon to potentially improve metallurgical performance. Both sets of cyclones are
upgrading gold in the cyclone underflow. Gold, having a high specific gravity,
will tend to report to a cyclone underflow despite measuring a finer sizing than
the majority of the cyclone feed stream.
Based on this observation, the most likely improvement in the circuit would be
realized by including either gravity concentration or flash flotation on a bleed of
the D-15 cyclone underflow.
FIGURE 1
SIMPLIFIED FLOWSHEET AND METALLURGICAL BALANCE
2.4 Scavenger
1.3 Cyclones D- 2.5 Rougher Concentrate
15 O/F Tailing 27µm K80 2.6 Final Tailing
1.1 Cyclones
92µm K80 89µm K80 92µm K80
D-15 Feed
256µm K80
From SAG
Mill 2.3 Rougher
2.2 Cleaner
Concentrate
Tailing
33µm K80 2.7 Regrind
22µm K80
Cyclone Feed
1.2 Cyclones 46µm K80
D-15 U/F 2.1 Cleaner
379µm K80 Feed
23µm K80
2.9 Regrind
Discharge 2.10 Final Con
51µm K80 Column 23µm K80
2.8 Regrind
Cyclone
Underflow
72µm K80
Sample Point
The schematic showing the D-15 cyclones in closed circuit with the ball mill is
again shown in Figure 2, but in this case the potential bleed stream reporting to a
gravity or flash flotation unit is shown in red. Also shown is the metallurgical
balance for the D-15 Cyclones, the mass, gold and silver deportment by size to the
cyclone overflow, as well as the distribution of gold and silver by size in the
cyclone products.
It is clear that gold is upgrading in the cyclone underflow. This stream grades just
under 8 g/tonne gold compared to about 2.3 g/tonne in the mill feed (cyclone
overflow). Of the gold in the cyclone feed, about 87 percent reports to the
cyclone underflow. In comparison, only about 66 percent of the mass in the
cyclone feed reports to the cyclone underflow. This shows how gold has built up
a circulating load of about 650 percent in the ball mill circuit versus a mass
circulating load of about 200 percent.
The deportment chart shows that for the overall stream, the cut size d50 is about
70µm. This is the size at which there is about 50 percent probability of reporting
to the cyclone underflow or overflow. Coarser than this, particles will tend to
report to the underflow and finer particles tend to report to the overflow. For gold
and silver, this sizing was about 30µm, substantially finer than most of the
remaining mass in the stream. Gold or silver particles coarser than 30µm will
most likely return to the ball mill and be ground further, and in this manner the
recirculating load of gold and silver is generated. Removal of a bleed stream, for
gold and silver recovery, would be expected to reduce this effect to some degree.
The distributions of gold and silver by size for the cyclone overflow shows that a
significant component of gold and, to a greater degree, silver, is in the finest size
fraction, less than 12µm. Such fine particles will be more difficult to recover via
flotation. Conversely, the cyclone underflow contained very little silver or gold
finer than 31µm, and may be suitable for either gravity concentration or flash
flotation. Testing would be recommended to evaluate these two options.
5
FIGURE 2
D-15 CYCLONES OPERATION SUMMARY
90 Ag
Mass / Gold / Silver Deportment to
80 Au
Mass
70
Overflow - percent
60
50
40
30
20
10
0
1 10 100 1000
Nominal Particle Size - µm
45 45 Silver
Silver
40 40 Gold
Gold
35 35
30 30
25 25
20 20
15 15
10 10
5 5
0 0
6
The recovery of gold and silver by size curve for the roughers is very typical of
that observed for most operating rougher circuits, in our experience. High
recoveries of particles in what would be considered intermediate size fractions
were recorded; however, recovery of fine and coarse particles was lower. This is
generally due to the coarser particles not being liberated, and the finer particles
having slow flotation kinetics.
* KM3113 “A Mineralogical Assessment of Plant Performance – August 11, 2011”, December 2, 2011 .
7
FIGURE 3
ROUGHER / SCAVENGER OPERATION SUMMARY
Flowsheet Summary Metallurgical Balance
2.2 Cleaner Mass Assay-g/tonne Distribution-percent
Tailing
22µm K80 Circuit/Product percent Ag Au Ag Au
2.4 Scavenger
Concentrate Roughers
27µm K80 Rougher Conc. 15.4 1547 17.3 86.4 86.0
Rougher Tailing 84.6 44 0.51 13.6 14.0
Rougher Feed 100.0 276 3.10 100 100
2.5 Rougher 2.6 Final
1.3 Cyclones D- Tailing Scavengers
15 O/F Tailing
92µm K80
89µm K80 92µm K80 Scavenger Conc. 12.8 194 2.42 55.8 60.6
2.3 Rougher Final Tailing 87.2 23 0.23 44.2 39.4
Concentrate
Rougher Tailing 100.0 44 0.51 100 100
33µm K80
Recovery by Size
Roughers Scavengers
100 100
Mass/Gold/Silver Recovery - percent
80 Au
80
Mass
70 70
60 60
50 50
40 Ag 40
30 Au
30
Mass
20 20
10 10
0 0
1 10 100 1000 1 10 100 1000
Nominal Particle Size - µm Nominal Particle Size - µm
Silver
Ag/Au Distribution by Size - percent
Silver
60 60
Gold Gold
50 50
40 40
30 30
20 20
10 10
0 0
Note: A detailed metallurgical balance, head assays and size fraction assays are provided in Appendix I.
8
5.0 Regrinding
The circulating load of gold around the regrinding circuit measured about 440
percent. Conversely, the circulating load for mass measured only 54 percent. As
for the D-15 cyclones, gold is preferentially being concentrated in the cyclone
underflow because of the high specific gravity of gold compared to other
minerals. The cyclone underflow graded about 140 g/tonne gold, higher than that
measured for the final concentrate. However, if this stream was directed to final
concentrate, the circulating load would be broken and gold would return to the
grade of the rougher concentrate measuring about 17 g/tonne. The same
phenomenon was not as apparent for silver.
90 Silver
60
80 Gold
70 50
Overflow- percent
60 40
50
30
40
30 20
Ag
20 Au 10
10 Mass
0 0
1 10 100 1000
Nominal Particle Size - µm
Silver 60 Silver
60
Gold Gold
50 50
40 40
30 30
20 20
10 10
0 0
10
6.0 Cleaners
The performance of the cleaner block was poorer than might be expected. It is
somewhat difficult to evaluate due to the circulating load from the cleaner tailing
into the roughers and back into the cleaners. As compared to the mill feed, the
cleaner tailing contained about 61 percent of the gold and 44 percent of the silver,
the majority of which is then recovered by the roughers and returned to the
cleaner block.
A summary of the cleaner block performance, on the basis of the feed to the
cleaners, is provided as Figure 5. The following comments relate to those results:
- As a result, the silver and gold losses to the cleaner tailing were, like the
scavenger concentrate, predominantly contained in the fine size fractions.
It is unlikely such particles require further regrinding, and it is unclear
why these particles should be returned to the rougher circuit. However,
the flowsheet appears to be relatively effective (despite high circulating
loads) and the roughers and scavenger may simply be serving as increased
flotation residence time and a source of additional collector to allow
recovery of these finer particles back into the cleaner block.
11
FIGURE 5
CLEANER CIRCUIT OPERATION SUMMARY
Recovery by Size
100
Mass / Gold / Silver Recovery - percent
90
80
70
60
50
40
30 Ag
20 Au
10 Mass
0
1 10 100 1000
Nominal Particle Size - µm
Silver Silver
50 50
Gold Gold
40 40
30 30
20 20
10 10
0 0
12
On the 14th of May, 2014, a full plant survey of the Minera Cerro Bayo
concentrator was conducted. With the support of Mandalay personnel, ALS
Metallurgy collected 13 samples for size by assay analysis to identify potential
opportunities for improvement. A belt cut was also obtained for further testing as
required; no testing has been conducted so far on that sample.
Results of the analyses show that gold, and to a lesser degree silver, are
concentrating in the cyclone underflow of both the D-15 cyclones and the regrind
cyclones. This indicates that there may be opportunity for gold recovery by flash
or gravity concentration on a bleed of the cyclone underflow(s). Testing would be
required to evaluate these two options.
This should first be tested in the D-15 cyclone circuit as it may recover the gold
and silver particles that are concentrating in the regrind cyclones. The addition of
such a process may have two effects. It may recover the coarser binary particles
that are not being recovered by the flotation process. It may also limit the
circulating load around the milling stages, which is currently extensive. In the D-
15 cyclones, the circulating load is about 650 percent for gold. This compares to
the mass recirculating load of about 200 percent. This recirculation could be
resulting in the excessive generation of fine particles, less than 12µm, that are the
predominant form of gold and silver losses to the final tailing.
Rougher performance was relatively typical of that observed for flotation circuits.
Gold and silver in the scavenger concentrate and cleaner tailings both were
generally contained in the finer size fractions. The benefit of recirculating these
streams to the rougher may be related to the application of additional collector, or
available residence time in the rougher circuit. However, additional regrinding is
unlikely to further benefit these streams.
13
PHASE 2
SAMPLE ORIGIN
1
On the 14th of May, 2014 from 10:55 to 11:50 am, the Minera Cerro Bayo plant
was surveyed by ALS personnel. During the survey period, thirteen samples were
obtained via two rounds of sampling. The list of samples collected is provided as
Table I-1. Photos of selected sample locations, as well as a picture of the
samplers, are provided as Figures I-1A to I-1F. The photos were provided by
Mandalay personnel.
TABLE I-1
LIST OF SAMPLE LOCATIONS
Samples
Location
No. Description
1.1 Cyclones D-15 Feed Ball Valve on D-15 Distributor
1.2 Cyclones D-15 U/F Discharge of D-15 Cyc U/F Pipe
1.3 Cyclones D-15 O/F Flotation Feed Sampler
2.1 Cleaner Feed Discharge of Regrind Overflow Pipe
2.2 Cleaner Tail Cleaner tailings pipe discharge
2.3 Rougher Concentrate Rougher Concentrate Pipe Discharge(s)
2.4 Scavenger Concentrate Scavenger Concentrate Pipe Discharge
2.5 Rougher Tail Dip Sample from bottom of Rougher Cell 4
2.6 Final Tail Final Tailing Sampler
2.7 Regrind Cyclone Feed Regrind Cyclone Feed E-DART Sampler
2.8 Regrind Cyclone U/F Manual sampling of cyclone underflows
2.9 Regrind Discharge Regrind Discharge pipe
2.10 Final Concentrate Final Concentrate Sampler
During the survey, the plant was understood to be processing relatively ‘typical’
ore and operations appeared to be stable. The average throughput at the time of
the survey was 68 tonnes per hour, wet. Key chemical conditions and reagent
dosages at the time of the surveys are provided in Tables I-2 and I-3.
2
TABLE I-2
PH AND EH FOR EACH SAMPLE ROUND
TABLE I-3
CHEMICAL DOSAGES
Location / Reagent
Concentration PAX 3477 MIBC
Concentration - percent 5 5 100
Dosage - mL/min
Primary Cyclones 600 500 30
Rougher Feed 300 300 10
Rougher 4 100 100 -
Dosage - g/tonne
Primary Cyclones 26.5 22.1 21.4
Rougher Feed 13.2 13.2 7.1
Rougher 4 4.4 4.4 -
Note: Dosages in g/tonne are based on the belt throughput, unadjusted for moisture content.
After completion of the survey, at around 2 pm the same day, a belt cut ahead of
the Minera Cerro Bayo SAG mill was conducted.
The thirteen samples were filtered and shipped as wet filter cake to ALS
Metallurgy Santiago. Upon receipt, ALS Metallurgy Santiago dried and prepared
the thirteen samples. Standard bulk preparation was conducted for the Belt Cut.
The prepared samples were shipped to ALS Metallurgy Kamloops. In addition,
about 4.1 kilograms was shipped to ALS Metallurgy Balcatta for diagnostic leach
tests. Each of the thirteen samples was assayed for a series of elements of interest.
Head assays, masses and densities for the thirteen samples are summarized in
Table I-4.
3
TABLE I-4
HEAD ASSAYS
TABLE I-5
METALLURGICAL BALANCE
An additional sub-cut of each of the samples was also cyclosized into appropriate
size fractions for gold and silver assays. These assays are summarized in Tables
I-6A to I-6M. Tables I-7A to I-7F summarize recoveries by size fraction for each
block of the circuit.
The 282 kilogram belt cut sample was placed into storage at ALS Metallurgy
Kamloops.
5
Size Weight Metal Assays Size Weight Metal Assays Size Weight Metal Assays
Fraction percent Ag Au Fraction percent Ag Au Fraction percent Ag Au
>300µm 16.1 174 2.70 >300µm 25.1 140 2.71 >300µm 0.0 0 0.00
<300>150µm 21.3 202 4.82 <300>150µm 29.2 132 3.60 <300>150µm 5.0 46 0.41
<150>106µm 12.2 266 14.1 <150>106µm 12.9 278 15.0 <150>106µm 10.3 63 0.84
<106>53µm 16.1 344 9.15 <106>53µm 12.7 654 16.4 <106>53µm 22.5 103 2.53
<53µm>C2 5.9 882 15.0 <53µm>C2 3.8 1242 19.6 <53µm>C2 9.6 346 9.64
<C2>C3 5.2 246 2.42 <C2>C3 2.8 208 2.35 <C2>C3 10.2 170 2.26
<C3>C5 7.1 256 2.16 <C3>C5 3.7 196 1.76 <C3>C5 13.9 236 1.92
<C5 16.0 314 1.16 <C5 9.7 292 1.22 <C5 28.5 270 1.08
Calc Head 100.0 293 6.01 Calc Head 100.0 282 6.74 Calc Head 100.0 192 2.41
Size Weight Metal Assays Size Weight Metal Assays Size Weight Metal Assays
Fraction percent Ag Au Fraction percent Ag Au Fraction percent Ag Au
>300µm 0.0 0 0.00 >300µm 0.0 0 0.00 >300µm 0.0 0 0.00
<300>150µm 0.0 0 0.00 <300>150µm 0.0 0 0.00 <300>150µm 0.0 0 0.00
<150>106µm 0.0 0 0.00 <150>106µm 0.0 0 0.00 <150>106µm 4.6 793 14.8
<106>53µm 4.1 630 8.73 <106>53µm 4.1 384 3.86 <106>53µm 8.9 1345 31.0
<53µm>C2 8.6 1677 39.1 <53µm>C2 6.3 506 7.75 <53µm>C2 11.6 2175 35.8
<C2>C3 16.7 1356 19.5 <C2>C3 14.7 466 7.34 <C2>C3 14.3 1193 14.4
<C3>C5 29.0 1241 14.4 <C3>C5 28.5 452 7.96 <C3>C5 26.5 1107 12.3
<C5 41.5 2027 13.5 <C5 46.4 770 7.33 <C5 34.1 1950 11.0
Calc Head 100.0 1599 16.8 Calc Head 100.0 602 7.40 Calc Head 100.0 1537 16.7
6
Size Weight Metal Assays Size Weight Metal Assays Size Weight Metal Assays
Fraction percent Ag Au Fraction percent Ag Au Fraction percent Ag Au
>300µm 0.0 0 0.00 >300µm 0.0 0 0.00 >300µm 0.0 0 0.00
<300>150µm 0.0 0 0.00 <300>150µm 0.0 0 0.00 <300>150µm 0.0 0 0.00
<150>106µm 3.1 224 1.94 <150>106µm 14.3 24 0.17 <150>106µm 15.3 17 0.15
<106>53µm 7.3 189 1.75 <106>53µm 20.6 20 0.16 <106>53µm 22.4 12 0.09
<53µm>C2 4.9 200 3.03 <53µm>C2 8.5 26 0.19 <53µm>C2 8.7 14 0.09
<C2>C3 8.8 148 1.69 <C2>C3 9.7 23 0.24 <C2>C3 9.8 9 0.03
<C3>C5 18.5 150 2.67 <C3>C5 14.7 32 0.52 <C3>C5 14.2 12 0.14
<C5 57.4 263 2.69 <C5 32.1 93 1.13 <C5 29.5 45 0.53
Calc Head 100.0 222 2.52 Calc Head 100.0 47 0.54 Calc Head 100.0 22 0.23
TABLE I-7A
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE D-15 CYCLONES - 15th of MAY 2014
KM4202
TABLE I-7B
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE ROUGHERS - 15th of MAY 2014
KM4202
>300µm 0 0 0.00 0 0
<150>150µm 0 0 0.00 0 0
<150>106µm 100 66 1.00 100 100
<106>53µm 100 117 2.49 100 100
<53µm>C2 100 454 7.51 100 100
<C2>C3 100 271 3.34 100 100
<C3>C5 100 298 3.52 100 100
<C5 100 393 2.76 100 100
TABLE I-7C
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE SCAVENGERS - 15th of MAY 2014
KM4202
>300µm 0 0 0.00 0 0
<150>150µm 0 0 0.00 0 0
<150>106µm 100 22 0.20 100 100
<106>53µm 100 19 0.16 100 100
<53µm>C2 100 26 0.30 100 100
<C2>C3 100 23 0.22 100 100
<C3>C5 100 31 0.53 100 100
<C5 100 86 0.99 100 100
TABLE I-7D
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE REGRIND CYCLONE FEED - 15th of MAY 2014
KM4202
>300µm 0 0 0.00 0 0
<150>150µm 0 0 0.00 0 0
<150>106µm 100 925 43.6 100 100
<106>53µm 100 1572 91 100 100
<53µm>C2 100 2599 150 100 100
<C2>C3 100 1550 26.9 100 100
<C3>C5 100 1297 16.4 100 100
<C5 100 2331 30.5 100 100
TABLE I-7E
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE REGRIND CYCLONES - 15th of MAY 2014
KM4202
>300µm 0 0 0.00 0 0
<150>150µm 0 0 0.00 0 0
<150>106µm 100 927 41.5 100 100
<106>53µm 100 1665 102 100 100
<53µm>C2 100 2948 180 100 100
<C2>C3 100 1841 37.3 100 100
<C3>C5 100 1275 15.5 100 100
<C5 100 1967 14.5 100 100
TABLE I-7F
SIZE BY ASSAY AND SIZE BY RECOVERY FOR THE CLEANERS - 15th of MAY 2014
KM4202
>300µm 0 0 0.00 0 0
<150>150µm 0 0 0.00 0 0
<150>106µm 0 0 0.00 0 0
<106>53µm 100 359 4.03 100 100
<53µm>C2 100 1932 52.9 100 100
<C2>C3 100 1352 20.7 100 100
<C3>C5 100 1194 15.5 100 100
<C5 100 1877 12.1 100 100
FIGURE I-1A
SAMPLE POINTS
Note: A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
14
FIGURE I-1B
SAMPLE POINTS
Note: A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
Note: A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
15
FIGURE I-1C
SAMPLE POINTS
Notes: a) This is an example of one of the four rougher discharge pipes that was sampled.
b) The same number of cuts was samples from each discharge pipe, with the same cutting speed.
c) A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
Note: A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
16
FIGURE I-1D
SAMPLE POINTS
FIGURE I-1E
SAMPLE POINTS
Notes: a) The same number of cuts was taken from each operating cyclone and combined into a single sample.
b) A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
Note: A sample cutter, shown at the bottom of Figure I-1F was used to collect this sample.
18
FIGURE I-1F
SAMPLE POINTS
Note: The same number of cuts was taken from each operating cyclone and combined into a
single sample.
Samplers
Note: From left to right, there is a sample cutter, dip sampler, and a second sample cutter.
APPENDIX II – KM4202
PHASE 2
TABLE II-1
CYCLOSIZING ANALYSIS
KM4202 Cyclones D-15 Feed 1.1
Total 89.33 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
2
TABLE II-2
CYCLOSIZING ANALYSIS
KM4202 Cyclones D-15 Underflow 1.2
Total 82.60 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
3
TABLE II-3
CYCLOSIZING ANALYSIS
KM4202 Cyclones D-15 Overflow 1.3
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
4
TABLE II-4
CYCLOSIZING ANALYSIS
KM4202 Cleaner Feed 2.1
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
5
TABLE II-5
CYCLOSIZING ANALYSIS
KM4202 Cleaner Tailing 2.2
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
6
TABLE II-6
CYCLOSIZING ANALYSIS
KM4202 Rougher Concentrate 2.3
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
7
TABLE II-7
CYCLOSIZING ANALYSIS
KM4202 Scavenger Concentrate 2.4
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
8
TABLE II-8
CYCLOSIZING ANALYSIS
KM4202 Rougher Tailing 2.5
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
9
TABLE II-9
CYCLOSIZING ANALYSIS
KM4202 Final Tailing 2.6
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
10
TABLE II-10
CYCLOSIZING ANALYSIS
KM4202 Regrind Cyclone Feed 2.7
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
11
TABLE II-11
CYCLOSIZING ANALYSIS
KM4202 Regrind Cyclone Underflow 2.8
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
12
TABLE II-12
CYCLOSIZING ANALYSIS
KM4202 Regrind Discharge 2.9
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)
13
TABLE II-13
CYCLOSIZING ANALYSIS
KM4202 Final Concentrate 2.10
Total 100.00 **
100
90
Cumulative Percent Passing
80
70
60
50
40
30
20
10
0
1 10 100 1000
Particle Size (microns)